1205K320Q0010_Ape Cave Site Prep Solicitation Attachments_.pdf
PDF 6 MB Posted
- Attached to
- Ape Cave Foundation Preparation Federal contract opportunity
- Solicitation number
- 1205K320Q0010
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 1205K320Q0010_SF30_Amendment 02.pdf | ||
| 1205K320Q0010_SF30.pdf | ||
| 1205K320Q0010_Ape Cave Site Prep Solicitation.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USDA FOREST SERVICE, R6
MSHNVM COMFORT STATION REPLACEMENT PROJECT
SECTION 011900 - MOBILIZATION
PART 1 - GENERAL
1.1 SUMMARY
A. This item is intended to compensate the Contractor for operations including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for payment of premiums for bonds and insurance for the project; and for any other work and operations which must be performed or costs that must be incurred incident to the initiation of meaningful work at the site and for which payment is not otherwise provided for under the contract.
1.2 MEASUREMENT AND PAYMENT
A. The measurement shall be lump sum for mobilization. Payment shall be as follows:
1. Bond premiums will be reimbursed after receipt of the evidence of payment.
2. 50% of the lump sum, not to exceed 5% of the original contract amount, will be paid following completion of 5% of the original contract amount not including mobilization and bond premiums.
3. Payment of the remaining portion of the lump sum, up to 10% of the original contract amount, will be paid following completion of 10% of the original contract amount not including mobilization and bond premiums.
4. Any portion of the lump sum in excess of 10% of the original contract amount will be paid after final acceptance.
5. Progress payments for mobilization and preparatory work shall be subject to retainage.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
END SECTION 011900
JANUARY 2020
MSHNVM TOILET REPLACEMENT PROJECT
SECTION 013300 - SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other miscellaneous submittals. See Table 013300-1 for a summary of required submittals.
B. See other specification section within this package for additional requirements on submittal.
1.2 SUBMITTAL PROCEDURES
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.
a. The Contracting Officer (CO) reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
B. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on CO's receipt of submittal.
1. Initial Review: Allow 2 days for initial review of each submittal. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.
2. If intermediate submittal is necessary, process it in same manner as initial submittal.
3. Allow 2 days for processing each re-submittal.
4. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.
C. Identification: Place a permanent label or title block on each submittal for identification.
1. Indicate name of firm or entity that prepared each submittal on label or title block.
2. Provide a space on label or beside title block to record Contractor's review and approval markings and action taken by CO.
3. Include the following information on label for processing and recording action taken:
a. Project name.
b. Date.
c. Name and address of Contractor.
d. Name of manufacturer.
e. Unique identifier, including revision number.
f. Number and title of appropriate Specification Section.
g. Drawing number and detail references, as appropriate.
h. If more than one item is shown on submittal sheet, identify item.
D. Deviations: Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.
E. Additional Copies: Unless additional copies are required for final submittal, and unless CO observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.
F. Use for Construction: Use only final submittals with mark indicating action taken by CO in connection with construction.
1.3 MEASUREMENT AND PAYMENT
A. No separate measurement and/or payment will be made for this section. Payment shall be included with work shown in the schedule of items.
PART 2 - PRODUCTS
2.1 ACTION SUBMITTALS – (Submittals requiring CO approval)
A. General: Prepare and submit Action Submittals required by individual Specification Sections.
1. Number of Copies: Submit one (1) electronic copy of each submittal in pdf format, unless otherwise indicated. CO will return one (1) electronic copy. Mark up and retain one returned copy as a Project Record Document.
B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer's written recommendations.
b. Manufacturer's product specifications.
c. Manufacturer's installation instructions.
d. Manufacturer's catalog cuts.
e. Wiring diagrams showing factory-installed wiring.
f. Compliance with recognized trade association standards.
g. Compliance with recognized testing agency standards.
C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.
1. Preparation: Include the following information, as applicable:
a. Dimensions.
b. Identification of products.
c. Fabrication and installation drawings.
d. Roughing-in and setting diagrams.
e. Wiring diagrams showing field-installed wiring, including power, signal, and control wiring.
f. Notation of dimensions established by field measurement.
2. Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring.
D. Contractor's Construction Schedule: The contractor shall submit a Construction Schedule, for approval by CO, in accordance with the contract provisions within 3 days after receiving notice to proceed.
E. Samples: Prepare physical units of materials or products, including the following:
1. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.
2.2 INFORMATIONAL SUBMITTALS – (Submittals NOT requiring CO approval)
A. General: Prepare and submit Informational Submittals required by other Specification Sections.
1. Number of Copies: Submit one (1) electronic copy of each submittal, unless otherwise indicated. CO will not return copies.
2. Certificates and Certifications: Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.
3. Test and Inspection Reports: Comply with requirements in Section 014100 "Quality Control."
B. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements.
C. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements.
D. Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment.
E. Manufacturer's Instructions: Prepare written or published information that documents manufacturer's recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer.
PART 3 - EXECUTION
3.1 GENERAL
A. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to CO.
