Response_to_Contractor_Questions_2.pdf

PDF 9 KB Posted

Attached to
Land Port of Entry (LPOE) Lamp Replacements at four locations. See the Statement of Work (SOW) for additional details.
Solicitation number
10PSPR-15-0025
Issued by

View the file

Other files

File Type Posted
1-SF_30_RFQ_SOW_Extension.pdf PDF
5-LPOEPriceSheet_revised_6-4-15.xlsx XLSX spreadsheet
Response_to_Contractor_Questions.pdf PDF
1-SF_30_RFQ_SOW_Extension-MERGE.pdf PDF
1-SF_30_RFQ_SOW_Extension-MERGE.pdf PDF
4c-LPOE_Lighting_Price_Sheet.xlsx XLSX spreadsheet
1-SF_30_RFQ_Schedule_Site_Visit-MERGE.pdf PDF
LPOEPriceSheet.xlsx XLSX spreadsheet
CompleteRFQPackage.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

General Services Administration (GSA)

Questions and Answers—Two

RFQ#10PSPR-15-0025—LPOE LED Lighting Project

1. After the successful installation of a LED bulb that works off a MH or HPS ballast, who will be responsible for the removal, replacement and installation of a new MH or HPS ballast if it dies within the warranty period of the LED Bulb?

GSA Response: The General Services Administration will be responsible for any ballasts that may die during the warranty period for the LED Bulb. That being said the preference is for the bulbs to bypass the ballasts, if feasible and cost-effective.

2. Are you requiring a bid bond or insurance?

GSA Response: Neither bid bonds nor insurance are required for this project, as it is going to be a firm-fixed price supply contract.

(End of Question and Answer Two)