This is a Revised Statement of Work for repair and renovation services at the Stuttgart National Aquaculture Center (SNARC), a USDA Agricultural Research Service facility located at 2955 Highway 130 E, Stuttgart, Arkansas 72160. The project involves comprehensive metal building repairs including replacement of approximately 130 linear feet of deteriorating 3' x 8' metal panels and red iron support braces; sealing all panels at top and bottom to prevent rodent and bird entry; applying weatherproof sealants to fasteners; installation of waterproof PVC or FRP board on interior walls covering approximately 75' x 7' to protect deteriorating insulation; replacement of two sets of commercial 36"x84" double doors and frames with white epoxy coating; and repair of the existing ridge cap with hardware cloth for bird exclusion. The contractor must provide all necessary equipment, materials, supplies, tools, scaffolding, hoisting, transportation, and labor. All work must comply with applicable codes and standards including ANSI, ASME, NEC, NFPA 72, OSHA, and ADA requirements.
The contractor must submit a Site Safety Specific Plan within 14 days of contract award and verify all dimensions and site conditions prior to work commencement. Work hours are Monday through Friday, 7:00 A.M. to 4:00 P.M., excluding government holidays, with project completion not to exceed 180 days from notice to proceed. The contractor is responsible for daily work area cleanup, weekly debris removal, maintaining an on-site superintendent during installation, providing their own restroom facilities, and proper disposal of used oils and fluids. A government representative will conduct final inspection and acceptance with minimum 10 days' advance written notice required. Material submittals must be provided to the Engineering Project Manager (Everett Wilson, 720-618-0703, everett.wilson@usda.gov), Site Research Leader (Dr. Yulin Jia, 870-672-6129), and Location POC (Robert Ideker, 870-672-8266). The project includes photographs documenting existing conditions showing rusted metal panels, deteriorated doors, corroded support structures, and damaged building envelopes.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of Agriculture Agricultural Research Service
REVISED STATEMENT OF WORK
Repair metal Panels, Door, and Ridge Cap
Stuttgart National Aquaculture Center
(SNARC)
2955 Highway 130 E Stuttgart, AR 72160
Prepared by Robert Ideker
February 5, 2026
Statement of Work USDA, Agricultural Research Service
Scope Statement
This is for the repair of a metal building at the Stuttgart National Research Center. This repair will consist of replacing metal panels that are deteriorating and the red iron support braces to anchor the metal panels. There are approximately 130’ metal panels 3’ x 8’ that will need to be replaced. Sealing all panels at the top and bottom to prevent the entry of rodents and birds. Apply weatherproof seals to fasteners to ensure durability.
Installation of a waterproof PVC board or FRP board on the interior of the building to cover up deteriorating insulation. There is approximately 75’ x 7’ area that will need to be covered. Replace the areas where the insulation is gone. The board will need to be braced at the bottom and the seams with a weatherproof material. Replace two sets of commercial 36”x 84” double doors and frames. The doors will need to be painted with an epoxy coating (white) to prevent rust and deterioration. Repairing the existing Ridge cap by installing hardware cloth to keep birds out.
Summary of services:
Contractor will be responsible for providing all necessary equipment, materials, supplies, tools, scaffolding, hoisting, transportation, unloading, and handling required for the proper installation and completion of this project.
The contractor shall include all services and field labor, equipment and software to make program adjustments, necessary to preform the service contract and personal protective equipment necessary to perform the work.
The contractor will be responsible for the proper disposal of all the used oil and fluids.
Applicable Codes and Standards apply and are not limited to the following:
ANSI - American National Standards Institute.
ASME - American Society of Mechanical Engineers.
NEC - National Electrical Code, NFPA 72.
OSHA - Occupational Safety and Health Administration ADA – Americans with Disabilities Act
Project Objectives The project consists of the following elements:
1.Removal of existing components 2.Preparation for installation 3.Installation of new components
4. Structural enhancements
5. Ridge cap work
6. Color must be matched as close as possible to existing material
Site Visit
Contractors are encouraged to visit the site and be escorted by a government representative to confirm locations, dimensions, and conditions of the project before a bid is submitted. The site visit shall be for the purpose of observing first-hand any conditions relevant to the completion of this project. No consideration will be given to claims based on lack of knowledge of existing conditions, except where Contract Documents make definite provisions for adjustment in cost or extension due to existing conditions not readily foreseeable.
