AMEND 2_06092020.pdf

PDF 220 KB Posted

Attached to
Allegheny National Forest: Forest Road 504/508 Road Reconstruction
Solicitation number
1224H820R0001
Issued by

View the file

Other files

File Type Posted
AMEND 4_06162020.pdf PDF
AMEND 3_06152020.pdf PDF
AMEND 1_05262020.pdf PDF
1224H820R0001.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

Amendment 2: Questions and Answers

North East Acquisition Team 4 Farm Colony Drive Warren PA 16365

See block 6

1224H820R0001

1 3

06/09/2020

05/15/2020

Solicitation: 1224H820R0001

Date: 9 Jun 2020

AMENDMENT 02:

QUESTIONS AND ANSWERS:

1. QUESTION: Is the stone bedding and backfill material for the culvert replacements included within the culvert item 60230-A? Or, is the stone included in another pay item?

RESPONSE: The Pa2A backfill for cross drains and the arch culvert is paid out of the #30116 line item. The item accounts for delivery, placement, and compaction of the stone. The # 60230-A Item includes supply, delivery and placement per ft.

2. QUESTION: Is the Structure Backfill and Bedding material for the structural plate arch included with the arch item? Or is this stone included with another pay item(s)?

RESPONSE: The stone is called out in the work description and is part of the individual stone pay items. #30116, 30104-A, and surfacing #30150. Structural backfill is covered in the cost of stone backfill as well as in #20417/#20404.

3. QUESTION: Is the R3, R4, R5, and #57 Streambed material for the structural plate arch included with the arch item? Or is this stone included with other pay items?

RESPONSE: The streambed material is not part of the structural plate arch. It is covered in the individual stone items that include: supply, delivery, and placement per item.

4. QUESTION: Item 20305: Is this for removal of the existing culvert where the new structural plate arch is?

RESPONSE: Yes, item #20305 is for the removal of the existing culvert where the structural plate arch is to be installed.

5. QUESTION: Item 20417: Could you clarify what is included with this lump sum excavation item?

RESPONSE: Item# 20417 is to reconstruct the roadside embankment around the structural pipe arch #20404 is for the roadway excavation and compaction of the arch and concrete footers.

(End of Amendment 2)

File details come from the government source that posted it. Updated .