Specifications.pdf
PDF 452 KB Posted
- Attached to
- Mike Harris Campground Electrical Federal contract opportunity
- Solicitation number
- 1202NV20Q0003
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment3.pdf | ||
| Amendment2.pdf | ||
| Amendment1.pdf | ||
| Drawings.pdf | ||
| 1202NV20Q0003.pdf | ||
| Presolicitation_Notice.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-1
Section C - Description/Specifications/Statement of Work
GENERAL SPECIFICATIONS
MIKE HARRIS CAMPGROUND ELECTRICAL
Final – 7/30/2019
1.1 SCOPE OF CONTRACT
A. This project includes constructing a new electrical system for the Mike Harris Campground.
B. The work includes:
1. Primary work for power company, including:
a. Boring under road and wet land.
b. Trench work and providing a location for the transformer pad.
c. Secondary trench to utility building.
2. Installing a new 200 amp service on the utility building with generator transfer.
3. Installing a utility building electrical and well controls and feeder.
4. Installing feeder for two campground hosts with power pedestals.
5. Restoration of road, pad and other surfaces.
C. Quantities associated with these options are identified in the Schedule of Items.
1.2 PROJECT LOCATION
A. The Mike Harris Campground is located on the Teton Basin Ranger District of the Caribou-Targhee National Forest, in Teton County, Idaho, approximately 4 miles southeast of Victor, Idaho. The campground is approximately 4 miles by road from Victor, Idaho via Idaho highway 33/Wyoming highway 22, near the confluence of Trail Creek and Mike Harris Creek. The well is located near the center of Section 30, T3N, R46E (Latitude 43°33'24"N, Longitude 111°04'11"W) at an elevation of approximately 6560 feet.
1.3 SITE INFORMATION AND LIMITATIONS
A. The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:
1. Construction sites will be closed to the public during construction. The Forest Service will issue a closure order to the public. The Contractor will be responsible for signing and limiting public access.
2. Contractor will provide all materials and labor necessary to protect streams, wet or dry, during construction activities. The Contractor will be required to submit a stream protection plan and receive approval from the COR, in writing, prior to the beginning of construction.
3. All construction equipment shall be pressure washed before entering National Forest System lands.
The removal of mud and debris from treds, tracks and undercarriage, with emphasis on axles, frame, cross-members, motor mounts, and underneath steps, running boards, and front bumper/brushguard assemblies will be required. The purpose is to reduce or eliminate the transportation of noxious weeds, which is required by Federal and State regulations.
4. Utilities are not available at the site for construction purposes.
5. Toilet facilities are available at the site.
1.4 TRAFFIC CONTROL AND CONSTRUCTION SIGNING
A. No work that endangers, interferes, or conflicts with traffic or access to work sites shall be performed until a plan for satisfactory warning and handling of traffic has been submitted by the contractor and approved by the COR and Idaho Department of Transportation. Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices (MUTCD). All traffic control signs will be placed in areas adequate for a truck pulling a fifth wheel trailer to be turned around. Contractor shall not be paid
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-2
directly for this item, rather it will be considered incidental to other items of work listed in the Schedule of Items.
1.5 WORK CAMPS, STAGING AND STORAGE AREAS
A. Areas for staging operations and storage of materials shall be approved by the CO. The Contractor must request in writing for approval from the CO to stage trailers (work or housing) on site.
1.6 INSPECTION OF WORKSITE
A. The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work, and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.
1.7 START DATE
A. Fall 2019
1.8 CONTRACT TIME
A. Base Bid: 90 Calendar Days
1.9 SPECIFICATIONS
A. The following specifications are attached. Some sections in the schedule of items refer to other sections not listed and are subsidiary to, or are included in payment for other pay items in this contract. These items are considered incidental and no additional compensation will be made.
Section 011250 - Measurement And Payment Section 011900 - Mobilization Section 023701 - Sediment And Erosion Control Measures Section 024100 - Waste Material Disposal Section 260500 - Common Work Results For Electrical Section 260519 - Low-Voltage Electrical Power Conductors And Cables Section 260526 - Grounding And Bonding For Electrical Systems Section 260533 - Raceways And Boxes For Electrical Systems Section 260553 - Identification For Electrical Systems Section 262726 - Wiring Devices Section 311000 - Clearing And Grubbing Section 312000 - Earthwork Section 321204 - Crushed Aggregate Base Or Surface Course
END OF SECTION C
January 2020
COMMON WORK RESULTS FOR ELECTRICAL 260500--5
USDA FOREST SERVICE, R4
MIKE HARRIS CAMPGROUND ELECTRICAL
SECTION 011250 - MEASUREMENT AND PAYMENT
PART 1 - GENERAL
1.1 SUMMARY
A. Measurement and payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work, labor, materials, equipment, and incidentals necessary to successfully complete the project will be considered as included in the payment for items shown. This section defines the method of measurements and basis of payment for work items listed in the Schedule of Items.
B. When more than one class, size, type, thickness, etc. is specified in the Schedule of Items for any pay item, suffixes will be added to the item number to differentiate between the pay items.
1.2 DETERMINATION OF QUANTITIES
A. The following measurements and calculations shall be used to determine contract quantities for payment.
1. For individual construction items, longitudinal and lateral measurements for area computations shall be made horizontally or corrected to horizontal measurement unless otherwise specified.
Measurements for geotextiles, netting and erosion control blankets shall be along slope lines.
2. For excavation or embankment volumes, the average end area method shall be used to compute volumes. However, if in the judgment of the Contracting Officer (CO), the average end area method is impractical, measurement shall be made by volume in hauling vehicles or by other three-dimensional methods.