Utilization of Bio-Based Products
The contractor shall utilize products and material based from bio- based materials as applicable, (e.g. bio-based greases; bio-based hydraulic fluids, bio-based absorbents), to the maximum extent possible without jeopardizing the intended end use of detracting from the overall quality delivered to the end user. All supplies and materials shall be of a type and quality that conform to the applicable Federal Specifications and Standards. All supplies and materials to be used in the performance of work described herein are subject to the approval of the Contracting Officer Representative (COR). Products can be found at:
www.biopreferred.gov
Safety
The contractor will submit a Site Safety Specific Plan/Accident Prevention Plan in industry recognizable format to the Contracting Officer within 14 days of contract award.
Contractor shall furnish a Site-Specific Safety Plan (SSSP) and the Government shall review the SSSP prior to the start any construction activities. SSSP shall be in typically accepted industry format.
Base Bid
Contractor shall perform the work as specified in the Statement of Work.
Contractor Responsibilities
The project has a base bid to be performed per the following specifications:
1. Contractor will verify all dimensions and existing site conditions prior to beginning work.
2. Contractor shall keep work area clean daily and take measures to control debris while work is being performed.
3. Contractor is required to manage the project and consult with the Government prior to beginning all work phases.
4. Contractor shall perform work in a manner that minimizes the impact of the work on Government operations, research, and functions.
5. All work must be performed in such a manner as to not adversely affect daily operations of the facility and its workers.
6. Contractor shall remove and dispose of all construction related materials from all work areas daily and remove these waste materials from the site on a weekly basis.
7. Contractor must have a superintendent on the jobsite when crews are performing the installation work.
8. Contactor will provide their own restroom facility.
Material / Submittals:
The material for the entire work shall include but are not limited to those detailed above necessary to successfully complete the project and deliver a functioning system as required. Submittals on all material used on this project shall be submitted to the EPM, Site RL, and Contracting Specialist as noted in this document. Electronic submittals are acceptable.
Installation Procedure:
Contractor will verify all dimensions and site conditions prior to beginning work.
Contractor is required to provide labor, specified material, equipment, and other tools required to perform the job fully and completely. No Government equipment will be available for use by the contractor. The contractor shall always be responsible for protecting his work and ensuring the safety of his crew and ARS employees. Upon completion of the project, the contractor shall remove from the premises all accumulated materials and rubbish caused by the project. Premises shall be left in a clean, orderly, and acceptable condition.
Damage to Property:
Any damage to the Government buildings, utilities, etc. caused as the result of the contractor’s activities shall be repaired or replaced to the satisfaction of the Government.
Inspection and Acceptance:
A government representative shall inspect and approve the work performed on this project. The Contractor shall schedule inspection a minimum of 10 days in advance, in writing, to the location POC.
Project Schedule:
The completion of this project shall not exceed 180 days from date of notice to proceed.
A request for time extension must be submitted to the Contracting Officer in writing. Each request must include specific and detailed reasons in support of the schedule alteration.
Work Hours:
Contractor work hours shall be Monday through Friday, seven (7) A.M. to four (4) P.M.
with the exception of Government holidays. Any changes to work schedule shall be submitted to Contacting Officer for written approval prior to schedule change.
Photos of Work Site
Project Contacts
RESEARCH LEADER (RL)
Dr. Yulin Jia Phone: 870-672-6129
USDA, ARS, SEA
2890 HWY 130 East Stuttgart, AR, 72160 Email: Jia.yulin@usda.gov
ADMINSTRATIVE OFFICER (AO)
Raeann Braithwaite Phone: 870-672-8254
USDA, ARS, SEA
2955 Highway 130 East Stuttgart, AR 72160 Email: Raeann.braithwaite@usda.gov
Location POC
Robert Ideker Phone: 870-672-8266
USDA, ARS, SEA
2955 Highway 130 East Email: Robert.Ideker@usda.gov Stuttgart, AR 72160
ENGINEERING PROJECT MANAGER (EPM) & (CO)
Everett Wilson Phone: 720-618-0703 USDA, ARS, SEA Facilities 3550 Main Street, #5121 Houston TX 77002 Email: everett.wilson@usda.gov
AREA SAFETY AND HEALTH MANAGER (ASHM)
Joel Ledbetter (SNARC) Phone: 870-672-8255
USDA, ARS, SEA
2890 HWY 130 East Stuttgart, AR 72160-0287 Email: joel.ledbetter@usda.gov