B. Submittals not required by the Contract Documents will not be reviewed and may be discarded.
C. Substitutions – Whenever materials, products, and equipment are listed by name or brand in the specifications and/or on the drawings, it is used as a measure of quality, utility, or standard. If the Contractor prefers to use any other brand or manufacturer of same quality, appearance and utility to that specified, the Contractor shall request substitution as provided below, not less than ten (10) days before the planned installation of the item.
The Contracting Officer will approve or disapprove the request for substitution.
D. Requests for substitutions will only be considered if contractor submits the following:
1. Complete technical data including drawings, complete performance specifications, test data, samples and performance tests of the article proposed for substitution.
Submit additional information if required by Contracting Officer. All items in the above information shall be circled, tagged, or marked in some way to indicate all deviations or differences which the proposed item differs from the originally specified item.
2. Similar data as above for item originally specified. All items shall be marked to identify where/how the proposed substitution will differ.
3. A statement by the Contractor that the proposed substitution is in full compliance with the contract documents, applicable codes, and laws.
4. The Contractor shall be responsible for any effect upon related work in the project for any substitution and shall pay any additional costs generated by any substitutions.
3.2 SUBMITTAL SCHEDULE – Submittals shall be made as required by and called for in the drawings and specifications. The following table is a summary of the required submittals for the project - the table is to assist the Contractor and may not be all inclusive
– additional submittals may be required by specific specifications:
A.
TABLE 013000-1
Spec.
Section Section Title Subse ction Required Submittal
C General Specifications 1.4 A Traffic Control Plan
Spec.
Section Section Title Subse ction Required Submittal
013300 Submittal Procedures 2.1 D Construction Schedule 014100 Quality Control 1.3 A Contractor quality control plan 014100 Quality Control 1.3 B Permits, Licenses, and Certificates 014100 Quality Control 1.3 C Test and inspection reports 023701 Sediment and Erosion Control 1.2 A Sediment and Erosion Control
Plan 023701 Sediment and Erosion Control 1.2 B Product Data 024116 Structure Demolition 1.4 A Engineering Survey 024116 Structure Demolition 1.4 B Proposed Protective Measures 024116 Structure Demolition 1.4 C Schedule of Building Demolition
Activities 024116 Structure Demolition 1.4 D Pre-Demolition Photos 024116 Structure Demolition 1.5 A Closeout Survey 321200 Hot Mix Asphalt Paving 1.2 A Product Data 321200 Hot Mix Asphalt Paving 1.2 B Job-Mix Designs 321200 Hot Mix Asphalt Paving 1.2 C Material Certificates 321204 Crushed Aggregate Base or Surface
Course
1.2 A Aggregate – Source, Gradation, Material Properties
END OF SECTION 013300
LOWER FALLS CG TOILET REPLACEMENT PROJECT
SECTION 014100 - QUALITY CONTROL
PART 1 - GENERAL
1.1 This work shall consist of providing quality control in conformance with the inspection, testing, and product certification requirements of this contract to ensure compliance with the drawings and specifications. The Contractor shall provide all personnel, equipment, tests, and reports necessary to meet the requirements of the contract.
1.2 QUALITY CONTROL
A. The Contractor shall provide and maintain a quality control system that will ensure all services, supplies, and construction work required under this contract conforms to the contract requirements. The Contractor shall perform, or cause to be performed, the sampling, inspection, and testing required to substantiate that all services, supplies, and construction conform to the contract requirements.
B. Special Tests and Inspections: Contractor will engage a testing agency to conduct required special tests and inspections. The Contractor shall authorize the testing agency to perform the required testing and inspections on the work completed. The authority shall include:
1. Testing agency will interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from the Contract Documents.
2. Testing agency will re-test and re-inspect corrected work.
C. Re-testing/Re-inspecting: Contractor shall provide quality-control services for retesting and re-inspection for replaced construction work or for work that failed to comply with the requirements under the contract.
1.3 SUBMITTALS
A. Contractor Quality Control Plan
B. Permits, Licenses, and Certificates
C. Test and Inspection Reports
1.4 MEASUREMENT AND PAYMENT
A. No separate payment will be made for the work included under this section; rather payment shall be considered to be included in the items of work listed in the Schedule of Items.
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION
3.1 QUALITY CONTROL SYSTEM
A. General: Perform required testing, inspections, sampling, and similar services per direction specified in the contract drawings and specifications and in accordance with established industry standards.
3.2 CONTRACTOR QUALITY CONTROL PLAN
A. At the time of the preconstruction conference, the Contractor shall submit for approval a written Contractor Quality Control Plan.
1. If the plan requires any revisions or corrections, the Contractor shall resubmit the plan within 3 days.
2. The Government reserves the right to require changes in the plan during the contract period as necessary.
3. No change in the approved plan may be made without written concurrence by the Contracting Officer.
4. At a minimum, the plan shall include the following:
a. A list of personnel responsible for quality control and assigned duties.
Include each person's qualifications.
b. A copy of a letter of direction to the Contractor's Quality Control Supervisor outlining assigned duties.
c. Names, qualifications, and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms.
d. Methods of performing, documenting, and enforcing quality control of all work.
e. Methods of monitoring and controlling environmental pollution and contamination as required by all applicable regulations and laws.
