Attachment 1_SOW BLDG 20 North Side Improvements.pdf

PDF 262 KB Posted

Attached to
Bldg. 20 Exterior Improvements, Ames, Iowa
Solicitation number
1232SA25Q0339
Issued by

About this file

This Statement of Work (SOW) details exterior improvements for Building 20 at the National Centers for Animal Health in Ames, Iowa, scheduled for March 6, 2025. The project encompasses four primary sections: (1) replacing a 12-inch CMU block wall and its foundation, (2) installing a new concrete spill containment basin around six electrical transformers, (3) implementing a new rainwater drainage system to redirect water away from the building, and (4) replacing approximately 1,400 square feet of the employee entrance sidewalk.

The project requires comprehensive site work including demolition of existing structures, precise concrete and masonry installation, drainage system implementation, and restoration of surrounding landscape areas. Key technical requirements include constructing a new wall with specific painting specifications, creating a spill containment basin sized to hold one transformer's capacity plus additional freeboard, installing a French drainage system, and ensuring proper water flow management. The contractor must adhere to multiple regulatory standards including NFPA, OSHA, and local building codes, and will need to provide detailed submittals, warranties, and documentation for all project components.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

Building 20 North Side Improvements Project

National Centers for Animal Health

Ames, Iowa

3/6/25

BACKGROUND:

On the north side of building 20, there is a CMU block wall that separates the building 20 employee entrance from the electrical equipment feeding the building. This wall has deteriorated over the years due to salt application of the adjacent sidewalk. The sidewalk has also begun to crack and sink due to salt application and poor drainage. Additionally, the 6 electrical transformers that are on the east side of the CMU wall, do not have a spill containment basin to capture any oil leaks from the transformers in the event of a failure of one of the transformers. Finally, during periods of heavy rain or melting snow, the north side of building 20 will get overly saturated and cause rainwater to infiltrate into the main electrical room in the basement of building 20.

SCOPE:

There are 4 sections to this project:

1. Replace the 12-inch CMU block wall. This shall include replacement of the foundation of the wall.

2. Install a new concrete spill containment basin around the 6 transformers.

3. Install a new rainwater drain system that will direct rainwater and groundwater away from the building and also direct any water that collects in the spill containment into this new drainage system.

4. Replace approximately 1400 square feet of the employee entrance sidewalk on the north side of building 20.

SECTION 1: NEW 12-INCH CMU WALL

1. Remove existing metal wall panels and metal trim.

2. Demolish existing 12-inch CMU block wall down to the concrete foundation.

3. Demolish existing concrete foundation for the current wall.

4. Install new concrete wall foundation as shown on page P04 of the drawings. Depth of new footing to match original. Subbase shall be level.

5. Construct a new 12-inch CMU block wall following existing specifications.

6. Paint east side of 12-inch CMU block wall using Perma-Crete High Build 100% Acrylic

Topcoat 4-22 (Pastel)or approved equivalent. Apply according to manufacturer’s recommendations. Apply two finish coats.

7. Install new non-insulated metal wall panels and trim on west side of CMU wall. Metal wall panels shall match the non-insulated metal wall panels that were removed previously in material and color.

SECTION 2: NEW SPILL CONTAINMENT

1. Remove existing river rock and any landscaping fabric from around the 6 transformers to allow installation of new spill containment basin. River rock may be reused.

Landscaping fabric shall be appropriately removed and disposed of and replaced with new.

2. Construct new concrete spill containment basin around all 6 transformers sized as to provide storage for the capacity of one transformer plus 6-inches of freeboard for a 25-year, 24-hour storm event.

3. New concrete spill containment basin shall slope to a single point that will drain into the new rainwater drainage system referenced on page P16 of the drawings.

4. When completed, the new concrete spill containment pad shall be free of cracks and any joints shall be sealed to prevent seepage through the pad and into the ground. Any defects found in new spill containment basin shall be replaced/repaired by the contractor.

5. New concrete spill containment basin shall have a 2-inch spring actuated drain valve located in the southwest corner of the new basin. That location shall be the lowest point in the new basin and will drain into the new French drainage system via the new river rock bed. New 2-inch drain valve shall be normally closed to prevent transformer oil from entering storm drainage system.