3. For Structures, they shall be measured according to neat lines shown on the drawings or as altered by the CO, in writing, to fit field conditions.
4. For items that are measured by the linear foot, such as pipe culverts, fencing, guardrail, piping, utilities, and underdrains, measurements shall be made parallel to the base or foundation upon which the structures are placed.
5. For aggregates weighed for payment, the tonnage shall not be adjusted for moisture content, unless otherwise provided for.
6. For standard manufactured items (such as fence, wire, plates, rolled shapes, pipe conduits) identified by gauge, weight, section dimensions, and so forth, such identifications shall be considered the nominal weights or dimensions. Unless controlled by tolerances in cited specifications, manufacturer's tolerances shall be accepted.
B. Earthwork Tolerances - Adjustments of horizontal or vertical alignment, within the tolerances specified in this contract, or shifts of balance points up to 100 feet shall be made by the contractor as necessary to produce the designed sections and to balance earthwork. Such adjustments shall not be considered as "Changes."
1.3 UNITS OF MEASUREMENT
A. Payment shall be by units defined and determined according to U.S. Standard measure and by the following:
1. Acre: Make longitudinal and transverse measurements for area computations horizontally.
2. 50lb Bag: Measurement will be for the actual number of 50lb bags of standard bentonite grout.
3. 94lb Bag: Measurement will be for the actual number of 94lb bags of standard cement or grout.
4. Cubic Yard (CY): A measurement computed by one of the following methods:
a. Excavation, Embankment, or Borrow. The measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.
b. Material in Place or Stockpile. The measurement computed using the dimensions of the in-place material.
COMMON WORK RESULTS FOR ELECTRICAL 260500--4
c. Material in the Delivery Vehicle. The measurement computed using measurements of material in the hauling vehicles at the point of delivery. Vehicles shall be loaded to at least their water level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.
5. Each (EA): One complete unit, which may consist of one or more parts.
6. Gallons (GAL): The quantity shall be measured by any of the following methods:
a. Measured volume in container.
b. Metered volume by approved metering system.
c. Commercially package volume.
7. Hour (HR): Measurement will be for the actual number of hours (or fraction thereof) ordered by the Contracting Officer and performed by the contractor.
8. Linear Foot (LF): Measurement of work along its length from point-to-point; parallel to the base or foundation. Do not measure overlaps.
9. Lump Sum (LS): One complete unit.
10. Mile: Measured horizontally along the centerline of each roadway, approach, or ramp.
11. Pound (LB): For sacked or packaged material, measurement will be the net weight as packed by the manufacturer.
12. Square Foot (SF): Measured on a plane parallel to the surface being measured.
13. Square Yard (SY): Measured on a plane parallel to the surface being measured.
14. Ton: Measured as a short ton consisting of 2,000 pounds.
1.4 METHOD OF MEASUREMENT
A. One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:
1. ACTUAL QUANTITIES (AQ) - These quantities are determined from actual measurements of completed work.
2. DESIGNED QUANTITIES (DQ) - These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units shown in the Schedule of Items may be authorized under any of the following conditions:
a. As a result of changes in the work authorized by the CO.
b. As a result of the CO determining that errors exist in the original design that cause a pay item quantity to change by 15 percent or more.
c. As a result of the Contractor submitting to the CO a written request showing evidence of errors in the original design that cause a pay item quantity to change by 15 percent or more.
The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.
3. LUMP SUM QUANTITIES (LSQ) - These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall not be measured.
4. STAKED QUANTITIES (SQ) - These quantities are determined from staked measurements prior to construction.
5. VEHICLE QUANTITIES (VQ) - These quantities are measured or weighed in hauling vehicles.
PART 2 - PRODUCTS (NOT APPLICABLE)
PART 3 - EXECUTION (NOT APPLICABLE)
END OF SECTION 011250
January 2020
MIKE HARRIS CAMPGROUND ELECTRICAL
COMMON WORK RESULTS FOR ELECTRICAL 260500--3
SECTION 011900 - MOBILIZATION
PART 1 - GENERAL
1.1 SUMMARY
A. This item is intended to compensate the Contractor for operations including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for payment of premiums for bonds and insurance for the project; and for any other work and operations which must be performed or costs that must be incurred incident to the initiation of meaningful work at the site and for which payment is not otherwise provided for under the contract.
1.2 MEASUREMENT AND PAYMENT
A. The measurement shall be lump sum for mobilization. Payment shall be as follows:
1. Bond premiums will be reimbursed after receipt of the evidence of payment.
2. 50% of the lump sum, not to exceed 5% of the original contract amount, will be paid following completion of 5% of the original contract amount not including mobilization and bond premiums.
3. Payment of the remaining portion of the lump sum, up to 10% of the original contract amount, will be paid following completion of 10% of the original contract amount not including mobilization and bond premiums.
4. Any portion of the lump sum in excess of 10% of the original contract amount will be paid after final acceptance.
5. Progress payments for mobilization and preparatory work shall be subject to retainage.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
END OF SECTION 011900
January 2020
USDA FOREST SERVICE, R4
MIKE HARRIS CAMPGROUND ELECTRICAL
SECTION 023701 - SEDIMENT AND EROSION CONTROL MEASURES
PART 1 - GENERAL
1.1 The work under this section consists of furnishing all necessary labor, equipment, materials, and performing all operations in connection with construction sediment and control measures.
A. General
1. All erosion and sediment control measures are to be placed prior to any disturbance caused by grading and or excavation and shall conform to the requirements of the appropriate regulatory agency for the State.
2. The Contractor shall be solely responsible for ensuring that erosion and sediment control measures are implemented and maintained at the site.
