Solicitation 12-046W-18-Q-0003
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Eagle_Creek_Suspension_Bridge_Removal_Site_Visit_Q&A.pdf | ||
| Updated_Description_of_Work_information.pdf | ||
| pre-bid_Attendance.pdf | ||
| Rail_drawings.docx | DOCX document | |
| Amendment_0002.pdf | ||
| R34601-ALL.PDF | ||
| General_Decision_Number_OR170001_9_22_2017.docx | DOCX document | |
| 2017_photos.pdf | ||
| Experience_Questionaire.docx | DOCX document | |
| 1997_crane_photos.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AT A MINIMUM, QUOTER SHALL SUBMIT THE FOLLOWING DOCUMENTS AS THEIR RESPONSE TO THIS
SOLICITATION:
1. SF-18 Request For Quotation (Complete, date, and sign)
2. Section B – Schedule of Items. (Complete Unit Price and Amount)
3. Section K – Representations and Certifications. (Complete the Representations and Certifications electronically via the System for Award Management (SAM) website at www.sam.gov)
4. Section J – Evaluation Exhibits
5. Acknowledgement of Amendment (If Any)
IT IS REQUIRED THAT YOU WRITE THE SOLICITATION NUMBER ON THE OUTSIDE OF YOUR
ENVELOPE.
Return to: MT. HOOD NATIONAL FOREST
ATTN: ROXANNE ANDERSON - CONTRACTING
16400 CHAMPION WAY
SANDY, OREGON 97055
Email to: rdanderson@fs.fed.us
IT IS REQUIRED THAT ALL CONTRACTOR’S BE REGISTERED IN THE SYSTEM FOR AWARD MANAGEMENT DATABASE
(SAM.GOV) PRIOR TO AWARD UNDER THIS SOLICITATION. SEE CLAUSE 52.204-7 SYSTEM FOR AWARD MANAGEMENT
FOR DETAILS ON HOW TO APPLY.
MT. HOOD NATIONAL FOREST INSTRUCTIONAL COVER SHEET
ISSUING OFFICE : U.S. DEPARTMENT OF AGRICULTURE
FOREST SERVICE – MT. HOOD NATIONAL FOREST
16400 CHAMPION WAY, SANDY, OREGON 97055
SOLICITATION NO .: 12-046W-18-Q-0003
QUOTES ARE SOLICITED FOR : EAGLE CREEK SUSPENSION BRIDGE REMOVAL AND DISPOSAL
SET - ASIDE : S MALL B USINESS S ET - A SIDE
IMPORTANT – NOTICE TO QUOTER :
mailto:rdanderson@fs.fed.us
REQUEST FOR QUOTATION
(THIS IS NOT AN ORDER)
THIS RFQ IS IS NOT A SMALL BUSINESS SET- ASIDE X
PAGE OF PAGES
1 40
1. REQUEST NO. 2. DATE ISSUED 3. REQUISITION/PURCHASE REQUEST NO. 4. CERT. FOR NAT.DEF. RATING
12-046W-18-Q-0003 11/03/2017 UNDER BDSA REG. 2
AND/OR DMS REG. 1
5a. ISSUED BY 6. DELIVER BY (Date) Mt. Hood National Forest, 16400 Champion Way, Sandy, OR 97055 See Contract Time
5b. FOR INFORMATION CALL (NO COLLECT CALLS) 7. DELIVERY FOB DESTINATION OTHER (See Schedule)
NAME
Roxanne Anderson –Contracting
David Strahl – Technical
TELEPHONE NUMBER X
AREA CODE
(503)
(503)
NUMBER
668-1730
808-2230
9. DESTINATION
a. NAME OF CONSIGNEE
Section C - Location & Description
8. TO:
a. NAME b. COMPANY b. STREET ADDRESS
c. STREET ADDRESS c. CITY
d. CITY e. STATE f. ZIP CODE d. STATE e. ZIP CODE
10. PLEASE FURNISH QUOTATIONS TO THE
ISSUING OFFICE IN BLOCK 5A ON OR
BEFORE CLOSE OF BUSINESS
IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in BLOCK 5A.
This request does not commit the Government to pay any costs incurred in the preparation of the Wed., November 22, 2017 no later than 1:00 p.m. PST submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this
Request for Quotations must be completed by the quoter.
11. SCHEDULE (Include applicable Federal, State and local taxes)
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
(a) (b) (c) (d) (e) (f)
EAGLE CREEK SUSPENSION BRIDGE
Removal and Disposal
Project Location: Columbia River Gorge National Scenic Area
This requirement is being procured as a fixed-price Simplified Acquisition.
