SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-1

Section C - Description/Specifications/Statement of Work

GENERAL SPECIFICATIONS

Hilltop Campground Reconstruction Project

3.1.19

1.1 SCOPE OF CONTRACT

A. This project consists of the reconstruction of the existing Hilltop Campground. Work includes the construction and installation of asphalt roads, parking spurs, culverts, retaining walls, family campground units, kiosk, fee tube, wheel stops, precast vault toilet buildings, utility building, dumpster pads, concrete and aggregate pathways, concrete and block stairs, unit markers, and host unit that includes septic holding tank with trailer hook up, propane system with trailer hook up and generator installation with trailer hook up.

Work will include the demolition and disposal of existing above ground construction features including but not limited to site furnishings (pedestal grills, picnic tables, fire rings, concrete and unit markers), retaining structures, kiosk, curb stops, stairs, water hydrants, valves, and drains, sewer system manholes, septic tank, leach lines, toilet and shower buildings, culverts and other below ground structures when encountered. Asphalt roads, parking areas, and spurs shall be pulverized and re-used as road base for new asphalt road construction.

B. Quantities associated with these options are identified in the Schedule of Items.

1.2 PROJECT LOCATION

A. The project is located in the Spring Mountains National Recreation Area of the Humboldt-Toiyabe National Forest, Clark County, Nevada, in Section 8, T19S, R57E of Mt. Diablo Base Meridian. It is located approximately 25 miles North of North Las Vegas, NV off State Highway 158.

1.3 SITE INFORMATION AND LIMITATIONS

A. The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:

1. Construction sites will be closed to the public during construction. The Forest Service will issue a closure order to the public. The Contractor will be responsible for signing and limiting public access.

2. All construction equipment shall be pressure washed before entering National Forest System lands. The removal of mud and debris from treads, tracks and undercarriage, with emphasis on axles, frame, cross-members, motor mounts, and underneath steps, running boards, and front bumper/brushguard assemblies will be required. The purpose is to reduce or eliminate the transportation of noxious weeds, which is required by Federal and State regulations.

3. Utilities are not available at the site for construction purposes.

Attachment #1 12026119R0003

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-2

4. The Contractor shall provide temporary toilet facilities (porta-potty) at the site during all construction work.

5. No fuel storage on site is permitted. Fuel trucks must be equipped with spill containment kits and portable berms that meet all state and federal regulations. A spill containment plan must be submitted and approved prior to construction.

6.

1.4 TRAFFIC CONTROL AND CONSTRUCTION SIGNING

A. No work that endangers, interferes, or conflicts with traffic or access to work sites shall be performed until a plan for satisfactory warning and handling of traffic has been submitted by the contractor and approved by the COR and Nevada Department of Transportation. Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices (MUTCD). All traffic control signs will be placed in areas adequate to prevent traffic from turning off of State Highway 158. Contractor shall not be paid directly for this item, rather it will be considered incidental to other items of work listed in the Schedule of Items.

1.5 WORK CAMPS, STAGING AND STORAGE AREAS

A. Areas for staging operations and storage of materials shall be approved by the CO. The Contractor must request in writing for approval from the CO to stage trailers (work or housing) on site.

1.6 INSPECTION OF WORKSITE

A. The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work, and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.

1.7 PERMITS

A. The Contractor will be responsible for obtaining and paying fees for the following permits:

1. Dust Permit (County)

2. NPDES Permit (State)

B. The Forest Service will obtain permits and pay fees for the following:

1. Wastewater System

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-3

1.8 START DATE

A. May 1, 2019

1. To avoid breeding season (May 19 – July 20) behaviors on the project, vegetation removal activities will need to occur prior to May 19, 2019 by the contractor. If construction activities occurring before July 20, a raptor survey will be initiated within the project area and within 0.5 mile of the project boundaries by the USFS.

A nest search will be completed by the Forest Service prior to start of construction.

If nests are found, a limited operating period will be initiated from May 19 to July 20 during which no vegetation removal or construction will be conducted within

0.5 mile of the nest until nestlings fledge.

1.9 CONTRACT TIME

A. Base Bid: 180 Calendar Days

1.10 SPECIFICATIONS

A. The following specifications are attached. Some sections in the schedule of items refer to other sections not listed and are subsidiary to, or are included in payment for other pay items in this contract. These items are considered incidental and no additional compensation will be made.

Section 010250 - Construction Staking Section 011250 - Measurement And Payment With Asphalt Section 011900 - Mobilization Section 013300 - Submittal Procedures Section 014100 - Quality Control Section 023701 - Sediment And Erosion Control Measures Section 024100 - Waste Material Disposal Section 024102 - Removal And Disposal Of Structures And Obstructions Section 026460 - Concrete Dumpster Pad Section 033000 - Cast-In-Place Concrete Section 033020 - Concrete From Packaged Dry Mix For Minor Structures Section 033440 - Concrete Stairs Section 033540 - Concrete Sidewalk Section 048100 - Unit Masonry Assemblies Section 053000 - Sheet Metal Roofing Section 055210 - Pipe And Tube Railings Section 055215 - Tubular Steel And Steel Fasteners Section 055300 - Expanded Metal Mesh Section 062030 - Carpentry For Kiosks Section 099110 - Exterior Painting Section 099113 - Exterior Paints And Coatings Section 099114 - Exterior Powder Coatings

