This is a comprehensive bid document package (Book 2 of 2) for a public improvement project issued by Washington County Department of Land Use & Transportation in Oregon for the Century Boulevard Extension project from SE Lois Street to E Main Street. The project encompasses multiple construction disciplines including roadway widening, water infrastructure, stormwater management, retaining walls, bridge construction over Rock Creek, a flood overflow channel, landscaping, and traffic signal systems. The bid documents include special provisions modifying the 2024 and 2021 Oregon Standard Specifications for Construction, detailed technical requirements for materials and methods, and estimated quantities for all work items. The project is structured as a comprehensive package with two contract time deadlines: completion of lighting work at specific intersections by September 30, 2026; completion of the joint utility trench and conduit work by August 31, 2026; and all remaining work except seeding and plant establishment by October 31, 2027. A preconstruction conference is required within 15 calendar days of the Notice to Proceed, and bidders must comply with extensive submittal requirements including working drawings, traffic control plans, erosion control plans, and utility coordination documentation.
The project is classified as Bridges and Structures with an estimated cost range of $20,000,000 to $50,000,000. Liquidated damages are assessed at $500 per day for the first contract time period, $1,500 per day for the second period, and $3,400 per day for the final period. The contractor must maintain prevailing wage rates as published by Oregon's Bureau of Labor and Industries and provide comprehensive insurance coverage including $2 million per occurrence commercial general liability and $1 million per occurrence commercial automobile liability. The project utilizes an electronic bidding system through OpenGov Procurement and requires electronic document management through ProjectTeam or similar approved platforms for all post-award submissions. Bid guaranties may be submitted as bonds, irrevocable letters of credit, or certified checks. The contract includes provisions for asphalt cement price escalation/de-escalation adjustments and payment retainage options including traditional cash retainage or surety bonds under recently enacted Oregon legislation. Washington County, the City of Hillsboro, and Clean Water Services are designated as additional insureds on all liability policies.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DATE ISSUED: February 2, 2026
BOOK 2 OF 2
OF THE BID DOCUMENTS FOR:
Century Blvd. Extension SE Lois Street to E Main Street
GRADING, DRAINAGE, STRUCTURES, PAVING, SIGNALS, SIGNING, STRIPNG,
ILLUMINATION & LANDSCAPING
BID NUMBER: 2026.013-LUT CPS
PROJECT NUMBER: 100343
A WASHINGTON COUNTY
DEPARTMENT OF LAND USE & TRANSPORTATION
PUBLIC IMPROVEMENT PROJECT
BOOK 2 OF 2
OF THE BID DOCUMENTS
FOR:
PREPARED BY:
WASHINGTON COUNTY
DEPARTMENT OF LAND USE & TRANSPORTATION
CAPITAL PROJECT SERVICES
1400 SW WALNUT STREET, MS#18
HILLSBORO, OR 97123-5625
BID NUMBER: 2026.013-LUT CPS
PROJECT NUMBER: 100343
DATE ISSUED: February 2, 2026
BOOK 2
TABLE OF CONTENTS
PROJECT INFORMATION ................................................................................................................ i
PREVAILING WAGE RATES .......................................................................................................... iii
NON-FIELD TESTED MATERIALS ................................................................................................ iv
ENGINEER OF RECORD CERTIFICATIONS
SPECIAL PROVISIONS
Century Blvd. Extension i Project # 100343 SE Lois Street to E Main Street Bid # 2026.013-LUT CPS
PROJECT INFORMATION
WORK TO BE DONE
The work to be done under this contract consists of the following in Washington County:
1. Construct roadway widening including curbs, curbs and gutters, curb ramps, bike lanes, driveways, and sidewalks.
2. Construct new water lines, water meters, utilities and structure.
3. Construct storm conveyance system and storm water treatment facility.
4. Construct retaining walls.
5. Install Rectangular Rapid Flashing Beacon (RRFBs), and illumination.
6. Install conduits and junction boxes for future signal interconnect.
7. Install new signing and striping.
8. Install/Extend sanitary sewer laterals.
9. Reconstruct/Overlay pavement.
10. Construct a bridge over Rock Creek.
11. Construct Flood Overflow Channel.
12. Construct Landscaping improvements per the Plans.
13. Perform additional and Incidental Work as called for by the Specifications and Plans.
CLASS OF WORK
The Class of Work for this Project is: Bridges and Structures
APPLICABLE SPECIFICATIONS
The Specifications that are applicable to the Work on this Project, for sections 00110 through 00210, is the 2024 edition of the "Oregon Standard Specifications for Construction", as modified by these Special Provisions.
The Specifications that are applicable to the Work on this Project, for sections 00220 and above, is the 2021 edition of the "Oregon Standard Specifications for Construction", as modified by these Special Provisions.
Century Blvd. Extension ii Project # 100343
All number references in these Special Provisions shall be understood to refer to the Sections and subsections of the Standard Specifications bearing like numbers and to Sections and subsections contained in these Special Provisions in their entirety.
PROJECT CONTACTS
Submit questions only in writing on the County's OpenGov Procurement Portal with the Question/Answer feature on the project page: www.washcopurch.com/biz.
Replies to these questions will be posted on the County portal as well.
PROJECT STAFF WILL ONLY RESPOND TO QUESTIONS SUBMITTED IN
WRITING.
Renus Kelfkens, Senior Project Manager 1400 SW Walnut St, MS #18 Hillsboro, OR 97123-5625 Phone: 503-846-7808
Kira Furby, Engineering Associate 1400 SW Walnut St, MS #18 Hillsboro, OR 97123-5625 Phone: 503-969-7990 http://www.washcopurch.com/biz
Century Blvd. Extension iii Project # 100343
PREVAILING WAGE RATES
Prevailing Wage Rates are hereby incorporated into these Specifications by reference, and the text for these publications are available on BOLI’s website at:
https://www.oregon.gov/boli/employers/Pages/prevailing-wage-rates.aspx
The applicable publications are:
• October 5, 2024 – Definitions of Covered Occupations for Public Works Contracts
• January 5, 2026 – Prevailing Wage Rates for Public Works Contracts
• January 5, 2026 – Apprenticeship Rates
You may also request a copy of the rules by calling the Bureau of Labor and Industries directly.
https://www.oregon.gov/boli/employers/Pages/prevailing-wage-rates.aspx
Century Blvd. Extension iv Project # 100343
NON-FIELD TESTED MATERIALS
Non-Field Tested Materials are hereby incorporated into these specifications by reference and are available by visiting the Oregon Department of Transportation website at:
http://www.oregon.gov/ODOT/Construction/Pages/Structure-Services.aspx http://www.oregon.gov/ODOT/Construction/Pages/Structure-Services.aspx
100% Century Blvd 2021 Specs_NV5 Working Version 01162026.docx Page 2
WASHINGTON COUNTY, OREGON
FOR
PROFESSIONAL OF RECORD CERTIFICATION:
Seal w/signature I certify the Special Provision Section(s) listed below are applicable to the design for the subject project for Temporary Features and Appurtenances, Roadwork, Drainage and Sewers, Bases, Wearing Surfaces, Right of Way Development and Control, and Water Supply Systems. Modified Special Provisions were prepared by me or under my supervision.