3. Soil disturbing activities include but are not limited to: Clearing and grubbing, excavation for utilities and foundations, roadway and parking lot construction, construction or modification of site drainage, grading, and preparation for final seeding.
1.2 SUBMITTALS
A. The Contractor shall be required to submit a sediment and erosion control plan in accordance with this specification for approval by the Contracting Officer 2 weeks prior to start of work.
1.3 MEASUREMENT AND PAYMENT
COMMON WORK RESULTS FOR ELECTRICAL 260500--2
A. No separate measurement and/or payment will be made for this section. Payment shall be included with work shown in the schedule of items.
PART 2 - PRODUCTS
2.1 SYNTHETIC FILTER FABRIC FOR SILT FENCES.
A. Pervious sheet of polypropylene, nylon, or polyethylene fabric conforming to the following physical and hydraulic characteristics:
• Physical Properties (Min.) Requirement Test Method
• Grab Tensile, lbs. W120/F100 ASTM-D-4632
• Grab Elongation, % 15 ASTM-D-4632
• Mullen Burst, psi 275 ASTM-D-3786
• Puncture, lbs. 65 ASTM-D-4833
• Trapezoidal Tear, lbs. 50 ASTM-D-4533
• UV Resistance, % 80 ASTM-D-4355
• AOS, US Sieve # 30/40 ASTM-D-4751
• Permittivity gal/min-sq. ft. 90 ASTM-D-4491
B. Filter fabric should contain ultraviolet ray inhibitors and stabilizers to provide a minimum of 6 months of expected usable construction life at a temperature range of 0 to 120 F.
C. Support Posts: 4 foot - 2 x 2 wood.
2.2 STRAW BALES
A. Oat or wheat straw, free from weeds, viable weed seeds, foreign matter detrimental to plant life, and dry.
1. Grass hay bales are not acceptable.
2. In order to prevent deterioration of the bindings, all bales shall be either wire-bound or string-tied so that bindings are oriented around the sides rather than along the tops and bottoms of the bales.
2.3 STRAW WATTLES OR ROLLS
A. Furnish straw wattles or rolls that are manufactured from weed free straw and wrapped in a tubular photodegradable plastic netting made from 85% high density polyethylene, 14% ethyl vinyl acetate and 1% color for UV inhibition. Conform to the following:
1. Diameter 9 inches min.
2. Netting strand thickness 0.030 inches
3. Netting knot thickness 0.055 inches
4. Mass of netting 0.315 to 0.385 ounces per foot
PART 3 - EXECUTION
3.1 CONSTRUCTION
A. Install straw bales at local drainage ways to prevent silt intrusion upon adjacent drainage courses. Remove straw bales following establishment of vegetation cover and utilize as mulch at swales or on steep slopes.
B. Prior to construction, install silt fence along the downhill construction limits to prevent silt intrusion upon adjacent land.
C. Install sediment and erosion control measures on the down slope toe of all top soil stock piles.
D. Maintain and remove all erosion controls as specified.
E. Temporary seeding shall be placed on exposed surfaces that will not be brought to final grading or permanent cover treatment within 30 days of the exposure to reduce erosion and sedimentation by
COMMON WORK RESULTS FOR ELECTRICAL 260500--1
stabilizing exposed soils. Seeded areas shall be checked regularly for bare spots, washouts, and healthy growth to assure that a good stand of grass is being maintained. Reseed areas that fail to establish vegetation cover as soon as such areas are identified.
3.2 DUST CONTROL
A. In areas subject to surface and air movement of dust, where on-site or off-site damage is likely to occur, one or more of the following preventive measures shall be taken for dust control:
1. Minimize the period of soil exposure through the use of temporary ground cover and other temporary stabilization practices.
2. Sprinkle the site with water until surface is wet. Repeat as needed.
3.3 SILT FENCE
A. Silt fences are appropriate for the following general locations:
1. Immediately upstream of the point(s) of runoff discharge from a site before flow becomes concentrated. Below disturbed areas where runoff may occur in the form of overland flow.
2. Along the down slope toe of all top soil stock piles.
B. Materials.
1. Utilize standard strength synthetic filter fabric for sediment barriers. The filter fabric shall be purchased in a continuous roll cut to the length of the barrier to avoid the use of joints. When joints are necessary, filter cloth shall be spliced together only at a support post, with a minimum 6 inch overlap, and securely sealed.
2. The standard strength filter fabric shall be stapled or wired to the fence and 6 inches of the fabric shall be extended into the ground. Filter fabric shall not be stapled to existing trees.
3. Support posts shall be spaced at a maximum 6 feet and driven securely into the ground a minimum of 24 inches.
4. Filter fabric shall be buried a minimum of 12 inches.
5. The height of a silt fence shall not exceed 36 inches. Higher fences may impound volumes of water sufficient to cause failure of the structure.
C. Maintenance.
1. Silt fences and filter barriers shall be inspected immediately after each rainfall and at least daily during prolonged rainfall.
2. Silt fences shall be inspected for depth of sediment, tears, and to see if the fabric is securely attached to the fence posts, and to see that the fence posts are firmly in the ground. Any deficiencies shall be repaired immediately.
3. Should the fabric on a silt fence of filter barrier decompose or become ineffective prior to the end of the expected usable life and the barrier still be necessary, the fabric shall be replaced promptly.
4. Sediment deposits should be removed after each storm event and/or when deposits reach approximately 1/3 the height of the barrier or when the sediments limit or prevent the flow of water through the fabric hydraulic.
5. Any sediment deposits remaining in place after the silt fence or filter barrier is no longer required shall be dressed to conform with the existing grade, prepared, and seeded.