Quotes received after the exact time specified for receipt of quotes will not be considered.
FACSMILE (FAX) WILL NOT BE ACCEPTED.
PLEASE PLACE YOU
R QUOTE IN
SECTION B- SC
HEDULE OF ITEMS
12. DISCOUNT FOR PROMPT PAYMENT
a. 10 CALENDAR DAYS (%)
b. 20 CALENDAR DAYS
c. 30 CALENDAR DAYS
d. CALENDAR DAYS
NUMBER PERCENTAGE
NOTE: Additional provisions and representations are not attached.
13. NAME AND ADDRESS OF QUOTER 14. SIGNATURE OF PERSON AUTHORIZED TO
SIGN QUOTATION
15. DATE OF
QUOTATION a. NAME OF QUOTER
DUNS # _________________ CAGE CODE ____________
b. STREET ADDRESS 16. SIGNER
a. NAME (Type or print) b. TELEPHONE
c. COUNTY AREA CODE
d. CITY
e. STATE f. ZIP CODE c. TITLE (Type or Print) NUMBER
NSN 7540-01-152-8084 18-121 STANDARD FORM 18 (Rev. 6-95) Previous edition not usable Prescribed by GSA-FAR (48 CFR) 53.215-1(a)
X are
PART I--THE SCHEDULE SECTION B--SUPPLIES OR SERVICES AND PRICES
EAGLE CREEK SUSPENSION BRIDGE REMOVAL AND DISPOSAL
Columbia River Gorge National Scenic Area
Hood River Ranger District
Mt. Hood National Forest
Multnomah County, Oregon
This solicitation and any resulting contract is a firm-fixed price type of contract, which under the definition in
FAR 16.202-1, “this type of contract provides for a price that is not subject to any adjustment on the basis of the contractor’s cost experience in performing the contract. This contract type places upon the contractor maximum risk and full responsibility for all costs and resulting profit or loss.”
Quoter’s shall submit a quote for all Base Items in the Schedule of Items. Failure to comply with the instructions may render your quote nonresponsive and ineligible for contract award.
Prices on the Schedule shall reflect Contractor’s full cost for materials, labor, supervision, overhead costs, and incidental items.
B- 1 - Schedule of Items BASE ITEM
Eagle Creek Suspension Bridge Removal
Pay
Item
Item Description Quantity Unit Unit Price Amount
15101
Mobilization
LS
20301
Removal of Structure and
Obstructions
LS
TOTAL AMOUNT QUOTED
* Designated Method of Measurement: LS - Lump Sum
B- 2: Quote on all items. Only quotes to the nearest cent will be accepted.
12-046W-18-Q-0003 Eagle Creek Suspension Bridge Removal and Disposal
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C- 1 - Project Description and Location
(a) Description of Work.
This work consists of removal and disposal of the Eagle Creek suspension Bridge and railing adjacent to approaches.
Furnish all labor, equipment, supplies, supervision, and transportation necessary to perform this contract. The bridge is a wire cable suspension bridge with steel suspenders attached to treated timber elements such as Needle Beams, Stringers, Deck and Railing. The Bridge partially collapsed in September of 2017 and was further damaged by a storm event mid-
October, 2017. The bridge was reconstructed in 1997 with Plans R34601-ALL attached for reference. Also included are photos of similar demolition by mobile crane removal from 1997 as well as 2017 photos of recent condition.
The upstream cable has failed near the northeast anchor block. The other main suspension cable remains suspending most of the failed structure but its condition and structural capacity is unknown. The northeast tower has rotated off 2 of the 3 pedestal supports and is unstable. All concrete foundations and anchor assemblies are to remain in place except for salvage of a single anchor assembly. All suspension cables, suspenders, hardware and pressure treated wood elements are to be removed and disposed of off National Forest System Lands.
Disassemble and remove in a manner that does not alter flowing water or scarify the stream channel, gravel bars, banks or flood plain. Machinery and debris shall not be allowed in the active stream. Use of the gravel bar for staging and by machinery is allowed if not covered in water. Any vegetation cleared from gravel bar to facilitate operations is to be slash piled in an area above the high water mark and approved by the CO. Likely east of the southwest tower location.
(b) Project Location.
The Eagle Creek Suspension Trail Bridge is located east of Portland, OR, and 0.2 miles southeast of exit 41 of I-84 at
Lat/Long: 45.639948, -121.923841. The rotated and failing northeast tower can be accessed by a paved 12 foot wide road that goes under the remaining back stay cable. The road terminates at the Eagle Creek Trailhead parking lot 0.3 miles beyond the bridge. There is a paved parking area with widened road just before the bridge site where a crane and out-riggers have previously staged for similar work.