Section(s) 00210, 00220, 00221, 00222, 00224, 00225, 00228, 00245, 00270, 00280, 00290, 00298, 00305, 00310, 00320, 00330, 00331, 00350, 00390, 00405, 00415, 00440, 00442, 00445, 00470, 00490, 00495, 00620, 00641, 00730, 00744, 00749, 00759, 01300, 02030, 02050, 02320, 02440, 02450, 02510, 02560, 02830, 02910, 02926, 03010.
Date Signed: __________________
1/21/26
Scott Zelenka Digitally signed by Scott Zelenka
DN: C=US,
E=szelenka@emeriodesign.com, O=Emerio Design LLC, CN=Scott Zelenka Date: 2026.01.21 09:54:47-08'00'
100% Century Blvd 2021 Specs_NV5 Working Version 01162026.docx Page 3
Seal w/signature I certify the Special Provision Section(s) listed below are applicable to the design for the subject project for Bridges and Materials. Modified Special Provisions were prepared by me or under my supervision.
Section(s) 00510, 00520, 00530, 00540, 00543, 00545, 00560, 00581, 00582, 00583, 00585,00587, 00589, 00593, 00594, 00596A, 00596C, 103355PE
OREGON
EXPIRES: 12/31/2026
2026.01.20 16:16:59-08'00'
100% Century Blvd 2021 Specs_NV5 Working Version 01162026.docx Page 4
Seal w/signature I certify the Special Provision Section(s) listed below are applicable to the design for the subject project for Pavement Markings, Permanent Signing, Traffic Signals, and Illumination. Modified Special Provisions were prepared by me or under my supervision.
Section(s) 00850, 00855, 00865, 00867, 00868, 00905, 00920, 00930, 00940, 00942, 00950, 00960, 00962, 00963, 00970, 00990.
Date Signed: __________________1/21/2026
Anthony S Yi 2026.01.21 07:40:05-08'00'
100% Century Blvd 2021 Specs_NV5 Working Version 01162026.docx Page 5
Seal w/signature
I certify the Special Provision Section(s) listed below are applicable to the design for the subject project for Landscape and Irrigation. Modified Special Provisions were prepared by me or under my supervision.
Section(s) 01030, 01040 and 01120, 01050, 01065, 01070, 01091, 01120, 01140, 01150, 01160, 01170.
Mike.Smyth Image
Mike.Smyth Text Box January 21, 2026
Century Blvd. Extension 1 Project # 100343
TABLE OF CONTENTS
SECTION 00110 - ORGANIZATION, CONVENTIONS, ABBREVIATIONS AND
DEFINITIONS
SECTION 00120 - BIDDING REQUIREMENTS AND PROCEDURES
SECTION 00130 - AWARD AND EXECUTION OF CONTRACT
SECTION 00140 - SCOPE OF WORK
SECTION 00150 - CONTROL OF WORK
SECTION 00160 - SOURCE OF MATERIALS
SECTION 00165 - QUALITY OF MATERIALS
SECTION 00170 - LEGAL RELATIONS AND RESPONSIBILITIES
SECTION 00180 - PROSECUTION AND PROGRESS
SECTION 00190 - MEASUREMENT OF PAY QUANTITIES
SECTION 00195 - PAYMENT
SECTION 00196 - PAYMENT FOR EXTRA WORK
SECTION 00197 - PAYMENT FOR FORCE ACCOUNT WORK
SECTION 00199 - DISAGREEMENTS, PROTESTS, AND CLAIMS
SECTION 00210 - MOBILIZATION
SECTION 00220 - ACCOMMODATIONS FOR PUBLIC TRAFFIC
SECTION 00221 - COMMON PROVISIONS FOR WORK ZONE TRAFFIC CONTROL
SECTION 00222 - TEMPORARY TRAFFIC CONTROL SIGNS
SECTION 00223 - WORK ZONE TRAFFIC CONTROL LABOR AND VEHICLES
SECTION 00224 - TEMPORARY TRAFFIC CHANNELIZING DEVICES
SECTION 00225 - TEMPORARY PAVEMENT MARKINGS
SECTION 00228 - TEMPORARY PEDESTRIAN AND BICYCLIST ROUTING
SECTION 00245 - TEMPORARY WATER MANAGEMENT
SECTION 00270 - TEMPORARY FENCES
SECTION 00280 - EROSION AND SEDIMENT CONTROL
SECTION 00290 - ENVIRONMENTAL PROTECTION
SECTION 00298 - WELL PRESERVATION AND ABANDONMENT
SECTION 00305 - CONSTRUCTION SURVEY WORK
SECTION 00310 - REMOVAL OF STRUCTURES AND OBSTRUCTIONS
SECTION 00320 - CLEARING AND GRUBBING
SECTION 00330 - EARTHWORK
SECTION 00331 - SUBGRADE STABILIZATION
SECTION 00350 - GEOSYNTHETIC INSTALLATION
SECTION 00390 - RIPRAP PROTECTION
SECTION 00405 - TRENCH EXCAVATION, BEDDING, AND BACKFILL
SECTION 00415 - VIDEO PIPE INSPECTION
SECTION 00440 - COMMERCIAL GRADE CONCRETE
SECTION 00442 - CONTROLLED LOW STRENGTH MATERIALS
SECTION 00445 - SANITARY, STORM, CULVERT, SIPHON, AND IRRIGATION PIPE ... 75
SECTION 00470 - MANHOLES, CATCH BASINS, AND INLETS
SECTION 00490 - WORK ON EXISTING SEWERS AND STRUCTURES
SECTION 00495 - TRENCH RESURFACING
SECTION 00510 - STRUCTURE EXCAVATION AND BACKFILL
SECTION 00520 - DRIVEN PILES
SECTION 00530 - STEEL REINFORCEMENT FOR CONCRETE
SECTION 00540 - STRUCTURAL CONCRETE
SECTION 00543 - ARCHITECTURAL TREATMENT
Century Blvd. Extension 2 Project # 100343
