The document is an Invitation to Bid (ITB) issued by the Town of Fairfield, Connecticut, specifically the Engineering Department, for a Culvert Replacement Project on Verna Hill Road. The project involves replacing a damaged 36-inch culvert pipe near the intersection of Verna Hill Road and Hillside Road, which was impacted by Storm Ida and approved by USACE, FEMA, and the Fairfield Inland Wetland Commission. The proposed replacement will be a 36-inch reinforced concrete pipe approximately 24 feet in length, with a potential alternative of a High-Density Polyethylene pipe pending approvals. A mandatory site meeting is scheduled for September 25th, 2025, at 10:00 am, and the project goal is to complete all work by October 30th, 2025, with a 30-day construction timeline.

The project specifications are based on a combination of Town specifications and CT DOT Form 819, with detailed requirements for mobilization, site preparation, excavation, pipe installation, pavement restoration, and environmental considerations. The contractor will be responsible for traffic management, erosion control, utility coordination, and site restoration. A bid bond of 5% of the total estimated bid is required, with small businesses having the option to provide an irrevocable letter of credit or cashier's check. The project includes provisions for potential add-alternate items, such as additional roadway repairs, slope stabilization, and a parapet stone wall repair. The town has allocated funds for police protection and will handle future guiderail installation after project completion.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2026-09 On-Call Service and Repairs – HVAC Controls

TOWN OF FAIRFIELD

INVITATION TO BID

2026-12 Culvert Replacement – Verna Hill Road

The Town of Fairfield (Town) on behalf of its Engineering Department (ENG) is seeking competitive bids from qualified Contractors to provide all labor, material, equipment, and all else necessary for the Verna Hill Road Culvert replacement as specified.

PROJECT OVERVIEW

This project is for the replacement of pipe/culvert under Verna Hill Road located near the intersection of Verna Hill Road and Hillside Road in Fairfield, CT. This culvert experienced damage during Storm Ida and is beyond repair. Replacement is necessary and is approved by USACE and FEMA and the Town of Fairfield Inland Wetland Commission. The damaged pipe is approximately 36 inch x 22 inch ACCMP sleeved within a collapsing 5 ft x 3 ft stone culvert used as a bypass pipe.

There is a “sister” 4.5 ft by 6ft high stone culvert that carries Browns Brook that was not damaged by the storm located approximately 80 ft west of the damaged pipe. The sister stone culvert will remain as is and is not in the project replacement contract.

PROJECT SCHEDULE

The awarded Contractor shall have site access upon contract execution. The Town is anticipating all work to be substantially completed by October 30th, 2025.

SITE VISIT

A site meeting will commence at Verna Hill Road and Hillside Road intersection, Fairfield, CT 06824 at 10:00am Thursday, 25th September 2025 for all prospective bidders who are interested in bidding this project.

Prospective bidders are strongly encouraged to inspect relevant facilities prior to submitting a bid.

No special arrangements or private tours shall be accommodated outside of the scheduled meeting.

While the meeting is non-mandatory, prospective bidders will be required to sign-in at commencement of the meeting. The sign-in sheet will be posted as a Public Notice through the Town’s e-Procurement Portal.

SCOPE OF WORK

The Town proposal to replace the damaged pipe/culvert with a 36inch reinforced concrete pipe, approximately 24 ft in length has received all applicable permits; although a 36 inch High Density Polyethylene Pipe is considered an “add alternate” material pending FEMA approval, budget, supply chain/availability and Contractor schedule that results in road closure. The project will follow CT Soil and Sediment Control Guidelines.

SPECIFICATIONS

The Town will base the specifications on a combination of Town specifications and CT DOT Form 819 specifications.

Because of the small nature of the project, several items have been combined or had the method of payment revised. Most quantities are known and the project has basic limits of construction. Listed in the Bid Pricing Proposal Form and specifications are Add Alternate Items. These are listed in case of additional material is required to stabilize the slope and/or complete the project. The Contractor must follow permit requirements which are listed in the bid package. A pre- Construction meeting between the Town, Contractor and Utilities is required before any disturbance can take place.

Payment for Contract Pay items are listed by quantity and unit price or lump sum and shall include all labor, materials, delivery and equipment to perform the item to complete the project. Any item not specifically listed as a pay item in this contract shall be considered a miscellaneous item to be covered under various pay items.