3.4 STRAW BALE EROSION CONTROL FENCE
A. Straw bale erosion control fences are appropriate for the following general locations:
1. Sheet flow applications: Straw bales shall be placed in a single row, lengthwise on the contour with ends of adjacent bales tightly abutting one another.
2. Channel flow applications: Straw bales shall be placed in a single row, lengthwise and oriented perpendicular to the direction of flow with ends of adjacent bales tightly abutting one another. The barrier shall be extended to such a length that the bottoms of the end bales are higher in elevation than the top of the lowest middle bale to assure that sediment laden runoff will flow either through or over the barrier but not around it.
COMMON WORK RESULTS FOR ELECTRICAL 260500-0
B. The barrier shall be entrenched and backfilled. A trench shall be excavated the width of a bale and the length of the proposed barrier to a minimum depth of 4 inches. After the bales are staked and chinked, the excavated soil shall be backfilled against the barrier. Backfill shall conform to the ground level of the downhill side and shall be built up to 4 inches against the uphill side of the barrier.
C. Each bale shall be securely anchored by at least 2 stakes or rebar driven through the bale. The first stake in each bale shall be driven toward the previously laid bale to force the bales together. Stakes or rebar shall be driven a minimum of 12 inches into the ground or deep enough into the ground to securely anchor the bales, whichever is greater.
D. The gaps between bales shall be chinked (filled by wedging with straw to prevent water from escaping between the bales). Loose straw scattered over the area immediately uphill from a straw bale barrier tends to increase barrier efficiency.
3.5 STRAW WATTLE OR ROLL
A. Straw wattles shall be installed in accordance to manufacturer’s installation guidelines.
B. At a minimum:
1. The wattle shall be entrenched and backfilled. A trench shall be excavated the width of the straw waddle and the length of the proposed barrier to a depth of 2-3 inches.
2. Each wattle shall be securely anchored by at least one 18-24 inch stake every 3-4 feet and with a stake on each end. Stakes shall be driven perpendicular to slope face through the middle of the wattle until 2-3 inches remains exposed above the waddle.
3. After the wattles are staked, compact excavated soil against the uphill side of the barrier.
4. Adjacent wattles should tightly abut.
3.6 MAINTENANCE
A. Inspection shall be frequent and repair or replacement shall be made promptly as needed. Straw bale carriers shall be removed when they have served their usefulness, but not before the upslope areas have been permanently stabilized.
END OF SECTION 023701
January 2020
USDA FOREST SERVICE, R4
MIKE HARRIS CAMPGROUND ELECTRICAL
SECTION 024100 - WASTE MATERIAL DISPOSAL
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the loading, handling, hauling, and placing of excess excavation material, unsuitable excavation material, clearing and grubbing debris, and construction and demolition debris.
1.2 MEASUREMENT AND PAYMENT
A. There will be no separate measurement or payment for work in this Section. Waste material disposal is considered incidental to other items of work shown in the Schedule of Items.
PART 2 - PRODUCTS – NOT APPLICABLE
PART 3 - EXECUTION
3.1 WASTE MATERIAL TO BE HAULED TO A DISPOSAL AREA
A. All excavated material not used in the construction of embankments or backfilling of trenches, or other excess material resulting from the excavation and embankment operation shall be hauled to a disposal area.
COMMON WORK RESULTS FOR ELECTRICAL 260500-1
B. All unsuitable excavated material and oversize boulders shall be hauled to a disposal area.
C. All stumps, slash and other clearing and grubbing debris shall be hauled to a disposal area.
D. Disposal Area: All waste material above shall be hauled to the disposal area on Government property as designated by the Contracting Officer.
1. Waste material shall be piled and compacted to form a dense layer.
2. The size and shape of the piled waste material shall be designated by the Contracting Officer.
3. The piled material shall be covered with soil to a uniform depth of six inches minimum and sloped to 2:1 or flatter.
4. The disposal site shall be left suitable for seeding.
3.2 WASTE MATERIAL TO BE HAULED TO A LANDFILL
A. All demolition materials, garbage, and other refuse generated shall be removed from the project site and legally disposed off of Government property in an approved landfill.
B. The contractor is responsible for all costs and permits associated with landfill disposal.
C. The Government is not responsible for waste material upon its departure from the project site.
END OF SECTION 024100
January 2020
USDA FOREST SERVICE, R4
MIKE HARRIS CAMPGROUND ELECTRICAL
SECTION 260500 - COMMON WORK RESULTS FOR ELECTRICAL
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Electrical equipment coordination and installation.
2. Grout.
3. Common electrical installation requirements.
4. Hangers and supports.
5. As-built drawings.
1.2 SUBMITTALS
A. Product Data:
1. For any substitutions for equipment referred to by name in Division 26 specifications or the drawings.
1.3 QUALITY ASSURANCE
A. The installation shall conform to the 2017 Edition of the National Electrical Code (NFPA 70) and to the requirements specified herein.
B. The Contractor shall perform all work necessary and required to accomplish the task as detailed on the drawings and discussed in the installation notes. All work shall be done by a state licensed electrician.
1.4 MEASUREMENT AND PAYMENT
A. The work in this section, including all incidentals in other electrical sections, shall be measured and paid for by the following methods as shown in the Schedule of Items:
1. Electrical Distribution System, Primary Direct Boring – Actual Quantity Sum measured by Linear Foot of conduit installed in accepted bore. Includes full compensation for all labor, materials, and
COMMON WORK RESULTS FOR ELECTRICAL 260500-2
incidentals necessary to complete the work as shown on the drawings including all conduit, pull lines, trenching, bedding, backfill, and all other incidentals necessary for a functional system acceptable to the Power Company and Government.
