11-BP038 CSP Advertising Request Document.docx.pdf
PDF 370 KB Posted
- Attached to
- BP038 Sitework Package 3 - Package A
- Solicitation number
- CSP 26-037AL
- Issued by
- Fort Bend County, Texas
About this file
BP038 Sitework Package 3 CSP 26-037AL Summary
This is a Competitive Sealed Proposal (CSP) advertising document issued by Fort Bend Independent School District (FBISD) for sitework improvements across 13 school and non-school campuses. FBISD seeks a contractor to provide repairs and improvements to site elements at multiple locations throughout the district. The pre-proposal conference is scheduled for Tuesday, February 3, 2026, at 2:00 PM CST via Microsoft Teams. Pre-proposal walks are scheduled for Wednesday, February 4, and Thursday, February 5, 2026, at 10:00 AM CST at six locations on February 4 and seven locations on February 5, including Progressive High School, First Colony Middle School, Kempner High School, Garcia Middle School, Austin High School, Travis High School, and Crockett Middle School, among others. Proposals are due in three packages on Thursday, February 26, 2026: Package A (Base Bid and all documents except Alternates and SBE documents) due at 2:00 PM CST, and Packages B and C (Alternates and SBE documents) due at 3:00 PM CST. The public bid opening will be conducted via Microsoft Teams at 3:00 PM CST on the same date. The estimated substantial completion of work is July 2027, with Board of Trustees presentation for contract award tentatively scheduled for May 2026.
The estimated construction cost for the project is $4,750,000. Contractors must provide customer reference letters and proof of pertinent experience, including documentation of successful completion of projects within the last three to five years with minimum construction costs of $4,000,000 for K-12 exterior site improvements. Proposals are evaluated on a 100-point system covering price (40 points), experience and reputation (19 points), quality of goods or services (21 points), safety record (5 points), proposed personnel (5 points), financial capability (5 points), and SBE commitment (5 points). All submissions must be made electronically through the FBISD Bonfire e-bidding portal; hard-copy, faxed, or e-mailed submissions will not be accepted. The project is subject to prevailing wage requirements under Texas Government Code Chapter 2258, with prevailing wage rates established for various construction trades in the Texas Gulf Coast Area as of June 2, 2025. Contractors and subcontractors must comply with applicable prevailing wage rates or face penalties of $60 per worker per calendar day for underpayment.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Fort Bend Independent School District
Competitive Sealed Proposal for
BP038 Sitework Package 3
CSP 26-037AL
Package A Base Bid and all documents except Alternates & SBE documents.
DUE NO LATER THAN 2:00 PM Central Time CST February 26, 2026
Package B Alternates and Package C SBE
DUE NO LATER THAN
3:00 PM Central Time CST February 26, 2026
Bids will be opened and read aloud at 3:00 PM. Package A is still due at 2:00 PM CST and will be held by the district until the public opening at 3:00 PM CST.
LATE PROPOSALS WILL NOT BE ACCEPTED
SUBMIT PROPOSAL PACKET THROUGH:
FBISD Bid Portal: https://fortbendisd.bonfirehub.com/portal/
Docusign Envelope ID: 504F5270-F61F-4582-BA60-D12A51FAB890
1/9/2026
1/9/2026
1/9/2026
1/12/2026 https://fortbendisd.bonfirehub.com/portal/
BP038 Sitework Package 3
CSP 26-037AL
BACKGROUND:
Fort Bend ISD (FBISD) is a K-12 public school district in Fort Bend County serving a student enrollment of 78,000. The district currently consists of 83 campuses and multiple administrative sites.
The intention of this Competitive Sealed Proposal (CSP) is to solicit proposals for sitework improvements for 13 campuses (BP038). The estimated construction cost of work for this project
Four Million, Seven Hundred Fifty Thousand Dollars. ($4,750,000.00).