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-4

Section 101110 - Kiosk Section 101400 - Signs Section 129300 - Site Furnishing Section 129400 - Family Units Section 129500 - Host Utilities Section 129701 - Fee Tube Installation Section 133400 - Precast Concrete Utility Building Section 133401 - Precast Concrete Vault Restroom Building Section 221310 - Sewage Holding Tank Section 231126 - Facility Liquefied-Petroleum Gas Piping Section 311000 - Clearing And Grubbing Section 312010 - Select Borrow

Section 312100 - Project Site Preparation And Grading Section 312225 - Excavation & Embankment Section 321200 - Hot-Mix Asphalt Paving Section 321204 - Crushed Aggregate Base Or Surface Course Section 321206 - Loose Rock Riprap Section 322100 - Tent Pads Section 322205 - Barrier Rocks Section 322625 - Recycled Plastic Curb Stop Section 322640 - Pavement Marking Section 322706 - Asphalt Pavement Pulverizing Section 323230 - Segmental Retaining Walls Section 332228 - Culvert Pipe And Pipe Arches

END OF SECTION C

CONSTRUCTION STAKING 010250-1

USDA FOREST SERVICE, R4

Hilltop Campground Reconstruction Project

SECTION 010250 - CONSTRUCTION STAKING

PART 1 - GENERAL

1.1 SUMMARY

A. This work shall consist of the construction staking of roads, parking lots, parking spurs, family units, tent pads, paths, stairways, culverts, retaining walls, buildings, and utilities in accordance with the Drawings and Specifications. The work includes the furnishing of all labor, equipment, instruments, materials, transportation and other incidentals necessary to complete the construction staking in accordance with these specifications and acceptable engineering practice.

1.2 QUALITY CONTROL

A. Construction staking shall be accomplished under the direction of a Civil Engineer, Engineering Technician, or Land Surveyor closely associated and familiar with construction staking; periodic visits to the project site are required.

1.3 MEASUREMENT AND PAYMENT

A. Measurement shall be lump sum for surveying and staking the project through all phases of construction.

PART 2 - PRODUCTS

2.1 GOVERNMENT-FURNISHED SURVEY CONTROL

A. The Government will provide the contractor with a set of survey control points showing horizontal and vertical control for site. The Government will provide the Contractor with AutoCAD drawings so they can develop survey layout information that will include:

1. Control Points - Northing, Easting, Existing Elevations.

2. Roads, Spurs, Parking Areas - Northing, Easting, and Finish Elevations for subgrade centerline and edge and corners of roads, spurs, parking areas.

3. Pathways - Northing, Easting, and Finish Elevations for subgrade centerline.

4. Buildings and Other Structures - Northing, Easting, and Finish Elevations for corners of buildings and other structures (septic tanks, dumpster pads, etc).

5. Family Units and Tent Pads - Northing, Easting, and Finish Elevations for corners.

6. Segmented Retaining Walls - Northing, Easting, and Existing Elevations (for reference) for subgrade (at top and bottom of wall) at start and end of wall, corners, stairs, and at maximum 25 foot along wall. (points at top of wall and bottom of wall). Note - Top of wall shall be a minimum of 4 inches above finish grade and bottom of wall shall be a minimum of 12 inches below finish grade.

CONSTRUCTION STAKING 010250-2

2.2 STAKES

A. Identification stakes and hubs shall be of sufficient length and width to be solid set in the ground and to provide space for marking above ground when applicable. Other dimensions and materials may be used, such as steel reinforcing bars, wire flagging and markers, and metal pins, if approved in writing by the Contracting Officer (CO). The top 2 inches of all slope, guard, reference, clearing, and structure stakes shall be painted or marked with plastic flagging. Colors used on stakes or for flagging shall be as follows:

1. Roads, parking lots, and parking spurs -Orange

2. Utilities, and culverts -Blue

3. Family Units, retaining walls, stairs, and paths -Red

4. Buildings, excavation and grading -Yellow

5. Tent pads -Blue/White Striped

PART 3 - EXECUTION

3.1 GENERAL

A. The Contractor shall be required to provide all necessary staking and control for all phases of construction. The contractor shall use the data and information shown on the project drawings to establish the location of all facilities to be constructed under this contract.

The Contractor may choose any method of establishing horizontal and vertical controls provided the following minimum precision and accuracy requirements are met.

B. Accuracy requirements:

1. Minimum position close; 1/1000

2. Vertical closure: 0.05 ft (vertical)/station (100 feet horizontal)

3. Cross section and slope stake precision:

a. Allowable deviation of cross section line projection from a true perpendicular to tangents, a true bisector of angle points, or a true radius of curves: +/-3 degrees.

b. Cross section topography measurements shall be taken so that variations in ground form a straight line connecting the cross section points will not exceed: 1.0 ft.

c. Horizontal and vertical accuracy for slope stake, slope stake references, and clearing limits. In feet or percentage of horizontal distance measured form centerline or reference stake, whichever is greater. Slope reference stakes and slope stakes: 0.15 ft or 0.6%. Clearing limits: 1.0 ft.

