102-353 CPM Addendum 1.docx

DOCX document 24 KB Posted

Attached to
Capital Project Manager / Allied Health & Sciences Building Construction
Solicitation number
102-353
Issued by
Rutherford County, North Carolina

About this file

This document is an addendum to a Request for Qualifications (RFQ) issued by Isothermal Community College (ICC) for capital project management and owner's representative advisory services for an Allied Health & Sciences Design-Build construction project. The revised scope of work includes responsibilities across various project phases, such as zoning, permitting, schematic drawings, SCO document review, schedule and budget development, utility relocation, site work, design-build team management, cost/budget and timeline tracking, quality assurance, move management, and closeout documentation. The proposal submission deadline has been extended to 3:00 PM EST on August 26, 2024, with interested parties required to submit two copies - one printed copy sealed and sent to the Vice President of Operations, and one electronic copy sent to the purchasing specialist.

The project is located in North Carolina and is funded by ICC. The addendum clarifies that payment bonds are not a requirement for this project and provides updated details on the project timeline and scope of work responsibilities.

View the file

Other files

File Type Posted
102-353 CPM Addendum 2.pdf PDF
RFQ 102-353 Project Manager.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Isothermal Community College

Refer ALL Inquiries regarding solicitation Madeline Smith mjsmith@isothermal.edu 828-395-1293

RFQ 102-353

Proposals will be publicly opened: August 26. 2024 @ 3:00pm

Owner: Isothermal Community College
Capital Project Management & Owners’ Representative Services

Solicitation Addendum #1 Addendum: #1 Addendum Date: August 19, 2024

RFQ 102-353 Corrections

1) Section #3 Submittal Payment bonds are not a requirement for this project.

2) Section #7 Revised scope of work shall include the following responsibilities.

1. Scope of Work Timeline Project Kickoff Phase (September – December 2024)

· Zoning, permits, schematic drawings, and SCO document review

· Schedule and budget development

Design & Early Site Work Phases (December 2024 – May 2025)

· Relocation of existing utilities, clearing, grading, water, sewer, etc.

· Final document preparation and submission to SCO

Construction Phase (May 2025 – July 2026)

· DB team management

· Cost/budget and timeline tracking

· Quality assurance

Move Management Phase (July 2026 – August 2026)

· Relocation of existing lab and classroom space to new facility

· Furniture procurement and delivery

Closeout Phase (Fall 2026)

· Closeout documentation

· O&M manual development

3) Link to submit electronic proposal is not working.

Interested parties are to submit two copies of their SOQ. One printed copy sealed, sent to Madeline Smith, Vice President of Operations. Along with one electronic copy sent to Kevin Johnson jkjohnson@isothermal.edu , purchasing specialist at Isothermal Community College. By 3:00 PM EST, August 26, 2024.