PRE-PROPOSAL CONFERENCE:
A pre-proposal conference will be held on Tuesday, February 3, 2026 at 2:00 PM CST meeting will be held virtually using Microsoft Teams. Attendance is highly recommended in order to have an understanding of the requirements of this CSP. For this pre-proposal meeting, persons with disabilities requiring special accommodations should contact: Antoinette Lewis at
Antoinette.lewis@fortbendisd.gov at least two (2) days before the conference. Any questions/clarifications that result from the visit should be submitted through the Ask a Question section in Bonfire. Meeting Link: Join the meeting now.
WALK SCHEDULE:
A pre-proposal walk is scheduled for Wednesday, February 4 and Thursday, February 5, 2026
10:00 AM CST at:
February 4, 2026
Progressive HS 1555 Independence Blvd., Missouri City, TX 77489
PFC 13600 Murphy Rd., Stafford, TX 77477
First Colony MS 3225 Austin Pkwy., Sugar Land, TX 77479
Sartartia MS 8125 Homeward Bound Way, Sugar Land TX 77479
Administration Bldg. 16431 Lexington Blvd., Sugar Land, TX 77479
Technical Education Center 540 Dulles Ave., Sugar Land, TX 77479
February 5, 2026
Sugar Land MS 321 7th Street, Sugar Land, TX 77498
Kempner HS 14777 Voss Rd., Sugar Land, TX 77498
Kempner AG 14777 Voss Rd., Sugar Land, TX 77498
Garcia MS 18550 Old Richmond Rd., Sugar Land, TX 77498
Austin HS 3434 Pheasant Creek Dr., Sugar Land, TX 77498
Travis HS 11111 Harlem Rd., Richmond, TX 77406
Crockett MS 19001 Beechnut St., Richmond, TX 77407
Attendance is highly recommended in order to have an understanding of existing site conditions and the project’s scope of work.
https://teams.microsoft.com/l/meetup-join/19%3ameeting_NTJmYTIwZmUtZjQ0NC00MzhjLWFiNzQtZDg3NzliZTBmZmI2%40thread.v2/0?context=%7b%22Tid%22%3a%22497d6241-391a-4277-91ac-bdd2a99f7054%22%2c%22Oid%22%3a%220baeac95-4de2-42b8-b2db-9cf3c1c9a596%22%7d mailto:Antoinette.lewis@fortbendisd.gov https://teams.microsoft.com/l/meetup-join/19%3ameeting_Njk1ZGI5MmMtMWRmNy00NWNlLWFhYTAtZDRkNzUzNGMyNWY1%40thread.v2/0?context=%7b%22Tid%22%3a%22497d6241-391a-4277-91ac-bdd2a99f7054%22%2c%22Oid%22%3a%2221f2c5e4-b473-4689-bd5b-4ad0004676b0%22%7d
SPECIAL NOTE:
Please be reminded that all Fort Bend ISD campuses and departments are tobacco, drug, and weapon-free facilities. Contractors are responsible for the conduct of their employees and adherence to Fort
Bend ISD building policies.
QUESTIONS AND ANSWERS:
Any questions or needed clarifications shall be submitted through the Ask a Question section in
Bonfire before the deadline for questions due date and time Wednesday, February 11, 2026 at
10:00 AM CST. Questions received by the deadline and corresponding answers will be included in an Addendum and posted in FBISD e-bidding portal, Bonfire.
All Fort Bend ISD procurement solicitations and addendums can be accessed on Bonfire at https://fortbendisd.bonfirehub.com PLEASE NOTE THAT IT IS THE RESPONSIBILITY OF THE
PROPOSERS TO CHECK FOR ANY ADDENDUMS ON THE BONFIRE ELECTRONIC BIDDING
SYSTEM PRIOR TO SUBMITTING A PROPOSAL.
GENERAL TERMS, CONDITIONS, AND REQUIREMENTS FOR SOLICITATIONS:
This solicitation shall be governed by the documents incorporated herein as well as the Fort Bend
ISD General Provisions for Purchasing Solicitations are incorporated herein. A copy may be obtained at general-provisions-for-purchasing-solicitations-and-contracts.pdf or by contacting the
Fort Bend ISD Buyer listed on the coversheet.