3.2 ESTABLISHING AND REFERENCING IMPROVEMENT LOCATIONS

A. Access Roads, Parking Spurs, and Parking lots:

1. Slope stakes (cut and fill catch points), clearing limits, and slope stake references shall be established on both sides of the centerline at each station established. Slope stakes and slope stake references shall be located on a line at right angles to tangents

CONSTRUCTION STAKING 010250-3

and on radial lines or curves. Slope stake catch points shall be located by using the grading plans and/or profiles, typical road section templates, as shown on the drawings and the information provided with staking points.

2. Slope stakes shall be set at 50-foot intervals, at significant breaks in the ground profile, culvert locations, and widening transition points. Slope stakes shall be set at 25 foot intervals around curves having a radius less than 100 feet.

B. Family Units and Tent Pads

1. Slope stakes shall be established at the corners of family units. Slope stakes shall be written to reference the finish grade of the unit or pad being staked.

C. Pathways

1. Slope stakes (cut and fill catch points), clearing limits, and slope stake references shall be established on both sides of the centerline at each station established. Slope stakes and slope stake references shall be located on a line at right angles to tangents and on radial lines or curves. Slope stake catch points shall be located by using the grading plans and/or profiles, and typical path and trail section templates as shown on the drawings.

2. Slope stakes shall be set at 10-foot intervals, at significant breaks in the ground profile, culvert locations, and widening transition points.

D. Culverts

1. Slope stakes and slope reference stakes shall be set at all culvert locations. A culvert reference stake and hub shall be set on the centerline of the culvert 10 feet from each end or beyond the clearing limit, which ever is greater. The following shall be recorded on these stakes:

a. The actual field measured length

b. The vertical and horizontal distance from hubs to the invert at the ends of the culvert.

E. Buildings

1. Slope stakes and slope stake references shall be established at each corner and as necessary to provide adequate construction control.

F. Segmented Retaining Walls

1. Construction stakes shall be established at start and end of wall, corners, stairs, and at maximum 25 feet along wall. Stakes shall establish top of wall, bottom of wall, and finish grade at top of wall and bottom of wall.

2. Additional stakes shall be established at required stepping of wall (top and bottom).

Note - Top of wall shall be a minimum of 4 inches above finish grade and bottom of wall shall be a minimum of 12 inches below finish grade.

3.3 DISCREPANCIES

CONSTRUCTION STAKING 010250-4

A. The contractor shall compare the staked centerline horizontal and vertical alignment with the design data. Differences between previously recorded and observed elevations of bench marks shall be referred to the Contracting Officer. Differences in centerline profile elevations exceeding 1 foot at any two or more consecutive points shall be reported to the contracting Officer for evaluation and possible revision. Staking of these areas shall be deferred until the Contacting Officer resolves these differences.

3.4 VERTICAL CONTROL

A. Vertical control for construction shall be as referenced on the Drawings.

3.5 MARKING STAKES

A. All stakes shall be legibly marked, in the format agreed upon with the Contracting Officer, with a stake pencil that leaves an imprinted or with waterproof ink. Marking shall conform to the nomenclature below;

PI Point of Intersection of tangents PC Point of curvature POC Point on curve Pt Point of tangency POT Point on tangent RP Reference point P P-line (preliminary location line) L L-line (final location line) BM Bench mark TBM Temporary bench mark BT Begin taper (any) ET End taper (any) C Cut F Fill L Centerline D Ditch W Width

3.6 SURVEY POINTS

A. All survey point data developed and used shall be provided in electronic format to the Government at the end of the project. This data shall include Northing, Easting, Elevation and Point Description.

END OF SECTION 010250

MEASUREMENT AND PAYMENT WITH ASPHALT 011250-1

Hilltop Campground Reconstruction Project

SECTION 011250 - MEASUREMENT AND PAYMENT WITH ASPHALT

PART 1 - GENERAL

1.1 SUMMARY

A. Measurement and payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work, labor, materials, equipment, and incidentals necessary to successfully complete the project will be considered as included in the payment for items shown. This section defines the method of measurements and basis of payment for work items listed in the Schedule of Items.

B. When more than one class, size, type, thickness, etc. is specified in the Schedule of Items for any pay item, suffixes will be added to the item number to differentiate between the pay items.

1.2 DETERMINATION OF QUANTITIES

A. The following measurements and calculations shall be used to determine contract quantities for payment.

1. For individual construction items, longitudinal and lateral measurements for area computations shall be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for geotextiles, netting and erosion control blankets shall be along slope lines.

2. For excavation or embankment volumes, the average end area method shall be used to compute volumes. However, if in the judgment of the Contracting Officer (CO), the average end area method is impractical, measurement shall be made by volume in hauling vehicles or by other three-dimensional methods.

3. For Structures, they shall be measured according to neat lines shown on the drawings or as altered by the CO, in writing, to fit field conditions.

4. For items that are measured by the linear foot, such as pipe culverts, fencing, guardrail, piping, utilities, and underdrains, measurements shall be made parallel to the base or foundation upon which the structures are placed.

