Unit Cost Total Cost

201(01)A Clearing and Grubbing, Slash Treatment Methods for Top and Limbs (4), Logs (4), and stumps (4), Utilization of Timber

DQ ac 2.90

201(10) Clearing and Grubbing, Decking of Markable Timber DQ ac 2.90

203(01) Excavation, Placement Method 1 DQ yd3 2358

203(16) Drainage Excavation, Type Outlet Ditches DQ ft 48

203(16)A Drainage Excavation, Construct Broad Base Dip DQ Each 5

204(01) Temporary Seeding AQ ac 2.20

204(07) Silt Fence AQ ft 120 251(03)A Placed Riprap, Class II, Method A DQ yd2 16.0

304(11)A Crushed Aggregate Base, 1 1/2 Crusher Run Compaction B VQ T 2195

304(11)B Crushed Aggregate Base, AASHTO # 2, Compaction

B VQ T 150

601(01) Mobilization LSQ ls 1 603B(01)18 18 inch HDPE pipe, Type S, Method B SQ ft 180 603B(01)24 24 inch HDPE pipe, Type S, Method B SQ ft 93

625(02) Seeding DQ ac 1.10 633(02) Steel Post DQ ft 12

633(16) Route Marker DQ each 1

Total

Road Construction Cost

Schedule of Items - Forest Road 1560G Road Construction Project (1.05 mi)

Item No. Description Method Measure Unit Quantity