3.3 TEST AND INSPECTION REPORTS
A. Submit one (1) electronic copy of complete test results no later than two (2) calendar days after the test was performed.
B. Submit failing test results at the end of each work day, and proposed remedial actions for the noted deficiency. If failing test results were remedied on the same day, also provide at the end of each work day any documentation to prove those results.
C. Testing and Inspection Reports shall include the following:
1. Date of issue.
2. Project title and number.
3. Name, address, and telephone number of testing agency.
4. Dates and locations of samples, tests, or inspections.
5. Names of individuals performing tests and inspections.
6. Reference Specification Section(s).
7. Complete test or inspection data.
8. Test and inspection results and an interpretation of test results.
9. Ambient conditions at time sample was taken, tested, or inspected.
10. Comments or professional opinion on whether tested or inspected work complies with the Contract Document requirements.
11. Name and signature of laboratory inspector.
12. Recommendations on re-testing and re-inspecting.
3.4 PERMITS, LICENSES, AND CERTIFICATES
A. For Contracting Officer’s records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations relevant to the on performance of the work.
3.5 AS-BUILT DRAWINGS
A. The Contractor shall maintain a set of the contract drawings depicting as-built conditions.
These drawings shall be maintained in a current condition and shall be available for review. All variations from the original contract drawings shall be indicated in red on the drawings. Upon completion of the contract work, as-built drawings shall be submitted to the Contracting Officer.
3.6 SAMPLING, TESTING, AND CERTIFICATION REQUIREMENTS
A. Sampling, testing, and Certification requirements and frequency for specific items shall be as specified in the drawings and specification. The following table is a summary of the required sampling, testing, and certification for the project - the table is to assist the Contractor, but may not be all inclusive – additional submittals may be required by specific specification section:
B.
TABLE 014100-1
Item
Subsection Certification or Test Required
Frequency
312000 3.15A Compaction Test – Subgrade under buildings
One test per building (vault)
312000 3.18C Compaction Test – Backfill/Fills under Buildings
One test every 600 S.F. area per lift, minimum of one test per building
312225 1.3B Moisture-Density Relationship One Test for Each Soil Type
Encountered
END OF SECTION 014100
SECTION 023701 - SEDIMENT AND EROSION CONTROL MEASURES
PART 1 - GENERAL
1.1 The work under this section consists of furnishing all necessary labor, equipment, materials, and performing all operations in connection with construction sediment and control measures.
A. General
1. All erosion and sediment control measures are to be placed prior to any disturbance caused by grading and or excavation and shall conform to the requirements of the appropriate regulatory agency for the State.
2. The Contractor shall be solely responsible for ensuring that erosion and sediment control measures are implemented and maintained at the site.
3. Soil disturbing activities include but are not limited to: Clearing and grubbing, excavation for utilities and foundations, roadway and parking lot construction, construction or modification of site drainage, grading, and preparation for final seeding.
4. All products shall be certified weed-free.
1.2 SUBMITTALS
A. The Contractor shall be required to submit a sediment and erosion control plan in accordance with this specification for approval by the Contracting Officer 3 days after receiving the notice to proceed.
B. Product data, including weed-free certification.
1.3 MEASUREMENT AND PAYMENT
A. No separate measurement and/or payment will be made for this section. Payment shall be included with work shown in the schedule of items.
PART 2 - PRODUCTS
2.1 SYNTHETIC FILTER FABRIC FOR SILT FENCES.
A. Pervious sheet of polypropylene, nylon, or polyethylene fabric conforming to the following physical and hydraulic characteristics:
• Physical Properties
(Min.)
Requirement Test Method
• Grab Tensile, lbs. W120/F100 ASTM-D-4632
• Grab Elongation, % 15 ASTM-D-4632
• Mullen Burst, psi 275 ASTM-D-3786
• Puncture, lbs. 65 ASTM-D-4833
• Trapezoidal Tear, lbs. 50 ASTM-D-4533
• UV Resistance, % 80 ASTM-D-4355
• AOS, US Sieve # 30/40 ASTM-D-4751
• Permittivity gal/min-sq. ft. 90 ASTM-D-4491
B. Filter fabric should contain ultraviolet ray inhibitors and stabilizers to provide a minimum of 6 months of expected usable construction life at a temperature range of 0 to 120 F.
C. Support Posts: 4 foot - 2 x 2 wood.
2.2 STRAW BALES
A. Oat or wheat straw, free from weeds, viable weed seeds, foreign matter detrimental to plant life, and dry.
1. Grass hay bales are not acceptable.
2. In order to prevent deterioration of the bindings, all bales shall be either wire-bound or string-tied so that bindings are oriented around the sides rather than along the tops and bottoms of the bales.
2.3 STRAW WATTLES OR ROLLS
A. Furnish straw wattles or rolls that are manufactured from weed free straw and wrapped in a tubular photodegradable plastic netting made from 85% high density polyethylene, 14% ethyl vinyl acetate and 1% color for UV inhibition. Conform to the following:
1. Diameter 9 inches min.
2. Netting strand thickness 0.030 inches
3. Netting knot thickness 0.055 inches
4. Mass of netting 0.315 to 0.385 ounces per foot
PART 3 - EXECUTION
3.1 CONSTRUCTION
A. Install straw bales at local drainage ways to prevent silt intrusion upon adjacent drainage courses. Remove straw bales following establishment of vegetation cover and utilize as mulch at swales or on steep slopes.
