Questions_&_Answers_for_Solicitation_1204R419Q0019.docx

DOCX document 14 KB Posted

Attached to
Conifer Tree Climbing & Conifer Cone Collection
Solicitation number
1204R419Q0019
Issued by

About this file

Questions & Answers for Solicitation 1204R419Q0019 Amendment 0001

View the file

Other files

File Type Posted
Q&A_1204R419Q0019_Amendment_0002.docx DOCX document
RFQ_1204R419Q0019_Amendment_0002.pdf PDF
RFQ_1204R419Q0019_Amendment_0001.pdf PDF
WBPContractsGreenMt.pdf PDF
Genetic Sites.pdf PDF
Fall viewing _cone collection.pdf PDF
WBPContractsYamsiMt.pdf PDF
WBPContractsGrizzly.pdf PDF
Fall viewing _cone collection2.pdf PDF
WBPContractsDrakePeak.pdf PDF
WBPContractsCraneMt.pdf PDF
WBPContractsGuyerCr.pdf PDF
WBPContractsPelicanButte.pdf PDF
WBPContractsAbertRim.pdf PDF
WBPContractsHagerMt.pdf PDF
General District Map.pdf PDF
WBPContractsDeadhorse.pdf PDF
WBPContractsBaldButte.pdf PDF
RFQ_1204R419Q0019.pdf PDF
Attachment2-R6-FS-6300-52.pdf PDF
Attachment1-WageDetermination.docx DOCX document
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions & Answers for Solicitation 1204R419Q0019

Question 1: Does item 6.3 of the schedule of items include climbing or is it just the caging? Or, would the tree need to be climbed and paid for under 6.1 to exercise 6.3 as implied in the relationship of 6.2 to 6.1? Or, is 6.1 applied every time the tree is climbed or once for both cone collecting and caging?

Answer 1: Item 6.3 is just for caging. If climbing is needed in order to cage, the contractor will be paid under 6.1 to climb, and paid under 6.3 to cage. Please note that item 8 will be removed because it is already covered under sub-item 6.3.

Question 2: Under Item 2; does “genetic site” = seed orchard? If so, what is the location(s) and what condition is it (are they) in (age, ht, competing vegetation, etc)?

Answer 2: Maps have been posted that identify potential sites, to include the genetic site. Genetic sites on the Forest are not equivalent to a well-groomed seed orchard that you would find at a nursery.

Question 3: Does platform under item 7 = boom truck or cherry picker? Are there any conforming specs or limitations?

Answer 3: No specifications are identified for item 7 other than safety operations. The contractor may choose their aerial platform, as long as the platform will not cause damage to the site, stand, or individual tree. A boom truck or cherry picker would be acceptable.

Question 4: For items 1 and 3-6 “natural stands” are tree locations spread throughout the several seed zones of each district?

Answer 4: Yes, there may be multiple seed zones across multiple districts.

Question 5: In the Work statement under 1.0 Introduction; are the estimated quantities for all seven districts for each year or for all seven districts for the 5 years of contract duration?

Answer 5: The estimates are the annual estimate needed for the entire Forest, assuming there was a viable crop each year.