SECTION 00545 - REINFORCED CONCRETE BRIDGE END PANELS
SECTION 00560 - STRUCTURAL STEEL BRIDGES
SECTION 00585 - EXPANSION JOINTS
SECTION 00587 - BRIDGE RAILS
SECTION 00589 - UTILITY ATTACHMENTS ON STRUCTURES
SECTION 00593 - POWDER COATING METAL STRUCTURES
SECTION 00594 - PREPARING AND COATING METAL STRUCTURES
SECTION 00596A - MECHANICALLY STABILIZED EARTH RETAINING WALLS
SECTION 00596C - CAST-IN-PLACE CONCRETE RETAINING WALLS
SECTION 00620 - COLD PLANE PAVEMENT REMOVAL
SECTION 00641 - AGGREGATE SUBBASE, BASE, AND SHOULDERS
SECTION 00730 - EMULSIFIED ASPHALT TACK COAT
SECTION 00744 - ASPHALT CONCRETE PAVEMENT
SECTION 00749 - MISCELLANEOUS ASPHALT CONCRETE STRUCTURES
SECTION 00759 - MISCELLANEOUS PORTLAND CEMENT CONCRETE
STRUCTURES
SECTION 00850 - COMMON PROVISIONS FOR PAVEMENT MARKINGS
SECTION 00855 - PAVEMENT MARKERS
SECTION 00865 - LONGITUDINAL PAVEMENT MARKINGS - DURABLE
SECTION 00867 - TRANSVERSE PAVEMENT MARKINGS - LEGENDS AND BARS
SECTION 00868 - COLORED LANE MARKINGS
SECTION 00902 - CROSSWALK CLOSURE SUPPORTS
SECTION 00905 - REMOVAL AND REINSTALLATION OF EXISTING SIGNS
SECTION 00920 - SIGN SUPPORT FOOTINGS
SECTION 00930 - METAL SIGN SUPPORTS
SECTION 00940 - SIGNS
SECTION 00942 - PERMANENT BARRICADES
SECTION 00950 - REMOVAL OF ELECTRICAL SYSTEMS
SECTION 00960 - COMMON PROVISIONS FOR ELECTRICAL SYSTEMS
SECTION 00962 - METAL ILLUMINATION AND TRAFFIC SIGNAL SUPPORTS
SECTION 00963 - SIGNAL SUPPORT DRILLED SHAFTS
SECTION 00970 - HIGHWAY ILLUMINATION
SECTION 00990 - TRAFFIC SIGNALS
SECTION 01011 - STORMWATER CONTROL, WATER QUALITY AND DETENTION
POND (EXTENDED DRY BASIN)
SECTION 01030 - SEEDING
SECTION 01040 - PLANTING
SECTION 01050 - FENCES
SECTION 01065 - MONUMENT BOXES
SECTION 01070 - MAILBOX SUPPORTS
SECTION 01091 - WATERWAY ENHANCEMENTS
SECTION 01120 - IRRIGATION SYSTEMS
SECTION 01140 - POTABLE WATER PIPE AND FITTINGS
SECTION 01150 - POTABLE WATER VALVES
SECTION 01160 - HYDRANTS AND APPURTENANCES
SECTION 01170 - POTABLE WATER SERVICE CONNECTIONS, 2 INCH AND
SMALLER
SECTION 01300 - UNDERGROUND UTILITY SYSTEM
SECTION 02030 - SUPPLEMENTARY CEMENTITIOUS MATERIALS
SECTION 02050 - CURING MATERIALS
SECTION 02320 - GEOSYNTHETICS
Century Blvd. Extension 3 Project # 100343
SECTION 02440 - JOINT MATERIALS
SECTION 02450 - MANHOLE AND INLET MATERIALS
SECTION 02510 - REINFORCEMENT
SECTION 02560 - FASTENERS
SECTION 02830 - METAL HANDRAIL
SECTION 02910 - SIGN MATERIALS
SECTION 02926 - HIGHWAY ILLUMINATION MATERIALS
SECTION 03000 - FLOOD OVERFLOW CHANNEL
SECTION 03000 - FLOOD OVERFLOW CHANNEL SPECIFICATIONS
SECTION 03010 - FENCING MATERIALS
SUBSECTION 03100 - MISCELLANEOUS ITEMS
SUBSECTION 03101 - ENGINEERING GUIDANCE DURING CONSTRUCTION
SUBSECTION 03102 - MOBILIZATION
SUBSECTION 03103 - DEMOBILIZATION
SUBSECTION 03104 - SURVEY STAKEOUT
SUBSECTION 03105 - AS-BUILT SURVEY
SUBSECTION 03106 - TEMPORARY ROCK CREEK BYPASS
SUBSECTION 03107 - FOC BMPS
SUBSECTION 03200 - GENERAL SITE WORK
SUBSECTION 03201 - CLEARING AND GRUBBING TREES WITHIN FOC
FOOTPRINT
SUBSECTION 03202 - HAUL AND DISPOSE OF EXCESS TREES AND ROOTWADS . 195
SUBSECTION 03203 - EXCAVATE, HAUL AND DISPOSE OF SOIL EXCAVATED
FROM FOC
SUBSECTION 03204 - EXCAVATE, HAUL, AND DISPOSE OF SOIL FROM OVER-
EXCAVATED AREAS
SUBSECTION 03300 - IMPORTED BED MATERIALS
SUBSECTION 03301 - RIPRAP LAYER
SUBSECTION 03302 - BANKRUN GRAVEL LAYER
SUBSECTION 03303 - COBBLE LAYER
SUBSECTION 03304 - TOPSOIL LAYER
SUBSECTION 03400 - BANK STRUCTURES
Century Blvd. Extension 5 Project # 100343
SECTION 00110 - ORGANIZATION, CONVENTIONS, ABBREVIATIONS AND DEFINITIONS
Comply with Section 00110 of the Standard Specifications modified as follows:
00110.05(e) Reference to Websites - Add the following bullet list to the end of this subsection:
American Traffic Safety Services Association (ATSSA) www.atssa.com
B2Gnow washcopurch.mwdbe.com/?TN=washcopurch
EquipmentWatch www.equipmentwatch.com
ODOT Construction Section www.oregon.gov/odot/construction/pages/index.aspx
ODOT Construction Section - Qualified Products List (QPL) www.oregon.gov/ODOT/Construction/Pages/Qualified-Products.aspx
ODOT Estimating www.oregon.gov/ODOT/Business/Pages/Steel.aspx
ODOT Oregon Trucking Online - "Highway Restriction Notice - Size and/or Weight" (Form No.
