This document contains questions and answers related to a construction project at Dolly Copp Campground. The project will continue upgrades in several areas of the campground including the volunteer's loop sign and entrance area, site work on Little Meadow and Big Meadow, work on host sites, runoff improvements on Birch Lane, and additional work under potential Alternates 1 and 2 if funding becomes available. The project is located in Gorham, New Hampshire on National Forest land off Pinkham B Road and has a magnitude between $500,000 and $1 million. Bidders will have the opportunity to visit the site during a pre-bid meeting. Specifications will follow the FP03 Federal Highways standards and Forest Service supplemental specifications. The period of performance is from September 1, 2020 through August 31, 2021, allowing work during winter months depending on weather and the ability to plow. All wood from clearing will be disposed of in coordination with the Ranger. Bidders must include plans for staging and office areas within construction limits for approval. Power will be available year-round on site.

View the file

Other files for this federal contract opportunity

Other files attached to Dolly Copp Construction Phase III, newest first.
File Type Posted
12148420R0001-0001 extension to 071520.pdf PDF
070220 Dolly Copp Phase III QA.docx DOCX document
Attach 4 GovtProvidedTechnicalProposalForms.docx DOCX document
Attach 3 DBWD NH20200008 Highway COOS 010320.pdf PDF
Attach 1 Phase III - 100 percent Construction Plans 04-28-20.pdf PDF
12148420R0001 Complete.pdf PDF
Attach 2 Copp Phase III - Specifications 04-28-20.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

12148420R0001 Dolly Copp Phase III Questions 06/17/2020

1. G201-protection of trees, detail on L403, shows a tree with a fence 360 degrees around the tree, with sign, orange polyethylene at the drip edge. The camp sites have multiple trees, is it the intent to install this around most campsites?

· Section 1 on Sheet L-401, is a suggestion on how to protect a tree to close to any operations.

2. General- please clarify the term “clear and grub”, no mention of stumping, or stump removal, are stumps to be removed?

201.04 Clearing. Within the clearing limits, clear trees, brush, downed timber, and other vegetation as follows:

(a) Cut all trees so they fall within the clearing limits.

(b) In areas of cut slope rounding, cut stumps flush with or below the final groundline.

(c) In areas outside the excavation, embankment, and slope rounding limits, cut stumps to within 6 inches of the ground.

(d) Trim tree branches that extend over the road surface and shoulders to attain a clear height of 20 feet. If required, remove other branches to present a balanced appearance. Trim according to accepted tree surgery practices. Treat wounds with tree wound dressing.

201.05 Grubbing. Grub deep enough to remove stumps, roots, buried logs, moss, turf, or other vegetative debris as follows:

(a) Grub all areas to be excavated except for cut slope rounding areas.

(b) Grub all embankment areas. Undisturbed stumps may be left in place if they protrude less than 6 inches above the original ground and will be covered with more than 4 feet of embankment.

(c) Grub pits, channel changes, and ditches only to the depth necessary for the excavation.

(d) Backfill stump holes and other grubbing holes with backfill material to the level of the surrounding ground according to Subsection 209.10. Compact backfill according to Subsection 209.11.

FP03 from Federal Highways are the specifications used on this project. Also read the FS supplemental specification attached on this solicitation package.

3. G-302 Culvert removal, what is the material of the existing culvert? Metal/concrete or HDPE?

All old culvert are metal. There will be opportunity to verify it on the pre-bid meeting on site.

4. General – “protect archeological”, what controls/fence etc is desired to protect? Would orange fence with signage, the same as tree protection?

Orange fence and keep all operations away from those areas will be enough.

5. L-107 Hayes field, the fields have limit of construction lines, don’t see any work planned in those areas?

Please read the legends and schedules at the bottom to interpret the work needed on Sheet L-107. Work is clearly defined with hatches and notes. For further details please read the specifications for this project, Federal Highway FP03 and Forest Service Supplemental Specifications for the FP03.

6. L -108, by site 166, the rip rap to the river, the edge of the river is lined with rock, the plan calls for rip rap, is it the intent that this is an access point for pedestrian/fishing or a kayak launch?

No access point for pedestrian/fishing or kayak. This is a drainage collection point. No recreational use.

7. For the clearing work, is the campground interested in retaining any of the firewood?

The wood produced by clear and grubbing is property of the United States. To properly dispose of it, coordination with the Ranger needs to be done.

8. Is there an area to stock pile material?

Every bidder have to submit its own plan for staging area within the construction limits. Staging area will be approved during the preconstruction submittal process.

9. Temporary office trailer/equipment trailer site for crews, will there be an area provided? Will electricity remain all winter be available to access?

Every bidder should plan for an office/trailer area within construction limits. Area will be approved during submittal process. Power is available year round. Bidder should plan to have their own meter to sustain any office during construction.

10. Period of Performance: 09/01/2020 to 08/31/2021, will work be allowed during the winter months, snow removal, does access remain open all year?

Access can remain open all year, weather permitting and ability of bidders to keep areas plowed. If temperature get too low and earthwork is not feasible a winter break will be allowed.

11. Is all the work shown as Future Development another Phase for the project?

It is not listed as an Alternate 1 or Alternate 2.

Correct everything marked as Future Development will be done by partners