This Statement of Work (SOW) details a flooring replacement project at the U.S. National Poultry Research Center in Athens, Georgia. The project involves abating asbestos floor tiles in the B1 2nd floor hallways and installing new 12x12 vinyl composition tile (VCT) with new cove base, with all work to be performed on weekends only from 6:00 A.M. to 5:00 P.M. on Saturdays and Sundays. The contractor must be a small business with expertise in environmental remediation services, registered in the System for Award Management (SAM), and will be responsible for providing all labor, equipment, materials, and safety measures required for asbestos removal and flooring installation.

Key requirements include submitting a Site Specific Safety Plan, using certified asbestos abatement workers, minimizing disruption to facility operations, and completing the project within 45 days of the notice to proceed. The project is a 100% small business set-aside with a project value between $25,000 and $100,000, falling under NAICS code 562910. The contractor must comply with all applicable safety regulations, building codes, and provide a one-year guarantee on workmanship, with any deficiencies to be corrected within 24 hours of notification.

View the file

Other files

File Type Posted
Questions and Answers Aug 1.pdf PDF
AMENDMENT 1 SF 30 1232SA25Q0383.pdf PDF
Floor Plan Sketches.pdf PDF
Attachment 2 Wage Determination.pdf PDF
Attachment 1 Statement of Work.pdf PDF
1232SA25Q0383.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Department of Agriculture Agricultural Research Service

STATEMENT OF WORK

Replace 12x12 flooring in B1 2nd Floor Hallways

U.S. National Poultry Research Center 950 College Station Road

Athens, Georgia 30605

1. Scope of Work

The contractor shall provide all professional services necessary to remove and replace asbestos floor tiles per section 3.

The contractor shall include all services and field labor, equipment (including cranes, rigging and material handling equipment), materials, testing and personal protective equipment necessary to perform the work.

Equipment and services provided by the Government for contractor use are listed below:

- None provided

1.1 Base Bid

The contractor shall provide a detailed proposal and cost breakdown for the entire project including submittals for proposed equipment and materials.

1.2 Site Visit

Contractors are strongly encouraged to visit the site and be escorted by a government representative to confirm locations, dimensions, and conditions of the project before a bid is submitted. The site visit shall be for the purpose of observing conditions relevant to the completion of this project. No consideration will be given to claims based on lack of knowledge of existing conditions, except where contract documents make definite provisions for adjustment in cost or extension due to existing conditions not readily foreseeable.

Contractor must be registered in System for Award Management, (SAM), prior to submitting a bid.

2. Codes and Standards

Applicable Codes and Standards apply and are not limited to the following

ANSI - American National Standards Institute.

ASME - American Society of Mechanical Engineers.

NEC - National Electrical Code, NFPA 72.

OSHA - Occupational Safety and Health Administration ADA – Americans with Disabilities Act

All work must meet Local, State and Federal codes, and latest IBC codes.

3. Project Summary

1) Abate asbestos floor tiles and mastic in hallways

2) Install new 12 x 12 VCT and new cove base

3) Work must comply with all required asbestos regulations

The facility will be occupied during construction activities. All work shall be scheduled in advance and coordinated with the facility representative to minimize the disruption to traffic, daily operations and research programs.

4. Safety

The contractor will submit a Site Safety Specific Plan (SSSP) in industry recognizable format to the Contracting Officer within 14 days of contract award. The Government shall review the SSSP prior to the start any construction activities.

Safety and health matters, as they relate to the work, are the exclusive responsibility of the contractor.

The contractor shall furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions that may be required by law or local authorities for the protection and security of the grounds, facilities, and personnel.

5. Contractor Requirements

The contractor shall provide a complete and functional installation, including all labor, supervision, tools, materials, equipment, apparatus, transportation, rigging and other equipment and services necessary to accomplish the work in accordance with the intent and meaning of this statement of work.

The project work shall be performed per the following guidelines:

1) Contractor will verify all dimensions and site conditions prior to beginning work.

2) The contractor shall always be responsible for protecting his work and ensuring the safety of his crew and ARS employees.

3) Contractor shall remove and dispose of all construction related materials from all work areas daily and remove these waste materials from the site weekly.

4) Contractor is required to manage the project and consult with the Government prior to beginning all work.

5) Contractor will provide a certified asbestos abatement supervisor for all abatement work

6) Contractor will use only certified asbestos abatement workers for abatement work.

7) All workers must provide valid ID to enter property.

8) Contractor shall perform work in a manner that minimizes the impact to daily operations of the facility and its workers. The building will be occupied during construction work.

9) All work is to be performed according with building codes, ordinances and laws of the Authority having jurisdiction on the project. When the requirements of the building codes, ordinances, and laws conflict with any other part of the building codes, ordinances and laws, the most restrictive requirement shall prevail.

6. Material Submittals

Submittals and O&M documentation must be provided for all materials used on this project.

7. Pre-Construction Submittals

Contractor’s Site Specific Safety Plan (SSSP) must be provided to and approved by USDA before installation can begin.

8. Damage to Property:

The Contractor shall protect the work, the site, and all existing property and structures within the limits of the construction activities or that may be affected thereby until acceptance of the work. Any damage to property shall be repaired to pre-damaged condition to the satisfaction of the USDA.

9. Inspection and Acceptance A government representative shall inspect and approve the work. The Contractor shall schedule inspection a minimum of 2 days in advance.

10. Period of Performance

The completion of this project shall not exceed 45 days from date of notice to proceed. A request for time extension must be submitted to the Contracting Specialist in writing. Each request must include specific and detailed reasons in support of the schedule alteration.

10.1 Work Hours:

In an effort to reduce the interruption of to the occupants on the floor, this work will be performed on weekends only. The weekend hours will be from 6:00 A.M. to 5:00 P.M. Saturday and Sunday. An escort will be mandatory. Therefore, coordination of arrival will be pre-arranged at least 48 hours in advance.

Any changes to work schedule shall be submitted to Contracting Officer for written approval prior to the schedule change.

11. Guaranty

The contractor shall provide and submit a single guarantee stating that all portions of the work are in accordance with Contract requirements. Guarantee all work against faulty and improper material and workmanship for a period of one (1) year from date of final acceptance by the USDA, except where manufacturer guarantees or warranties are for longer terms. The contractor shall correct any deficiencies which occur during the guarantee period within 24 hours after notification.

United States Department of Agriculture
Agricultural Research Service
1. Scope of Work
1.1 Base Bid
1.2 Site Visit
2. Codes and Standards
3. Project Summary
4. Safety
5. Contractor Requirements
6. Material Submittals
7. Pre-Construction Submittals
8. Damage to Property:
10. Period of Performance
10.1 Work Hours:

11. Guaranty