734-2357) www.oregontruckingonline.com/cf/MCAD/pubMetaEntry/restriction/
ODOT Procurement Office - Conflict of Interest Guidelines and Disclosure Forms www.oregon.gov/ODOT/Business/Procurement/Pages/PSK.aspx
ODOT Procurement Office - Construction Contracts Unit Notice of Intent www.oregon.gov/ODOT/Business/Procurement/Pages/NOI.aspx
ODOT Procurement Office - Construction Contracts Unit prequalification forms www.oregon.gov/odot/business/procurement/pages/bid_award.aspx
ODOT Traffic Control Plans Unit www.oregon.gov/ODOT/Engineering/Pages/Work-Zone.aspx
ODOT Traffic Standards www.oregon.gov/ODOT/Engineering/Pages/Signals.aspx
Oregon Legislative Counsel www.oregonlegislature.gov/lc http://www.atssa.com/ file://nv5.com/shares/ORWIL/Projects/Washington%20County,%20OR/P0021687W.1/Execution/Design/Specifications/Final%20Submittal%20Nov%202025/washcopurch.mwdbe.com/?TN=washcopurch http://www.equipmentwatch.com/ http://www.oregon.gov/odot/construction/pages/index.aspx http://www.oregon.gov/ODOT/Construction/Pages/Qualified-Products.aspx http://www.oregon.gov/ODOT/Business/Pages/Steel.aspx http://www.oregontruckingonline.com/cf/MCAD/pubMetaEntry/restriction/ http://www.oregon.gov/ODOT/Business/Procurement/Pages/PSK.aspx http://www.oregon.gov/ODOT/Business/Procurement/Pages/NOI.aspx http://www.oregon.gov/odot/business/procurement/pages/bid_award.aspx http://www.oregon.gov/ODOT/Engineering/Pages/Work-Zone.aspx http://www.oregon.gov/ODOT/Engineering/Pages/Signals.aspx http://www.oregonlegislature.gov/lc
Century Blvd. Extension 6 Project # 100343
Oregon Secretary of State: State Archives sos.oregon.gov/archives/Pages/default.aspx
OregonBuys https://oregonbuys.gov/bso/view/login/login.xhtml
OpenGov Procurement http://www.washcopurch.com/biz
ProjectTeam https://app.projectteam.com/
00110.10 Abbreviations - Add the following:
BCC - Board of County Commissioners DLUT - Department of Land Use and Transportation ECATS - Washington County Electronic Contract Administration and Tracking System
Delete the following paragraph:
DBE - Disadvantaged Business Enterprise
00110.20 Definitions - Add or modify the following:
Bid Booklet - Delete this definition.
Bid Documents - Replace with the following:
The two Books (Book 1 and Book 2) of the Solicitation Documents and other documents as identified in 00120.10.
Contract Administration Engineer - Add the following:
The County Engineer who presides over the Step 2 claim review under 00199.40.
Contract Documents - Replace with the following:
As defined by Article 2 of the Contract Agreement. See Book 1 of the Bid Documents.
Effective Date of the Agreement - The date recorded on the Contract Agreement when it is executed by the last party to sign.
Extra Work Directive - Written order issued by the Engineer modifying or requesting work and if applicable establishing the basis of payment per Change Order. The cost of this order has to be within the contract approved contingency as stated in the Bid Schedule for Extra Work.
Field Directive - Supplemental instructions, clarifications, and/or minor changes consisting of a written directive which may or may not modify the contract or the contract amount.
file://nv5.com/shares/ORWIL/Projects/Washington%20County,%20OR/P0021687W.1/Execution/Design/Specifications/Final%20Submittal%20Nov%202025/sos.oregon.gov/archives/Pages/default.aspx https://oregonbuys.gov/bso/view/login/login.xhtml http://www.washcopurch.com/biz http://www.washcopurch.com/biz https://app.projectteam.com/
Century Blvd. Extension 7 Project # 100343
Notice to Proceed - Replace with the following:
A written notice to the Contractor from the Agency to begin tasks required of the contractor prior to beginning onsite construction.
Principal Engineer - The Project Delivery Team Chief Engineer who will be presiding over Step 1 level claim review under 00199.40.
Substantial Completion - The Work or specified parts of the Work which are sufficiently complete, in accordance with the Contract Documents in order that they can be utilized by the Agency for the purposes intended as determined by the Engineer.
Work Day - Any and every calendar day from January 1 through December 31 of every year, excluding Saturdays, Sundays, and legal holidays.
Work Hour - For the purpose of bidding and related submittals, any hour in a Work Day between 8:00 a.m. and 5:00 p.m., including lunch-hour, when the Agency is performing regular business.
SECTION 00120 - BIDDING REQUIREMENTS AND PROCEDURES
Comply with Section 00120 of the Standard Specifications modified as follows:
00120.00 Prequalification of Bidders - Add the following bullet to the end of the bullet list:
• If delivered by electronic mail, the application shall be sent to:
ODOTProcurementOfficeConstruction@odot.oregon.gov
Replace the bullet that begins “If delivered by mail…” with the following bullet:
• If delivered by mail or parcel delivery service, the application shall be sent to:
Oregon Department of Transportation Procurement Construction Contracts, MS #33 355 Capitol Street NE Salem, OR 97301
00120.01 General Bidding Requirements - Replace this subsection, except the subsection number and title, with the following:
Bidders may only submit Bids electronically using OpenGov Procurement website (see 00110.05(e)), Bidders shall create a FREE account with OpenGov by signing up at https://procurement.opengov.com/signup.
As and when applicable, the Contractor shall maintain the certifications required by ORS 279A.107.
https://procurement.opengov.com/signup
Century Blvd. Extension 8 Project # 100343
00120.05 Request for Plans, Special Provisions, and Bid Booklets - Replace this subsection with the following:
00120.05 Request for Bid Documents - Bid Documents may be obtained only via the OpenGov Procurement website (see 00110.05(e)). No paper copies of Bid Documents will be made available for prospective bidders.
Plans and specifications are available for viewing at locations listed in the invitation to bid.
00120.10 Bid Booklet - Replace this subsection with the following:
00120.10 Bid Documents - The Bid Documents may include, but are not limited to:
Book 1 - Book 1 includes, but is not limited to:
• Part 1.0, "Bid Information"
• Signature Page
• Bid Guaranty Form
• First-tier Subcontractors Disclosure Form
• Part 2.0, "Contract Forms"
• Contract Agreement
• Performance Bond
• Payment Bond
• Selection of Retainage Option
• Retainage Bond
Book 2 - Book 2 includes, but is not limited to:
• Project Information
• Prevailing Wage Rates
• Non-Field Tested Materials Acceptance Guide
• Special Provisions
Other documents referenced in the Bid Documents, including the Plans and Specifications, are part of the Bid Documents by reference. These include, but are not limited to:
• The "Oregon Standard Specifications for Construction", 2024 Edition, as published by the Oregon Department of Transportation (ODOT).
