Pre-Bid Site Visit Q&A's
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_0002.pdf | ||
| Updated_Description_of_Work_information.pdf | ||
| Rail_drawings.docx | DOCX document | |
| pre-bid_Attendance.pdf | ||
| 2017_photos.pdf | ||
| Experience_Questionaire.docx | DOCX document | |
| Solicitation_12-046W-18-Q-0003_Eagle_Creek_Suspension_Bridge_Removal.pdf | ||
| R34601-ALL.PDF | ||
| General_Decision_Number_OR170001_9_22_2017.docx | DOCX document | |
| 1997_crane_photos.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Eagle Creek Suspension Bridge Removal – Site Visit
Announcement given at site visit:
1. Salvage of anchor assembly will be removed from contract requirements.
2. Railing adjacent to Road will not be removed and is to remain in place.
3. The utility vault and water lines are not to be damaged during bridge removal.
Questions & Answers:
Q: Are dates hard and fast?
A: Performance time will be extended to allow multiple approaches for removal.
Q: Is tree removal allowed?
A: Hazard tree removal is allowed.
Q: What is the estimated cost of removal?
A: The estimated value of this contract is between $25,000-$100,000.
Q: Is limbing allowed?
A: Selective limbing will be allowed for equipment access
Q: What access is there to the SW side?
A: There is no motorized vehicle access. The pedestrian trail starts about 2 miles away and is narrow with approximate 18” tread width. It ascends/descends a steep hill.
Q: Does Demolition plan require a PE stamp A: There is no requirement stated in contract. Plan is subject to CO approval.
Q: Is Rigging allowed A: Yes, Plan is subject to CO approval.
Q: What are the estimated weights of bridge components?
A: The government estimates the towers each weigh less than 4 tons and that the suspended portion weighs less than 6 tons. It is the responsibility of the contractor to determine their own estimate.
Q: What type of Treatment was used for the pressure treated wood?
A: The Plans indicate the majority of the structure is treated with pentachlorophenol. The Tower legs are assumed to be Creosote treated. Contractor is responsible to verify.
Q: Is a Bid Bond Required?
A: No, Only a payment bond is required.
Q: Is there a contract contingency for weather?
A: No, the site visit occurred on the second straight day of rain and it seems reasonable to expect similar conditions during contract performance dates.
Q: Can the brush be cleared away up to the NW tower for equipment access?
A: Yes, the brush will need to be scattered over the disturbed area upon completion. Removal plan needs to be approved by the CO.
Q: Are the 1997 photos of the bridge being built?
A: No, Those photos show the method of removal of the previous bridge that was damaged by an ice debris flow.
EMAIL Question/Answers:
Q: Was the site visit to the Eagle Creek Suspension Bridge Removal & Disposal Project that was held on November 9, 2017 mandatory?
A: The site visit was for the benefit of prospective bidders and was not mandatory.
Q: I have a couple of questions about bonding and insurance requirements. This project would require us to sub out the crane work as well as possible salvage. could you clarify what would be needed for our company as well as the subs.
A: Bond requirements vary based on contract price, please reference FAR 28.102-2 for specifics.
As for Subcontractor work, all work/requirements flows through the Prime contractor, payments, bonding…etc. It is the Prime Contractor responsibility to make sure their subs are capable of performing. Also, I assume you know that the prime contractor has to perform more than 50% of the contract.
Q: Was the site visit to the Eagle Creek Suspension Bridge Removal & Disposal Project that was held on November 9, 2017 mandatory?
A: The site visit was for the benefit of prospective bidders and was not mandatory.
Q: is there a estimated value for the project? Never hurts to ask, Lol!
A: The estimated value of this contract is between $25,000-$100,000.
Q: how far away is the secondary Crossing to get to the other bank? In the one set of old pictures you have from 1997 there are lifts on both sides of the bank?
A: Access to other side is by pedestrian trail only. Shown in the 1997 photos is a man-lift being ‘lifted’ onto the gravel bar by Mobile Crane.
Q: What are the most updated pictures you have available? What is shown?
A: The posted photos are the most current.
Q: What kind of access is there to either bank?
A: As mentioned in the solicitation, paved road accesses one side of bridge, and pedestrian trail on the other side.
Q: Normal water flow depth? Frequency of flash floods?
A: The bidder is responsible to perform any hydrologic analysis deemed necessary. The Bridge is within an area that had a fire a few months ago and any historic hydraulic information would likely no longer apply. Reference ‘Profile View’ on Sheet 1 of 6 of R34601 for channel estimates.