1. Mobilization & Site Preparation - This will include mobilization, purchasing paperwork, bonding, and project preparation. Also included are erosion and sediment controls required for the project examples are silt fencing, haybales, and (turbidity curtain, if needed depending on Contractor means and methods). Silt fence/haybales or E&S control item (wattles) shall be installed around any stockpiles or downstream of any proposed general ground disturbance. Ref: DOT spec 9.75, 2.19

2. Minor Clearing and Grubbing, Road Excavation, Cut and Removal of Bituminous Concrete Pavement - Project involves minor clearing and grubbing for access and to remove vegetation, old guiderails, unstable stones within work zone, if applicable. Contractor shall perform a neat saw cut in pavement to perform trench work. Reference:

DOT specs sec 2.01, 2.03

3. Tree Removal - The project requires the removal of a cedar tree that abuts the stream (brook). By removing the tree, stumps and roots, this will create a small area that will shift flow away from the roadway slope and provide additional access to the culvert.

4. Removal of Stone Culvert - Work for this item includes but is not limited to structure excavation, general excavation, sandbags or cofferdam for flow diversion, any dewatering, bypass pipes or pumping needed to work in dry or near dry conditions. Ref: DOT sec 5.03

5. Excavation and reuse of existing channel bottom material where the culvert is located. This will include excavation for pipe bedding, reusing the streambed material for placement where tree was located or along edge of toe of slope.

Approval of the Engineer is required for reuse of any material at a location outside of the work area. Stream material reuse area is estimated at 120 square feet, basically the length and width of the culvert.

6. 36 Inch Diameter Reinforced Concrete Pipe - The Contractor shall supply, install and set at proper invert elevation and location 36 inch RCP. Also included in this pay item is a 6 inch concrete anti seep collar to prevent “piping” flow to occur around the pipe AND pipe bedding material – 4 inch thick layer. Contractor to compact around pipe and on top of pipe 12 inches. Ref: DOT Sec.6.86

7. Repair/Restore Stone Headwall - The contractor shall repair or restore stone masonry headwall. Mortar/concrete can be used to help provide stability to the headwall/culvert inlet. This is a lump sum item.

8. Non-woven Geotextile fabric is proposed in the slope stabilization detail. Installation is required where applicable.

Ref: DOT sec. 7.55.

9. Pavement Restoration - Contractor shall furnish and install Binder Course of Bituminous Asphalt meeting DOT specs Sec. 4.06. DPW wants Contractor to install 2 inch lift using Class 2 asphalt mix for Binder. AND….

10. Pavement Restoration – Contractor shall furnish and install Top Course of Bituminous Asphalt meeting DOT specs

Sec.4.06. DPW wants Contractor to install 2 inch lift using class 2 asphalt mix for Top Course.

Contractor shall Roll with a minimum weight 10 ton roller. Prior to overlaying, all cracks greater than 1/8” shall be filled in with liquid bitumastic material. Before paving, paint existing pavement with liquid bituminous tack coat.

11. Processed Aggregate - Contractor to install 4 inch layer of processed aggregate meeting State DOT Specs 3.04.

This will be used as Road subbase.

12. Maintenance and Protection of Traffic - The Contractor shall provide a MUTCD compliant Detour plan. This will include detour signs, road closed signs, jersey barriers and with reflective construction barricades (Type 3) and high intensity flashing light. See attached Detour plan included in bid documents.

13. Uniform Police- The Project will have an allowance of up to 40 hours for police protection. IT is anticipated that there will be 2 Policemen required for the first day of setup and for public traffic control. Additional Police may be required if the intersection of Hillside and Verna Hill Road is affected or for deliveries, large equipment or when needed. Contractor shall utilize “Off Duty Management” to hire Fairfield Police. There is another option that the Town can discuss with the awarded Contractor should this item be modified by the Town.

In the event the Town decides to extend the scope of work or should additional materials be needed for the project; the Town may elect to award add alternates.

This mainly involves if additional material is needed for roadway repairs or slope stabilizations. Also included as an add alternate is for the Contractor to repair a parapet stone wall recently damage by a vehicle.

ADDITIONAL NOTES:

1. The Contractor is to restore the site to its original condition all disturbed or damaged areas including pavement resulting from construction activities.

2. The Contractor at no cost to the Town repair any damage to private or public property including utilities.

3. The Contractor shall utilize the “Call Before You Dig” process prior to any excavation.

4. The Contractor shall also obtain “street Opening permit” through the Town WPCA (sewer office) but shall come at no cost to the Contractor for said permit.