Copy of the Construction contract, the A101 and A 201, are incorporated herein.
Texas Education Code 44.031(a)(5); Texas Government Code Chapter 2269
Purchasing and Acquisition, FBISD Policy CH (Legal)
Purchasing and Acquisition, FBISD Policy CH (Local)
Facilities and Construction, FBISD Policy CV (Legal)
Facilities and Construction, FBISD Policy CV (Local)
Proposers are required to respond to all requests identified in this CSP and indicate their acceptance or objection to the terms of the CSP, the General Provisions, and the terms of the Agreement for Construction
Services. Any exceptions to the terms and conditions in the CSP, the General Provisions, or the Agreement for Construction Services must be clearly indicated in the Proposer’s submitted proposal. Each Proposer, by submitting its proposal, represents that the Proposer has read, understands, and agrees with the CSP, the General Provisions, and the Agreement for Construction Services, excluding any exception specifically made by Proposer in its proposal.
VENDOR COMMUNICATION:
Please remember that during the selection process, FBISD desires to avoid even the perception of preferential treatment.
Therefore:
• Other than the designated contact person listed in this CSP: All Communication regarding this
CSP with District employees, staff, consultants, Architects/Engineers or Board members is strictly forbidden and may result in disqualification.
• All requests for clarification must be provided in writing through the e-bidding portal Ask a
Question section to the designated contact person.
• The answer to the request for clarification and all other communication, clarification, or questions regarding this CSP will be issued in writing to all participating firms through the e-bidding portal
(Bonfire).
https://fortbendisd.bonfirehub.com/documents/view/4551620
Scope of Work
FBISD is seeking a contractor to provide repairs and improvements to site elements across 13 multiple school campuses and non-school campuses.
Contractor Experience and References
Contractor must provide customer references letter in order to receive points in the evaluation criteria section. Contractor must provide proof of pertinent experience (previous educational experience) along with documentation of successful completion of projects completed within the last 3 to 5 years with a minimum construction cost for interior K-12 exterior site improvements for the cost of $4,000,000.
For information and questions regarding this CSP process, please contact:
Senior Buyer: Antoinette Lewis
Email: Antoinette.lewis1@fortbendisd.gov mailto:Antoinette.lewis1@fortbendisd.gov
EVALUATION CRITERIA:
Proposals shall be evaluated using the evaluation criteria listed below, and the scope of work will be awarded by Project. Based on scope of work, FBISD reserves the right to award the Project to the top ranked contractor in the manner that provides the best value to the district based on price and other evaluation criteria.
Evaluation Criteria (Government Code 2269)
Point
System
The price; Section 2269.055.a (1)
Total Proposed Pricing - Provides thoroughly developed, competitive pricing using the tables in Pricing Delivery information section of the CSP
40 points
Offeror’s experience and reputation; Section 2269.055.a (2)
Provides evidence of your experience in planning, staging and delivery of recent projects of similar scope and scale (14 pts)
19 points
Past experience with FBISD and other school districts
Provides a summary of nature of work, on time delivery and quality of work contracted with FBISD and/or other school districts and FBISD’s assessment of the presented summary. (5 pts)
Quality of the offeror’s goods or services; Section 2269.055.a (3)
Contractor’s products should be new and be of the highest quality with an option to substitute for a company branded item of equivalent quality. (14pts)
21 points
Quality of contractor’s response in the proposal
Effectively responds and processes all request for information and documentation included in this CSP (2pts)
Project Plan and schedule (5pts)
Utilization of historically underutilized businesses; Section 2269.055.a (4)
N/A
Offeror’s safety record; Section 2269.055.a (5)
Provides a summary of Experience Modification Rate (EMR) for the last three years, as well as a summary of your company’s safety policies and procedures 5 points
Offeror’s proposed personnel; Section 2269.055.a (6)
Proposed Personnel, personnel directly assigned to work on this project 5 points
Offeror’s financial capability appropriate to the size and scope of the project;
Section 2269.055.a (7)
Provide proof of Insurance, financial stability and Letter of Surety from Bonding
Company
5 points
SBE Commitment; CV (Local) 2017.04
5 points
TOTAL
TIME TABLE:
FBISD anticipates following the time table listed below for this proposal: The time table is only an estimate and actual dates may vary.
