11.24.2020 GPPSS Structured Cabling RFP APP A.xlsx
XLSX spreadsheet 86 KB Posted
- Attached to
- Structured Cabling
- Solicitation number
- RFP GPPS 210000000334 2
- Issued by
- Wayne County, Grand Rapids City, Michigan
About this file
This is an Appendix A Required Forms List document for the Grosse Pointe Public School System's Structured Cabling Request for Proposal (RFP), prepared by Plante Moran. The RFP solicits bids for structured cabling installation and infrastructure across seven school buildings: Brownell Middle School, Maire Elementary School, North High School, Richard Elementary School, Parcells Middle School, South High School, and Monteith Elementary School. The project scope includes installation of Category 6 cabling systems, patch panels, backbone fiber cabling, network closets, and related infrastructure components. Bid quantities vary by building, with total requirements including 342 audio/visual data cables, 582 wireless access point cables, 1,153 general data cables, and additional drop allocations across all locations. The project encompasses removal and demolition of existing infrastructure at 19 IDF closets and 2 MDF closets, reinstallation of 326 wireless access points, and creation of 6 new network closets. All cabling systems must include a certified 15-year performance guarantee, and vendors must demonstrate Category 6 certification capability and appropriate bonding and insurance limits.
Bidders must submit all required forms in Microsoft Excel format, including a Proposal Summary Form, Non-Familial Relationship Affidavit, School Safety Affidavit, Comply Exception Form, Iran Economic Sanctions Act Form, Vendor Questionnaire, equipment specifications, bid quantities, and cost schedules. The cost structure requires line-item pricing for base bid costs per building, performance bond percentages, and unit costs for various add/alternate options including Category 6A cabling upgrades, raceway installations, patch panel variations, backbone cabling, and removal/demolition services. Vendors must confirm compliance with all RFP terms and conditions, provide references with three recent projects, demonstrate workforce capacity to complete the project on an accelerated schedule (two shifts daily, six days per week from July 15 through August 15), and indicate ability to hold pricing through 2023 for future phase additions or provide guaranteed percentage discounts off educational list pricing for hardware or cabling costs.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Required Forms List
APPENDIX A
REQUIRED FORMS LIST - Electronic Copy Must be submitted in Microsoft Excel format (See Section 1.4 of the RFP for Submittal Requirements)
| REQUIRED FORMS: |
| The following forms MUST be submitted as a part of your RFP Response |
| Proposal Summary Form |
| Non-familial Relationship Affidavit |
| School Safety Affidavit |
| Comply Exception Form |
| Iran Economic Sanctions Act Form |
| Vendor Questionnaire |
| Specifications |
| Bid Quantities |
| Cost |
| Your bid response must include a completed copy of each form above, in the order listed above. An electronic copy of these forms in a Microsoft Excel (.xls) format must also be submitted. Failure to submit each of the above forms may be cause for rejection of the bid response. |
&"Lato,Regular"&11Appendix A &"+,Bold"&11Grosse Pointe Public School System Structured Cabling RFP
&"+,Bold"&8Prepared by: Plante Moran &"Lato,Regular"&8&P/&N
Proposal Summary
| Proposal Summary |
| * Notice to vendors: Please place in front of bid packet as first page * |
| Company Name |
| Proposal Preparer |
| Phone Number |
| Fax Number |
| Email Address |
| Total Base Bid Cost (per building) | |
| Brownell Middle School | |
| Maire Elementary School | |
| North High School | |
| Richard Elementary School | |
| Parcells Middle School | |
| South High School | |
| Monteith Elementary School | |
| The undersigned, the owner or authorized officer of ___________________________ (the "Contractor"), pursuant to the familial disclosure requirement provided in the Grosse Pointe Public School System (the "District") Request for Proposal for Structured Cabling, hereby represents and warrants that, except as provided below, no familial relationships exist between the owner or any employee of the Contractor and any member of the Board of Education of the School District or the Superintendent of the School District. A list of the School District's Board of Education members at its Superintendent may be found on the District website. |
Addendum Number Dated Initials
| Other Acknowledgments |
| On this ______________day of ________________, 20____, the undersigned declares that he/she has carefully examined the Instructions/Conditions for this Bid and will honor all purchase orders, prices, and specifications set forth in the Request for Proposal. |
The undersigned understands that the Grosse Pointe Public School System reserves the right to accept or reject in whole or in part any and all Proposals, to waive informalities and irregularities therein, to award the contract to other than the lowest bidder, and to award the Contract to one (1) or more Contractors in the Grosse Pointe Public School System's sole and absolute discretion. If award is made to our firm based upon our Proposal, we agree to enter into the attached form of Contract with the Grosse Pointe Public School System to furnish the proposed solution and/or services in strict accordance with the Request for Proposals, the Contract, the Use Agreement, and our Proposal.
My signature certifies that the Proposal as submitted complies with all terms and conditions as set forth in the Request for Proposals, unless specifically enumerated as an exception as part of our Proposal. I hereby certify that I am authorized to sign as a Representative for the firm.
CONTRACTOR HEREBY SUBMITS THIS PROPOSAL PRICING FORM IN ACCORDANCE WITH THE TERMS AND CONDITIONS OF THE RFP.
| Name of Company |
| Authorized Signature |
| Printed Name |
&"Lato,Regular"&11Appendix A &"+,Bold"&11Grosse Pointe Public School System Structured Cabling RFP
&"+,Bold"&8Prepared by: Plante Moran &"Lato,Regular"&8&P/&N
Non-Familial Relationship
| Non-Familial Relationship |
| Affidavit |
| THE AFFIDAVIT SET FORTH BELOW MUST BE EXECUTED ON BEHALF OF |
THE VENDOR AND FURNISHED WITH EVERY BID
| State of |
| County of |
| Tax ID Number |
The undersigned, the owner or authorized officer of ___________________________ (the "Contractor"), pursuant to the familial disclosure requirement provided in the Grosse Pointe Public School System (the "District") Request for Proposal for Structured Cabling, hereby represents and warrants that, except as provided below, no familial relationships exist between the owner or any employee of the Contractor and any member of the Board of Education of the School District or the Superintendent of the School District. A list of the School District's Board of Education members at its Superintendent may be found on the District website.
List any Familial Relationships (If "no exceptions", please state)
| Contractor: |
| By: |
| Its: |
SWORN TO and subscribed before me, a Notary Public, in and for the above named State and County this day of ________, ___________.
| (Notary Public) |
| _________________ County, _________ |
| My Commission Expires: |
| Acting in the County of: |
&"Lato,Regular"&11Appendix A &"+,Bold"&11Grosse Pointe Public School System Structured Cabling RFP
&"+,Bold"&8Prepared by: Plante Moran &"Lato,Regular"&8&P/&N
School Safety Affidavit School Safety Affidavit
THE AFFIDAVIT SET FORTH BELOW MUST BE EXECUTED ON BEHALF OF
THE VENDOR AND FURNISHED WITH EVERY BID
| The Board of Education will not accept this bid without this completed, signed and notarized form |
| School Safety Legislation |
| State of |
| County of |
__________________ , the authorized officer of ______________ (the "Contractor") being duly sworn, certifies, warrants and represents that any and all persons who will work directly or indirectly for the Contractor, including but not limited to employees, agents, vendors, subcontractors or consultants, and who will work at or on any School district property, shall, at all times, be in compliance with MCL 380.1230, 380.1230a, 380.1230c, 3801230d, and 380.1230g and have not been convicted of any "listed offenses". In this regard, Contractor agrees, without limitation, to report within 3 business days to the School District when any such person is charged with a crime listed in Section 1535a(1) of the Revised School Code or a substantially similar law, and to immediately report to Grosse Pointe Public School System if that person is subsequently convicted, pleads guilty or pleads no contest to that crime.
Exceptions:
(If no exceptions, please state "none")
(Affiant) SWORN TO and subscribed before me, a Notary Public, in and for the above named State and County this
_______ day of ________, _________.
(Notary Public)
&"Lato,Regular"&11Appendix A &"+,Bold"&11Grosse Pointe Public School System Structured Cabling RFP
&"+,Bold"&8Prepared by: Plante Moran &"Lato,Regular"&8&P/&N
Comply Exception Comply Exception
| The vendor must clearly indicate whether you either comply or take an exception to any of the sections in this RFP, including all Appendices. A completed form MUST be submitted with every response. |
| Please indicate any sections below that you do not comply with and please |
state your exception and a reason.
