This document is an Engineer's Opinion of Probable Construction Cost Estimate prepared by Edgar Hernandez on 11/11/2024 for the New Mexico Department of Transportation (NMDOT) and the City of Rio Communities for the Damon Street Pavement Rehabilitation Project. The project involves roadway improvements including blading and reshaping, prime coat material application, minor paving with hot mix asphalt, removal of existing surfacing, and associated construction engineering and traffic control management. The estimated quantities include 1 mile of blading, 5 tons of prime coat material, 390 tons of hot mix asphalt paving, and 2,350 square yards of surfacing removal.

The total estimated project cost is $186,763.35, which includes roadway work at $168,352.35, construction engineering at $10,830.00, and construction signing at $7,581.00. The cost estimate includes New Mexico Gross Receipts Tax at 8.3%, with no contingency funds allocated. Key line items include mobilization, traffic control management, construction staking, post-construction plans, and traffic control devices. The project appears to be fully funded and ready for procurement, with a comprehensive breakdown of anticipated construction and associated soft costs.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ENGINEER'S OPINION OF PROBABLE CONSTRUCTION COST ESTIMATE

PROJECT NUMBER: HW2L300355

PREPARED BY: Edgar Hernandez

DATE PREPARED: 11/11/2024

CATEGORY: ROADWAY

NMDOT SHORT DESCRIPTION UNIT ESTIMATE ESTIMATE ESTIMATE

ITEM NO. QUANTITY UNIT PRICE AMOUNT

209000 BLADING AND RESHAPING MILE 1 $9,950.00 $9,950.00

408100 PRIME COAT MATERIAL TON 5 $1,200.00 $6,000.00

416104 MINOR PAVING TYPE I, HMA SP-IV TON 390 $215.00 $83,850.00

601110 REMOVAL OF SURFACING S.Y. 2,350 $17.00 $39,950.00

621000 MOBILIZATION LS LS $15,700.00 $15,700.00

SUBTOTAL: $155,450.00

CONTINGENCY (0.0%): $0.00

SUBTOTAL WITH CONTINGENCY: $155,450.00

NMGR TAX @ 8.3000%: $12,902.35

ROADWAY SUBTOTAL: $168,352.35

CATEGORY: CONSTRUCTION ENGINEERING

NMDOT SHORT DESCRIPTION UNIT ESTIMATE ESTIMATE ESTIMATE

ITEM NO. QUANTITY UNIT PRICE AMOUNT

618000 TRAFFIC CONTROL MANAGEMENT LS LS $2,800.00 $2,800.00

801000 CONSTRUCTION STAKING BY THE CONTRACTOR LS LS $4,200.00 $4,200.00

802000 POST CONSTRUCTION PLANS LS LS $3,000.00 $3,000.00

SUBTOTAL: $10,000.00

CONTINGENCY (0.0%): $0.00

SUBTOTAL WITH CONTINGENCY: $10,000.00

NMGR TAX @ 8.3000%: $830.00

CONSTRUCTION ENGINEERING SUBTOTAL: $10,830.00

CATEGORY: CONSTRUCTION SIGNING

NMDOT SHORT DESCRIPTION UNIT ESTIMATE ESTIMATE ESTIMATE

ITEM NO. QUANTITY UNIT PRICE AMOUNT

702810 TRAFFIC CONTROL DEVICES FOR CONSTRUCTION LS 0 $7,000.00 $7,000.00

SUBTOTAL: $7,000.00

CONTINGENCY (0.0%): $0.00

SUBTOTAL WITH CONTINGENCY: $7,000.00

NMGR TAX @ 8.3000%: $581.00

CONSTRUCTION SIGNING SUBTOTAL: $7,581.00

COST ESTIMATE SUMMARY

SHORT DESCRIPTION SUBTOTAL CONTINGENCY GR TAX TOTAL

AMOUNT 0% 8.3000% AMOUNT

ROADWAY $155,450.00 $0.00 $12,902.35 $168,352.35

CONSTRUCTION ENGINEERING $10,000.00 $0.00 $830.00 $10,830.00

CONSTRUCTION SIGNING $7,000.00 $0.00 $581.00 $7,581.00

TOTAL = $172,450.00 $0.00 $14,313.35 $186,763.35