• The current edition Oregon Standard Drawings as of the date of the Bid
• Manual of Field Test Procedures
• The "Construction Manual", current edition, published by ODOT.
• Certificate of nondiscrimination regarding ORS 279A.110 and certificate regarding policy and practice against sexual harassment, sexual assault and discrimination against employees who are members of a protected class as required by HB 3060 (2017)
00120.15 Examination of Work Site and Solicitation Documents; Consideration of Conditions to be Encountered - Add the following to the end of this subsection:
Century Blvd. Extension 9 Project # 100343
Certain Specifications included in the Project require additional experience or personnel qualifications. Refer to the subsection requirements that may affect bidding considerations, including but not limited to the following:
Subsection Title
00294.30 Personnel Qualifications
00298.30 Personnel Qualifications
00543.30 Personnel Qualifications
00585.30 Personnel Qualifications
00759.30 Personnel Qualifications
00963.30 Personnel Qualifications
00970.30 Personnel Qualifications
00990.31 Personnel Qualifications
01030.30 Personnel Qualifications
00120.16 Material, Equipment, and Method Substitutions - Replace this subsection, except for the subsection number and title, with the following:
Bidders shall not submit proposals for substitute Materials or services. Proposals for substituting Materials or services will only be accepted after the Agency has executed the Contract.
Substitution after Contract execution is specified in 00180.31(b), 00180.31(c), and 00180.31(d).
00120.30 Changes to Plans, Specifications, or Quantities before Opening of Bids - Replace the last sentence of the first paragraph with the following:
The Agency will provide Addenda only by publishing them on the OpenGov Procurement website (see 00110.05(e)).
In the second paragraph, in the sentence that begins "Addenda may…" replace "ODOT eBIDS" with " OpenGov Procurement".
In the third paragraph, in the sentence that begins "Bids may be…" replace "ODOT eBIDS" with " OpenGov Procurement".
Delete the fourth paragraph that begins "In the event that access…".
00120.40(a) General - Replace this subsection, except the subsection number and title, with the following:
Bidders shall prepare and submit Bids using the OpenGov Procurement website (see 00110.05(e)). Bidders shall complete the certifications and statements included in the Bidder Questionnaire Section of the electronic Bid Solicitation Page for the Project according to the instructions.
00120.40(b) Bidding Considerations - Add the following to the end of the list:
00160.20(d) Build America Buy America Act Requirements
00170.89 Protection of Utility, Fire-Control, and Railroad Property and
Service; Repair; Roadway Restoration
00120.40(c)(1) Paper Bid Schedule Entries - Delete this subsection.
Century Blvd. Extension 10 Project # 100343
00120.40(d) Bidder's Address and Signature Pages - Replace this subsection, except for the subsection number and title, with the following:
Bidders shall include in the Bid the address to which all communications concerning the Bid and the Contract should be sent. The Bid signature page shall be completed and must be signed by a duly authorized representative of the Bidder. A scanned electronic copy of the Bid signature page shall be attached with the Bid.
00120.40(e) Bid Guaranty - Revise this subsection as follows:
(1) Bid Guaranty with Paper Bids - Delete this subsection.
(2) Bid Guaranty with Electronic Bids - Replace with the following:
If Bidders elect to provide a Bid bond as a Bid guaranty, use the "Bid Guaranty Form" provided in Book 1 of the Bid Documents. Bidders shall complete and sign the Bid Guaranty Form, make a copy of the Bid Bond, and include an electronic copy of each with the Bid as an attachment.
After the Bid Opening, the Agency may require the bidders to submit the completed and signed Bid Guaranty Form and the original Bid Bond form, with original signatures and the Surety's seal affixed.
If the Bidder chooses to submit a Bid guaranty in the form of an irrevocable letter of credit issued by an insured institution as defined in ORS 706.008, or a cashier's check or certified check made payable to the Agency (see ORS 279C.365(4)), it shall be submitted by mail, or delivery service to the address below, and postmarked before the time of Bid Opening given in the Bid Documents. A postmarked date must be stamped on the delivery envelope by the USPS or any other delivery service, a self-service mailing date stamp will not be accepted.
Washington County Department of Land Use and Transportation Attn: Finance Team Capital Project Services - MS 18 1400 SW Walnut Street Hillsboro, OR 97123
Acceptable Surety companies are limited to those authorized to do business in the State of Oregon. Forfeiture of Bid guaranties is covered by 00130.60 and return of guaranties is covered by 00130.70.
00120.40(f) Disclosure of First-Tier Subcontractors - Replace this subsection, except for the subsection number and title, with the following:
If a Bidder's Bid on a public improvement Project exceeds $100,000, the Bidder shall, within 2 working hours of the time Bids are due to be submitted, submit to the Agency, on a form provided by the Agency, a disclosure identifying any first-tier Subcontractors that will furnish labor or labor and materials, and whose contract value is equal or greater than:
• 5% of the total Project Bid, but at least $15,000; or
• $350,000, regardless of the percentage of the total Project Bid
For each Subcontractor listed, Bidders shall state:
• Name of the Subcontractor
Century Blvd. Extension 11 Project # 100343
• Dollar amount of the subcontract
• Category of Work that the Subcontractor would be performing
If no subcontracts subject to the above disclosure requirements are anticipated, a Bidder shall so indicate by entering "NONE" or by filling in the appropriate check box. For each Subcontractor listed, Bidders shall provide all requested information. An incomplete form will be cause for rejection of the Bid.
The First Tier Subcontractors Disclosure Form shall be completed and submitted electronically using only one of the following two options:
1. Submit with Bid using OpenGov Procurement website, OR
2. Submit via a linked project solicitation on the OpenGov Procurement website. This solicitation will be activated at the time of Bid Opening and will only be accessible for two hours. The title of this website page will be the project name along with the words “First-Tier Subcontractors Disclosure”.
The Agency is not responsible for partial, failed, illegible or partially legible submittals, and such forms may be rejected as incomplete. First Tier Subcontractors Disclosure forms submitted by email, by fax, or in person, will not be accepted.
00120.40(g) Disclosure of Conflict of Interest - Delete this subsection.
