PERFORMANCE WORK STATEMENT

REMOVE OLD FLOORING COVERING AND INSTALLATION OF NEW FLOOR COVERING

AT

BUILDING 10810

LACKLAND AIR FORCE BASE

1. SCOPE OF WORK. Contractor shall provide all personnel, equipment, tools, and materials, labor, transportation, and supervision necessary to remove existing floor covering, and install new floor covering in the following building:

Building 10810, 1180 Femoyer Street, Lackland AFB, TX 78236-5405

All activities shall be coordinated with the Food Service Staff Office and Dining Facility Managers. All work shall be accomplished in accordance with product manufacturer’s recommendations and industry standards, and meet all municipal, state, and federal codes, standards, and guidelines.

2. SPECIFIC TASKS: The contractor shall:

a. Remove old carpeting in the dining room area from the facility and dispose of the old materials off of the installation.

b. inspect floor to ensure that all low spots are leveled and the floor is readied for installation of new Vinyl Composite Tile (VCT)

c. Estimated square footage is 9138 (see page five for dimensions) (see page six for area to tile)

d. Install new VCT flooring in the dining room area in Bldg 10810.

e. All tools and supplies must be cleared out of the dining room area at the end of each work period, as to not cause a safety risk to the daily patrons during times of operation.

f. At the conclusion of each work day all areas in which the contractor has been working in must be cleaned as to not cause additional work for the government.

g. For items A, B, D above, this work can be performed after 7:00 PM to 3:00 AM Monday thru Friday and 7:00 AM to 6:00 PM on the weekends.

h. Contractor will move all necessary equipment at the start of each work shift to accomplish the removal of floor covering, floor preparation and installation of new flooring and place equipment back from where it was removed at the end of each day's work.

3. SAFETY: The contractor shall ensure compliance with OSHA Safety and Health Regulations, prior to daily commencement of work, the contractor shall properly secure the work site and locate and secure tools, equipment, and material as necessary to ensure the safety and protection of personnel, equipment and property.

4. ENVIRONMENTAL COMPLIANCE: The contractor shall be responsible for the removal and disposal of all waste generated from unpacking and installation of these products and removal of old flooring. The Contractor shall notify the HAZMAT Pharmacy of any hazardous chemicals.

5. HAZARDOUS AND/OR TOXIC MATERIALS. A hazardous material (HAZMAT) is one that poses a risk to the health and safety of the public, and/or the environment if not properly controlled during the handling, storage, manufacture, processing, packaging, use, disposal, or transportation. Hazardous material may be elements or compounds, and can be found as gases, solids, or liquids. HAZMAT is defined under Section 1910.1200© of Title 29 of the Code of Federal Regulations.

5.1 Contractor shall identify and report HAZMAT usage to the HAZMAT Pharmacy according to local procedures. The contractor shall submit a completed AF Form 3952, Chemical Hazardous Material Request/Authorization listing all HAZMAT that will be used in performance of the contract. Additionally the contractor is required to submit Material Safety Data Sheets (MSDS) for each of the listed materials in accordance with safety regulations.

5.2 The phone number for the Lackland AFB Hazardous Material Pharmacy is 671-5389. A direct Point of Contact will be provided upon contract award.

6. WORKMANSHIP AND REGULATORY COMPLIANCE. This is an occupied building. Materials on site must be kept in such a manner that continuing working operations is not impaired. The contractor shall take precautions to prevent damage to government property. The contractor shall repair or replace damaged items at no additional cost to the government. All analysis, workmanship, and quality control performed under this contract shall conform to published and recognized authoritative sources of good industry standard and practices in compliance with OSHA Standard 1926 Subparts H and O. The contractor will be responsible for any additional cost required to insure compliance to said standards and practices.

7. WASTE DISPOSAL AND ENVIRONMENTAL PROTECTION. At the end of each work day, the contractor shall remove all residual equipment, components, materials, and /or debris generated and disposed of in appropriate government containers. All areas shall be cleaned of debris at the end of each working day and prior to final acceptance of the work.

8. SECURITY AND CLEAN-UP. All facilities shall be secured at the end of each day. The contractor shall ensure that all work accomplished is limited to the terms and conditions outlined in this SOW. The contractor shall coordinate with the government representative(s) designated during the pre-con upon arrival and prior to leaving the work site each day. The government representative(s) will be located in building 7065, Suite 228.

9. WARRANTIES. Installation shall be warranted from defect for one year, and all standard system warranties shall apply. Warranty shall begin the day of completion and acceptance by 802 FSS/FSVF.

10. STORAGE OF LEFT-OVER ITEMS. All items awaiting installation or items that are left over following final installation shall be stored in Bldg 1530, locate at the following address: 410 N Frank Luke Dr., North end Bay E Door 22, San Antonio TX 78226.

11. COMPLETION OF WORK. The contractor shall ensure that work for this project is performed in accordance with the criteria herein, and that all equipment and systems shall be fully operational at the completion of work for this project. All areas in which the contractor has worked or stored items shall be cleaned, i.e. carpet(s) vacuumed, tiled floor(s) swept & mopped.

II. GENERAL INFORMATION

1. POINTS OF CONTACT. Upon award, the contractor will provide to the contracting officer a list of all contract personnel who will be performing services on this contract. The on-site government representative will be designated during the pre-performance conference.

2. HOURS OF WORK: Normal hours of work are 07:00 PM to 3:00 AM Monday thru Friday, and 7:00 AM to 6:00 PM on the weekends.

3. GOVERNMENT FURNISHED SERVICES.

3.1 UTILITIES. The government will provide utilities (water and electricity) and emergency, fire and security police response services.

3.2 POLICE PROTECTION. The 802d Security Forces Squadron shall provide security and law enforcement response and service to the contractor.

3.3 FIRE PROTECTION. The Lackland Fire Departments shall provide initial response, EMS, and fire protection services to the contractor.

4. TRAFFIC REGULATIONS. The contractor employees shall comply with all base traffic regulations, and are subject to random vehicle speed control checks. The contractor’s personnel cited for speeding on the installation may suffer loss of base driving privileges, debarment from the base, or other administrative action. The use of cell phones, except hand-free phones, is prohibited while driving on military installations in San Antonio, TX. (See attached contract clauses LAFB 0009-Cell Phone and LAFB 0010-Security Requirements for solicitations and contracts.)

5. QUALITY ASSURANCE. The government will evaluate the contractor’s performance during various phases of the project. Quality assurance maybe performed randomly by 802 TRW/SE (Wing Safety), 802 FSS/FSVF (Food Service), and /or the contracting officer and representatives. They may observe performance to monitor quality of work, insure cleanliness, and compliance with safety and security procedures. At the time of award, the contractor shall designate a program manager who will be available throughout the project to discuss with the government inspectors any quality issues that may arise.

6. INSPECTION AND ACCEPTANCE. All services performed under this PWS are subject to inspection by the government at the completion of each task. The contractor, at no additional expense to the government, shall promptly correct unsatisfactory services.

III. APPENDIX

1. PUBLICATIONS. The contractor may access the following websites for government forms and publications: Publications: http://www.e-publishing.af.mil/

2. Occupational Safety and health Administration (OSHA): www.osha.gov image1.jpeg image2.png

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .