1. Will the prime contract holder be required to be a SUE Level "A" entity, or can the prime contract holder be a SUE Level "B" entity that is permitted to subcontract the dig portions to a third-party hydro-vacuum-excavation company?
Govt Response: PWS will be updated to Revision 1 and remove the word ‘dig’.
2. I'm assuming that there are limits on what percentage of the prime contract can be subcontracted as outlined in the Simplified Acquisition Threshold, but not sure if the SAT applies to the base contract period of one year, or if it applies to the total combined amount for all 5 years (base +4 Option).
Govt Response: The Simplified Acquisition Threshold requirement would be established on the base + 4 option years. Based upon our market research and IGE, FAR Clause 52.219-14, Limitations on Subcontracting, is not required to be incorporated within FAR Clause 52.212-5.