1205K320Q0010_SF30.pdf

PDF 353 KB Posted

Attached to
Ape Cave Foundation Preparation Federal contract opportunity
Solicitation number
1205K320Q0010
Issued by
Department of Agriculture Forest Service R6-Pacific Northwest Region

View the file

Other files for this federal contract opportunity

Other files attached to Ape Cave Foundation Preparation, newest first.
File Type Posted
1205K320Q0010_SF30_Amendment 02.pdf PDF
1205K320Q0010_Ape Cave Site Prep Solicitation Attachments_.pdf PDF
1205K320Q0010_Ape Cave Site Prep Solicitation.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x) x

1205K320Q0010 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

1100305688#

05K3

VANCOUVER WA 98661

501 E 5TH STREET 404

GIFFORDPINCHOT NATIONAL FOREST

USDA FOREST SERVICE

See Block 16C

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO.

5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

05/08/2020

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

D. OTHER (Specify type of modification and authority) x 1

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

STEVONNE FULLER

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Amendment 01 is to replace the Schedule of Items and page 13 in the current solicitation.

This amendment does extend the closing date to May 28, 2020 1200 PT.

USDA FOREST SERVICE

GIFFORDPINCHOT NATIONAL FOREST

501 E 5TH STREET 404

VANCOUVER WA 98661 US

Continued ...

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

XX

USDA Forest Service

BASE ITEM

NUMBER DESCRIPTION

METHOD

OF MEAS UNIT QUANTITY PRICE TOTAL

011900 Mobilization LSQ LS 1 $ $

024116-1

Structure Demolition - Remove and dispose existing comfort stations and vaults AQ EA 3 $ $

024116-2

Structure Demolition, Site Improvements - Remove and dispose or salvage LSQ LS 1 $ $

133460-1

Comfort Station Installation (Includes aprons) -

Double Vault (Ape Cave Western) AQ EA 1 $ $

133460-2

Comfort Station Installation (Includes aprons) -

Double Vault (Ape Cave Northeastern) AQ EA 1 $ $

133460-3

Comfort Station Installation (Includes aprons) -

Double Vault (Trail of Two Forest) AQ EA 1 $ $

312100 Site Preparation and Grading LSQ LS 1 $ $

321200-1 Asphalt Surfaced Pad, WSDOT Mix Design DQ SF 330 $ $

321204-1 Crushed Aggregate Base Course, WSDOT Gradation DQ SF 330 $ $

322205-1 Barrier Rocks (Commercial Source) AQ EA 20 $ $

329206 Hydro-Seeding LSQ LS 1 $ $

Total Base Items $

OPTIONAL

ITEM

NUMBER DESCRIPTION

METHOD

OF MEAS UNIT QUANTITY PRICE TOTAL

321200-2 Asphalt Surfaced Pad, WSDOT Mix Design DQ SF 187 $ $

321204-2 Crushed Aggregate Base Course, WSDOT Gradation DQ SF 187 $ $

321400 Aggregate Surfaced Pad - Crusher Fines DQ CY 10 $ $

027070-1 Temporay Construction Chain Link Fencing LSQ LS 1 $ $

027070-2 Temporay Construction Chain Link Fencing LSQ LS 1 $ $

027070-3 Temporay Construction Chain Link Fencing LSQ LS 1 $ $

027070-4 Temporay Construction Chain Link Fencing LSQ LS 1 $ $

027070-5 Temporay Construction Chain Link Fencing LSQ LS 1 $ $

027071-1 Temporary Porta-Potties LSQ LS 1 $ $

027071-2 Temporary Porta-Potties LSQ LS 1 $ $

027071-3 Temporary Porta-Potties LSQ LS 1 $ $

027071-4 Temporary Porta-Potties LSQ LS 1 $ $

027071-5 Temporary Porta-Potties LSQ LS 1 $ $

Total $

CONTRACT TOTAL- BASE AND OPTION ITEMS $

SCHEDULE OF ITEMS

MSHNVM Comfort Station Replacement Project

1205K320Q0010 Ape Cave Site Preparation GPNF

3. Contractor shall obtain all necessary floor plans and specifications from CXT prior to the start of work, and shall be utilized in conjunction with the documents in this contract.

B. The Government shall be responsible for providing the following items:

1. Seed for hydro-seeding.

C.12 PRICE RANGE

The Government’s estimate is:

(c) Between $100,000 and $250,000.

C.13 AMENDMENT UPDATES REGARDING CLOSURES

A. The FS will keep the Ape Cave recreational area closed to the public until the end of

July. As a result, the contractor can work Monday-Friday, at the Ape Cave recreational area throughout the duration of the project. The Ape Cave recreational area closure will be maintained by the FS, by way of closing and maintaining the gate closure on the 8303 RD, just past the entrance to the Trail of Two Forests recreational area. The contractor will be provided a key to the gate to access the Ape Cave recreational area. As a result, the contractor will not need to bid on fencing or porta potties for the Ape Cave recreational area. Reference of the fencing and porta potties within the specifications and/or plans for the Ape Cave recreational area can be disregarded. The contractor is still expected to meet deadlines as listed in the contract, such as start date, CXT toilet installation date, and the contract completion date. The contractor will still be responsible for securing the work site, as the FS cannot stop the general public from walking into the Ape Cave recreational area, just as this could occur at any other job site.

B. The FS will keep the Trail of Two Forests recreational area open to the public, as currently stated in the contract. As a result, the contractor will need to bid on fencing and porta potties for the Trail of Two Forests recreational area. Reference of the fencing and porta potties within the specifications and/or plans for the Trail of Two Forests recreational area still applicable to the contract. The contractor is still expected to meet deadlines as listed in the contract, such as start date, CXT toilet installation date, and the contract completion date. The contractor will still be responsible for securing the work site, as stated in the current contract. However, if the FS determines that the agency’s response to COVID-19 needs to be more restrictive, this could result in the site being closed off to the public. If this occurs, the FS will have the responsibility to performing and maintaining that closure.

File details come from the government source that posted it. Updated .