About this file
This document is an amendment to solicitation 12305B24R0017 for the B307 Fiber Upgrade project issued by the United States Department of Agriculture (USDA) Agricultural Research Service (ARS). The amendment provides answers to 8 questions related to the project requirements, including the depth of the direct buried fiber, use of existing conduit, fiber installation specifications, and site conditions. The amendment also establishes the period of performance as 04/15/2024 to 07/14/2024. The original solicitation is a Request for Proposals for a firm-fixed price contract to install fiber optic cable at the Beltsville Agricultural Research Center, with a total small business set-aside and a NAICS code of 238210. The magnitude of construction is between $25,000 and $100,000, and interested vendors are encouraged to conduct a site visit before submitting proposals.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 12305B24R00170001.pdf | ||
| 12305B24R0017.pdf | ||
| Attachment 2 - WD Prince Georges County MD Buidling MD20240054 - 23FEB2024.pdf | ||
| Attachment 1 - SOW - B307 Fiber Upgrade.pdf | ||
| Attachment 3 - WD Prince Georges County MD Heavy MD20240021 - 05JAN2024.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
12305B24R0017 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
ARS-12305B
BELTSVILLE MD 20705
BLDG 003, RM 223, BARC-WEST
10300 BALTIMORE AVENUE
USDA ARS NEA AAO ACQ/PER PROP
03/07/20240002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
03/07/2024
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Questions 1 through 8 and Answers 1 through 8 on the continuation page of this amendment are hereby implemented into the solicitation.
Period of Performance: 04/15/2024 to 07/14/2024
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
ROGER D. AMMONS
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Question 1: What is the depth you would like this direct buried fiber installed?
Answer 1: At least 12” below the surface.
Question 2: If existing conduit is available and passable, can we use it for parts of this installation?
Answer 2: Yes, existing conduit can be used.
Question 3: Do you also require ISP rated ID to be installed inside the buildings-or just run the fiber bare to termination point(s)?
Answer 3: No.
Question 4: Section C.1, Description of Work, pg. 6, B307 fiber upgrade, it states direct burial fiber optic cabling. Is the accepted methodology to have trench the entire run distance and install conduit or just trench and bury the cable?
Answer 4: Trench and bury.
Question 5: Will markers and handholes be required?
Answer 5: No.
Question 6: Is it the contractor’s responsibility to return the ground as find to include backfill, Grass seed or sod?
Answer 6: No.
Question 7: Is the preferred methodology for crossing the 12 feet of concrete or asphalt to saw cut and patch or bore under the roadway utilizing conduit?
Answer 7: Either.
Question 8: Per section H.4 Submittals and Drawings pg. 18, Will Drawings/Blueprints be released prior to due date?
Answer 8: No drawings are available.
END