5. For aggregates weighed for payment, the tonnage shall not be adjusted for moisture content, unless otherwise provided for.

6. For standard manufactured items (such as fence, wire, plates, rolled shapes, pipe conduits) identified by gauge, weight, section dimensions, and so forth, such identifications shall be considered the nominal weights or dimensions. Unless controlled by tolerances in cited specifications, manufacturer's tolerances shall be accepted.

B. Earthwork Tolerances - Adjustments of horizontal or vertical alignment, within the tolerances specified in this contract, or shifts of balance points up to 100 feet shall be

MEASUREMENT AND PAYMENT WITH ASPHALT 011250-2

made by the contractor as necessary to produce the designed sections and to balance earthwork. Such adjustments shall not be considered as "Changes."

1.3 UNITS OF MEASUREMENT

A. Payment shall be by units defined and determined according to U.S. Standard measure and by the following:

1. Acre: Make longitudinal and transverse measurements for area computations horizontally.

2. 50lb Bag: Measurement will be for the actual number of 50lb bags of standard bentonite grout.

3. 94lb Bag: Measurement will be for the actual number of 94lb bags of standard cement or grout.

4. Cubic Yard (CY): A measurement computed by one of the following methods:

a. Excavation, Embankment, or Borrow. The measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.

b. Material in Place or Stockpile. The measurement computed using the dimensions of the in-place material.

c. Material in the Delivery Vehicle. The measurement computed using measurements of material in the hauling vehicles at the point of delivery.

Vehicles shall be loaded to at least their water level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.

5. Each (EA): One complete unit, which may consist of one or more parts.

6. Gallons (GAL): The quantity shall be measured by any of the following methods:

a. Measured volume in container.

b. Metered volume by approved metering system.

c. Commercially package volume.

7. Hour (HR): Measurement will be for the actual number of hours (or fraction thereof) ordered by the Contracting Officer and performed by the contractor.

8. Linear Foot (LF): Measurement of work along its length from point-to-point;

parallel to the base or foundation. Do not measure overlaps.

9. Lump Sum (LS): One complete unit.

10. Mile: Measured horizontally along the centerline of each roadway, approach, or ramp.

11. Pound (LB): For sacked or packaged material, measurement will be the net weight as packed by the manufacturer.

12. Square Foot (SF): Measured on a plane parallel to the surface being measured.

13. Square Yard (SY): Measured on a plane parallel to the surface being measured.

14. Ton: Measured as a short ton consisting of 2,000 pounds.

1.4 METHOD OF MEASUREMENT

MEASUREMENT AND PAYMENT WITH ASPHALT 011250-3

A. One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:

1. ACTUAL QUANTITIES (AQ) - These quantities are determined from actual measurements of completed work.

2. DESIGNED QUANTITIES (DQ) - These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units shown in the Schedule of Items may be authorized under any of the following conditions:

a. As a result of changes in the work authorized by the CO.

b. As a result of the CO determining that errors exist in the original design that cause a pay item quantity to change by 15 percent or more.

c. As a result of the Contractor submitting to the CO a written request showing evidence of errors in the original design that cause a pay item quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.

3. LUMP SUM QUANTITIES (LSQ) - These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall not be measured.

4. STAKED QUANTITIES (SQ) - These quantities are determined from staked measurements prior to construction.

5. VEHICLE QUANTITIES (VQ) - These quantities are measured or weighed in hauling vehicles.

PART 2 - PRODUCTS (NOT APPLICABLE)

PART 3 - EXECUTION (NOT APPLICABLE)

END OF SECTION 011250

MOBILIZATION 011900-1

Hilltop Campground Reconstruction Project

SECTION 011900 - MOBILIZATION

PART 1 - GENERAL

1.1 SUMMARY

A. This item is intended to compensate the Contractor for operations including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for payment of premiums for bonds and insurance for the project; and for any other work and operations which must be performed or costs that must be incurred incident to the initiation of meaningful work at the site and for which payment is not otherwise provided for under the contract.

1.2 MEASUREMENT AND PAYMENT

A. The measurement shall be lump sum for mobilization. Payment shall be as follows:

1. Bond premiums will be reimbursed after receipt of the evidence of payment.

2. 50% of the lump sum, not to exceed 5% of the original contract amount, will be paid following completion of 5% of the original contract amount not including mobilization and bond premiums.

3. Payment of the remaining portion of the lump sum, up to 10% of the original contract amount, will be paid following completion of 10% of the original contract amount not including mobilization and bond premiums.

4. Any portion of the lump sum in excess of 10% of the original contract amount will be paid after final acceptance.

5. Progress payments for mobilization and preparatory work shall be subject to retainage.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION 011900

SUBMITTAL PROCEDURES 013300-1

Hilltop Campground Reconstruction Project

SECTION 013300 - SUBMITTAL PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other miscellaneous submittals. See Table 013300-1 for a summary of required submittals.

B. See other specification section within this package for additional requirements on submittal.

1.2 SUBMITTAL PROCEDURES

A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

1. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.

a. The Contracting Officer (CO) reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

B. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on CO's receipt of submittal.