B. Prior to construction, install silt fence along the downhill construction limits to prevent silt intrusion upon adjacent land.
C. Install sediment and erosion control measures on the down slope toe of all top soil stock piles, and primarily downslope of all ground disturbance just outside the clearing limits and work areas.
D. Maintain and remove all erosion controls as specified.
E. Temporary seeding shall be placed on exposed surfaces that will not be brought to final grading or permanent cover treatment within 30 days of the exposure to reduce erosion and sedimentation by stabilizing exposed soils. Seeded areas shall be checked regularly for bare spots, washouts, and healthy growth to assure that a good stand of grass is being maintained. Reseed areas that fail to establish vegetation cover as soon as such areas are identified.
3.2 DUST CONTROL
A. In areas subject to surface and air movement of dust, where on-site or off-site damage is likely to occur, one or more of the following preventive measures shall be taken for dust control:
1. Minimize the period of soil exposure through the use of temporary ground cover and other temporary stabilization practices.
2. Sprinkle the site with water until surface is wet. Repeat as needed.
3.3 SILT FENCE
A. Silt fences are appropriate for the following general locations:
1. Immediately upstream of the point(s) of runoff discharge from a site before flow becomes concentrated. Below disturbed areas where runoff may occur in the form of overland flow.
2. Along the down slope toe of all top soil stock piles.
B. Materials.
1. Utilize standard strength synthetic filter fabric for sediment barriers. The filter fabric shall be purchased in a continuous roll cut to the length of the barrier to avoid the use of joints. When joints are necessary, filter cloth shall be spliced together only at a support post, with a minimum 6 inch overlap, and securely sealed.
2. The standard strength filter fabric shall be stapled or wired to the fence and 6 inches of the fabric shall be extended into the ground. Filter fabric shall not be stapled to existing trees.
3. Support posts shall be spaced at a maximum 6 feet and driven securely into the ground a minimum of 24 inches.
4. Filter fabric shall be buried a minimum of 12 inches.
5. The height of a silt fence shall not exceed 36 inches. Higher fences may impound volumes of water sufficient to cause failure of the structure.
C. Maintenance.
1. Silt fences and filter barriers shall be inspected immediately after each rainfall and at least daily during prolonged rainfall.
2. Silt fences shall be inspected for depth of sediment, tears, and to see if the fabric is securely attached to the fence posts, and to see that the fence posts are firmly in the ground. Any deficiencies shall be repaired immediately.
3. Should the fabric on a silt fence of filter barrier decompose or become ineffective prior to the end of the expected usable life and the barrier still be necessary, the fabric shall be replaced promptly.
4. Sediment deposits should be removed after each storm event and/or when deposits reach approximately 1/3 the height of the barrier or when the sediments limit or prevent the flow of water through the fabric hydraulic.
5. Any sediment deposits remaining in place after the silt fence or filter barrier is no longer required shall be dressed to conform with the existing grade, prepared, and seeded.
3.4 STRAW BALE EROSION CONTROL FENCE
A. Straw bale erosion control fences are appropriate for the following general locations:
1. Sheet flow applications: Straw bales shall be placed in a single row, lengthwise on the contour with ends of adjacent bales tightly abutting one another.
2. Channel flow applications: Straw bales shall be placed in a single row, lengthwise and oriented perpendicular to the direction of flow with ends of adjacent bales tightly abutting one another. The barrier shall be extended to such a length that the bottoms of the end bales are higher in elevation than the top of the lowest middle bale to assure that sediment laden runoff will flow either through or over the barrier but not around it.
B. The barrier shall be entrenched and backfilled. A trench shall be excavated the width of a bale and the length of the proposed barrier to a minimum depth of 4 inches. After the bales are staked and chinked, the excavated soil shall be backfilled against the barrier.
Backfill shall conform to the ground level of the downhill side and shall be built up to 4 inches against the uphill side of the barrier.
C. Each bale shall be securely anchored by at least 2 stakes or rebar driven through the bale.
The first stake in each bale shall be driven toward the previously laid bale to force the bales together. Stakes or rebar shall be driven a minimum of 12 inches into the ground or deep enough into the ground to securely anchor the bales, whichever is greater.
D. The gaps between bales shall be chinked (filled by wedging with straw to prevent water from escaping between the bales). Loose straw scattered over the area immediately uphill from a straw bale barrier tends to increase barrier efficiency.
3.5 STRAW WATTLE OR ROLL
A. Straw wattles shall be installed in accordance to manufacturer’s installation guidelines.
B. At a minimum:
1. The wattle shall be entrenched and backfilled. A trench shall be excavated the width of the straw waddle and the length of the proposed barrier to a depth of 2-3 inches.
2. Each wattle shall be securely anchored by at least one 18-24 inch stake every 3-4 feet and with a stake on each end. Stakes shall be driven perpendicular to slope face through the middle of the wattle until 2-3 inches remains exposed above the waddle.