00120.45 Submittal of Bids - Replace this subsection, except for the subsection number and title, with the following:
Bids shall be submitted electronically using OpenGov Procurement website (see 00110.05(e)). It is the responsibility of the bidder to submit electronic bids before the deadline date and time as posted on OpenGov. Agency is not responsible for problems with the Internet, Bidders should make sure that all documents are uploaded well in advance of the deadline. The County's OpenGov system will close promptly at the published Bid deadline date and time.
00120.60 Revision or Withdrawal of Bids - Replace this subsection, except for the subsection number and title, with the following:
Information entered into the Bid Document by the Bidder may be changed after the Bid has been uploaded to OpenGov up to the time of Bid Closing.
A Bidder may withdraw their Bid after it has been uploaded to OpenGov up to the time of Bid Closing.
00120.65 Opening and Comparing Bids - Replace the first paragraph with the following:
All Bids received will be opened immediately after the time stated in the "Invitation to Bid" (Advertisement), and the total price for each Bidder's Bid will be read publicly at that time. Bidders and other interested parties are invited to be remotely present via Microsoft Teams. A link to the online bid opening will be posted on the OpenGov Procurement website.
Century Blvd. Extension 12 Project # 100343
Add the following subsection:
00120.68 Mistakes in Bids:
(a) General - Clarifications to or withdrawal of a Bid after bid opening because of an inadvertent, non-judgmental mistake in the Bid requires careful consideration by the Agency to protect the integrity of the competitive bidding system and to assure fairness to all Bidders.
Bid correction or withdrawal by reason of a non-judgmental mistake is permissible, but only to the extent it is not contrary to the interest of the Agency or the fair treatment of other Bidders.
(b) Mistakes Discovered After Bid Closing but Before Award - This subsection prescribes standards to be applied in situations where mistakes in Bids are discovered after the time and date set for bid closing, but before Award.
(1) Minor Informalities - Insignificant mistakes of form that are evident from the Bid Documents and do not affect price, quality, quantity, delivery, or contractual obligations except in the case of informalities involving unit price. Minor informalities can be waived or corrected promptly without prejudice to other Bidders or to the Agency. Examples include, but are not limited to:
• Failure to return the number of signed bids or the number of other documents as required by the Bid Documents.
• Failure to sign the bid form in the designated block so long as a signature appears in the Bid Documents evidencing an intent to be bound.
• Failure to acknowledge receipt of an Addendum to the Bid Documents but only:
• If it is clear from the Bid that the Bidder received the Addendum and intended to be bound by its terms, or
• If the Addendum involved had a negligible effect on price, quality, quantity, or delivery.
00120.70 Rejection of Non-responsive Bids - Delete the fifth bulleted item which begins with “The Bid is submitted..”, the seventh bulleted item which begins with “The Bid has entries..”, and eighth bulleted item which begins with “Each Change..”.
Replace the 20th bulleted item which begins "An electronic Bid…" with the following:
• The Bidder has failed to comply with all requirements of OpenGov.
Replace the last bulleted item which begins "The Bidder has liquidated…" with the following:
• The Bidder has liquidated and delinquent debt owed to Washington County or any department or agency of the County.
Add the following bullet to the end of the bullet list:
• The Agency determines that any Pay Item is significantly unbalanced to the potential detriment of the Agency.
Delete the bullet that begins “The Bidder has not complied with the DBE…”.
00120.95 Opportunity for Cooperative Arrangement - Delete this subsection.
Century Blvd. Extension 13 Project # 100343
SECTION 00130 - AWARD AND EXECUTION OF CONTRACT
Comply with Section 00130 of the Standard Specifications modified as follows:
00130.10 Award of Contract - Replace the paragraph that begins with "The Agency will provide Notice…" with the following:
The Agency will provide Notice of Intent to Award on the OpenGov Procurement website (see 00110.05(e)).
00130.15 Right to Protest Award - Replace this subsection, except for the subsection number and title, with the following:
Within 7 calendar days following the date of Notice of Intent to Award, any adversely affected or aggrieved Bidder may submit a written protest to the Purchasing Manager in accordance with Section No. 5 of the Preface “Protest of Award - Protests and Judicial Review of Contract Award” in the Project Page on the OpenGov Procurement website. The protest shall specify the grounds upon which the protest is based.
The Agency is not obligated to consider late protests.
00130.30 Contract Booklet - Replace this subsection with the following:
00130.30 Contract Document - The Contract Document may include but is not limited to:
• Special Provisions
• Addenda
• Schedule of Items
• Contract Agreement
• Performance Bond
• Payment Bond
• Certification of workers' compensation coverage
00130.40 Contract Submittals - Add the following paragraph to the beginning of this subsection:
The Agency, in its sole discretion, may require execution of documents identified in subsections (a), (b) and (c) with a form of electronic signature (including but not limited to sealing and signing) acceptable to the Agency.
00130.40(c) Workers' Compensation - Replace this subsection, except for the subsection number and title, with the following:
To certify compliance with the workers' compensation insurance coverage required by 00170.61(a) and 00170.70(e), the successful Bidder shall provide evidence of such insurance coverage acceptable to the Agency.
Century Blvd. Extension 14 Project # 100343
00130.40(f) Selection of Retainage Option - The successful Bidder shall furnish the Agency the completed and signed Selection of Retainage Option form.
00130.50 Execution of Contract and Bonds - Add the following paragraph to the end of this subsection:
The Agency, in its sole discretion, may require execution of documents identified in subsection
(a) with a form of electronic signature (including but not limited to sealing and signing) acceptable to the Agency.
00130.50(a) By the Bidder - Replace the first paragraph with the following:
The successful Bidder shall deliver the Performance Bond, Payment Bond, evidence of Workers' Compensation Coverage, the required Certificate of Insurance, and a completed Selection of Retainage Option form to the Agency in accordance with 00130.40 within 10 calendar days after the date of Award Letter. Insurance certificates and the Selection of Retainage Option form can be submitted electronically, original Performance and Payment Bonds are required. The Agency will prepare the contract document and send it to the Bidder electronically for an electronic signature, the Bidder shall review, electronically sign, and return the contract document within 3 days.
The successful bidder agrees that Bonds will be dated effective the same day as the contract.
Certificates of insurance for coverages that are permitted by the Agency under 00170.70(a) to be obtained by appropriate Subcontractors shall be delivered electronically by the Contractor to the Agency together with the Contractor's request under 00180.21 for approval of the subcontract with that Subcontractor.
The Agency, in its sole discretion, may require execution of documents identified in subsection
(a) with a form of electronic signature (including but not limited to sealing and signing) acceptable to the Agency.