The site is currently closed to the public. However, a site visit is scheduled to allow bidders access to the site to determine the scope & complexity of the project prior to bidding. It is anticipated that the site will remain closed to the public until after demolition is complete.
(c) Site Visit.
A site visit has been scheduled at the project location on Thursday, November 9, 2017; from 10am to
12pm. Contact the Technical Contact – David Strahl at (503)808-2230 or email: dstrahl@fs.fed.us for information pertaining to the site visit.
(d) Start Work.
It is estimated that work will begin on or shortly after Tuesday, December 5th, 2017. Upon issuance of the
Notice to Proceed.
mailto:dstrahl@fs.fed.us
(e) Period of Performance.
Full contract performance time from the Notice to Proceed to final inspection is estimated to be no more than 15 days.
C- 2 – Requirement of Items
ESTIMATION OF ITEMS.
Although not limited to, it is anticipated that removal is to be performed using a mobile crane. Contractor to verify all methods, weights, distances and clearances.
SPECIFICATIONS
15101 – MOBILIZATION
DESCRIPTION
Mobilization This work consists of moving personnel, equipment, material, and incidentals to the project and performing work necessary before beginning work at the project site. This work also includes obtaining permits, insurance, and bonds.
MEASUREMENT
Lump Sum. Do not measure directly. The bid amount is complete payment for all work described in the contract and necessary to complete the work for that pay item. The quantity is designated as "All". Estimated quantities of lump sum work shown in the contract are approximate.
20301 – REMOVAL OF STRUCTURES AND OBSTRUCTIONS.
DESCRIPTION
This work consists of salvaging, removing and disposing of fences, structures and other obstructions from
National Forest System Lands as described in Description of work.
SALVAGING MATERIAL.
Salvage with reasonable care the anchor assembly of the Northeast anchor block intact with the (2) 1-
3/8”anchor rods with (8) nuts, plate, spelter block attached to failed cable with an approximate length of 2 ft. Cables to be removed with spelter block or may be cut 6” below ground level. If spelter block is removed, replace all nuts on 1-3/8” anchor rods. Nuts of embedded 1-5/8” anchor rod to remain installed at completion of work. Reference
CABLE ANCHOR detail on Sheet 6 of 6, R34601-ALL.
Stockpile salvaged material at a designated location in parking area near the project.
REMOVING MATERIAL.
(a) Submittals. Submit a bridge removal plan for approval before commencement of work. Include the following:
(1) Methods and equipment to be used;
(2) Measures to be used for protecting the environment, public, adjacent property, and workers; and
(3) Methods to keep debris out of the stream and streambed.
DISPOSING OF MATERIAL. Dispose of debris and all material as follows:
(a) Remove from project. Repurpose, Recycle or dispose of material legally off National Forest System
Lands. Submit a statement documenting the nature and quantity of material processed or sold for recycling.
Otherwise, submit a signed copy of the disposal agreement before or with final invoice.
(b) Hazardous material. Submit a copy of disposal permits. Dispose of material according to Federal, state, and local regulations.
Acceptance. Removal of structures and obstructions will be evaluated based on visual inspection of the work for compliance with the contract and prevailing industry standards.
MEASUREMENT
Lump Sum. Do not measure directly. The bid amount is complete payment for all work described in the contract and necessary to complete the work for that pay item. The quantity is designated as "All". Estimated quantities of lump sum work shown in the contract are approximate.
C- 3 – Field Work Notice
The project area is located on the Mt. Hood National Forest, within the Columbia River Gorge National Scenic
Area. The contractor will be working within and exposed to natural conditions including, but not limited to, traveling over uneven and rocky terrain, encounters with wildlife, river crossings, plants, and inclement weather.
The contractor is responsible for ensuring that all employees are trained and have proper safety equipment prior to commencing work in the project area. No government-furnished property will be provided under this contract.
C- 4 – Biopreferred Products
The Contractor must comply with the Farm Security and Rural Investment Act of 2002 (FSRIA), 7 U.S.C.
8102; the Food, Conservation and Energy Act of 2008 (FCEA), 7 U.S.C. 8102; the Federal Acquisition
Regulation; Executive Order (EO) 13514, “Federal Leadership in Environmental, Energy and Economic
Performance,” dated October 5, 2009; EO 13423, “Strengthening Federal Environmental, Energy, and
Transportation Management,” dated January 24, 2007; and Presidential Memorandum, “Driving Innovation and Creating Jobs in Rural America through Biobased and Sustainable Product Procurement,” dated February, 2012 to provide biobased products.
