Amendment Two (2)
Site Visit Question and Answer Document, Time Extension, Revised Bid Schedule and Revised Construction Specification No. 6
Solicitation: 122B4618Q0023
Question:
How to handle the C-Chanel?
Response:
NRCS is ok with a cap
Question:
How do you want the yard seeded – Slip, Hydro or Broadcast?
Response:
Broadcast with Mulch
Question:
Relevant to erecting the structure if county approves. Does that bring up walls, weir and require backfill?
Response:
Yes to walls and weir. The levee is already high enough.
Question:
How should contractor dispose of trees?
Response:
Drop in marsh for habitat.
Question:
How should contractor perform excavation of bid item 008?
Response:
Excavate a foot and that volume does not include the vegetation map.
2. Solicitation due date is being extended FROM: 6/20/18 TO:
07/12/2018 resulting from the proposed rescission of WRP funding by Office of Management and Budget.
3. The revised Bid Schedule is attached, adding bid item 8 as a result of breaking out bid item 07 discussed during the Site Visit.
4. NRCS is also providing an additional sheet to Construction Specification Number 6. Please note, the changed page is 6.3 of the attached Construction Specification (see attached).