2. Electrical Distribution System, Utility Trench - Actual Quantity Sum measured by Linear Foot of trench. Includes full compensation for all labor, materials, and incidentals necessary to complete the work as shown on the drawings including all pull lines, trenching, bedding, backfill, and all other incidentals necessary for a functional system acceptable to the Power Company and Government.
3. Utility Building Electrical System - Lump Sum including full compensation for all labor, materials, and incidentals necessary to complete the work as shown on the drawings including all grounding, wiring, trenching, bedding, backfill, and all other incidentals necessary for a functional system.
Includes all exterior work within 5 feet of the buildings perimeter, and all feeder work related to the well.
4. Electrical Distribution System, Host Feeder - Actual Quantity Sum measured by Linear Foot of trench center line to edge of road. Includes full compensation for all labor, materials, and incidentals necessary to complete the work as shown on the drawings including all wires, trenching, bedding, backfill, and all other incidentals necessary for a functional system acceptable to the Power Company and Government.
5. Host Unit Power Pedestal - Lump Sum including full compensation for all labor, materials, and incidentals necessary to complete the work as shown on the drawings including all grounding, wiring, trenching, bedding, backfill, and all other incidentals necessary for a functional system.
6. Surface Repair - Lump Sum includes full compensation for all labor, materials, and incidentals necessary to complete road, and RV pad and developed amenities surface restoration including gravel or other required surfacing, compaction, and related work, and all other incidentals necessary to repair developed surfaces to original condition.
PART 2 - PRODUCTS
2.1 PRODUCTS REFERRED TO BY NAME
A. The materials referred to by trade name, make, or catalog number on the drawings shall be regarded as establishing a minimum standard of quality; substitutions of equal or greater quality can be made by submitting a data sheet of the proposed substituted item to the Contracting Officer, for approval.
2.2 GROUT
A. Nonmetallic, Shrinkage-Resistant Grout: ASTM C 1107, factory-packaged, nonmetallic aggregate grout, noncorrosive, nonstaining, mixed with water to consistency suitable for application and a 30-minute working time.
PART 3 - EXECUTION
3.1 COMMON REQUIREMENTS FOR ELECTRICAL INSTALLATION
A. Comply with NECA 1.
B. Measure indicated mounting heights to bottom of unit for suspended items and to center of unit for wall-mounting items.
C. Headroom Maintenance: If mounting heights or other location criteria are not indicated, arrange and install components and equipment to provide maximum possible headroom consistent with these requirements.
D. Equipment: Install to facilitate service, maintenance, and repair or replacement of components of both electrical equipment and other nearby installations. Connect in such a way as to facilitate future disconnecting with minimum interference with other items in the vicinity.
E. Right of Way: Give to piping systems installed at a required slope.
3.2 RACEWAY AND SIMILAR PENETRATIONS (NON-FIRE RATED, NOT SLEEVED)
COMMON WORK RESULTS FOR ELECTRICAL 260500-3
A. Concrete Slabs and Walls: Core-drilled holes.
1. Fill oversized holes with grout to within 1/4-inch (6 mm).
B. Aboveground, Exterior-Wall Penetrations: Seal exterior opening around the raceway or cable, using a flexible, waterproofing, joint sealant appropriate for size, depth, and color to closely match the surrounding surface. Finish interior openings, filling opening and matching the exiting surface with appropriate materials and finish quality for the space.
3.3 HANGERS AND SUPPORTS
A. Installation:
1. Comply with NECA 1 and NECA 101 for installation requirements, except as specified in this article.
2. Separate dissimilar metals and metal products from contact with wood or cementitious materials by painting each metal surface in area of contact with a bituminous coating or by other permanent separation.
3. Raceway Support Methods: In addition to methods described in NECA 1, conduit may be supported by openings through structure members, as permitted in NFPA 70.
4. Strength of Support Assemblies: Where not indicated, select sizes of components so strength will be adequate to carry present and future static loads within specified loading limits. Minimum static design load used for strength determination shall be weight of supported components plus 200 lb (90 kg).
5. Mounting and Anchorage of Surface-Mounted Equipment and Components: Anchor and fasten electrical items and their supports to building structural elements by the following methods, unless otherwise indicated or required by Code:
a. To Existing Concrete: Expansion anchor fasteners.
6. Drill holes for expansion anchors in concrete at locations and to depths that avoid reinforcing bars.
3.4 AS-BUILT DRAWINGS
A. The Contractor shall maintain a set of the contract drawings depicting as-built conditions. These drawings shall be maintained in a current condition and shall be available for review. All variations from the original contract drawings shall be indicated in red on the drawings. Upon completion of the contract work, as-built drawings shall be submitted to the Contracting Officer.
END OF SECTION 260500
LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES 260519-1
MIKE HARRIS CAMPGROUND ELECTRICAL
SECTION 260519 - LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Copper building wire rated 600 V or less.
2. Connectors, splices, and terminations rated 600 V and less.
1.2 MEASUREMENT AND PAYMENT
A. No separate measurement or payment will be made for work specified in this section. All work will be included in other items listed in the Schedule of Items.
PART 2 - PRODUCTS
2.1 COPPER BUILDING WIRE
A. Description: Flexible, insulated and uninsulated, drawn copper current-carrying conductor with an overall insulation layer or jacket, or both, rated 600 V or less.
B. Standards:
1. Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and use.
C. Conductors: Copper, complying with ASTM B 3 for bare annealed copper and with ASTM B 8 for stranded conductors.
D. Conductor Insulation:
1. Type THHN/THWN-2: Comply with UL 83.
E. Cable: Comply with NEMA WC 70/ICEA S-95-658 for:
1. Type SO and similar cables with ground wire.
2.2 CONNECTORS AND SPLICES
A. Description: Factory-fabricated connectors and splices of size, ampacity rating, material, type, and class for application and service indicated.