Section # RFP Item Exception / Reason
By signing below, you indicate the you fully comply with the RFP, including all parts (RFP, Attachments, Standard Agreement), except as noted above. We agree that if award is made to our firm based upon our Proposal, we agree to enter into the Standard Agreement included in the RFP and furnish the Services in strict accordance with this Request for Proposal, the Standard Agreement and our Proposal
| Signature: |
| Printed Name: |
| Title |
&"Lato,Regular"&11Appendix A &"+,Bold"&11Grosse Pointe Public School System Structured Cabling RFP
&"+,Bold"&8Prepared by: Plante Moran &"Lato,Regular"&8&P/&N
Iran Economic Sanctions Act Iran Economic Sanctions Act
| The Board of Education will not accept this bid without this completed, signed and notarized form |
| AFFIDAVIT OF COMPLIANCE – IRAN ECONOMIC SANCTIONS ACT |
Michigan Public Act No. 517 of 2012
The undersigned, the owner or authorized officer of the below-named contractor (the “Contractor”), pursuant to the compliance certification requirement provided in the Grosse Pointe Public School System (the “School District”) Request For Proposals For Structured Cabling (the “RFP”), hereby certifies, represents and warrants that the Contractor (including its officers, directors and employees) is not an “Iran linked business” within the meaning of the Iran Economic Sanctions Act, Michigan Public Act No. 517 of 2012 (the “Act”), and that in the event Contractor is awarded a contract as a result of the aforementioned RFP, the Contractor will not become an “Iran linked business” at any time during the course of performing any services under the contract.
The Contractor further acknowledges that any person who is found to have submitted a false certification is responsible for a civil penalty of not more than $250,000.00 or 2 times the amount of the contract or proposed contract for which the false certification was made, whichever is greater, the cost of the School District’s investigation, and reasonable attorney fees, in addition to the fine. Moreover, any person who submitted a false certification shall be ineligible to bid on a request for proposal for three (3) years from the date it is determined that the person has submitted the false certification.
CONTRACTOR:
| By: | Name of Contractor |
| Its: | |
| Date: |
| STATE OF | ) | |
| ) | ss. | |
| COUNTY OF | ) |
This instrument was acknowledged before me on the ____ day of __________, 20__, by
| , Notary Public | |
| County, | |
| My Commission Expires: | |
| Acting in the County of: |
&"Lato,Regular"&11Appendix A &"+,Bold"&11Grosse Pointe Public School System Structured Cabling RFP
&"+,Bold"&8Prepared by: Plante Moran &"Lato,Regular"&8&P/&N
Vendor Questionnaire
| Vendor Questionnaire |
| General |
| Company name |
| Company address |
| Contact name |
| Phone |
| Services provided by your firm: |
| Primary |
| Secondary |
| Business structure (corporation, partnership, sole proprietor, other) |
| Number of years in business as the company named above: |
| Work Force: |
| Administrative |
| Field |
| Other |
| Total |
| Companies largest single contract: |
| Annual gross revenue for last three (3) years: |
| 2019 |
| 2018 |
| 2017 |
| Bonding Limits |
| Single Project |
| Aggregate Project |
| Contact who can verify limits |
| Insurance limits (attach a certificate as well) |
| Geographical area of operations for your firm: |
| Please confirm that your hardcopy bid is identical to the electronic copy of the bid. |
| Signature: |
| Printed name: |
| References |
| Reference 1 |
| Organization name |
| Contact name |
| Contact phone |
| Contact email |
| Project description |
| Dates |
| Reference 2 |
| Organization name |
| Contact name |
| Contact phone |
| Contact email |
| Project description |
| Dates |
| Reference 3 |
| Organization name |
| Contact name |
| Contact phone |
| Contact email |
| Project description |
| Dates |
| Personnel |
| Project personnel |
| # of crews prior to 7/15 |
| # of crews per building, per shift (7/15-8/15, M-F) |
| # of crews per building, per shift (7/15-8/15, Sat.) |
| # of staff per crew |
| Composition of crew |
| Average experience of crew |
| Service |
| Is on-site service available? |
| Hourly service rates for system-certified technicians: |
| Normal: |
| After hours: |
| Sunday / holiday: |
| Is there a trip charge? |
If so, what is the trip charge?
If no trip charge, is travel time charged?
If so, explain:
What is the normal service call response time?
Guaranteed maximum?
What is the emergency service call response time?