Finding BioPreferred products is simple, using the program’s online catalog. To view the catalog, go to www.biopreferred.gov.
C- 5 – Inspection of Worksite
The Contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work, and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the Contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.
C- 6 – Recycling and Disposal of Refuse
With the exception of materials specifically indicated or specified to be salvaged for reuse in construction, or turned over to the Government, all refuse, excess or waste materials resulting from construction operations shall become the property of the Contractor and shall be recycled and/or disposed of. All disposals shall be in accordance with federal, state, and local laws and regulations. No disposal, viewing or sale of materials and/or equipment shall be allowed on Government property.
C- 7 – Safety
During the execution of this contract, the Contractor shall conform to the rules and regulations as set forth by
OSHA Safety and Health Standards, 29 CFR Part 1926 - Safety and Health Regulations for Construction.
Smoking will not be permitted in any building or structure.
C- 8 – Temporary Facilities
(a) STAGING AREA: The Government will provide adequate staging area as close to the job site as practicable. The Contractor shall be responsible for protecting materials stockpiled against adverse weather, damage, theft, and other risks of loss. The Government assumes no responsibility for material or equipment left in the storage area.
(b) SANITARY FACILITIES: Toilet facilities will not be provided by the Government at job sites. The
Contractor shall provide temporary toilet facilities (porta-potty) at the site during all construction work. Toilet facilities shall be provided at a rate of one stool for every 10 workers assigned or working on site with a minimum of one required.
(c) WATER AND ELECTRICITY: Water and utilities are not available at the site for construction purposes. The Contractor will be responsible for coordinating the installation of temporary power for the site and the cost for the service.
http://www.biopreferred.gov/ http://www.biopreferred.gov/
C- 9 – Existing Utilities
The Contractor shall field verify all utility locations before digging or trenching. This shall include, but not be limited to, the use of sonic, electronic or magnetic detection devices, by noting pull box and utility box locations at the surface, use of locator services, and by potholing. Contractor shall be responsible for repairing any utilities damaged during construction at no additional cost to the Government.
C- 10 - AGAR 452.211-73 Attachments to Statement Of Work/Specifications (FEB 1988)
The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.
NOTE: Offeror’s are cautioned to carefully review these Project Specifications prior to submission of offers. All specifications contained in Section J are binding on the parties signing the contract.
C-11 – Replacement of Equipment
Contractor shall provide quality equipment capable of safely performing the work under the terms of the contract. If equipment is rejected because it down not meet minimum requirements, including but not limited to safety and operability, or if it becomes inoperative, the Contractor shall correct the deficiencies or furnish replacement equipment meeting contract requirements within 2 days. All repairs are the total responsibility of the Contractor.
C-12 – Pollution and Erosion Control
During all operations under this contract, the Contractor shall exercise reasonable measures to direct surface runoff water to stabilized waterways and to keep the drainage systems functioning effectively to prevent or minimize soil erosion and pollution of water and other resources. All refuse, including garbage, rubbish, and solid or liquid wastes from the Contractor’s operations, including camps, parking areas, and equipment maintenance areas shall be stored and collected in a sanitary manner and disposed of in a state-approved sanitary landfill.
SECTION D—PACKAGING AND MARKING
NONE
SECTION E--INSPECTION AND ACCEPTANCE
E- 1 - FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.246-12 Inspection of Construction (AUG 1996)
E- 2 – Pre-Final and Final Inspection
a. Pre-final Inspection: The Government may, at its own discretion, conduct a pre-final inspection prior to the contractor requesting a final inspection. Any discrepancies noted shall be corrected prior to final inspection.
b. Final Inspection: When the work is ready for final inspection, the Contractor shall submit a written request for the final inspection to the duly assigned Contracting Officer’s Representative at least seven (7) days prior to the desired final inspection date. The final inspection will be performed with the Contractor by the appropriate Government personnel. If any discrepancies are noted, they shall be handled in accordance with
52.246-12.
http://www.arnet.gov/far/
SECTION F--DELIVERIES OR PERFORMANCE
F- 1 - FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/
52.242-14 Suspension of Work (APR 1984)
F- 2 - FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 15 calendar days from the start date identified on the notice to proceed. The time stated for completion shall include final cleanup of the premises.
SECTION G—CONTRACT AND ADMINISTRATION DATA
SECTION H--SPECIAL CONTRACT REQUIREMENTS
H- 1 - Use of Premises
The Contractor shall comply with the regulations governing the operation of premises which are occupied and shall perform the contract in such a manner as not to interrupt or interfere with the conduct of Government business.