Item Activity Date
1. Job starts to advertise (1st run) 1/18/2026
2. Job advertises (2nd run) 1/25/2026
3. Pre-Proposal Conference 2:00 PM CST 2/3/2026
4. Final Questions due 10:00 AM CST 2/11/2026
5a. Proposal Package “A” Due 2:00 PM CST Base Bid and all documents, except Alternates and SBE documents. Click or tap here to enter text.
2/26/2026
5b.
Proposal Package “B” Due 3:00 PM CST Alternates only
2/26/2026
5c.
Proposal Package “C” Due 3:00 PM CST SBE documents only
2/26/2026
6. Presentation to Board of Trustees for contract award (Tentative, subject to change)
05/2026
7. Tabulations and awards posted to https://fortbendisd.bonfirehub.com/portal/?tab=pastOpportunities
05/2026
8. Substantial Completion of the Work 07/2027
SUBMISSION DEADLINE:
Fort Bend ISD will accept proposals submitted electronically through Bonfire e-bidding portal until
Thursday, February 26, 2026 at 2:00 PM CST. https://fortbendisd.bonfirehub.com.
Proposals must be uploaded and finalized prior to the closing date and time. Proposals received after the opening will not be accepted. Public bid opening will be conducted via Microsoft Teams Thursday, February
26, 2026 at 3:00 PM CST. Meeting Link: Join the meeting now.
It is recommended that once you have completed your final submission and received a notice status of “Submission
Complete” from Bonfire, you access your account again and review the documents to verify that the correct content has been provided.
Once the close date has passed, you will be unable to submit an opportunity or make changes to any of the submitted documents. HARD-COPY PAPER FAXED OR E-MAILED SUBMISSIONS WILL NOT
BE ACCEPTED. Only responses properly submitted to FBISD Bonfire Purchasing Portal will be considered.
https://fortbendisd.bonfirehub.com/portal/?tab=pastOpportunities https://fortbendisd.bonfirehub.com/portal/ https://teams.microsoft.com/l/meetup-join/19%3ameeting_YmE0N2Q0MTUtNDZjMC00ODNkLThhOTUtNGUyOTYyZWI5MmM4%40thread.v2/0?context=%7b%22Tid%22%3a%22497d6241-391a-4277-91ac-bdd2a99f7054%22%2c%22Oid%22%3a%2221f2c5e4-b473-4689-bd5b-4ad0004676b0%22%7d
Prevailing Wage Rate
Determination Information
The following information is from Chapter 2258 Texas Government Code:
Sec. 2258.021. Right to be Paid Prevailing Wage Rates.
(a) A worker employed on a public work by or on behalf of the state or a political subdivision of the state shall be paid:
(1) not less than the general prevailing rate of per diem wages for work of a similar character in the locality in which the work is performed; and
(2) not less than the general prevailing rate of per diem wages for legal holiday and overtime work.
(b) Subsection (a) does not apply to maintenance work.
(c) A worker is employed on a public work for the purposes of this section if the worker is employed by a contractor or subcontractor in the execution of a contract for the public work with the state, a political subdivision of the state, or any officer or public body of the state or a political subdivision of the state.
Sec. 2258.023. Prevailing Wage Rates to be paid by Contractor and Subcontractor; Penalty.
(a) The contractor who is awarded a contract by a public body or a subcontractor of the contractor shall pay not less than the rates determined under Section 2258.022 to a worker employed by it in the execution of the contract.
(b) A contractor or subcontractor who violates this section shall pay to the state or a political subdivision of the state on whose behalf the contract is made, $60 for each worker employed for each calendar day or part of the day that the worker is paid less than the wage rates stipulated in the contract. A public body awarding a contract shall specify this penalty in the contract.
