This document is a Scope of Work (SOW) for deck covering replacement on the USCGC WAESCHE, a United States Coast Guard vessel. The project involves comprehensive flooring upgrades for three specific areas: the Officer Wardroom/Lounge (390 sq ft), First Class Lounge (130 sq ft), and Crew's Lounge (264 sq ft), totaling 784 square feet. The contractor is required to remove existing vinyl and carpet down to bare metal, prepare surfaces according to precise Coast Guard specifications, and install Mannington Amtico Spacia Decking in American Walnut Cocoa color.

The solicitation (Number 11702PR250000363) is issued by the Department of Homeland Security US Coast Guard, with a proposal due date of April 25, 2025, and all work to be completed by June 13, 2025. The project falls under NAICS category 336611 for Ship Building and Repairing, and is not set aside for any specific business category. Key technical requirements include power tool cleaning of surfaces, installing self-leveling underlayment, applying cove base molding, and conducting visual inspections. Contractors must implement extensive protective measures to prevent contamination of vessel components during the renovation, with work to be performed at the Coast Guard facility in Alameda, California.

View the file

Other files

File Type Posted
Scope of work for Deck Covering.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Scope of work for Deck Covering, Vinyl, Demolition and Replace PR #11702PR25XXXXXXX

Purpose and objective:

CGC WAESCHE seeks to purchase materials and service for flooring upgrades to the Wardroom, First Class Lounge, and Crew’s Lounge to have finished by June 6th, 2025.

Scope: This work item describes the requirements for the Contractor to replace deck flooring as identified in Table 1 with Mannington from Amtico Spacia Decking.

Table 1 – Decking System

LOCATION
AREA SQ FEET
DECK MTL
COVER BASE
UNDERLAYMENT REQUIREMENT
AMTICO SPACIA DECKING/ SYSTEM COLOR
SUGGESTED SOURCE OF SUPPLY
Officer Wardroom/ Lounge (1-44-2-L)
390
Steel
Y
Remove all decking material to bare metal
American Walnut Cocoa
Residential Luxury Vinyl, Laminate & Hardwood Flooring | Mannington
First Class Lounge (2-26-1-L)
130
Steel
Y
Remove all decking material to bare metal
American Walnut Cocoa
Residential Luxury Vinyl, Laminate & Hardwood Flooring | Mannington
Crew Lounge (2-47-2-L)
264
Steel
Y
Remove all decking material to bare metal
American Walnut Cocoa
Residential Luxury Vinyl, Laminate & Hardwood Flooring | Mannington

REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 750-WMSL 100-60, Rev C, General Arrangements Hull 3 & Follow (AS3100001)

Guard Drawing 750-WMSL 640-4, Rev -, Arrangements of Living Spaces (ASC640001)

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2012, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2012, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2012, Requirements for Preservation of Ship Structures

Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), 2012, Install Interior Deck Covering Systems

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP11), 2004, Power Tool Cleaning to Bare Metal

The contractor shall:

· Protective measures - general. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces in the vicinity of the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

· Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below listed:

· Chair Securing Clamps

· Visual inspection. The Contractor shall perform a visual inspection of all existing underlayment following vinyl and carpet removal. Submit a CFR.

· The Contractor shall perform all tasks specified in SFLC Std Spec 6341 and herein, to install a new covering system in the location(s) specified in Table 1.

· To minimize distribution to Cutter’s personnel, the Contractor shall propose a work plan to the Coast Guard Inspector.

· Removal. The Contractor shall remove and dispose existing vinyl and carpet and cove base in accordance with SFLC Std Spec 0000 and SFLC Std Spec 6341 at the location specified in the Table 1.

· Cleaning. Power tool clean to bare metal all steel decks in the work areas in accordance with SSPCSP11 (or SSPC-SP 10/NACE No. 2 with dust control). Surfaces shall be completely free of corrosion products, mill scale, dirt, oil, grease, moisture, deteriorated paint, and other surface contaminants.

· In the presence of the Coast Guard Inspector, conduct a visual inspection of the clean deck in the work area for corrosion and deterioration. Submit a CFR to the Coast Guard Inspector.3.3 Vinyl strip Amtico Specia installation. The Contractor shall install Vinyl strip Amtico Specia system at the location specified in Table 1. The Contractor shall prepare existing deck surfaces for Vinyl strip Amtico Specia installation in accordance with SFLC Std Spec 6341 and manufacturer’s instruction.

· The Contractor shall provide and install self level underlayment to achieve level foundation. Underlayment shall be installed so that all installed deck fittings are flush with final decking.

· The Contractor shall provide and install cove base around entire perimeter of the compartment.

· Cove base. Install cove base molding at corners between deck and bulkhead in the work areas specified in Table 1 where applicable in accordance with SFLC Std Spec 6341. Unless otherwise specified, apply caulking compound at other corners.

· Touch-up preservation. The Contractor shall prepare and coat all new and disturbed exterior and interior surfaces to match existing adjacent surfaces, in accordance with SFLC Std Spec) 6310. Abide by all touch-up requirements outlined in SFLC Std Spec) 6310.