H- 2 - AGAR 452.237-74 Key Personnel (FEB 1988)
(a) The Contractor shall assign to this contract the following key personnel: Project Foreman
(b) During the first ninety (90) days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.
(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the
Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.
H- 3 - Incidental Payment Items
The intent of the contract is to provide for the completion of the project described in the contract. Unless otherwise provided, the Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in accordance with drawings, specifications, and provisions of the contract. Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered as incidental to and included in the payment for items shown.
H- 4 - Conformity With Drawings and Specifications
Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the drawings, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is compliance with reasonable and customary manufacturing and construction tolerances.
H- 5 - Samples, Tests, Cited Specifications
Reference made in the contract to specifications, standards, or test methods adopted by AASHTO, ASTM, GSA, or other recognized National technical associations, shall mean specifications, standards, or test methods
(including interim or tentative issues) which are in effect on the date of the solicitation.
H- 6 - Barricades, Warning Signs, and Other Devices
The Contractor shall provide, erect, and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public.
H- 7 - Contract Administration
(a) CONTRACTING OFFICER means a person with the authority to enter into, administer and/or terminate contracts and make related determinations and findings. The Contracting Officer signs all contractual documents, approves and signs all modifications to contracts, processes and approves payment requests, reviews and makes final decisions on contractual discrepancies, and administers the contract. The
Contracting Officer is the only authorized individual to make changes to a contract.
(b) CONTRACTING OFFICER'S REPRESENTATIVE. The Contracting Officer will designate a representative, hereinafter referred to as the Contracting Officer's Representative (COR) or, alternatively, as the
Engineer, who will provide on-the-ground administration for the Government. The COR will be designated in writing and a copy of the designation will be furnished to the Contractor before or at the pre-work conference.
The Contractor is cautioned to read the COR designation because certain authority under the contract is reserved solely for the Contracting Officer. The term "Contracting Officer" as used throughout the contract shall be interpreted to include the Contracting Officer's designated representative(s) acting within the limits of their delegation of authority.
(c) CONTRACTOR'S REPRESENTATIVE. Any representative of the Contractor shall be designated in writing. The designation shall clearly indicate the name and limitations of authority, if any, of the representative.
H- 8 – Work Schedule
A Work Schedule shall define the overall time required to perform the identified work. Each major task, including beginning time and ending time, shall be identified within the schedule. Notify the Contracting
Officer whenever there are significant departures from the approved Work Schedule. Submit any requests to modify the Work Schedule, in writing to the Contracting Officer with an explanation for the deviation.
H- 9 - Subcontract Data
The Contractor shall submit an executed Statement and Acknowledgment Standard Form 1413, to the
Contracting Officer for every subcontractor (including every subcontractor of the second or lower tier) that will be performing work at the construction site. This shall be submitted before the subcontractor begins work. This form provides an acknowledgment by the subcontractor that mandatory "flowdown" contract clauses have been included in their contract in accordance with FAR Clause 52.222-11. Completing this form creates no contractual relationship between subcontractors and the Government.
H-10 - Site Superintendent
It shall be the responsibility of the Contractor to provide a responsible site superintendent to represent the
Contractor in the field in all matters under this contract including, but not limited to construction, day-to-day coordination of activities, control over employees and subcontractors, and coordination with local Government personnel. The site superintendent shall be designated in writing. They shall be available on site in person to respond to any and all problems during normal working hours. The site superintendent shall be responsible for on-site Quality Control.
Site superintendent shall maintain on site a file containing the following project documents.
• Executed Copy of the Contract
• Contract Drawings
• Contract Specifications
• Quality Control Plan – (up to date)
• As-Built Drawing – (up to date) if required
• Work Orders
• Modifications
This file shall be maintained and available to the Contracting Officer upon request. If the Site Superintendent is replaced, the existing Superintendent shall review all documents and ongoing issues with the new
Superintendent.
H-11 - Designation of Contracting Officer Representative
Prior to the commencement of work, the COR will be designated. The COR is responsible for administering the performance of the work under this contract. In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by the Contracting Officer prior to the completion of this contract.
H-12 – Washing Equipment
All equipment used on the site shall be cleaned and inspected off National Forest land prior to its arrival on the site. The equipment must be 1) free of all mud, seeds, plants, and plant fragments; and 2) free of oil, fuel, or toxic leaks that would wash off into the water. Notify the Contracting Officer 48 hours in advance of mobilizing equipment to the site to arrange an inspection.