3. After the wattles are staked, compact excavated soil against the uphill side of the barrier.
4. Adjacent wattles should tightly abut.
3.6 MAINTENANCE
A. Inspection shall be frequent and repair or replacement shall be made promptly as needed.
Straw bale carriers shall be removed when they have served their usefulness, but not before the upslope areas have been permanently stabilized.
END OF SECTION 023701
SECTION 024100 - WASTE MATERIAL DISPOSAL
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the loading, handling, hauling, and placing of excess excavation material, unsuitable excavation material, clearing and grubbing debris, and construction and demolition debris.
1.2 MEASUREMENT AND PAYMENT
A. There will be no separate measurement or payment for work in this Section. Waste material disposal is considered incidental to other items of work shown in the Schedule of Items.
PART 2 - PRODUCTS – NOT APPLICABLE
PART 3 - EXECUTION
3.1 WASTE MATERIAL TO BE HAULED TO A DISPOSAL AREA
A. The following items shall be hauled to the disposal area shown on the drawings:
1. All excavated material not used in the construction of embankments or backfilling of trenches, or other excess material resulting from the excavation and embankment operation.
2. All unsuitable excavated material and oversize boulders
3. All stumps, slash, wood and other clearing and grubbing debris.
B. Disposal Area: The disposal area shall be located on Forest Road 8303, at milepost 2.78.
1. Trees designated for removal shall be cut into 12 inch lengths and removed off Forest.
2. Stumps of all tree species designated for removal shall be completely removed offsite and taken to the designated disposal site.
3.2 WASTE MATERIAL TO BE HAULED TO A LANDFILL
A. All demolition materials, garbage, and other refuse generated shall be removed from the project site and legally disposed off Government property in an approved landfill. Refer to Section 024116 “Structure Demolition”.
B. The contractor is responsible for all costs and permits associated with landfill disposal.
C. The Government is not responsible for waste material upon its departure from the project site.
3.3 MATERIALS TO BE SALVAGED
A. Items designated in the drawings for salvage shall be stored onsite in accordance with Section 024116 “Structure Demolition”.
END OF SECTION 024100
SECTION 024116 – STRUCTURE DEMOLITION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Demolition and removal of buildings and site improvements.
2. Removing below-grade construction.
3. Disconnecting, capping or sealing, and removing site utilities.
1.2 MATERIALS OWNERSHIP
A. Unless otherwise indicated, demolition waste becomes property of Contractor.
B. Historic items, relics, antiques, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques and tablets, and other items of interest or value to Owner that may be uncovered during demolition remain the property of Owner.
1. Carefully salvage in a manner to prevent damage and promptly return to Owner.
1.3 PRE-DEMOLITION MEETINGS
A. Pre-demolition Conference: Conduct conference at Project site.
1.4 SUBMITTALS
A. Engineering Survey: Submit engineering survey of condition of building.
B. Proposed Protection Measures: Submit report, including Drawings, that indicates the measures proposed for protecting individuals and property; and for environmental protection, noise control, and dust control. Indicate proposed locations and construction of barriers.
1. Adjacent Buildings and Site Improvements: Detail special measures proposed to protect adjacent buildings and site improvements to remain.
C. Schedule of building demolition activities with starting and ending dates for each activity.
D. Pre-demolition photographs and/or video.
1.5 CLOSEOUT SUBMITTALS
A. Inventory of items that have been removed and salvaged.
1.6 QUALITY ASSURANCE
A. Hazardous Waste Recovery Technician Qualifications: Certified by EPA-approved certification program.
1.7 FIELD CONDITIONS
A. Buildings to be demolished will be vacated and their use discontinued before start of the Work.
B. Conditions existing at time of inspection for bidding purpose will be maintained by Owner as far as practical.
1. Before building demolition, Owner will remove the following items:
a. No contents of the existing buildings will be removed.
C. Hazardous Materials: It is not expected that hazardous materials will be encountered in the Work.
1. If materials suspected of containing hazardous materials are encountered, do not disturb; immediately notify the Contracting Officer.
D. Composting Materials:
1. Dispose human waste at a suitable waste disposal site, in accordance with state, local and federal environmental requirements.
E. On-site storage or sale of removed items or materials is not permitted.
F. Arrange demolition schedule so as not to interfere with Owner's on-site operations.
1.8 MEASUREMENT AND PAYMENT
A. Measurement shall be for each (EA) structure demolished, including the removal and proper disposal of all materials off the project site.
B. Site Improvements designated for removal and disposal or salvage shall be lump sum (LS).
PART 2 - PRODUCTS
2.1 PERFORMANCE REQUIREMENTS
A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.
B. Standards: Comply with ANSI/ASSE A10.6 and NFPA 241.
2.2 SOIL MATERIALS
A. Satisfactory Soils: Comply with requirements in Section 312000 "Earth Moving."
PART 3 - EXECUTION
3.1 EXAMINATION
A. Verify that utilities have been disconnected and capped before starting demolition operations.
B. In accordance with OSHA regulations, perform an engineering survey of condition of building to determine whether removing any element might result in structural deficiency or unplanned collapse of any portion of structure or adjacent structures during building demolition operations.