1. Initial Review: Allow 14 days for initial review of each submittal. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.

2. If intermediate submittal is necessary, process it in same manner as initial submittal.

3. Allow 14 days for processing each re-submittal.

4. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.

C. Identification: Place a permanent label or title block on each submittal for identification.

1. Indicate name of firm or entity that prepared each submittal on label or title block.

2. Provide a space on label or beside title block to record Contractor's review and approval markings and action taken by CO.

3. Include the following information on label for processing and recording action taken:

a. Project name.

SUBMITTAL PROCEDURES 013300-2

b. Date.

c. Name and address of Contractor.

d. Name of manufacturer.

e. Unique identifier, including revision number.

f. Number and title of appropriate Specification Section.

g. Drawing number and detail references, as appropriate.

h. If more than one item is shown on submittal sheet, identify item.

D. Deviations: Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.

E. Additional Copies: Unless additional copies are required for final submittal, and unless CO observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.

F. Use for Construction: Use only final submittals with mark indicating action taken by CO in connection with construction.

1.3 MEASUREMENT AND PAYMENT

A. No separate measurement and/or payment will be made for this section. Payment shall be included with work shown in the schedule of items.

PART 2 - PRODUCTS

2.1 ACTION SUBMITTALS – (Submittals requiring CO approval)

A. General: Prepare and submit Action Submittals required by individual Specification Sections.

1. Number of Copies: Submit one copy of each submittal, unless otherwise indicated.

No copies will be returned. Mark up and retain one copy as a Project Record Document.

B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable.

3. Include the following information, as applicable:

a. Manufacturer's written recommendations.

b. Manufacturer's product specifications.

c. Manufacturer's installation instructions.

d. Manufacturer's catalog cuts.

e. Wiring diagrams showing factory-installed wiring.

f. Compliance with recognized trade association standards.

g. Compliance with recognized testing agency standards.

SUBMITTAL PROCEDURES 013300-3

C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.

1. Preparation: Include the following information, as applicable:

a. Dimensions.

b. Identification of products.

c. Fabrication and installation drawings.

d. Roughing-in and setting diagrams.

e. Wiring diagrams showing field-installed wiring, including power, signal, and control wiring.

f. Notation of dimensions established by field measurement.

2. Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring.

D. Contractor's Construction Schedule: The contractor shall submit a Construction Schedule, for approval by CO, in accordance with the contract provisions within 5 day of commencement of work.

E. Samples: Prepare physical units of materials or products, including the following:

1. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.

2.2 INFORMATIONAL SUBMITTALS – (Submittals NOT requiring CO approval)

A. General: Prepare and submit Informational Submittals required by other Specification Sections.

1. Number of Copies: Submit one copy of each submittal, unless otherwise indicated.

CO will not return copies.

2. Certificates and Certifications: Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.

3. Test and Inspection Reports: Comply with requirements in Section 014100 "Quality Control."

B. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements.

C. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements.

D. Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment.

SUBMITTAL PROCEDURES 013300-4

E. Manufacturer's Instructions: Prepare written or published information that documents manufacturer's recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer.

PART 3 - EXECUTION

3.1 GENERAL

A. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to CO.

B. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.

C. CO will not review submittals that do not bear Contractor's approval stamp and will return them without action.

D. Submittals not required by the Contract Documents will not be reviewed and may be discarded.

E. Substitutions – Whenever materials, products, and equipment are listed by name or brand in the specifications and/or on the drawings, it is used as a measure of quality, utility, or standard. If the Contractor prefers to use any other brand or manufacturer of same quality, appearance and utility to that specified, he shall request substitution as provided below, not less than 30 days before the planned installation of the item. The Contracting Officer will approve or disapprove the request for substitution.

F. Requests for substitutions will only be considered if contractor submits the following:

1. Complete technical data including drawings, complete performance specifications, test data, samples and performance tests of the article proposed for substitution.

Submit additional information if required by Contracting Officer. All items in the above information shall be circled, tagged, or marked in some way to indicate all deviations or differences which the proposed item differs from the originally specified item.

2. Similar data as above for item originally specified. All items shall be marked to identify where/how the proposed substitution will differ.

3. A statement by the Contractor that the proposed substitution is in full compliance with the contract documents, applicable codes, and laws.

4. The Contractor shall be responsible for any effect upon related work in the project for any substitution and shall pay any additional costs generated by any substitutions.

3.2 SUBMITTAL SCHEDULE – Submittals shall be made as required by and called for in the drawings and specifications. The following table is a summary of the required

SUBMITTAL PROCEDURES 013300-5

submittals for the project - the table is to assist the Contractor and may not be all inclusive

– additional submittals may be required by specific specifications:

TABLE 013000-1

Spec.