6. New spill containment basin shall be sloped in such a way to prevent pooling of rainwater inside new basin walls.

7. New spill containment basin shall be installed as to prevent pooling of water around the top of the basin. New 2-inch drain shall be placed to flow into the new French drainage system.

8. Contractor is allowed to remove perimeter fencing as needed. Chain link fence shall be reinstalled in the same location as it was prior to project.

9. Replace/repair any damaged areas around the new spill containment basin to normal or better condition than prior to the start of the project. Area around new spill containment basin shall be river rock as before.

SECTION 3: NEW DRAINAGE SYSTEM

1. Replace approximately 1400 square feet of the grass area between the fenced area and building 20 with river rock of the same size of the existing river rock that is around the switchgear and transformers. See page P16 of the drawings for reference.

2. New river rock bed shall have a base of sand and landscaping fabric to prevent weeds from growing. Sand bed for the new river rock shall be 4-inches and the sand bed shall be covered with landscaping fabric before adding the new river rock. New river rock bed shall have metal landscape edging on the east end to prevent rocks from entering the grass area. Landscape edging shall be of the same type and material as the product used around the transformer area.

3. New river rock area shall be blended into the existing river rock around the transformers. Slope shall be towards the new catch basin.

4. New river rock drainage bed shall be sloped to allow rainwater to flow from the 2-inch drain valve on the concrete spill containment basin and from the building downspout to the center of the river rock bed into the new catch basin.

5. Install a new catch basin as shown on the drawings in such a way that it will catch water from the downspout and the spill containment basin. New catch basin and grate shall have a flow capacity of no less than 60 gallons per minute to allow for runoff from the building downspout and the new spill containment basin.

6. Trench over to the existing northeast pump pit located on the northeast corner of building 20. See drawing P02 for location. Trench shall be below the frost line at 42-inches deep.

7. Drainage trench shall be sloped between 1% to 2% towards the northeast pump pit to allow water to dump into existing pit.

8. Install new 4-inch PVC pipe in new trench.

9. Connect new catch basin with 4-inch PVC pipe over to the northeast pump pit.

10. Core drill into the concrete column of the NE pit to allow the 4-inch PVC pipe to enter.

11. Seal around the newly installed 4-inch PVC pipe with 4-inch link seal.

12. Backfill drainage trench with clean soil.

13. Repair and reseed any areas affected by the installation of this new drainage trench back to normal or better condition than prior to the start of the project.

SECTION 4: REPLACE NORTH ENTRANCE SIDEWALK

1. Install pedestrian traffic barriers and signage to route employees away from and around construction area. Maintain barriers until concrete has fully set and sidewalk can be opened to the public or until construction operations in the area have ceased that may cause a danger to pedestrians; whichever comes later.

2. Remove landscaping edging stones to accommodate new sidewalk. Replace landscaping edging to original configuration once new sidewalk has been installed.

3. Light bollards and benches that are removed or damaged during the installation of the new sidewalk, shall be reinstalled or replaced by the contractor at no additional cost to the government.

4. Reuse existing river rock on west side of landscape stone edging. Any landscaping fabric that is removed or damaged by installation of new sidewalk shall be replaced by the contractor at no additional cost to the government.

5. Remove approximately 1400 square feet of the existing north employee entrance down to the existing base. Remove all debris from site.

6. Repair the subgrade to prevent runoff from affecting the new CMU wall. Sloping of new sidewalk shall be towards the north to the parking lot.

7. Replace sidewalk with new concrete to match original. New sidewalk shall be the same thickness as the existing concrete sidewalk. Use 6-inch by 6-inch welded wire fabric for reinforcement. See details on page P21 of the drawings.

8. New sidewalk shall have a broom finish when completed.

9. Replace landscaping stones to original configuration.

10. Repair and reseed any areas affected by the installation of the new employee entrance sidewalk back to normal or better condition than prior to the start of the project.

General Requirements

Work Restrictions & Conditions

1. All work shall be coordinated with the Contracting Officer’s Representative (COR) at least 2 weeks in advance prior to start of project.

2. Anything mentioned in the Scope of Work and not shown on the drawings or shown on the drawings and not mentioned in the Scope of Work, shall be of like effect as if shown or mentioned in both.