PART 3 - EXECUTION
3.1 CONDUCTOR MATERIAL APPLICATIONS
A. Circuits: Copper; solid for No. 10 AWG and smaller; stranded for No. 8 AWG and larger.
1. Aluminum is not allowed.
B. Exposed to Direct Sunlight: Sunlight resistant.
C. Power-Limited and Control: Solid for No. 12 AWG and smaller.
3.2 CONDUCTOR INSULATION AND MULTICONDUCTOR CABLE APPLICATIONS AND WIRING
METHODS
A. Service Entrance, Feeders, and Branch Circuits: Type THHN/THWN-2, single conductors in raceway.
LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES 260519-2
3.3 INSTALLATION OF CONDUCTORS AND CABLES
A. Complete raceway installation between conductor and cable termination points according to Section 260533 "Raceways and Boxes for Electrical Systems" prior to pulling conductors and cables.
B. Use manufacturer-approved pulling compound or lubricant where necessary; compound used must not deteriorate conductor or insulation. Do not exceed manufacturer's recommended maximum pulling tensions and sidewall pressure values.
C. Use pulling means, including fish tape, cable, rope, and basket-weave wire/cable grips that will not damage cables or raceway.
3.4 CONNECTIONS
A. Tighten electrical connectors and terminals according to manufacturer's published torque-tightening values.
If manufacturer's torque values are not indicated, use those specified in UL 486A-486B.
B. Make splices, terminations, and taps that are compatible with conductor material.
C. Wiring at Outlets: Install conductor at each outlet, with at least 6 inches (150 mm) of slack.
END OF SECTION 260519
GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 260526-1
MIKE HARRIS CAMPGROUND ELECTRICAL
SECTION 260526 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes grounding and bonding systems and equipment.
1.2 MEASUREMENT AND PAYMENT
A. No separate measurement or payment will be made for work specified in this section. All work will be included in other items listed in the Schedule of Items.
PART 2 - PRODUCTS
2.1 SYSTEM DESCRIPTION
A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.
B. Comply with UL 467 for grounding and bonding materials and equipment.
2.2 CONDUCTORS
A. Insulated Conductors: Copper wire or cable insulated for 600 V unless otherwise required by applicable Code or authorities having jurisdiction.
B. Bare Copper Conductors:
1. Solid Conductors: ASTM B 3.
2. Stranded Conductors: ASTM B 8.
2.3 CONNECTORS
A. Listed and labeled by a Nationally Recognized Testing Laboratory (NRTL) acceptable to authorities having jurisdiction for applications in which used and for specific types, sizes, and combinations of conductors and other items connected.
B. Welded Connectors: Exothermic-welding kits of types recommended by kit manufacturer for materials being joined and installation conditions.
C. Bolted Connectors for Conductors and Pipes: Copper or copper alloy.
2.4 GROUNDING ELECTRODES
A. Ground Rods: Copper-clad steel; 3/4 inch by 10 feet (19 mm by 3 m).
PART 3 - EXECUTION
3.1 APPLICATIONS
A. Conductors: Install solid conductor for No. 8 AWG and smaller, and stranded conductors for No. 6 AWG and larger unless otherwise indicated.
B. Underground Grounding Conductors: Install barecopper conductor, No. 2/0 AWG minimum.
1. Bury at least 24 inches (600 mm) below grade.
3.2 GROUNDING AT THE SERVICE
GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 260526-2
A. Equipment grounding conductors and grounding electrode conductors shall be connected to the ground bus.
Install a main bonding jumper between the neutral and ground buses.
3.3 EQUIPMENT GROUNDING
A. Install insulated equipment grounding conductors with all feeders and branch circuits.
B. Trailer Pedestals: Install a grounding electrode and a separate equipment grounding conductor in addition to grounding conductor installed with branch-circuit conductors.
3.4 INSTALLATION
A. Grounding Conductors: Route along shortest and straightest paths possible unless otherwise indicated or required by Code. Avoid obstructing access or placing conductors where they may be subjected to strain, impact, or damage.
B. Ground Rods: Drive rods until tops are 2 inches (50 mm) below finished floor or final grade unless otherwise indicated.
1. Interconnect ground rods with grounding electrode conductor below grade and as otherwise indicated. Make connections without exposing steel or damaging coating if any.
2. For grounding electrode system, install at least two rods spaced at least one-rod length from each other and located at least the same distance from other grounding electrodes, and connect to the service grounding electrode conductor.
C. Connections: Make connections so possibility of galvanic action or electrolysis is minimized. Select connectors, connection hardware, conductors, and connection methods so metals in direct contact are galvanically compatible.
1. Use electroplated or hot-tin-coated materials to ensure high conductivity and to make contact points closer in order of galvanic series.
2. Make connections with clean, bare metal at points of contact.
3. Coat and seal connections having dissimilar metals with inert material to prevent future penetration of moisture to contact surfaces.
END OF SECTION 260526
RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 260533-1
MIKE HARRIS CAMPGROUND ELECTRICAL
SECTION 260533 - RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Metal conduits and fittings.
2. Nonmetallic conduits and fittings.
3. Boxes, enclosures, and cabinets.
4. Handholes and boxes for exterior underground cabling.
1.2 DEFINITIONS
A. GRC: Galvanized rigid steel conduit.
B. IMC: Intermediate metal conduit.
1.3 MEASUREMENT AND PAYMENT
A. No separate measurement or payment will be made for work specified in this section. All work will be included in other items listed in the Schedule of Items.