H-13 - Prework Conference
Prior to commencement of work, the Contracting Officer will arrange a meeting with the Contractor to discuss the contract terms and work performance requirements. Also at this meeting such things as work progress schedule and fire prevention and suppression plans shall be developed and established in writing.
PART II--CONTRACT CLAUSES SECTION I--CONTRACT CLAUSES
I- 1 - FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
www.arnet.gov/far/ www.usda.gov/procurement/policy/agar.html
52.204-12 Unique Entity Identifier Maintenance (OCT 2016)
52.204-13 System for Award Management Maintenance (OCT 2016)
52.204-18 Commercial and Government Entity Code Maintenance (JUL 2016)
52.219-6 Notice of Total Small Business Set-Aside (NOV 2011)
52.219-28 Post-Award Small Business Program Rerepresentation (JUL 2013)
52.222-3 Convict Labor (JUN 2003)
52.222-6 Construction Wage Rate Requirements (MAY 2014)
52.222-7 Withholding of Funds (MAY 2014)
52.222-8 Payrolls and Basic Records (MAY 2014)
52.222-9 Apprentices and Trainees (JUL 2005)
52.222-10 Compliance with Copeland Act Requirements (FEB 1988)
52.222-11 Subcontracts (Labor Standards) (MAY 2014)
52.222-12 Contract Termination - Debarment (MAY 2014)
52.222-13 Compliance with Construction Wage Rate Requirements and Related Act Regulations
(MAY 2014)
52.222-14 Disputes Concerning Labor Standards (FEB 1988)
52.222-15 Certification of Eligibility (MAY 2014)
52.222-21 Prohibition of Segregated Facilities (APR 2015)
52.222-26 Equal Opportunity (SEPT 2016)
52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015)
52.222-50 Combating Trafficking in Persons (MAR 2015)
52.222-55 Minimum Wages Under Executive Order 13658 (DEC 2015)
52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts (SEP
2013)
52.223-3 Hazardous Material Identification and Material Safety Data (JAN 1997) Alternate I (JUL 1995)
52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2011)
52.223-6 Drug-Free Workplace (MAY 2001)
52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction Contracts (MAY
2008)
52.223-18 Contractor Policy to Ban Text Messaging While Driving (AUG 2011)
52.224-1 Privacy Act Notification (APR 1984)
52.225-13 Restrictions on Certain Foreign Purchases (JUN 2008) http://www.arnet.gov/far/ http://www.arnet.gov/far/ http://www.usda.gov/procurement/policy/agar.html
52.232-5 Payments Under Fixed-Price Construction Contracts (MAY 2014)
52.232-23 Assignment of Claims (MAY 2014)
52.232-27 Prompt Payment for Construction Contracts (MAY 2014)
52.232-33 Payment of Electronic Funds Transfer – System for Award Management (JUL 2013)
52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013)
52.233-1 Disputes (MAY 2014) Alternate I (DEC 1991)
52.233-3 Protest After Award (AUG 1996)
52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004)
52.236-2 Differing Site Conditions (APR 1984)
52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984)
52.236-5 Material and Workmanship (APR 1984)
52.236-6 Superintendence by the Contractor (APR 1984)
52.236-8 Other Contracts (APR 1984)
52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (APR
1984)
52.236-10 Operations and Storage Areas (APR 1984)
52.236-11 Use and Possession Prior to Completion (APR 1984)
52.236-12 Cleaning Up (APR 1984)
52.236-13 Accident Prevention (NOV 1991)
52.236-15 Schedules for Construction Contracts (APR 1984)
52.236-21 Specifications and Drawings for Construction (FEB 1997)
52.242-13 Bankruptcy (JUL 1995)
52.243-5 Changes and Changed Conditions (APR 1984)
52.244-6 Subcontracts for Commercial Items (DEC 2015)
52.246-21 Warranty of Construction (MAR 1994)
52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short Form) (APR 1984)
52.249-10 Default (Fixed-Price Construction) (APR 1984)
52.253-1 Computer Generated Forms (JAN 1991)
AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES
452.224-70 Confidentiality of Information (FEB 1988)
452.236-73 Archeological or Historic Sites (FEB 1988)
452.236-76 Samples and Certificates (FEB 1988)
452.236-77 Emergency Response (NOV 1996)
I- 2 - AGAR 452.209-71 Assurance Regarding Felony Conviction Or Tax Delinquent Status For
Corporate Applicants (FEB 2012) Alt I (FEB 2012)
(a) This award is subject to the provisions contained in the Consolidated Appropriations Act, 2012 (P.L. No.