3. Interested parties are strongly encouraged to visit the site of the proposed work and review the existing conditions there relating to construction and labor, and to be fully informed as to the facilities involved, and the difficulties and restrictions that may affect the performance of the Contract. Failure to visit the site will not disqualify those submitting a proposal. However, change order requests for items that could have been reasonably ascertainable from a site visit (and included in a proposal) will be reviewed by the CO and evaluated accordingly.

4. The completed installation shall comply with all applicable provisions of the Manufacturers Requirements, and the SOW (Drawings and Specifications), enclosed and/or attached.

5. All work will be performed by qualified personnel as designed by OSHA and as applicable per manufacturer’s specifications.

6. Contractor shall verify all equipment, and systems are operational and ensure that your quality control inspections and corrections have been accomplished before calling for the final inspection.

Site Security Access

1. Effective May 7th, 2025, a REAL ID compliant driver’s license will be required for entry onto any federal facility. Anyone without a REAL ID compliant driver’s license will be denied entry into the NCAH facility. Access to the construction site is controlled by a security fence and visitor/contractor check-in/check-out system. All contractor/sub-contractor employees shall sign in and out at the main site entrance gate and wear a contractor/visitor identification badge at all times while on the site. The ID badges will be turned in at the end of the workday.

2. All visitors must be pre-registered prior to coming onto campus. It is the responsibility of the contractor to ensure that the USDA is notified in the appropriate timeframe of any personnel that are performing work onsite and dates that work will be performed.

3. Contractor’s vehicles will be allowed to offload materials and tools on the north side of building 20 and then shall park their vehicles in the building 20 parking lot. All vehicles and equipment must not impede traffic or affect building 20 operations. Parking areas will be designated by the COR prior to commencement of work. Vehicle badges shall be displayed at all times while the contractor is on site.

4. The Contractor shall use only the service roads and access routes approved by the Contracting Officer’s Representative.

5. Work shall be confined to the areas identified on the Drawings. Unless accompanied by a NCAH/USDA employee, the Contractor, sub-contractors, and their employees shall not enter buildings or facilities not specifically part of this project. Reasons included, but are not limited to, disease control and health requirements.

6. Additional security requirements may be imposed when the Federal Government raises the Homeland Security Alert Level. Additional directions will be provided if the situation occurs.

7. Failure to comply with access requirements shall be adequate grounds for removal of the Contractor/sub-contractor employees from the site and barring further site access to individuals.

Work Hours: Regular work hours for the site are 7:00AM to 3:30PM, Monday through Friday, excluding Government holidays. Requests for exceptions to this schedule shall be made in writing 5 days in advance and approved by the Contracting Officer's Representative.

Work Outside Regular Work Hours: Work scheduled outside regular work hours including late hours, Saturdays, Sundays, and Government holidays requires the Contracting Officer’s Representative’s (COR) approval in advance. Make application to the COR at least 5 calendar days prior to such work to allow arrangements to be made by the Government for access to the work area and inspection & monitoring arrangements. Requests shall include the exact dates, hours, location, and purpose of the exception. If approved, the COR will coordinate access with the site security office.

1. Construct Work in stages to accommodate Owner’s use of premises during construction period.

Coordinate construction schedule and operations with Contracting Officer’s Representative

(COR).

2. Contractor shall coordinate use of premises under direction of the COR. Contractor shall confine construction equipment, storage of materials and equipment and operations of workers to areas permitted by law, ordinances, permits, or requirements of Contract Documents, and shall not unreasonably encumber premises with construction equipment or other material or equipment.

Contractor shall:

1. Assume full responsibility for protection and safekeeping of items under this Agreement, stored on site.

2. Move any stored items, under Contractor’s control, which interfere with operations of Owner or separate contractor.

3. Obtain and pay for use of additional storage or Work areas needed for operations.

4. Transport all materials needed to the site. No deliveries to the USDA warehouses. USDA shall refuse any deliveries to the USDA warehouse that are scheduled for this project.

Owner will occupy premises during the entire period of construction for its normal operations.

Coordinate with Contracting Officer’s Representative (COR) in all construction operations to minimize conflict, and to facilitate Owner usage. Contractor shall at all times conduct its operations as to ensure the least inconvenience to the Owner.