Guaranteed maximum?
| How do you define an emergency? |
| Explain your established trouble reporting procedures |
| Explain your policy for supporting customers who desire service on a Time & Materials basis - must they commit to a maintenance contract? |
| Do you prioritize maintenance customers over Time & Materials customers? |
| Solution |
| Please indicate any assumptions you made in your proposal. |
| Are you comfortable with the outlined implementation schedule and the work hours? |
| Please confirm that your proposal includes working 2 shifts per day, 6 days a week from 7/15-8/15. |
| Do you have the capacity to complete more than one building? Please indicate the discount, if any, for being awarded more than 1 building (e.g. 2 buildings is 5% off, etc) |
| Please confirm that you have included all required solution components for the quantities listed in this appendix and on the prints, and if your proposal does not include enough you will include these at no additional charge. |
| The District will be undergoing renovations in all buildings through 2023. Please indicate if you will hold your pricing so that the district may add a change order each summer for the next phase of buildings. |
| If you cannot hold your pricing, please indicate if you can guarantee a percentage off of educational list price for hardware. If so, what percentage is that? |
| If you cannot hold your pricing, please indicate if you can guarantee a percentage increase for cabling costs (e.g. in 2022 cabling would cost 1% more than bid pricing). |
| Please confirm that you have included all required solution components for the quantities listed in this appendix and on the prints, and if your proposal does not include enough you will include these at no additional charge. |
| State Cabling Manufacturer/ Model |
| Please list all cabling manufacturers that you are certified to install. |
| Please confirm that you have the necessary tools to certify a Category 6 cabling infrastructure. |
| Do all proposed cabling systems include a certified 15-year performance guarantee? |
| State specifically what organizations are responsible for the certified 15-year warranty. |
| Please include a copy of the performance guarantee with your proposal. |
&"Lato,Regular"&11Appendix A &"+,Bold"&11Grosse Pointe Public School System Structured Cabling RFP
&"+,Bold"&8Prepared by: Plante Moran &"Lato,Regular"&8&P/&N
Specifications
| Equipment Specifications | ||
| This spreadsheet is to be used to provide detail on the equipment necessary to fulfill the requirements as requested in the RFP. Indicate in the right column what brand and model you are proposing, and whether you comply, take exception or exceed the required spec. If exceed or exception, please list what this exception is. | ||
| Item | Requirement | Vendor Response |
Comply/Exceed/Exception
| STRUCTURED CABLING | |
| Patch Panels | |
| Manufacturer | Vendor to indicate manufacturer |
| Model Name | Vendor to indicate model name and number |
| Port Count per Panel | 24 or 48 (can be modular) |
| Performance | Category 6 |
| Port Configuration | 8P8C |
| Port Termination | 110 |
| Mounting Application | Rack |
| Wire Management (front) | One horizontal per patch panel |
| Wire Management (rear) | One horizontal per patch panel |
| Wiring Configuration | T568B |
| Horizontal Cabling | |
| Manufacturer | Vendor to indicate manufacturer |
| Model Name | Vendor to indicate model name and number |
| Performance/Cable Category | Category 6 |
| Jacket Insulation | Plenum |
| Pair Count | 4-Pair |
| Wiring Configuration | T568B |
| Gauge | 24-AWG |
| Connectors | IDC, 110-type jack |
| Standards & Compliance | ANSI/TIA-568.2-D, ISO 11801 Class EA, ANSI/TIA-1096-A, NEC 800, CMP; CMP-LP, CL3P-LP, 802.3bt Type 1, Type 2, Type 3, Type 4 |
| Color | See Inventory for color assignments |
| Certifications | Underwriters Lab (UL), FCC |
| Device Patch Cords | |
| Manufacturer | Vendor to indicate manufacturer |
| Model Name | Vendor to indicate model name and number |
| Performance/Cable Category | Category 6 |
| Jacket Insulation | Non-Plenum |
| Pair Count | 4-Pair |