Section Section Title

Sub-sec-tion

Required Submittal

C General Specifications 1.4A Traffic Control Plan 010250 Construction Staking 3.6 A Survey Points 013300 Submittal Procedures 2.1D Construction Schedule 014100 Quality Control 1.3 A Contractor quality control plan 014100 Quality Control 1.3 B Permits, Licenses, and Certificates 014100 Quality Control 1.3 C Test and inspection reports 014100 Quality Control 1.3 D As-Built drawings 023701 Sediment & Erosion Control

Measures 1.2A Sediment & Erosion Control Plan

033000 Cast-in-Place Concrete 1.3A Product Data 033000 Cast-in-Place Concrete 1.3B Design Mix 033000 Cast-in-Place Concrete 1.3C Material Test Reports 033540 Colored Concrete Sidewalk 1.2A Product Sample 047000 Manufactured Masonry 1.3A Product Data, Samples, Qualifica-tions, Instructions 099110 Exterior Painting 1.2A Product Data 099110 Exterior Painting 1.2B Product List 099113 Exterior Paints and Coatings 1.3A-

B Product Data, Samples

101400 Signs 1.2A Sign List Submittal 129400 Family Units 1.2A Product Data 129400 Family Units 1.2B Color Samples 129410 Site Furnishings 1.2A Product Data 129500 Host Utilities 1.1A Product Data 133400 Precast Concrete Utility Building 1.2A Manufacturer’s Literature 133400 Precast Concrete Utility Building 1.2B Shop Drawings 133400 Precast Concrete Utility Building 1.2C Design Calculations 133400 Precast Concrete Utility Building 1.2D Concrete Delivery Certificates 133401 Precast Concrete Vault Restroom

Building 1.2A Manufacturer’s Literature

133401 Precast Concrete Vault Restroom Building

1.2B Shop Drawings

133401 Precast Concrete Vault Restroom Building

1.2C Design Calculations

133401 Precast Concrete Vault Restroom Building

1.2D Concrete Delivery Certificates

221310 Sewage Holding Tank 1.3A Product Data 221310 Sewage Holding Tank 1.3B Shop Drawings 221310 Sewage Holding Tank 1.3C Coordination Drawings

SUBMITTAL PROCEDURES 013300-6

Spec.

Section Section Title

Sub-sec-tion

Required Submittal

221310 Sewage Holding Tank 1.3D Product Certificate 231126 Fac. Liquified-Petroleum Gas Piping 1.3A Field Quality-Control Reports 231126 Fac. Liquified-Petroleum Gas Piping 1.3B Operation and Maintenance Data 312000 Earthwork 1.3A Bedding and Backfill Certification 312000 Earthwork 1.3A Sieve Analysis 312000 Earthwork 1.3B Product Data 312225 Excavation and Embankment 1.3A Density Test Results 312225 Excavation and Embankment 1.3C Blasting Plan 312225 Excavation and Embankment 1.3D Permits and Licenses 321200 Hot Mix Asphalt Paving 1.2A Product Data 321200 Hot Mix Asphalt Paving 1.2B Job Mix Design 321200 Hot Mix Asphalt Paving 1.2C Material Certificate 321204 Crushed Aggregate Base or Surface

Course 1.2A Aggregate Base – Source, Grada-tion, Material Properties 321204 Crushed Aggregate Base or Surface

Course 1.2B Compaction Test Results and

Proctor 322100 Tent Pad Surface Material 2.3 Aggregate Gradation and Certifi-cate of Compliance 322622 Precast Concrete Curb 2.1B Certificate of Conformance –

Concrete Curb 322640 Pavement Markings 1.3A Product Data 332228 Culvert Pipe and Pipe Arches 1.3A Shop Drawings 332228 Culvert Pipe and Pipe Arches 1.3B Fabricator’s Certification 332228 Culvert Pipe and Pipe Arches 1.4A Culvert Locations and Lengths

END OF SECTION 013300

QUALITY CONTROL 014100-1

Hilltop Campground Reconstruction Project

SECTION 014100 - QUALITY CONTROL

PART 1 - GENERAL

1.1 This work shall consist of providing quality control in conformance with the inspection, testing, and product certification requirements of this contract to ensure compliance with the drawings and specifications. The Contractor shall provide all personnel, equipment, tests, and reports necessary to meet the requirements of the contract.

1.2 QUALITY CONTROL

A. The Contractor shall provide and maintain a quality control system that will ensure all services, supplies, and construction work required under this contract conforms to the contract requirements. The Contractor shall perform, or cause to be performed, the sampling, inspection, and testing required to substantiate that all services, supplies, and construction conform to the contract requirements.

B. Special Tests and Inspections: Contractor will engage a testing agency to conduct required special tests and inspections. The Contractor shall authorize the testing agency to perform the required testing and inspections on the work completed. The authority shall include:

1. Testing agency will interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from the Contract Documents.

2. Testing agency will re-test and re-inspect corrected work.

C. Retesting/Reinspecting: Contractor shall provide quality-control services for retesting and reinspection for replaced construction work or for work that failed to comply with the requirements under the contract.

1.3 SUBMITTALS

A. Contractor Quality Control Plan

B. Permits, Licenses, and Certificates

C. Test and Inspection Reports

D. As-Built Drawings

1.4 MEASUREMENT AND PAYMENT

A. No separate payment will be made for the work included under this section; rather payment shall be considered to be included in the items of work listed in the Schedule of Items.