C. Inventory and record the condition of items to be removed and salvaged.
3.2 PREPARATION
A. Salvaged Items: Comply with the following:
1. Clean salvaged items of dirt and demolition debris.
2. Pack or crate items after cleaning. Identify contents of containers.
3. Store items in a secure area until delivery to Owner.
4. Transport items to storage area designated by Owner or as indicated on Drawings.
5. Protect items from damage during transport and storage.
3.3 UTILITY SERVICES AND MECHANICAL/ELECTRICAL SYSTEMS
A. Existing Utilities to be disconnected: No water, gas or electrical utilities serve these buildings.
3.4 PROTECTION
A. Existing Facilities & Site Improvements: Protect adjacent walkways, loading docks, building entries, and other building facilities during demolition operations. Maintain exits from existing buildings.
B. Temporary Shoring: Provide and maintain interior and exterior shoring, bracing, or structural support to preserve stability and prevent unexpected movement or collapse of construction being demolished.
C. Temporary Protection: Erect temporary protection, such as walks, fences, railings, canopies, and covered passageways, where required by authorities having jurisdiction and as indicated.
1. Protect adjacent buildings and facilities from damage due to demolition activities.
2. Protect existing site improvements, appurtenances, and landscaping to remain.
3. Erect a plainly visible fence around drip line of individual trees or around perimeter drip line of groups of trees to remain.
4. Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.
5. Provide protection to ensure safe passage of people around building demolition area and to and from occupied portions of adjacent buildings and structures.
D. Remove temporary barriers and protections where hazards no longer exist. Where open excavations or other hazardous conditions remain, leave temporary barriers and protections in place.
3.5 DEMOLITION
A. General: Demolish indicated buildings and site improvements completely. Use methods required to complete the Work within limitations of governing regulations and as follows:
1. Do not use cutting torches until work area is cleared of flammable materials. Maintain portable fire-suppression devices during flame-cutting operations.
2. Maintain fire watch during and for at least 4 hours after flame-cutting operations.
3. Maintain adequate ventilation when using cutting torches.
4. Locate building demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing.
B. Site Access and Temporary Controls: Conduct building demolition and debris-removal operations to ensure minimum interference with roads, walks, walkways, and other adjacent occupied and used facilities.
1. Do not close or obstruct roadways, walks, walkways, or other adjacent occupied or used facilities without permission from Owner and authorities having jurisdiction.
Provide alternate routes around closed or obstructed traffic-ways if required by authorities having jurisdiction.
2. Use water mist and other suitable methods to limit spread of dust and dirt. Comply with governing environmental-protection regulations.
C. Explosives: Use of explosives is not permitted.
D. Proceed with demolition of structural framing members systematically, from higher to lower level. Complete building demolition operations above each floor or tier before disturbing supporting members on the next lower level.
E. Remove debris from elevated portions of the building by chute, hoist, or other device that will convey debris to grade level in a controlled descent.
F. Salvage: Items designated for salvage shall be placed where designated on the drawings.
Items to be removed and salvaged are indicated below:
1. Rock Curbing
2. Fee tubes
G. Existing Utilities: No utilities are located at the buildings designated for demolition.
H. Below-Grade Areas: Completely fill below-grade areas and voids resulting from building demolition operations with satisfactory soil materials according to backfill requirements in Section 312000 "Earth Moving."
I. Site Grading: Uniformly rough grade area of demolished construction to a smooth surface, free from irregular surface changes. Provide a smooth transition between adjacent existing grades and new grades.
J. Promptly repair damage to adjacent buildings and site improvements caused by demolition operations.
3.6 CLEANING
A. Remove demolition waste materials from Project site and dispose of them at an EPA-approved construction and demolition waste landfill acceptable to authorities having jurisdiction, and recycle or dispose of them in accordance to State, Local, and Federal regulations."
B. Do not burn demolished materials.
C. Clean adjacent structures and site improvements of dust, dirt, and debris caused by building demolition operations. Return adjacent areas to condition existing before building demolition operations began.
END OF SECTION 024116
SECTION 027070 – TEMPORARY CONSTRUCTION CHAIN LINK FENCE
PART 1 - GENERAL
1.1 SUMMARY
A. The work under this Section includes providing all labor, materials, tools and equipment necessary for furnishing and installing chain link fencing, as described in Section C.
1.2 MEASUREMENT AND PAYMENT
A. Payment shall have a unit price of “Lump Sum.” Note, each line item is for a two-week supply period. Once the Forest Service begins awarding this line item, the contractor will continue to provide this service to the end of the project, resulting in the potential for multiple line items to be awarded. The Forest Service will not expect the contractor to deliver, remove, and re-deliver the Chain Link Fencing.
1. This item is currently listed as an Optional Bid Item, as the Forest Service currently does not know if the site will be able to be open to the public during construction, based upon the current COVID-19 situation. As a note, the initial design/plan was to have sections of the site open to the public throughout the duration of the project.
PART 2 - PRODUCTS
2.1 CHAIN LINK FENCING
A. MATERIALS
1. Sizes of posts, gate frames, rails and braces shall be 1-1/4” nominal pipe size.
2. Posts. All posts shall be tubular, unless another construction chain link fencing is available.
3. Wire. The wire shall not be less than seven gauge plus, or minus 0.005-inch in diameter, unless another construction chain link fencing is available.