5. All dimensions are approximate and should be verified in the field.

6. For any loam and seed of disturbed areas (none anticipated), the Contractor shall regrade with 4 inches of good quality topsoil with bluegrass fescue mixture at rate of 4 pounds per 1000 square feet and water to insure growth.

7. After completion, the Town will hire its DAS guiderail installer to install a guiderail along unprotected section(s) of Verna Hill Road. The contractor shall provide a small shelf/shoulder for this future installation.

8. The goal for completion of the project is set for Oct 30, 2025. Concurrently the Town is applying for FEMA extension. Update may be posted in addendum. Time for completion of the project is 30 days, unless confirmed supply chain issue or other acceptable delay.

CONSTRUCTION SEQUENCE

(Contractor can provide their own, if approved by Engineering Department.

1. Provide Purchasing paperwork.

2. Follow inland wetland Permit and general permit for USACE, CT DEEP.

3. Secure permits, contract bid awards etc.

4. Preconstruction meeting - coordinate with Town, (utilities, if necessary). Aquarion to cut and cap existing water line.

5. Maintenance and protection of traffic, police, detour signs etc., eventually close road during construction.

6. Install erosion and sediment controls, minor clearing, remove guiderails.

7. Create stream diversion away from road and culvert-remove (Cedar) tree and stump/roots to help shift stream a few feet away from road, use sandbags, or makeshift cofferdam if necessary, depending on flows, weather report.

8. Improve slope stabilization with temporary measures such as concrete block, jersey barrier, large rocks nearby “on site” and other natural materials.

9. Cut bituminous pavement, remove pavement, subbase and subgrade material (10 ft × 18 ft or agreed upon dimensions). Stockpile to reuse any suitable materials.

10. Excavate approximately 7 ft depth from top of roadway for trench for removal of remaining culvert sleeve and stone culvert.

11. Remove any concrete/Corrugated Metal Pipe remnants and collapsing stone culvert.

12. Install pipe stone bedding, where needed upon field conditions.

13. Install new 36 inch Reinforced Concrete Pipe, provide concrete “6inch thick anti seep” collar to avoid future piping effect near but not at inlet.

14. Repair stone facing masonry headwalls. Some limited masonry/concrete may be utilized for stability.

15. Re Install heaviest rip rap/large stones to stabilize slope along road and stream bank.

16. Backfill around and cover pipe-Contractor shall provide compaction around pipe.

17. As contractor backfills trench, Restabilize road slopes, rip rap, soil for pocket plantings, compact in lifts every 6-

12 inches based on field conditions, especially under travelway. Contractor to attempt to follow detail but Town realizes road/stream elevations are set.

18. Where possible, install geotextile (fabric wrapped earth) for additional plantings for stabilization.

19. Reuse and reinstall road sub base for trenched/disturbed areas.

20. Install stockpiled process aggregate for trench/disturbed areas.

21. Pave asphalt binder (bituminous concrete)

22. Pave asphalt top course (bituminous concrete)

23. Loam and seed, vegetate side slopes. Install plantings, (ex. Elderberry, Winterberry, Bayberry, So. Arrowwood, hydroseed w/meadow mix) where applicable.

24. Remove any temporary erosion and sediment control measures.

25. reopen road to traffic and, restore site to pre project conditions.

BID BOND

The BID BOND furnished, as bid security, must be duly executed by the bidder as principal. It must be in the amount equal to five percent (5%) of the total estimated bid, as guarantee that, in case the contract is awarded to the bidder, the bidder will, within ten days thereafter, execute such contract and furnish a Performance Bond and Payment Bond.

Small businesses may elect to obtain an irrevocable letter of credit or cashier’s check in lieu of the Bid Bond. Such surety must also be in an amount equal to at least five percent (5%) of the total estimated bid.

All bid bonds shall be written by a surety company or companies licensed in the State of Connecticut, and shall have at least an A-VII policy holders rating, as reported by A.M. Best Rating Services, or otherwise deemed acceptable by the Town.

The Town always reserves the right to reject surety companies, if an approved surety bond cannot be provided, the bidder shall be deemed non-responsive.

A complete list of certified surety companies can be accessed on the U.S. Government Department of Treasury website:

https://www.fiscal.treasury.gov/fsreports/ref/suretyBnd/c570_a-z.htm

NOTE: Failure to provide a Bid Bond or equivalent security is not cause for a waiver defect. Any bid not accompanied by such security will be excluded from consideration.