PART 2 - PRODUCTS
2.1 METAL CONDUITS AND FITTINGS
A. Metal Conduit:
1. Listing and Labeling: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.
2. GRC: Comply with ANSI C80.1 and UL 6.
3. IMC: Comply with ANSI C80.6 and UL 1242.
4. PVC-Coated Steel Conduit: PVC-coated rigid steel conduit or IMC.
a. Comply with NEMA RN 1.
b. Coating Thickness: 0.040 inch (1 mm), minimum.
5. EMT: Comply with ANSI C80.3 and UL 797.
6. FMC: Comply with UL 1; zinc-coated steel.
B. Metal Fittings:
1. Comply with NEMA FB 1 and UL 514B.
2. Listing and Labeling: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.
3. Fittings, General: Listed and labeled for type of conduit, location, and use.
4. Coating for Fittings for PVC-Coated Conduit: Minimum thickness of 0.040 inch (1 mm), with overlapping sleeves protecting threaded joints.
2.2 NONMETALLIC CONDUITS AND FITTINGS
A. Nonmetallic Conduit:
1. Listing and Labeling: Nonmetallic conduit shall be listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.
2. RNC: Type EPC-40-PVC, complying with NEMA TC 2 and UL 651 unless otherwise indicated.
3. Rigid HDPE: Comply with UL 651A.
RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 260533-2
4. Continuous HDPE: Comply with UL 651A.
B. Nonmetallic Fittings:
1. Fittings, General: Listed and labeled for type of conduit, location, and use.
2. Fittings for RNC: Comply with NEMA TC 3; match to conduit type and material.
3. Solvents and Adhesives: As recommended by conduit manufacturer.
2.3 BOXES, ENCLOSURES, AND CABINETS
A. General Requirements for Boxes, Enclosures, and Cabinets: Boxes, enclosures, and cabinets installed in wet locations shall be listed for use in wet locations.
B. Sheet Metal Outlet and Device Boxes: Comply with NEMA OS 1 and UL 514A.
2.4 HANDHOLES AND BOXES FOR EXTERIOR UNDERGROUND WIRING
A. General Requirements for Handholes and Boxes:
1. Boxes and handholes for use in underground systems shall be designed and identified as defined in NFPA 70, for intended location and application.
2. Boxes installed in wet areas shall be listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.
3. Standard: Comply with SCTE 77.
4. Configuration: Designed for flush burial with open bottom unless otherwise indicated.
5. Cover: Weatherproof, secured by tamper-resistant locking devices and having structural load rating consistent with enclosure and handhole location.
6. Cover Finish: Nonskid finish shall have a minimum coefficient of friction of 0.50.
7. Cover Legend: Molded lettering, "ELECTRIC".
B. Polymer-Concrete Handholes and Boxes with Polymer-Concrete Cover: Molded of sand and aggregate, bound together with polymer resin, and reinforced with steel, fiberglass, or a combination of the two.
C. Fiberglass Handholes and Boxes: Molded of fiberglass-reinforced polyester resin, with frame and covers of polymer concrete, reinforced concrete, or cast iron.
D. Fiberglass Handholes and Boxes: Molded of fiberglass-reinforced polyester resin, with frame and covers of fiberglass.
PART 3 - EXECUTION
3.1 RACEWAY APPLICATION
A. Outdoors: Apply raceway products as specified below unless otherwise indicated:
1. Exposed Conduit: GRC or IMC.
a. Feeders and Branch Circuits: EMT allowed with UL listed raintight compression fittings, once the metal raceway is 5-ft (1.5-m) minimum above finished grade.
2. Underground Conduit: GRC or IMC.
a. Once direct buried beyond 5-ft (1.5-m) of exposed grade penetration or building foundation penetration: HDPE; or RNC, Type EPC-40-PVC direct buried.
3. Boxes and Enclosures, Aboveground: NEMA 250, Type 3R.
B. Indoors: Apply raceway products as specified below unless otherwise indicated:
1. Exposed, Not Subject to Physical Damage: Rigid metallic conduit or tubing.
2. Connection to Vibrating Equipment (Including Transformers and Hydraulic, Pneumatic, Electric
Solenoid, or Motor-Driven Equipment): FMC, except use LFMC in damp or wet locations.
3. Boxes and Enclosures: NEMA 250, Type 1.
RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 260533-3
C. Raceway Fittings: Compatible with raceways and suitable for use and location.
1. Rigid and Intermediate Steel Conduit: Use threaded rigid steel conduit fittings unless otherwise indicated. Comply with NEMA FB 2.10.
2. PVC Externally Coated, Rigid Steel Conduits: Use only fittings listed for use with this type of conduit. Patch and seal all joints, nicks, and scrapes in PVC coating after installing conduits and fittings. Use sealant recommended by fitting manufacturer and apply in thickness and number of coats recommended by manufacturer.
3. EMT: Comply with NEMA FB 2.10.
4. Flexible Conduit: Use only fittings listed for use with flexible conduit. Comply with
NEMA FB 2.20.
3.2 HANDHOLE APPLICATION
A. Application of Handholes and Boxes for Underground Wiring:
1. Handholes and Pull Boxes in Driveway, Parking Lot, and Off-Roadway Locations, Subject to Occasional, Nondeliberate Loading by Heavy Vehicles: Polymer concrete, SCTE 77, Tier 15 structural load rating.
2. Handholes and Pull Boxes in Sidewalk, within 5-ft (1.5-m) of a roadway and unprotected by terrain features, and Similar Applications with a Safety Factor for Nondeliberate Loading by Vehicles:
Polymer-concrete units or heavy-duty fiberglass units with polymer-concrete frame and cover, SCTE 77, Tier 8 structural load rating.
3. Handholes and Pull Boxes Subject to Light-Duty Pedestrian Traffic Only: Fiberglass-reinforced polyester resin, structurally tested according to SCTE 77 with 3000-lbf (13 345-N) vertical loading.