(c) A contractor or subcontractor does not violate this section if a public body awarding a contract does not determine the prevailing wage rates and specify the rates in the contract as provided by Section 2258.022.
(d) The public body shall use any money collected under this section to offset the costs incurred in the administration of this chapter.
(e) A municipality is entitled to collect a penalty under this section only if the municipality has a population of more than 10,000.
Sec. 2258.051. Duty of Public Body to Hear Complaints and Withhold Payment.
A public body awarding a contract, and an agent or officer of the public body, shall:
(1) take cognizance of complaints of all violations of this chapter committed in the execution of the contract; and
(2) withhold money forfeited or required to be withheld under this chapter from the payments to the contractor under the contract, except that the public body may not withhold money from other than the final payment without a determination by the public body that there is good cause to believe that the contractor has violated this chapter.
http://www.statutes.legis.state.tx.us/GetStatute.aspx?Code=GV&Value=2258.022 http://www.statutes.legis.state.tx.us/GetStatute.aspx?Code=GV&Value=2258.022
Prevailing Wage Rates – School Construction Trades
June 2, 2025
Texas Gulf Coast Area
CLASSIFICATION
HOURLY RATE
ASBESTOS WORKER $27.20
BRICKLAYER; MASON $24.90
CARPENTER; CASEWORKER $23.13
CARPET LAYER; FLOOR INSTALLER $26.20
CONCRETE FINISHER $23.83
DATA COMM/TELE COMM $24.33
DRYWALL INSTALLER; CEILING INSTALLER $24.33
ELECTRICIAN $29.86
ELEVATOR MECHANIC $39.78
FIREPROOFING INSTALLER $22.99
GLAZIER $23.25
HEAVY EQUIPMENT OPERATOR $22.17
INSULATOR $21.95
IRONWORKER $26.50
LABORER, HELPER $19.81
LATHERER; PLASTERER $22.75
LIGHT EQUIPMENT OPERATOR $28.75
METAL BUILDING ASSEMBLER $24.00
PAINTER; WALL COVERING INSTALLER $20.17
PIPEFITTER $29.82
PLUMBER $27.98
ROOFER $22.50
SHEET METAL WORKER $29.96
SPRINKLER FITTER $23.00
STEEL ERECTOR $26.00
TERRAZZO WORKER $22.75
TILE SETTER $22.00
WATERPROOFER; CAULKER $24.00
This document was developed by PBK Architects, Inc., in strict accordance with Chapter 2258 of the Texas Government Code.
Worker Classification Definition Sheet
CLASSIFICATION DEFINITION
ASBESTOS WORKER Worker who removes and disposes of asbestos materials.
BRICKLAYER; MASON
Craftsman who works with masonry products, stone, brick, block, or any material substituting those materials and accessories.
CARPENTER;
CASEWORKER
Worker who build wood structures or structures of any material which has replaces wood. Includes rough and finish carpentry, hardware and trim.
CARPET LAYER; FLOOR
INSTALLER
Worker who installs carpets and /or floor coverings, vinyl tile.
CONCRETE FINISHER Worker who floats, trowels, and finishes concrete.
DATA COMM/TELE COMM
Worker who installs data/telephone and television cable and associate equipment and accessories.
DRYWALL;
CEILING
INSTALLER
Worker who installs metal framed walls and ceiling, drywall coverings, ceiling grids, and ceilings.
ELECTRICIAN
Skilled craftsman who installs or repairs electrical wiring and devices. Includes fire alarm systems and HVAC electrical controls.
ELEVATOR MECHANIC Craftsman skilled in the installation and maintenance of elevators.
FIREPROOFING INSTALLER Worker who sprays or applies fire proofing materials.
GLAZIER Worker who installs glass, glazing, and glass framing.
HEAVY EQUIPMENT
OPERATOR
Includes but not limited to: all CAT tractors, all derrick-powered, all power operated cranes, back-hoes, back-fillers, power operated shovels, winch trucks, and all trenching machines.
INSULATOR Worker who applies, sprays, or installs insulation.