00130.50(b) By the Agency - Replace "7 Calendar Days" with "30 Calendar Days".
00130.80 Project Site Restriction - Replace the first paragraph which begins “Until the Agency sends …” with the following:
Until the Agency sends the Contractor written First Notification with the Work, and the Contractor has filed the public works bonds required in 00170.20, the Contractor shall not go onto the Project Site on which the Work is to be done, nor move Materials, Equipment, or workers onto that Project Site.
00130.90 Notice to Proceed - Replace “5 Calendar Days” with “21 Calendar Days”.
Century Blvd. Extension 15 Project # 100343
SECTION 00140 - SCOPE OF WORK
Comply with Section 00140 of the Standard Specifications modified as follows:
00140.60 Extra Work - Add the following:
When listed in the Bid Schedule, the amount(s) listed for the pay items under "Extra Work" are estimated amount(s) to provide adequate funding and bonding to cover Extra Work items if required by the Engineer.
SECTION 00150 - CONTROL OF WORK
Comply with Section 00150 of the Standard Specifications modified as follows:
00150.05 Cooperative Arrangements - Delete this subsection.
00150.15(b) Agency Responsibilities - Replace this subsection, except for the subsection number and title, with the following:
The Engineer will perform the responsibilities described in 00305.04.
00150.15(c) Contractor Responsibilities - Replace this subsection, except for the subsection number and title, with the following:
Perform the responsibilities described in 00305.05.
00150.30 Delivery of Notices - Replace the words “Doc Express” with “ProjectTeam” In the two bulleted items following the paragraph that begins with "Following Notice to Proceed, all notices…".
00150.35 Plans, 3D Engineered Models, Working Drawings, and 3D Models - Replace this entire subsection with the following subsection:
00150.35 Plans and Working Drawings:
(a) Plans - The Plans will show details of lines, grades, and Typical Section of the Roadway, and locations and design details of Structures.
(b) Working Drawings - The Contractor shall supplement the Agency-prepared Plans with stamped or unstamped Working Drawings that show all information necessary to complete the Work. The applicable Section or Subsection of the Standard Specifications will indicate the supplemental information required and whether the drawings are to be stamped or unstamped.
Stamped and unstamped Working Drawings are defined as follows:
Century Blvd. Extension 16 Project # 100343
(1) Stamped Working Drawings - Working Drawings, calculations, and other data which are prepared by or under the direction of a Professional Engineer licensed in the State of Oregon, and which bear the engineer's signature, seal, and expiration date.
(2) Unstamped Working Drawings - Working Drawings, calculations, and other data that do not bear an engineering seal.
(c) Number and Size of Drawings - The Contractor shall submit Working Drawings according to one of the following methods:
(1) Paper Submittal - For paper submissions, submit seven copies of Working Drawings for steel Structures and six copies of Working Drawings for other Structures to the Engineer.
The submitted copies shall be clear and readable. Drawing dimensions shall be 8 1/2 inches by 11 inches, 11 inches by 17 inches, or 22 inches by 36 inches in size. One copy of the submitted Working Drawings will be returned to the Contractor after processing. The Contractor shall submit such additional number of copies to the Engineer for processing that the Contractor would like to have returned.
(2) Electronic Submittal - The Contractor shall submit electronic Working Drawings as directed by the Engineer.
(d) Processing Working Drawings - The Engineer will process Working Drawings and include all comments on them as follows:
(1) Stamped Working Drawings - Stamped Working Drawings will be designated as "reviewed " or "reviewed with comments" by the Engineer.
(2) Unstamped Working Drawings - Unstamped Working Drawings will be designated on the face of the Drawing, as "approved", "approved as noted", or "returned for correction" by the Engineer.
The Contractor shall not fabricate or construct any structural components until the stamped or unstamped Working Drawings are returned by the Engineer with written notation of approval or review, as applicable, of the Working Drawings.
The Engineer's processing of the Working Drawings does not amend any contractual obligations of the parties.
The Engineer will process and return Working Drawings within 21 Calendar Days (65 Calendar Days if Railroad approval is required) after receipt by the Engineer. If the Engineer fails to return such drawings within this period of time, the Engineer will consider granting a Contract Time extension according to 00180.80.
00150.50(b) Agency Responsibilities - Replace this subsection, except for the subsection number and title, with the following:
During the design of this Project, the Agency made preliminary contacts with Utilities to make them aware of anticipated Agency Work within the limits of the project, how it may affect their facilities, and instructed the utilities to make arrangements to relocate their facilities that are known to be in conflict with anticipated Agency work. The Agency has listed in 00150.50(f) the known utilities, their owners, and contact information. The Plans will not normally show the anticipated new location of utilities that have been or will be adjusted.
Century Blvd. Extension 17 Project # 100343
00150.50(c) Contractor’s Responsibilities - Add the following bullets to the end of the bulleted list:
• Before meeting with the Engineer for the preconstruction conference, hold a group Utility scheduling meeting with representatives from the Utility companies involved with this Project. Incorporate each Utility's time needs into the Contractor's schedule submitted at the preconstruction conference.
• Check on-site locations of each Utility against known location data, if any, and notify the Utility of any discrepancies before starting the Work.
• Pothole underground utilities 200 feet in advance of all ground disturbing Work and provide the Agency with the pothole data by the end of the shift the data is collected. Pothole data supplied to the Agency shall include the pipe/conduits material type, size, elevations of top and bottom of the pipe/conduits/duct banks, and station with offset of each data point. The Contractor is to notify the Agency of any conflicts with proposed facilities.
• Hold a Utility scheduling meeting and monthly Utility coordination meetings (see also 00180.42)
Add the following:
The Contractor shall submit a written Utility Coordination Report to the Engineer not later than five Calendar Days prior to the preconstruction conference. The Utility Coordination Report shall:
• Identify each specific utility;
• Identify utility contact names and numbers;
• Identify dates for utility scheduling for the entire project;
• Contain documents showing that the Contractor has accomplished utility locates; and
• Contain documents showing that utility locates, along with applicable construction activities;
have been reviewed and discussed on-site with utility representatives.
The Contractor shall hold monthly utility coordination meetings with utilities and the Engineer to coordinate project activities with utilities and on-going utility relocation work.
The Contractor shall hold monthly utility coordination meetings in the office or in the field, as appropriate. The utility coordination meetings shall include, but not be limited to:
• Detailed discussions of existing and abandoned utilities,
• Detailed discussions of critical locations for potholing of utilities,
• Detailed discussions about the contractors potholing schedule,
• Detailed discussions of project activities, and
• Detailed discussions of on-going utility relocations in upcoming project activity areas.