3.3 INSTALLATION
A. Comply with NECA 1 and NECA 101 for installation requirements except where requirements on Drawings or in this article are stricter. Comply with NFPA 70 limitations for types of raceways allowed in specific occupancies and number of floors.
B. Complete raceway installation before starting conductor installation.
C. Arrange stub-ups so curved portions of bends are not visible above finished slab.
D. Make bends in raceway using large-radius preformed ells. Field bending shall be according to NFPA 70 minimum radii requirements. Use only equipment specifically designed for material and size involved.
E. Install conduits parallel or perpendicular to building lines.
F. Coat field-cut threads on PVC-coated raceway with a corrosion-preventing conductive compound prior to assembly.
G. Terminate threaded conduits into threaded hubs or with locknuts on inside and outside of boxes or cabinets.
Install bushings on conduits up to 1-1/4-inch (35mm) trade size and insulated throat metal bushings on 1- 1/2-inch (41-mm) trade size and larger conduits terminated with locknuts. Install insulated throat metal grounding bushings on service conduits.
H. Install raceways square to the enclosure and terminate at enclosures with locknuts. Install locknuts hand tight plus 1/4 turn more.
I. Cut conduit perpendicular to the length. For conduits 2-inch (53-mm) trade size and larger, use roll cutter or a guide to make cut straight and perpendicular to the length.
J. Comply with manufacturer's written instructions for solvent welding RNC and fittings.
K. Flexible Conduit Connections: Comply with NEMA RV 3. Use a maximum of 36 inches (915 mm) of flexible conduit for equipment subject to vibration, noise transmission, or movement; and for transformers and motors.
RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 260533-4
L. Mount boxes at heights indicated on Drawings. If mounting heights of boxes are not individually indicated, give priority to ADA requirements. Install boxes with height measured to center of box unless otherwise indicated.
M. Fasten junction and pull boxes to or support from building structure. Do not support boxes by conduits.
3.4 INSTALLATION OF UNDERGROUND CONDUIT
A. Direct-Buried Conduit:
1. Excavate trench bottom to provide firm and uniform support for conduit. Prepare trench bottom as specified in Section 312000 "Earth Moving" for pipe less than 6 inches (150 mm) in nominal diameter.
2. Install backfill as specified in Section 312000 "Earth Moving."
3. After installing conduit, backfill and compact. Start at tie-in point, and work toward end of conduit run, leaving conduit at end of run free to move with expansion and contraction as temperature changes during this process. Firmly hand tamp backfill around conduit to provide maximum supporting strength. After placing controlled backfill to within 12 inches (300 mm) of finished grade, make final conduit connection at end of run and complete backfilling with normal compaction as specified in Section 312000 "Earth Moving." [.]
4. Install manufactured rigid steel conduit elbows for stub-ups at poles and equipment. See 3.1 A.3.
this section, for building entrances.
5. Underground Warning Tape: Comply with requirements in Section 260553 "Identification for Electrical Systems."
6. Underground-Line Warning Tape: During backfilling of trenches install continuous underground-line warning tape directly above line at 6 to 8 inches (150 to 200 mm) below finished grade.
3.5 INSTALLATION OF UNDERGROUND HANDHOLES AND BOXES
A. Install handholes and boxes level and plumb and with orientation and depth coordinated with connecting conduits to minimize bends and deflections required for proper entrances.
B. Unless otherwise indicated, support units on a level bed of crushed stone or gravel, graded from 1/2-inch (12.5-mm) sieve to No. 4 (4.75-mm) sieve and compacted to same density as adjacent undisturbed earth.
C. Elevation: Set covers 1 inch (25 mm) above finished grade.
3.6 PROTECTION
A. Protect coatings, finishes, and cabinets from damage and deterioration.
1. Repair damage to galvanized finishes with zinc-rich paint recommended by manufacturer.
2. Repair damage to PVC coatings or paint finishes with matching touchup coating recommended by manufacturer.
END OF SECTION 260533
IDENTIFICATION FOR ELECTRICAL SYSTEMS 260553-1
MIKE HARRIS CAMPGROUND ELECTRICAL
SECTION 260553 - IDENTIFICATION FOR ELECTRICAL SYSTEMS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Signs.
2. Fasteners for labels and signs.
1.2 MEASUREMENT AND PAYMENT
A. No separate measurement or payment will be made for work specified in this section. All work will be included in other items listed in the Schedule of Items.
PART 2 - PRODUCTS
2.1 PERFORMANCE REQUIREMENTS
A. Comply with ASME A13.1.
B. Comply with NFPA 70.
C. Comply with 29 CFR 1910.144 and 29 CFR 1910.145.
D. Comply with ANSI Z535.4 for safety signs and labels.
E. Adhesive-attached labeling materials, including label stocks, laminating adhesives, and inks used by label printers, shall comply with UL 969.
F. Thermal Movements: Allow for thermal movements from ambient and surface temperature changes.
2.2 COLOR AND LEGEND REQUIREMENTS
A. Warning Label Colors:
1. Identify system voltage with black letters on an orange background.
B. Warning labels and signs shall include, but are not limited to, the following legends:
1. Workspace Clearance Warning: "WARNING - OSHA REGULATION - AREA IN FRONT OF
ELECTRICAL EQUIPMENT MUST BE KEPT CLEAR FOR 36 INCHES (915 MM)."
2.3 LABELS
A. Self-Adhesive Labels: Polyester or vinyl, thermal, transfer-printed, 3-mil- (0.08-mm-) thick, multicolor, weather- and UV-resistant, pressure-sensitive adhesive labels, configured…