QUALITY CONTROL 014100-2

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION

3.1 QUALITY CONTROL SYSTEM

A. General: Perform required testing, inspections, sampling, and similar services per direction specified in the contract drawings and specifications and in accordance with established industry standards.

3.2 CONTRACTOR QUALITY CONTROL PLAN

A. At the time of the preconstruction conference, the Contractor shall submit for approval a written Contractor Quality Control Plan.

1. If the plan requires any revisions or corrections, the Contractor shall resubmit the plan within 10 days.

2. The Government reserves the right to require changes in the plan during the contract period as necessary.

3. No change in the approved plan may be made without written concurrence by the Contracting Officer.

4. At a minimum, the plan shall include the following:

a. A list of personnel responsible for quality control and assigned duties.

Include each person's qualifications.

b. A copy of a letter of direction to the Contractor's Quality Control Supervisor outlining assigned duties.

c. Names, qualifications, and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms.

d. Methods of performing, documenting, and enforcing quality control of all work.

e. Methods of monitoring and controlling environmental pollution and contamination as required by all applicable regulations and laws.

3.3 TEST AND INSPECTION REPORTS

A. Submit one copy of complete test results no later than three calendar days after the test was performed.

B. Submit failing test results and proposed remedial actions within four hours of noted deficiency.

C. Testing and Inspection Reports shall include the following:

1. Date of issue.

2. Project title and number.

3. Name, address, and telephone number of testing agency.

4. Dates and locations of samples, tests, or inspections.

5. Names of individuals performing tests and inspections.

QUALITY CONTROL 014100-3

6. Reference Specification Section(s).

7. Complete test or inspection data.

8. Test and inspection results and an interpretation of test results.

9. Ambient conditions at time sample was taken, tested, or inspected.

10. Comments or professional opinion on whether tested or inspected work complies with the Contract Document requirements.

11. Name and signature of laboratory inspector.

12. Recommendations on retesting and reinspecting.

3.4 PERMITS, LICENSES, AND CERTIFICATES

A. For Contracting Officer’s records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations relevant to the on performance of the work.

3.5 AS-BUILT DRAWINGS

A. The Contractor shall maintain a set of the contract drawings depicting as-built conditions.

These drawings shall be maintained in a current condition and shall be available for review. All variations from the original contract drawings shall be indicated in red on the drawings. Upon completion of the contract work, as-built drawings shall be submitted to the Contracting Officer.

3.6 SAMPLING, TESTING, AND CERTIFICATION REQUIREMENTS

A. Sampling, testing, and Certification requirements and frequency for specific items shall be as specified in the drawings and specification. The following table is a summary of the required sampling, testing, and certification for the project - the table is to assist the Contractor, but may not be all inclusive – additional submittals may be required by specific specification section:

B.

TABLE 014100-1

Item

Subsection Certification or Test Required

Frequency

033000 2.12 Mixing and Delivery Each Truck 033000 3.13 Concrete – Slump, Air, Tempera-ture 1 composite per truck load delivered 033000 3.13 Concrete - Compression Test Spec-imens at 7 days and 28 days (see spec)

221310 3.4A Holding Tank Leakage Test Until Passing

231126 3.6 LPG Pipe Test, Inspect, & Purge See Spec.

312225 3.12B Moisture-Density Relationship One Test for Each

Soil Type Encoun-tered

QUALITY CONTROL 014100-4

TABLE 014100-1

Item

Subsection Certification or Test Required

Frequency 312225 3.12B Compaction – Road Embankment

(Method 4) One test every 300

sq. yd. of embank-ment per lift 312225 3.12B Compaction – Subgrade One test every 1000

sq. yd. of subgrade 321200 3.9B Gradation and Asphalt Content One per 700 tons or

Min. of 1 per Project 321200 3.9C Field Density Tests – Asphalt One test for every

300 sq. yd. of pave-ment

321204 3.4A Compaction Tests – Road Base and Surface Course

One test for every 300 sq. yd. of aggregate 321204 3.4A Compaction Tests – Aggregate

Base for Concrete Slabs One test for each family unit or group area

321204 3.4A Compaction Tests – Aggregate Base for Concrete Slabs

One test for each prefabricated build-ing pad

END OF SECTION 014100

SEDIMENT AND EROSION CONTROL MEASURES 023701-1

Hilltop Campground Reconstruction Project

SECTION 023701 - SEDIMENT AND EROSION CONTROL MEASURES

PART 1 - GENERAL

1.1 The work under this section consists of furnishing all necessary labor, equipment, materials, and performing all operations in connection with construction sediment and control measures.

A. General

1. All erosion and sediment control measures are to be placed prior to any disturbance caused by demolition, grading and or excavation and shall conform to the requirements of the appropriate regulatory agency for the State.

2. The Contractor shall be solely responsible for ensuring that erosion and sediment control measures are implemented and maintained at the site.

3. Soil disturbing activities include but are not limited to: Clearing and grubbing, excavation for utilities and foundations, roadway and parking lot construction, construction or modification of site drainage, grading, and preparation for final seeding.

1.2 SUBMITTALS

A. The Contractor shall be required to submit a sediment and erosion control plan in accordance with this specification for approval by the Contracting Officer 2 weeks prior to start of work.

