1204R420Q0015 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
04R4
SPRINGFIELD OR 97477
3106 PIERCE PARKWAY SUITE D
WILLAMETTE NATIONAL FOREST
USDA FOREST SERVICE
01/17/20200002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
01/17/2020
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this amendment is to answer questions about the solicitation requirements.
Fifteen questions have been received. Questions 1-7 were answered on the previous amendment. The following page has answers for questions 8-15.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
NSN 7540-01-152-8070
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Question 8: There are 780 logs/trees and 12 sites depicted on the project maps. This is approximately 65 logs per site. Most stream projects are 10 or less logs/trees per stream placement site pending complexity. Is the intention to fill gaps between sites or actually put approximately 65 logs/trees per site as depicted?
Answer 8: Yes, these jams are considerably larger than usual. For example, the jams in the North Fork Willamette will be approx. 40-45 logs per jam. The jams in North Fork Winberry are smaller but still approximately 15-20 logs per jam.
Question 9: If filling gaps, can we be assured the upper and lower depicted sites are the limits?
Answer 9: Yes, the upper and lower sites are the start and stop points of the project area.
Question 10: The logs/trees are not available for review at the listed staging sites. Is there a % of size available (i.e.
X = 3000lbs +, X = 3000lbs -?)?
Answer 10: The ranger district did not break out log size in that manner. The only information available is the description provided in the solicitation.
Question 11: Two of the staging sites for Winberry appear to be very small/tight wide spots along the 1802 road, is this correct?
Answer 11: Yes, that is correct.
Question 12: What is the method of delivery and decking at staging sites for the logs/trees?
Answer 12: Self-loader log truck.
Question 13: Will the logs/trees be stacked/decked loosely to allow for choking? Would contractor need to provide equipment to shift logs/trees at staging sites?
Answer 13: Logs are specified to be stacked in a nature that allows easy choking.
Question 14: Does the USFS have proposed Service landings? Is it safe to plan for previously used Service LZs in the Pernot TS for the North Fork portion and Service LZ used for Blanket TS on the Winberry?
Answer 14: Yes, those landings are typically used for these projects as well. However, the ranger district will need to check with timber operations to make sure they are available when we fly this project.
Question 15: Will the contractor be allowed to cut danger trees in the stream site areas?
Answer 15: Yes, that will be allowed with the COR’s approval. The issue would need to be forwarded to the Contracting Officer if the COR does not approve, so that the issue can be resolved. All operations and safety under the awarded contract shall be the responsibility of the contractor.