112-74), Division E, Sections 433 and 434 regarding corporate felony convictions and corporate federal tax delinquencies. Accordingly, by accepting this award the contractor acknowledges that it –
(1) does not have a tax delinquency, meaning that it is not subject to any unpaid Federal tax liability that has been assessed, for which all judicial and administrative remedies have been exhausted or have lapsed, and that is not being paid in a timely manner pursuant to an agreement with the authority responsible for collecting the tax liability, and
(2) has not been convicted (or had an officer or agent acting on its behalf convicted) of a felony criminal violation under any Federal law within 24 months preceding the award, unless a suspending and debarring official of the United States Department of Agriculture has considered suspension or debarment of the awardee, or such officer or agent, based on these convictions and/or tax delinquencies and determined that suspension or debarment is not necessary to protect the interests of the Government.
(b) If the awardee fails to comply with these provisions, the Forest Service may terminate this contract for default and may recover any funds the awardee has received in violation of sections 433 or 434.
I- 3 - FAR 52.225-9 Buy American Act-Construction Materials (MAY 2014)
(a) Definitions. As used in this clause—
“Commercially available off-the-shelf (COTS) item”—
(1) Means any item of supply (including construction material) that is—
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
“Component” means an article, material, or supply incorporated directly into a construction material.
“Construction material” means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
“Cost of components” means— https://acquisition.gov/far/current/html/Subpart%202_1.html#wp1145508 https://acquisition.gov/far/current/html/Subpart%202_1.html#wp1145508 http://uscode.house.gov/
(3) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(4) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
“Domestic construction material” means—
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if—
(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
“Foreign construction material” means a construction material other than a domestic construction material.
“United States” means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy
American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). The
Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that—
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
http://uscode.house.gov/ http://uscode.house.gov/ https://acquisition.gov/far/current/html/Subpart%2012_5.html#wp1077123 https://acquisition.gov/far/current/html/Subpart%2012_5.html#wp1077123
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute.
(1) (i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including—
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the
Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the
Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison
Construction Material Description Unit of Measure Quantity Price (Dollars)*
Item 1:
Foreign construction material _______ _______ _______
Domestic construction material _______ _______ _______
Item 2: _______ _______ _______
Foreign construction material _______ _______ _______
Domestic construction material
[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.]
[Include other applicable supporting information.]
[* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).]
I- 4 - FAR 52.223-20 Aerosols (JUN 2016)
(a) Definitions. As used in this clause–
“Global warming potential” means how much a given mass of a chemical contributes to global warming over a given time period compared to the same mass of carbon dioxide. Carbon dioxide’s global warming potential is defined as 1.0.
“High global warming potential hydrofluorocarbons” means any hydrofluorocarbons in a particular end use for which EPA’s Significant New Alternatives Policy (SNAP) program has identified other acceptable alternatives that have lower global warming potential. The SNAP list of alternatives is found at 40 CFR part 82 subpart G with supplemental tables of alternatives available at http://www.epa.gov/snap/).
“Hydrofluorocarbons” means compounds that contain only hydrogen, fluorine, and carbon.
(b) Unless otherwise specified in the contract, the Contractor shall reduce its use, release, or emissions of high global warming potential hydrofluorocarbons, when feasible, from aerosol propellants or solvents under this contract. When determining feasibility of using a particular alternative, the Contractor shall consider environmental, technical, and economic factors such as–
(1) In-use emission rates, energy efficiency;
(2) Safety, such as flammability or toxicity;
http://www.epa.gov/snap/
(3) Ability to meet technical performance requirements; and
(4) Commercial availability at a reasonable cost.
(c) The Contractor shall refer to EPA’s SNAP program to identify alternatives. The SNAP list of alternatives is found at 40 CFR part 82 subpart G with supplemental tables available at http://www.epa.gov/snap/.
I- 5 - FAR 52.223-21 Foams (JUN 2016)
(a) Definitions. As used in this clause–
“Global warming potential” means how much a given mass of a chemical contributes to global warming over a given time period compared to the same mass of carbon dioxide. Carbon dioxide's global warming potential is defined as 1.0.
“High global warming potential hydrofluorocarbons” means any hydrofluorocarbons in a particular end use for which EPA’s Significant New Alternatives Policy (SNAP) program has identified other acceptable alternatives that have lower global warming potential. The SNAP list of alternatives is found at 40 CFR part 82 subpart G with supplemental tables of alternatives available at http://www.epa.gov/snap/.
“Hydrofluorocarbons” means compounds that contain only hydrogen, fluorine, and carbon.