| Wiring Configuration | T568B |
| Gauge | 24-AWG |
| Connectors | RJ45 |
| Min. Cable Length | 6 ft |
| Standards & Compliance | ANSI/TIA-568.2-D, ISO 11801 Class EA, ANSI/TIA-1096-A,802.3bt Type 1, Type 2, Type 3, Type 4 |
| Color | Blue |
| Certifications | Underwriters Lab (UL), FCC |
| Patch Panel-to-Equipment Patch Cords | |
| Manufacturer | Vendor to indicate manufacturer |
| Model Name | Vendor to indicate model name and number |
| Performance/Cable Category | Category 6 |
| Jacket Insulation | Non-Plenum |
| Pair Count | 4-Pair |
| Wiring Configuration | T568B |
| Gauge | 24-AWG or 26-AWG |
| Connectors | RJ45 |
| Min. Cable Length | 1 ft |
| Qualifications | ANSI/TIA-568.2-D, ISO 11801 Class EA, ANSI/TIA-1096-A,802.3bt Type 1, Type 2, Type 3, Type 4 |
| Color | See Inventory for color assignments |
| Certifications | Underwriters Lab (UL), FCC |
| Backbone Cabling | |
| Manufacturer | Vendor to indicate manufacturer |
| Model Name | Vendor to indicate model name and number |
| Connectors | LC |
| Buffer tube design | Tight Buffer Tube |
| Core Diameter | 9 µm |
| Cladding Diameter | 125 µm |
| Strand Count | 12 |
| Jacket | Armored (dielectric), Plenum (OFNP) |
| Maximum Attenuation | @ 1310nm: .4 dB/km |
@ 1383nm: .4 dB/km @ 1550nm: .4 dB/km Standards & Compliance ANSI/TIA-568-3-D
ISO/IEC 11801, ANSI/ICEA S-83-596
| Power Distribution Unit | |
| Manufacturer | CyberPower (or equivalent) |
| Model Name | PDU15M2F10R (or equivalent) |
| Form-factor | Rack-mounted (19") |
| Input Voltage | 120V |
| Input Plug Type | NEMA 5-15P |
| # of Outlets | 12 |
| Outlet Types | NEMA 5-15R |
| Additional Features | Remote management, digital ammeter |
| Floor-mounted Cabinet | |
| Manufacturer | Hubbell (or equivalent) |
| Model Name | H3S4242 (or equivalent) |
| Rack Units | 47 |
| Rack Mount Spacing | 19" |
| Rack Material | Steel |
| Door Type | Rear and front perforated steel, key-locking |
| Additional Features | Ventilated front, rear, and side panels, top-mounted gland plate, rear and front vertical cable managers, levelers |
| Two-post Relay Rack | |
| Manufacturer | Hubbell (or equivalent) |
| Model Name | CS1973H (or equivalent) |
| Rack Units | 45 |
| Rack Mount Spacing | 19" |
| Rack Material | Extruded Aluminum or Steel |
| Door Type | N/A |
| Additional Features | Vertical cable management |
| Floor-mounted Wall Cabinet | |
| Manufacturer | Middle Atlantic (or equivalent) |
| Model Name | SR-40-28 (or equivalent) |
| Rack Units | 40 |
| Rack Mount Spacing | 19" |
| Rack Material | Steel |
| Door Type | Front perforated steel, key-locking |
| Additional Features | Ventilated side panels, top-mounted gland plate, rear and front vertical cable managers, levelers, reversible hinge |
| Wall-mounted Half Cabinet | |
| Manufacturer | Hubbell (or equivalent) |
| Model Name | HSQ4826 (or equivalent) |
| Rack Units | 26 |
| Rack Mount Spacing | 19" |
| Rack Material | Steel |
| Door Type | Front perforated steel, key-locking |
| Additional Features | Ventilated side panels, top-mounted gland plate, rear and front vertical cable managers |
&"Lato,Regular"&11Appendix A &"+,Bold"&11Grosse Pointe Public School System Structured Cabling RFP
&"+,Bold"&8Prepared by: Plante Moran &"Lato,Regular"&8&P/&N
Quantities
| BID QUANTITIES | ||||||||||
| Cabling Color Standard | Brownell Middle School | Maire Elementary | North High School | Richard Elementary | Parcells Middle School | South High School | Monteith Elementary | Total | Other Considerations | |
| Structured Cabling | ||||||||||
| Audio/Visual Data | Blue | 43 | 20 | 117 | 26 | 42 | 61 | 33 | 342 | Total count of cables indicated. All A/V drops will consist of a single cable per location. Cables will not require faceplates. Locations are specified in Appendix B. |
| Wireless Access Point | Green | 134 | 56 | 332 | 60 | 582 | Total count of cables indicated. All APs will have two cables per location. Cables will not require faceplates. Re-installation of APs is in-scope. Locations are specified in Appendix B. | |||
| General Data | Blue | 244 | 125 | 656 | 128 | 1153 | Total count of cables indicated. Quantity per location is specified in Appendix B. | |||
