This is a Questions and Answers amendment to RFQ# 1232SA26Q1424 for the Repair/Replace Low Water Crossing project in El Reno, Oklahoma. The document clarifies seven key requirements for potential offerors and does not address specific pricing terms, response dates, or award dates.
The amendment confirms that cast-in-place concrete box structures (ODOT CIP 4x12 standard) are acceptable alternatives to precast structures, addressing lead time concerns. Key subcontractor or team member attendance satisfies the mandatory September 8 site visit requirement if the attendee is identified on the government's sign-in sheet and their role is explained in the quote. The period of performance is 365 consecutive calendar days from Notice to Proceed, as specified in Section 01 00 11 of the specifications, superseding any conflicting language in the SF1442. Concrete rubble with minimal wire mesh content may be used as rip rap per specification section 31 00 00 2.2.2, subject to government and architect approval. Trees required for removal may be disposed of in an on-site burn pile at the contractor's responsibility for hauling. Additionally, existing damaged tin horns must be removed and disposed of off-site by the contractor.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment 2
RFQ# 1232SA26Q1424
Repair/Replace Low Water Crossing - El Reno, OK
Questions and Answers
1. Would the government consider a cast in place box structure in place of a precast structure? Attached is an ODOT standard 4x12 structure.
ANSWER: Yes, the attached ODOT CIP 4x12 would be an acceptable structure.
2. The solicitation states that the September 8 site visit is mandatory. If an offeror did not personally attend, may the requirement be satisfied through a proposed subcontractor/team member that attended the mandatory site visit and is identified on the Government’s site-visit sign-in sheet?
ANSWER: Key subcontractor/team member attendance is allowable to fulfil the site visit attendance requirement. The quote should identify who attended on the prime’s behalf and explain the subcontractor’s role in the project.
3. The SF1442/solicitation states a 120-calendar-day period of performance from Notice to Proceed, while Section 01 00 11 of the specifications states 365 consecutive calendar days after Notice to Proceed. Please confirm which performance period governs.
ANSWER: The Specifications are correct. PoP is 365 days from NTP.
4. Would cast in place concrete walls be authorized in place of precast box culvert.
Lead time constraints on precast box culverts may pose performance delays.
ANSWER: See Q1.
5. Confirm that the tree required to be removed can remain on site disposed of in burn pile.
ANSWER: Yes, the tree to be removed may be disposed of in the specified burn pile on the property. It will be the contractor’s responsibility to haul the tree from the construction location to the burn pile.
6. Confirm that concrete rubble broken up into a manageable size with minimal wire left can be used in correlation with the spec rip rap per plans .
ANSWER: Concrete rubble size / composure must be in accordance with spec section 31 00 00 2.2.2. Rubble with minimal wire mesh content will be considered for approval, but final approval is subject to the discretion of the GVMT / AE in the review and approval process outlined therein.
7. Confirm that existing damaged tin horns need to be removed and disposed of off-site.
ANSWER: Yes, the existing damaged tin horns are to be removed and disposed of off-site by contractor.