(b) Unless otherwise specified in the contract, the Contractor shall reduce its use, release, and emissions of high global warming potential hydrofluorocarbons and refrigerant blends containing hydrofluorocarbons, when feasible, from foam blowing agents, under this contract. When determining feasibility of using a particular alternative, the Contractor shall consider environmental, technical, and economic factors such as–
(1) In-use emission rates, energy efficiency, and safety;
(2) Ability to meet performance requirements; and
(3) Commercial availability at a reasonable cost.
(c) The Contractor shall refer to EPA’s SNAP program to identify alternatives. The SNAP list of alternatives is found at 40 CFR part 82 subpart G with supplemental tables available at http://www.epa.gov/snap/.
I- 6 – FAR 52.232-40 Providing Accelerated Payment to Small Business Subcontractors (DEC 2013)
(a) Upon receipt of accelerated payments from the Government, the Contractor shall make accelerated payments to its small business subcontractors under this contract, to the maximum extent practicable and prior to when such payment is otherwise required under the applicable contract or subcontract, after receipt of a proper invoice and all other required documentation from the small business subcontractor.
http://www.epa.gov/snap/ http://www.epa.gov/snap/ http://www.epa.gov/snap/ http://www.epa.gov/snap/
(b) The acceleration of payments under this clause does not provide any new rights under the Prompt
Payment Act.
(c) Include the substance of this clause, including this paragraph (c), in all subcontracts with small business concerns, including subcontracts with small business concerns for the acquisition of commercial items.
I- 7 – FAR 52.236-7 Permits and Responsibilities (NOV 1991)
The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State, and municipal laws, codes, and regulations applicable to the performance of the work. The Contractor shall also be responsible for all damages to persons or property that occur as a result of the Contractor's fault or negligence. The Contractor shall also be responsible for all materials delivered and work performed until completion and acceptance of the entire work, except for any completed unit of work which may have been accepted under the contract.
I- 8 - Order of Precedence--Construction
Any inconsistency in this solicitation or contract shall be resolved by giving precedence in the following order:
(a) The Schedule (excluding the Specifications) (Sections A-H).
(b) The representations and other instructions (Sections K and L).
(c) Contract clauses (Section I).
(d) Other Documents, Exhibits, and Attachments (Section J).
(e) The Specifications.
(f) Drawings.
PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS SECTION J--LIST
OF ATTACHMENTS
Construction Wage Rate Requirements: If this is a contract in excess of $2,000, the Davis Bacon Act requires the Contractor to pay certain minimum wages and benefits to employees working under this contract.
These required minimum wages are stated in the attached Wage Decision.
J- 1 - Wage Decision No. OR170001; Dated 09/22/2017
J- 2 - Photo(s) – See separate attached document. The following specifications are a part of this solicitation and any resulting contract.
J- 3 - Drawings(s) – See separate attached document. The following specifications are a part of this solicitation and any resulting contract. (For reference purposes)
J- 4 – Experience Questionnaire
PART IV--REPRESENTATIONS AND INSTRUCTIONS SECTION K--REPRESENTATIONS,
CERTIFICATIONS, ANDOTHER STATEMENTS OF OFFERORS OR RESPONDENTS
K- 1 - FAR 52.252-1 Solicitation Provisions Incorporated by Reference (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es): https://www.acquisition.gov
52.204-16 Commercial and Government Entity Code Reporting (JUL 2016)
52.204-17 Ownership or Control of Offeror (NOV 2014)
52.209-2 Prohibition on Contracting with Inverted Domestic Corporations – Representation
(NOV 2015)
52.225-25 Prohibition on Contracting with Entities Engaging in Certain Activities or
Transactions Relating to Iran – Representations and Certifications (OCT 2015)
K- 2 - FAR 52.204-8 Annual Representations and Certifications (APR 2016)
(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is
238910.
(2) The small business size standard is $15 Million.
(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.
(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the provision at 52.204-7 is not included in this solicitation, and the offeror is currently registered in the System for Award Management (SAM), and has completed the Representations and
Certifications section of SAM electronically, the offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The offeror shall indicate which option applies by checking one of the following boxes:
□ (i) Paragraph (d) applies.
□ (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.
https://www.acquisition.gov/ https://www.acquisition.gov/sites/default/files/current/far/html/52_200_206.html#wp1137850 https://www.acquisition.gov/sites/default/files/current/far/html/52_200_206.html#wp1137850 https://www.acquisition.gov/sites/default/files/current/far/html/52_200_206.html#wp1137850 https://www.acquisition.gov/sites/default/files/current/far/html/52_200_206.html#wp1137850
(c)(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:
(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or…