IRONWORKER Skilled craftsman who erects structural steel framing, and installs structural concrete Rebar.
LABORER, HELPER
Worker qualified for only unskilled or semi-skilled work. Lifting, carrying materials or tools, hauling, digging, clean up.
LATHERER; PLASTERER
Worker who installs metal framing and lath. Worker who applies plaster to lathing and installs associated accessories.
LIGHT EQUIPMENT
OPERATOR
Includes but not limited to , air compressors, truck crane drivers, flex planes, building elevators, form graders, concrete mixers less than 14cf), conveyers.
METAL
BUILDING
ASSEMBLER
Worker who assembles pre-made metal buildings.
PAINTER; WALL COVERING
INSTALLER
Worker who prepares wall surfaces and applies paint and/or wall coverings, tape, and bedding.
PIPEFITTER
Trained worker who installs piping systems, chilled water piping and hot water (boiler) piping, pneumatic tubing controls, chillers, boilers, and associated mechanical equipment.
PLUMBER
Skilled craftsman who installs domestic hot and cold water piping, waste piping, storm system piping, water closets, sinks, urinals, and related work.
ROOFER
Worker who installs roofing materials, Bitumen (asphalt and coal tar) felts, flashings, all types of roofing membranes, and associated products.
SHEET METAL WORKER
Worker who installs sheet metal products, Roof metal, flashings and curbs, ductwork, mechanical equipment, and associated metals.
SPRINKLER FITTER Worker who installs fire sprinklers systems and fire protectant equipment.
STEEL ERECTOR Worker who erects and dismantles structural steel frames of buildings and other structures.
TERRAZZO WORKER Craftsman who places and finishes Terrazzo
TILE SETTER Worker who prepares wall and/or floor surfaces and applies ceramic tiles to these surfaces.
WATERPROOFER;
CAULKER
Worker who applies water proofing material to buildings. Products include sealant, caulk, sheet membranes, and liquid membranes, sprayed, rolled or brushed.
| BACKGROUND: |
| PRE-PROPOSAL CONFERENCE: |
| WALK SCHEDULE: |
| A pre-proposal walk is scheduled for Wednesday, February 4 and Thursday, February 5, 2026 10:00 AM CST at: |
| February 4, 2026 |
| Progressive HS 1555 Independence Blvd., Missouri City, TX 77489 |
| PFC 13600 Murphy Rd., Stafford, TX 77477 |
| First Colony MS 3225 Austin Pkwy., Sugar Land, TX 77479 |
| Sartartia MS 8125 Homeward Bound Way, Sugar Land TX 77479 |
| Administration Bldg. 16431 Lexington Blvd., Sugar Land, TX 77479 |
| Technical Education Center 540 Dulles Ave., Sugar Land, TX 77479 |
| February 5, 2026 |
| Sugar Land MS 321 7th Street, Sugar Land, TX 77498 |
| Kempner HS 14777 Voss Rd., Sugar Land, TX 77498 |
| Kempner AG 14777 Voss Rd., Sugar Land, TX 77498 |
| Garcia MS 18550 Old Richmond Rd., Sugar Land, TX 77498 |
| Austin HS 3434 Pheasant Creek Dr., Sugar Land, TX 77498 |
| Travis HS 11111 Harlem Rd., Richmond, TX 77406 |
| Crockett MS 19001 Beechnut St., Richmond, TX 77407 |
| Attendance is highly recommended in order to have an understanding of existing site conditions and the project’s scope of work. |
| SPECIAL NOTE: |
| QUESTIONS AND ANSWERS: |
| GENERAL TERMS, CONDITIONS, AND REQUIREMENTS FOR SOLICITATIONS: |
| SUBMISSION DEADLINE: |
| Sec. 2258.021. Right to be Paid Prevailing Wage Rates. |
| Sec. 2258.023. Prevailing Wage Rates to be paid by Contractor and Subcontractor; Penalty. |
| Sec. 2258.051. Duty of Public Body to Hear Complaints and Withhold Payment. |