4. Post Supports. The fence system must be supported with a movable metal base.
5. Fence Height. Meet construction chain link fencing standards.
PART 3 - EXECUTION
3.1 GENERAL
A. All trees, brush, and other obstacles that would interfere with the installation of the fence shall be removed and disposed. It is currently assumed that large obstacles will not be encountered.
B. Prior to installing the fence, the existing ground along the line of the fence location shall be graded to a smooth, uniform surface, to the extent that no abrupt changes in grade exist between adjacent fence posts. After the removal of the fencing at the end of the project, the landscape must be returned to its prior condition.
C. The posts shall be set vertical and shall be of uniform, within reason to maintain integrity, and equal height above the ground, with a maximum horizontal spacing of ten feet, center-to-center.
END OF SECTION 027070
APRIL 2020
SECTION 027071 – TEMPORARY PORTA-POTTIES
PART 1 - GENERAL
1.1 SUMMARY
A. This section applies to the supply, placement, and weekly servicing of all porta-potties.
1.2 MEASUREMENT AND PAYMENT
A. Payment shall have a unit price of “Lump Sum.” Note, each line item is for a two-week supply period. Once the Forest Service begins awarding this line item, the contractor will continue to provide this service to the end of the project, resulting in the potential for multiple line items to be awarded. The Forest Service will not expect the contractor to deliver, remove, and re-deliver the Porta-Potties.
1. This item is currently listed as an Optional Bid Item, as the Forest Service currently does not know if the site will be able to be open to the public during construction, based upon the current COVID-19 situation. As a note, the initial design/plan was to have sections of the site open to the public throughout the duration of the project.
PART 2 - PRODUCTS
2.1 PORTA-POTTIES
A. The Contractor is expected to supplies industry standard porta-potties. The contractor shall provide the following listed below at the respective sites:
1. Ape Cave:
a. Upper Parking Lot: Two (2) Standard and one (1) ADA compliant.
b. Lower Parking Lot: Two (2) Standard and one (1) ADA compliant.
2. Trail of Two Forests:
a. Parking Lot: One (1) Standard and one (1) ADA compliant.
2.2 CRUSHED AGGREGATE LEVELING COURSE
A. According to Section 321204 “Crushed Aggregate Base or Surface Course.
PART 3 - EXECUTION
3.1 GENERAL
A. The Contractor must follow the scheduling stated within Section C.
B. It is expected that the Contractor will be responsible for pumping out of the septic waste (servicing) from the porta-potties every week, due to the amount of people that will be using the porta-potties during the contract time. The servicing must occur no sooner than Wednesday evening or no later than Thursday evening.
C. The Forest Service will accomplish daily cleaning and stocking of the porta-potties.
END OF SECTION 133401
SECTION 133401 - PRECAST CONCRETE VAULT RESTROOM
PART 1 - GENERAL
1.1 SUMMARY
A. This section applies to the fabrication of a precast concrete Vault Restroom building, including shipment to site, all work necessary to completely fabricate, and installation of other manufactured accessories needed or specified in this section for a complete Vault Restroom.
B. Related sections include the following:
1. Section 024100 Waste Material Disposal
2. Section 133460 Comfort Station Installation
3. Section 311000 Site Clearing
4. Section 312000 Earth Moving
5. Section 321204 Crushed Aggregate Base or Surface Course
1.2 MEASUREMENT AND PAYMENT
A. There will be no separate payment for work associated with this section.
PART 2 - PRODUCTS
2.1 PRECAST VAULT RESTROOM
A. Vault restroom, double unit with chase; model: Rocky Mountain, manufactured by CXT Incorporated. Shall be furnished and installed by the Forest Service. There are two (2) designated for Ape Cave.
B. Vault restroom, double unit without chase; model: Rocky Mountain, manufactured by CXT Incorporated. Shall be furnished and installed by the Forest Service. There is one
(1) designated for Trail of Two Forests.
2.2 CRUSHED AGGREGATE LEVELING COURSE
A. According to Section 321204 “Crushed Aggregate Base or Surface Course.
PART 3 - EXECUTION
3.1 COORDINATION
A. The Forest Service is responsible for furnishing and placing the vault comfort stations, including each vault.
B. The Contractor shall be responsible for having the foundation pad prepared prior to the installation of the new comfort station, which includes the removal of the existing comfort station, and backfilling the subgrade void left after the existing comfort station is removed. Refer to Section 133460 for details.
C. The Forest Service shall have a purchase order in place prior to the award of this contract and have the new comfort stations ready for installation no later than May 6th, 2020.
D. The contractor and Forest Service shall coordinate schedules at the pre-work meeting;
Contractor shall be responsible for providing projected completion date for all foundation preparation work, and the Forest Service shall provide the contractor an update on the fabrication schedule, and the projected date of installation.