During the monthly utility coordination meetings, the utilities will provide utility drawings and discuss the scope, extent, locations, and significance of all utility facilities before the Contractor begins work in a new activity area. The Contractor shall incorporate this information into the project schedules and furnish the utilities copies of the updated project schedules.
The Contractor shall plan and schedule all utility adjustment operations well in advance of On-Site Work. When the Contractor becomes aware of utility conflicts not previously identified, notify the applicable utilities in writing the same Calendar Day.
Century Blvd. Extension 18 Project # 100343
In accepting the above responsibilities, both stated and implied, the Contractor understands that it is highly likely that there will be interfering utilities, i.e. service laterals, drains, pipe and conduits (ducts), and related structures which are not shown or are not accurately indicated on the Plans or have not been previously discovered at the project site.
Utilities that are in the way of or in close proximity to the work, known as potential conflicts, may require a change in the Contractor's operations and should be reflected in the Contractor's Bid and in the project schedule.
Locating, such as potholing, excavations, or boring, deemed necessary to determine the exact locations(s) of any utility which may interfere with the work shall be done prior to the start of construction at no additional cost to the Agency unless otherwise indicated or provided for in these Contract Documents.
00150.50(d) Delays - Replace subsection, except for the number and title, with the following:
Existing utilities may affect the work causing additional time or cost. Reasonable delays or resulting cost increases will be considered as part of the normal progress of work and will not be cause for extra compensation to the Contractor. The Contractor agrees to provide for a reasonable amount of additional time or cost in the Bid.
Add the following subsection:
00150.50(f) Utility Information (No Anticipated Relocations) - Within the Project limits, there are no anticipated relocations with the Utilities listed in Table 00150-1. The Contractor shall contact those Utilities having buried facilities and request that they locate and mark them for their protection prior to construction.
Table 00150-1 Utilities affected Contact Office Number
Hillsboro-sewer/storm Charlie Shell (engineering) 503-681-6252 Hillsboro-water Kevin Meeuwsen CWS Marvin Spiering 503-681-5114
The Contractor shall notify, in writing, the Utilities listed above, with a copy to the Engineer, at least 14 Calendar Days before beginning Work on the Project. Utilities may require an on-site observer, at no cost to the Contractor.
Add the following subsection:
00150.50(g) Utility Information (Anticipated Relocations) - Contact those utilities having buried facilities and request that they locate and mark them for their protection prior to construction. The Utilities notification system telephone number is 811 or (800) 332-2344.
The organizations listed in Table 00150-2 may be adjusting Utilities within the limits of the Project during the period of the Contract.
Century Blvd. Extension 19 Project # 100343
Table 00150-2
Utilities affected Contact Mobile Number Email
1 NW Natural Steve Monier (217) 741-4403 Steven.Monier@nwnatural.com 2 PGE Daniel Sapp (971) 533-6526 daniel.sapp@pgn.com 3 Comcast Doug Ellison (971) 777-0948 Douglas_Ellison@comcast.com 4 Ziply Scott Binney (503) 643-0371 scott.binney@ziply.com
HiLight (city of Hillsboro - fiber) Suriya Phompat (503) 810-8219 suriya.pomphat@hillsboro-oregon.gov HiLight (city of
Hillsboro - fiber) Wes Huber (503) 430-9813 wes.huber@hillsboro-oregon.gov
Energized power lines overhang portions of the Work with a minimum vertical clearance of 18 feet. Contractors shall maintain at least 10 feet of safety clearance.
(1) NW Natural - "Gas Utility":
The Contractor shall notify the Gas Utility in writing, with a copy to the Engineer, at least 14 Calendar Days before beginning Work within 10 feet of the gas pipeline.
The Contractor shall notify the Gas Utility in writing, with a copy to the Engineer, 7 Calendar Days before the Contractor's estimated completion of Gas bedding backfill in the joint utility trench. After the Contractor has completed this Work or 7 Calendar Days after the Gas Utility receives the notification, whichever occurs later, the Contractor shall then allow the Gas Utility 7 Calendar Days to schedule and complete the relocation and adjustment work.
In the event of an emergency, and in addition to the calls required by the Utilities notification system, the Contractor shall call:
• Northwest Natural Gas 1-800-882-3377
(2) Portland General Electric - "Power Supplier":
The Contractor shall notify the Power Supplier(s) in writing, with a copy to the Engineer, at least 14 Calendar Days before beginning Work within 10 feet of the power line(s).
The Contractor shall notify the Power Supplier in writing, with a copy to the Engineer, 30 Calendar Days before the Contractor is scheduled to begin performing construction of the joint utility trench and conduit installation. After the Power Supplier receives the notification, the Contractor shall then allow the Power Supplier 14 Calendar Days to schedule and complete the installation of service poles.
The Contractor shall notify the Power Supplier in writing, with a copy to the Engineer, 14 Calendar Days before the Contractor's estimated completion of installing the conduit and vaults in the Joint Utility Trench, including backfill to the bottom of NW Natural). After the Contractor has completed this Work the Contractor shall then allow the Power Supplier 14 Calendar Days to schedule and complete the relocation and adjustment work.
Energized power lines overhang portions of the Work with a minimum vertical clearance of 18 feet. The Contractor shall maintain at least 10 feet of safety clearance. Exceptions require mailto:Steven.Monier@nwnatural.com mailto:daniel.sapp@pgn.com mailto:Douglas_Ellison@comcast.com mailto:scott.binney@ziply.com mailto:suriya.pomphat@hillsboro-oregon.gov mailto:suriya.pomphat@hillsboro-oregon.gov mailto:wes.huber@hillsboro-oregon.gov mailto:wes.huber@hillsboro-oregon.gov
Century Blvd. Extension 20 Project # 100343 written approval from the Power Supplier(s) and may require an on-site safety watcher, at no cost to the Contractor. The Contractor shall provide the Engineer a copy of the written approval of exception before beginning work.
(3) Comcast - "Telecommunication Utility":
The Contractor shall notify the Telecommunication Utility in writing, with a copy to the Engineer, at least 14 Calendar Days before beginning Work within 10 feet of the Telecommunication Utility facilities.
The Contractor shall notify the Telecommunication Utility in writing, with a copy to the Engineer, 14 Calendar Days before the Contractor's estimated completion of Joint Utility Trench, conduit, and vault installation. After the Contractor has completed this Work and PGE has relocated from overhead to underground, or, whichever occurs later, the Contractor shall then allow the Telecommunication Utility 14 Calendar Days to schedule and complete the relocation and adjustment work.
The Contractor shall coordinate Fiber Optic relocation work…