1.3 PERMITS

A. The Contractor shall apply for and pay for a National Pollutant Discharge Elimination System (NPDES) permit from the state the project resides in.

1.4 MEASUREMENT AND PAYMENT

A. No separate measurement and/or payment will be made for this section. Payment shall be included with work shown in the schedule of items.

PART 2 - PRODUCTS

2.1 SYNTHETIC FILTER FABRIC FOR SILT FENCES.

A. Pervious sheet of polypropylene, nylon, or polyethylene fabric conforming to the following physical and hydraulic characteristics:

• Physical Properties

(Min.)

Requirement Test Method

SEDIMENT AND EROSION CONTROL MEASURES 023701-2

• Grab Tensile, lbs. W120/F100 ASTM-D-4632

• Grab Elongation, % 15 ASTM-D-4632

• Mullen Burst, psi 275 ASTM-D-3786

• Puncture, lbs. 65 ASTM-D-4833

• Trapezoidal Tear, lbs. 50 ASTM-D-4533

• UV Resistance, % 80 ASTM-D-4355

• AOS, US Sieve # 30/40 ASTM-D-4751

• Permittivity gal/min-sq. ft. 90 ASTM-D-4491

B. Filter fabric should contain ultraviolet ray inhibitors and stabilizers to provide a minimum of 6 months of expected usable construction life at a temperature range of 0 to 120 F.

C. Support Posts: 4 foot - 2 x 2 wood.

2.2 STRAW BALES

A. Oat or wheat straw, free from weeds, viable weed seeds, foreign matter detrimental to plant life, and dry.

1. Grass hay bales are not acceptable.

2. In order to prevent deterioration of the bindings, all bales shall be either wire-bound or string-tied so that bindings are oriented around the sides rather than along the tops and bottoms of the bales.

2.3 STRAW WATTLES OR ROLLS

A. Furnish straw wattles or rolls that are manufactured from weed free straw and wrapped in a tubular photodegradable plastic netting made from 85% high density polyethylene, 14% ethyl vinyl acetate and 1% color for UV inhibition. Conform to the following:

1. Diameter 9 inches min.

2. Netting strand thickness 0.030 inches

3. Netting knot thickness 0.055 inches

4. Mass of netting 0.315 to 0.385 ounces per foot

PART 3 - EXECUTION

3.1 CONSTRUCTION

A. Install straw bales at local drainage ways to prevent silt intrusion upon adjacent drainage courses. Remove straw bales following establishment of vegetation cover and utilize as mulch at swales or on steep slopes.

B. Prior to construction, install silt fence along the downhill construction limits to prevent silt intrusion upon adjacent land.

C. Install sediment and erosion control measures on the down slope toe of all top soil stock piles.

SEDIMENT AND EROSION CONTROL MEASURES 023701-3

D. Maintain and remove all erosion controls as specified.

3.2 DUST CONTROL

A. In areas subject to surface and air movement of dust, where on-site or off-site damage is likely to occur, one or more of the following preventive measures shall be taken for dust control:

1. Minimize the period of soil exposure through the use of temporary ground cover and other temporary stabilization practices.

2. Sprinkle the site with water until surface is wet. Repeat as needed.

3.3 SILT FENCE

A. Silt fences are appropriate for the following general locations:

1. Immediately upstream of the point(s) of runoff discharge from a site before flow becomes concentrated. Below disturbed areas where runoff may occur in the form of overland flow.

2. Along the down slope toe of all top soil stock piles.

B. Materials.

1. Utilize standard strength synthetic filter fabric for sediment barriers. The filter fabric shall be purchased in a continuous roll cut to the length of the barrier to avoid the use of joints. When joints are necessary, filter cloth shall be spliced together only at a support post, with a minimum 6 inch overlap, and securely sealed.

2. The standard strength filter fabric shall be stapled or wired to the fence and 6 inches of the fabric shall be extended into the ground. Filter fabric shall not be stapled to existing trees.

3. Support posts shall be spaced at a maximum 6 feet and driven securely into the ground a minimum of 24 inches.

4. Filter fabric shall be buried a minimum of 12 inches.

5. The height of a silt fence shall not exceed 36 inches. Higher fences may impound volumes of water sufficient to cause failure of the structure.

C. Maintenance.

1. Silt fences and filter barriers shall be inspected immediately after each rainfall and at least daily during prolonged rainfall.

2. Silt fences shall be inspected for depth of sediment, tears, and to see if the fabric is securely attached to the fence posts, and to see that the fence posts are firmly in the ground. Any deficiencies shall be repaired immediately.

3. Should the fabric on a silt fence of filter barrier decompose or become ineffective prior to the end of the expected usable life and the barrier still be necessary, the fabric shall be replaced promptly.

4. Sediment deposits should be removed after each storm event and/or when deposits reach approximately 1/3 the height of the barrier or when the sediments limit or prevent the flow of water through the fabric hydraulic.

SEDIMENT AND EROSION CONTROL MEASURES 023701-4

5. Any sediment deposits remaining in place after the silt fence or filter barrier is no longer required shall be dressed to conform with…