Security Clearance Requirements

Use of Premises

1. Limit of premises to work in areas indicated. Do not disturb portions of site beyond areas in which the work is approved. If any existing equipment or structure is damaged, the contractor is required to return the condition back to pre-construction condition or better at no cost to the government.

2. Keep driveways, entrances, walkways, and doorways serving premises clear and available to the Government, employees, visitors, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

3. Limited parking may be available on the site away from building 20.

4. The contractor shall provide a list of all staff employees that will be working on the project to the Contracting Officer’s Representative (COR) a minimum of five days in advance.

Adherence to Security Policies and Procedures

1. The Contractor shall adhere to all Site, ARS, APHIS and USDA security policies and procedures including Code of Federal Regulations Requirements, Standard Operating Procedures, Security Directives, Security Procedures, General Orders, Post Orders and any applicable Government Policies and Procedures.

2. Failure to adhere to or violation of any above listed requirements, procedures, directives, orders and/or policies may result in criminal prosecution or contractor representative or contractor employee (violator) removal.

Intent of Contract Drawings

1. Government provided drawings, henceforth referred to as “Contract Drawings”, do not attempt to show complete details of building construction that may affect installation. Government provided diagrams of proposed systems are for reference only and do not necessarily show physical arrangement of all equipment and/or maximum number of devices. Minimum system requirements are shown.

2. Devices are shown diagrammatically only. System layout does not necessarily show maximum number of system components and should not be used for obtaining quantities for linear runs of piping and equipment.

3. Locations of existing and Government concept devices are approximate and may be distorted for clarity in representation.

Regulatory Requirements

The equipment materials, installation, workmanship, and operation shall conform to the most stringent applicable requirements of the most recent editions of the associated publications, in the below section and in the attached specifications unless otherwise noted:

1. National Fire Protection Association (NFPA)

2. NFPA 101 – Safety to Life from Fire in Buildings and Structures.

3. NFPA 1 – Uniform Fire Code

4. NFPA 5000 – Building Construction and Safety Code

5. Underwriters Laboratories, Inc. (U.L.)

6. Appropriate U.L. Standards

7. State and Local Building Codes as adopted by the Authority Having Jurisdiction (AHJ).

8. The Uniform Federal Accessibility Standards (UFAS)

9. Occupational Safety and Health Administration (OSHA)

10. Architectural Barriers Act (ABA)

11. Equipment Manufacturer Printed Instructions

12. Statewide Urban Design and Specifications (SUDAS) most recent edition, Section 4040:

Subdrains and Footing Drain Collectors.

Coordination

1. The contractor shall coordinate all work with the Contracting Officer's Representative. In general, Owner will need a minimum of two (2) weeks’ notice of onsite activities.

2. The contractor shall submit an installation schedule for review and approval by the Contracting Officer's Representative within ten (10) days of task order award.

3. The contractor shall be solely responsible for coordinating work with all sub-contractors and ensuring that all items of joint use in conjunction with installations are completed.

Special Provisions

1. The Contractor shall confine all operations to within the work limits of the project and exercise special care to maintain natural surroundings undamaged. All surfaces and groundwork that has been altered for the installation of the new employee entrance wall, new employee entrance sidewalk, new spill containment basin and new drainage system shall be refinished to match original condition by skilled personnel of the trades involved at no additional expense to the Government.

2. Finished surfaces of existing facilities that are affected, marred, scratched, or damaged by the contractor shall be refinished to match original condition.

3. Patching material shall be of the same type, style, and thickness, and shall be finished to match existing adjacent surface construction in color and texture.

4. Patching material, paint color, paint material and paint application methods shall be approved in advance by the Contracting Officer’s Representative.

5. No building structural members shall be cut or altered without prior approval of the Contracting Officer's Representative.

6. Any damage resulting from contractor's operation shall be brought to the attention of the Contracting Officer's Representative immediately.

7. The contractor shall take all necessary and reasonable measures to keep the work site clean of trash and debris. Work areas shall be cleaned immediately as work in that area is completed, and before moving to a new work site. Place all trash and debris in OSHA approved containers, remove, and dispose of trash off site daily.