| Additional Drop Allocation | 50 | 24 | 124 | 24 | 222 | Locations for drop allocations will be determined after project award. | ||||
| Backbone Fiber Runs (# of IDFs) | 4 | 0 | 11 | 0 | 15 | |||||
| AP Removals (qty of APs) | 71 | 39 | 182 | 34 | 326 | |||||
| Est. Cables to Remove | 1000 | 400 | 1500 | 400 | 3300 | |||||
| Network Closets | ||||||||||
| # of Network Closets to be renovated | 3 | 1 | 9 | 0 | 13 | Quantity of closets that will have existing equipment removed and repalced with new cabinets and cable management. Existing cable supports (e.g., ladder rack) can be use where feasible. | ||||
| # of Network Closets to be created | 2 | 0 | 3 | 1 | 6 | For spaces that are newly appointed network closets. Construction to provide coring and plywood backboards into these spaces. | ||||
| MDF Closet Removal/Demolition | 0 | 0 | 1 | 1 | 2 | Quantity of MDF locations requiring equipment removal and full decomission of the space. | ||||
| IDF Closet Removal/Demolition | 11 | 0 | 6 | 2 | 19 | Quantity of IDF locations requiring equipment removal and full decomission of the space. | ||||
| Floor-mounted Cabinet | 0 | 2 | 3 | 0 | 5 | |||||
| Two-post Relay Rack | 0 | 0 | 0 | 0 | 0 | |||||
| Floor-mounted Wall Cabinet | 6 | 0 | 3 | 2 | 11 | |||||
| Wall-mounted Half-Cabinet | 0 | 0 | 8 | 0 | 1 | 9 |
&"Lato,Regular"&11Appendix A &"+,Bold"&11Grosse Pointe Public School System Structured Cabling RFP
&"+,Bold"&8Prepared by: Plante Moran &"Lato,Regular"&8&P/&N
Cost
| COST | |||
| Structured Cabling | Perf. Bond Cost | Total | |
| Base Bid | |||
| Brownell Middle School | |||
| Maire Elementary School | |||
| North High School | |||
| Richard Elementary School | |||
| Parcells Middle School | |||
| South High School | |||
| Monteith Elementary School |
| Performance Bond % (to be used to adjust for any alternates/options selected): | |
| Add / Alternate Costs | |
| Total UPGRADE Cost | |
| A/A 1: Category 6A Cabling - Brownell | |
| A/A 1: Category 6A Cabling - Maire | |
| A/A 1: Category 6A Cabling - North | |
| A/A 1: Category 6A Cabling - Richard | |
| A/A 1: Category 6A Cabling - Parcells | |
| A/A 1: Category 6A Cabling - South | |
| A/A 1: Category 6A Cabling - Monteith |
| Unit Costs | |
| Unit Costs (add/deduct cost must be the same) | Unit Cost |
| Structured Cabling |
| V700 raceway |
(ceiling to 16" AFF with install) V2000 raceway (ceiling to 16" AFF with install) V700 raceway (ceiling to 75" AFF with install) V2000 raceway (ceiling to 75" AFF with install)
| Cat 6 Data Cables - 1 per location |
| Cat 6 Data Cables - 2 at same location |
| Cat 6 Data Cables - 3 at same location |
| Cat 6 Data Cables - 4 at same location |
| Cat 6 Data Cables - 5 at same location |
| Cat 6 Data Cables - 6 at same location |
| Cat 6A Data Cables - 1 per location |
| Cat 6A Data Cables - 2 at same location |
| Cat 6A Data Cables - 3 at same location |
| Cat 6A Data Cables - 4 at same location |
| Cat 6A Data Cables - 5 at same location |
| Cat 6A Data Cables - 6A at same location |
| Move 1 Data Cable |
| 48 port patch panel - Cat 6 |
| 24 port patch panel - Cat 6 |
| 48 port patch panel - Cat 6A |
| 24 port patch panel - Cat 6A |
| Backbone Cabling (300', 12-strand, SMF, armored, enclosures) |
| Backbone Cabling (addl. 50') |
| Network Closet Components |
| Rack-mounted Power Distribution Unit (5-20P Input, w/ Install) |
| Rack-mounted Power Distribution Unit (5-15P Input, w/ Install) |
| Floor-mounted Cabinet (w/ Installation) |
| Two-post Relay Rack (w/ Installation) |
| Floor-mounted Wall Cabinet (w/ Installation) |
| Wall-mounted Half Cabinet (w/ Installation) |
| Removal, Demolition, Reinstallation |
| Wireless Access Point Removal/Reinstallation (per AP) |
| Video Surveillance Camera Removal (per Camera) |
| IDF Demolition |
| MDF Demolition |
| Cabling Removal - 1 per location |
| Cabling Removal - 2 at same location |
| Cabling Removal - 4 at same location |
| Cabling Demo - hourly rate |
&"Lato,Regular"&11Appendix A &"+,Bold"&11Grosse Pointe Public School System Structured Cabling RFP
&"+,Bold"&8Prepared by: Plante Moran &"Lato,Regular"&8&P/&N