This document is Site Visit Guidance for Potential Contractors for a USDA-ARS facility project at Mississippi State University in Starkville, Mississippi. The site visit is scheduled for Monday, September 21st at 10 AM CT at 150 Twelve Lane, Starkville, MS 39762. Primary points of contact are Mr. Herbert Jones, Administrative Officer (phone: 662-320-7393; cell: 662-684-9886; email: Herbert.Jones@usda.gov) and Mr. Neil P. Johnson, Facilities Point of Contact/COR-2 (phone: 662-684-9141; email: Neil.Johnson@usda.gov).

The document provides guidance for conducting the site visit to help potential contractors understand physical conditions, project expectations, and operational constraints. Pre-visit preparation includes identifying accessible areas, gathering relevant documents and drawings, notifying internal stakeholders, and confirming contractor attendance with directions and safety requirements. During the walkthrough, contractors will receive an overview of project objectives, review safety rules and PPE requirements, and tour relevant project locations to observe existing conditions, utility access points, obstacles, and operational schedules. Key information to be clarified includes scope expectations and performance standards, access schedules and security procedures, environmental and structural considerations, project timelines and deliverables, and points of contact for questions. Post-visit actions include providing supplemental documents, summarizing key discussion points, reminding contractors of proposal due dates, and maintaining attendance records. The overarching goal is to ensure all contractors receive equal, accurate, and complete information to develop competitive, realistic, and responsible proposals.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Site Visit Guidance for Potential Contractors Site visit will be conducted on Monday, September 21st at 10 AM CT.

USDA - ARS at Mississippi State, MS 150 Twelve Ln, Starkville, MS 39762

POC:

Mr. Herbert Jones, Administrative Officer (AO) USDA, ARS MS State 150 Twelve Lane MS State, MS 39762 Phone: 662-320-7393 Cell: 662-684-9886 Email: Herbert.Jones@usda.gov

Mr. Neil P. Johnson, Facilities Point of Contact (POC)(COR-2) P.O. Box 5367, 150 Twelve Lane MS State, MS 39762

(662) 684-9141 Email: Neil.Johnson@usda.gov

Purpose of the Site Visit

A site visit provides potential contractors with an opportunity to understand the physical conditions, project expectations, and operational constraints of the location where work will be performed. It helps ensure accurate proposals, reduces misunderstandings, and promotes a transparent procurement process.

Preparation Before the Visit

• Identify the areas contractors need to access and ensure they are safe, accessible, and appropriately staffed.

• Gather any documents, drawings, or background information that may assist contractors in understanding the scope.

• Notify internal stakeholders (security, facilities, operations) about the visit schedule.

• Confirm attendance and provide directions, contact information, and any required identification or safety requirements.

Conducting the Site Walkthrough mailto:Herbert.Jones@usda.gov

• Begin with a brief overview of the project and the objectives of the visit.

• Review safety rules, required PPE, and any restricted areas.

• Walk contractors through all relevant project locations, pointing out:

o Existing conditions o Utility access points o Potential obstacles or constraints o Operational schedules that may impact work

• Encourage contractors to ask questions and take measurements or photos where permitted.

Information to Clarify During the Visit

• Scope expectations and performance standards

• Access schedules, security procedures, and site-specific work rules

• Any known environmental or structural considerations

• Anticipated project timelines and deliverables

• Points of contact for technical or administrative questions

Post-Visit Actions

• Provide contractors with any supplemental documents referenced during the walkthrough.

• Summarize key points discussed during the visit.

• Remind contractors of proposal due dates and submission requirements.

• Maintain a record of attendees and key questions raised for future reference.

Goal

To ensure all contractors have equal, accurate, and complete information so they can develop competitive, realistic, and responsible proposals.

Site Visit Guidance for Potential Contractors
Purpose of the Site Visit
Preparation Before the Visit
Conducting the Site Walkthrough
Information to Clarify During the Visit
Post-Visit Actions
Goal

File details come from the government source that posted it. Updated .