8. The contractor shall secure all materials, and equipment, including ladders and scaffolding from the site at the completion of each day's operation unless otherwise approved by the Contracting Officer's Representative.

9. The contractor shall provide proper safety equipment to workmen and ensure a safe environment for employees and the general public at all times. The contractor shall work to ensure free, unobstructed, and safe access to and about the work area.

Temporary Facilities

1. Utilities: The existing USDA utilities at the site may be used by the Contractor for completion of the contract work at no cost to the Contractor. The Contractor shall be responsible for making and removing any utility connections.

2. Telephones: The Contractor shall equip all his foremen and work leaders with cell phones as necessary to coordinate the work effort. The Government will not provide any phone service to the project.

3. Toilet Facilities: The Contractor shall provide and maintain portable toilet facilities for the project workers.

Submittal & Shop Drawings Procedures

Submittal Register: At the beginning of the project, the Contractor shall provide a Submittal Register identifying all the items called out in the SOW for submittal to the COR for approval. The Contractor shall update and maintain the Submittal Register to show the current status of all required submittals.

Submittal Requirements

Format: There is no formal submittal transmittal or format for this project other than the documents shall be submitted as PDF files, scanned, or created in documents that can be easily read when printed on 11x17 sheets. Exceptions for larger sheet sizes will be considered by the COR. Failure of the Contractor to provide legible submittals will be adequate grounds for rejection.

Identification: Submittals shall be labeled and marked for this project. The identification shall include Contractor/sub-contractor’s name, date of submittal, description of item, specification section, and details on product data that are marked clearly for this project.

Submittal Procedures: All submittals will be posted in PDF by the Contractor and sent to the USDA for review. This same submittal process will be used for RFIs, Change Bulletins, etc.

Approved Submittals: The approval/acceptance of submittals is not to be construed as a complete check. Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist.

Submittal items for this project:

1. CMU blocks

2. Paint for CMU wall

3. Non-insulated metal panels and trim

4. Rainwater catch basins and associated calculations to determine size

5. 4-inch corrugated drainage pipe

6. Calculations on spill containment basin

7. Concrete mix design for sidewalk

8. Concrete mix design for CMU wall footing

9. Mortar mix design

10. Reinforcement – CMU block wall and sidewalk

11. Joint Sealant for sidewalk

12. Joint Sealant for metal wall panels

13. 2-inch spring actuated manual ball valve for spill containment drain

14. 4-inch link seal (mechanical seal)

Warranty Documentation

1. Warranty List: Provide a warranty summary sheet in spreadsheet format with all the warranties listed by section, description, supplier, warranty contact, start date, end date. Provide electronic copy to the COR and place printed copy in the front of the Warranty Binder.

2. Warranty Copies in Binder: Provide one signed & dated copy of all warranties for all the new equipment, valves, hot tap saddles and piping installed on the project. The Warranty binder shall be divided by Specification Section and shall be provided to the COR. An electronic (scanned) copy of the Warranty Binder in a PDF file shall be submitted with the final close-out documentation.

Warranty Items:

1. CMU blocks

2. Non-insulated metal panels

3. Rainwater catch basin

4. Spill containment basin

5. New sidewalk (concrete)

6. French drain system

Operation & Maintenance Manuals: Contractor shall provide a printed copy of all Operation & Maintenance documentation provided with any associated equipment installed in the project and place the manuals in an organized binder. The O&M Manuals shall be organized by specification section and shall have an index at the front of the binder. The Contractor shall also provide a PDF version of the Manuals to be submitted with the close-out documentation.

Record Drawings

Redline Specifications: During the construction period the Contractor shall keep an updated & marked-up or “redline” copy of the project specifications on the jobsite. The redline set shall include notes on changes, RFI responses, and other field notes. At the end of the project the Contractor shall electronically scan the redline specifications and provide an electronic copy in PDF to the Owner along with the close-out documentation.

Redline Drawings: During the construction period the Contractor shall keep an updated “redline” or “conformed” copy of the project drawings on the jobsite. The redline set shall include notes on changes, RFI responses, and other field notes. At the end of the project the Contractor shall electronically scan the redline drawings at full-size and in color and provide an electronic copy in PDF to the Owner along with the close-out documentation.

END OF SECTION