END OF SECTION 133401
SECTION 133460 - PRECAST CONCRETE VAULT RESTROOM INSTALLATION
PART 1 - GENERAL
1.1 SUMMARY
A. This item shall consist of site grading and foundation (subgrade) preparation for precast concrete vault comfort stations, including the re-grading all areas at former comfort station locations. Work also includes construction all aggregate and asphalt surfaced aprons on all sides of the building, and excavation, backfill and leveling course for vaults, and installation of native surface pathways adjacent to newly installed comfort stations.
1.2 RELATED WORK
A. The work shall be in accordance with the following subsidiary specifications. The subsidiary specifications are referred to in the text by the Section designation only.
1. Section 311000 Clearing and Grubbing
2. Section 312000 Earthwork
3. Section 312010 Select Borrow
B. All backfilling and finish grading shall be the contractor’s responsibility and be part of this work.
1.3 MEASUREMENT AND PAYMENT
A. Payment shall be for each comfort station (EACH) installed, which includes the required excavation for precast concrete vaults, placement of aggregate leveling course, backfill around installed vaults, and aggregate and asphalt surfaced aprons around each side of the comfort station.
2.1 CLASSIFICATION
A. Excavation will be unclassified as to materials and shall include all materials which are encountered in the required excavation.
2.2 BACKFILL AND EMBANKMENT MATERIAL FOR FOUNDATION PAD
(COMFORT STATION SUBGRADE)
A. The backfill shall be a commercial crushed aggregate in accordance with Section 321204 “Crushed Aggregate Base or Course”.
1. Commercial crushed aggregate shall be used to backfill around vaults, after placement
2.3 CRUSHED AGGREGATE LEVELING COARSE
A. According to Section 321204 “Crushed Aggregate Base or Course”.
3.1 SCHEDULING
A. Refer to Section C and Section 133401 “Precast Concrete Vault Restroom” for details on scheduling.
3.2 CLEARING AND GRUBBING
A. Before starting any site preparation and grading, the Contractor shall have completed all necessary clearing and grubbing within the specified working limits, in accordance with Section 311000 “Clearing and Grubbing”.
3.3 CONSERVING TOPSOIL
A. Topsoil shall be removed from the area to be excavated and from the area where excavated material will be piled prior to excavating. Topsoil shall be kept separate from excavated material. Topsoil will be reused on those areas from which it came after backfilling and embankment construction is complete.
3.4 SAFETY, SHORING, AND PROTECTION
A. The Contractor shall meet the prescribed safety rules and regulations. If personnel are expected to work inside excavations, contractor shall work in accordance with OSHA regulations. All existing improvements, either on public or private property, will be fully protected from damage. If support bracing is used, it shall be removed after construction is completed and shall be withdrawn in a manner that will prevent the collapse of the sides of the excavation. All openings in the ground, caused by the removal of supports, shall be filled with suitable material properly compacted.
3.5 REMOVAL OF WATER
A. The Contractor shall provide and maintain, at all times during construction, ample means and devices with which to promptly remove and properly dispose of all water entering the excavations or other parts of the work without damage to adjacent property. All excavations shall be kept free from standing water. Any damage caused by water in the excavation shall be repaired by the Contractor at his expense.
3.6 EXCAVATION, BACKFILL, AND SITE GRADING
A. Coordination with the Manufacturer - The contractor shall be required to coordinate with the manufacturer of the comfort stations to accommodate installation at the time of delivery. The Contractor will be responsible for obtaining installation instructions from the manufacturer and perform the excavation, backfill, and site grading in accordance with those instructions. The Contractor must have excavation complete prior to delivery.
B. General - Excavation shall be performed by any acceptable method. Pile excavated material away from the ends of the hole to facilitate crane and delivery truck access. The crane and delivery truck typically need to be side-to-side during the placement.
1. The hole dug to accommodate the vaults shall be large enough to be workable and to allow the floor of the building to fit on the vaults when placed, but small enough to avoid excessive backfill after placement.
C. Foundation preparation – The contractor shall be responsible for constructing the foundation, including subgrade for sidewalks and aprons, to the lines and grades shown on the drawings, including backfilling void left after existing comfort stations and vaults are demolished. Backfills/fills for the foundation pad shall conform to the requirements in Section 312100 “Site Preparation and Grading”. Subgrade compaction shall be testing in accordance to Section 312000 “Earth Moving”.
1. Material used to fill the void left after vaults are removed shall be in accordance with Section 321204 “Crushed Aggregate Base and Leveling Course”.
2. If material below subgrade is determined to be unsatisfactory in accordance with these specifications, the contractor shall remove unsatisfactory material 2 feet below subgrade and replace with suitable import material. Placement and compaction shall be in accordance with Section 312225.
D. Gravel Leveling Base - The Contractor shall place a 6-inch thick leveled layer of gravel, prior to placement of the comfort station. Slope the top of the gravel 1% back to front and side to side out of the doorway. The goal is to have the containment area at the end of the vault to be slightly higher. Compaction shall be in accordance to Section 321204.
E. Backfill around buildings – The installer is not responsible for backfilling around the building after vaults and comfort stations have been placed. Backfill and embankments shall be layer placed 8-inches thick (loose measurement) and compacted with three (3) complete passes of an approved vibratory compactor. Backfill around the vaults until grades match adjacent elevations.
3.7 SIDEWALKS AND APRONS
A. Where shown on the drawings,…