100-CD---DRAWINGS---692-22-102-VAWC-Renovate-Specialty-Care.pdf

PDF 12 MB Posted

Attached to
3895--692-22-102 Renovate B211A for Specialty Care
Solicitation number
36C26026R0021
Issued by

About this file

These are construction documents for a renovation project at the White City VA Medical Center in White City, Oregon. The project involves renovating Building 211A Specialty Care, which is approximately 2,100 square feet, to address infrastructure facility condition deficiencies and improve utility infrastructure resiliency and capacity. The comprehensive set of architectural, mechanical, electrical, plumbing, and fire protection drawings covers demolition, new construction, equipment specifications, and system modifications. Key elements include renovating exam rooms, clinical support spaces, corridors, and associated infrastructure, with work involving architectural updates, mechanical system replacements, electrical system modifications, and upgrades to medical gas, plumbing, and fire protection systems. The project number is 692-22-102, and the documents are dated August 15, 2025, with the design by Spees Design Build from Kent, Washington.

View the file

Other files

File Type Posted
36C26026R0021.docx DOCX document
100-CD---SPECIFICATIONS---692-22-102-VAWC-Renovate-Specialty-Care.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ARCHITECTURAL

SPEES DESIGN BUILD

23830 PACIFIC HIGHWAY S. STE 203

KENT, WA 98032

PHONE: (206) 590-2118

DESIGN TEAM

ELECTRICAL

SPEES DESIGN BUILD

PLUMBING

SPEES DESIGN BUILD

MECHANICAL

SPEES DESIGN BUILD

23830 PACIFIC HIGHWAY S. STE 203

KENT, WA 98032

PHONE: (206) 590-2118

23830 PACIFIC HIGHWAY S. STE 203

KENT, WA 98032

PHONE: (206) 590-2118

23830 PACIFIC HIGHWAY S. STE 203

KENT, WA 98032

PHONE: (206) 590-2118

FIRE PROTECTION

SPEES DESIGN BUILD

23830 PACIFIC HIGHWAY S. STE 203

KENT, WA 98032

PHONE: (206) 590-2118

PROJECT INFORMATION

STATE:

COUNTY:

JURISTICTION:

OWNER:

CODE ANALYSIS

PROJECT DESCRIPTION

THE PROPOSED DESIGN SHALL ALTER,

MODIFY AND PARTIALLY RENOVATE BUIDLING

211A FOR SPECIALTY CARE TO ADDRESS

INFRASTRUCTURE FACILITY CONDITION

DEFICIENCIES/IMPROVE UTILITY

INFRASTRUCTURE RESILIENCY/CAPACITY.

APPLICABLE BUILDING

B211A

APPLICABLE CLINIC

SPECIALTY CARE

APPROX SQUARE FEET IN SCOPE

2,100 SF

OREGON

JACKSON

WHITE CITY

GOV, VETERANS AFFAIRS

GENERAL NOTES

1. COORDINATE WORK WITH ALL CONTRACT DOCUMENTS, INCLUDING BUT NOT LIMITED TO DRAWINGS &

SPECIFICATIONS.

2. SPECIFICATIONS SHALL SUPERSEDE DRAWINGS IN THE CASE OF ANY CONFLICTING INFORMATION.

BRING TO THE AWARENESS OF AND VERIFY WITH VA COR PRIOR TO PROCEEDING.

3. THE CONTRACTOR SHALL FIELD VERIFY ALL EXISTING CONDITIONS BEFORE BEGINNING WORK. ANY CONFLICTS BETWEEN EXISTING CONDITIONS AND THE CONTRACT DOCUMENTS SHALL BE BROUGHT

IMMEDIATELY TO THE ATTENTION OF THE COR.

4. ALL WORK SHALL BE PERFORMED WITH A HIGH-LEVEL OF WORKMANSHIP.

5. THE CONTRACTOR SHALL VERIFY ALL PRODUCT TYPES AND QUANTITIES DURING SITE WALK

THROUGH, PRIOR TO PURCHASING ANY MATERIALS, EQUIPMENT, PRODUCTS OR LABOR.

6. THE CONTRACTOR SHALL VERIFY AND COORDINATE WITH ALL INSTALLERS TO ENSURE COMPLIANCE

WITH THE CONTRACT DOCUMENTS.

211A

BUILDING WITHIN SCOPE OF THIS PROJECT

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

ENGINEERING DISCIPLINE:

G-001

COVER & DRAWING INDEX

SPEES DESIGN BUILD

23830 PACIFIC HIGHWAY S. SUITE 203

KENT, WA 98032

(206) 590-2118

RENOVATE B211A SPECIALTY

CARE

WHITE CITY VA MEDICAL CENTER - WHITE CITY, OR

692-22-102

211A

08/15/2025 MK AJ

CONSTRUCTION

DOCUMENTS

RENOVATE B211A SPECIALTY CARE

PROJECT #: 692-22-102

WHITE CITY VA MEDICAL CENTER - WHITE CITY, OREGON

1" = 100'-0"

FACILITY SITE PLAN - COVER

1/4" = 1'-0"

LOCATION PLAN

WHITE CITY VA MEDICAL CENTER,

WHITE CITY, OR

TRUE

NORTH

TRUE

NORTH

DRAWING INDEX

PAGE # SHEET # SHEET NAME

MECHANICAL

24 OF 45 M-001 MECHANICAL GENERAL NOTES

25 OF 45 M-002 MECHANICAL ABBREVIATIONS & LEGENDS

26 OF 45 MD101 DEMOLITION FLOOR PLAN - MECHANICAL DUCTWORK LAYOUT

27 OF 45 MD102 DEMOLITION FLOOR PLAN - MECHANICAL PIPING LAYOUT

28 OF 45 M-101 FLOOR PLAN - MECHANICAL DUCTWORK LAYOUT

29 OF 45 M-102 REFLECTED CEILING PLAN

30 OF 45 MP101 FLOOR PLAN - MECHANICAL PIPING LAYOUT

31 OF 45 M-501 MECHANICAL DETAILS

32 OF 45 M-601 MECHANICAL EQUIPMENT SCHEDULES

ELECTRICAL

33 OF 45 E-001 ABBREVIATION, GENERAL NOTES, AND SHEET INDEX

34 OF 45 E-002 ELECTRICAL LEGENDS

35 OF 45 ED101 OVERALL LIGHTING DEMOLITION PLAN

36 OF 45 ED102 OVERALL POWER AND SPECIAL SYSTEMS DEMOLITION PLAN

37 OF 45 EL101 OVERALL LIGHTING PLAN

38 OF 45 EP101 OVERALL POWER PLAN

39 OF 45 ET101 OVERALL SPECIAL SYSTEMS PLAN

40 OF 45 E-501 ELECTRICAL DETAILS

41 OF 45 E-502 ELECTRICAL DETAILS

43 OF 45 E-601 BUILDING 211A PARTIAL ONE-LINE DIAGRAM

44 OF 45 E-701 ELECTRICAL PANEL SCHEDULES

45 OF 45 E-702 ELECTRICAL GENERAL SCHEDULES

DRAWING INDEX

PAGE # SHEET # SHEET NAME

GENERAL

01 OF 45 G-001 COVER & DRAWING INDEX

02 OF 45 GS101 FACILITY SITE PLAN

ARCHITECTURAL

03 OF 45 A-001 ARCHITECTURAL SYMBOLS & ABBREVIATIONS

04 OF 45 AS101 ICRA PLAN

05 OF 45 AS201 FIRE AND LIFE SAFETY

06 OF 45 AD101 OVERALL DEMO FLOOR PLAN

07 OF 45 AD102 OVERALL DEMO REFLECTED CEILING PLAN

08 OF 45 AE101 OVERALL FLOOR PLAN

09 OF 45 AC101 OVERALL REFLECTED CEILING PLAN

10 OF 45 AE421a EXAM ROOM 124 - ENLARGED FLOOR PLAN AND INTERIOR ELEVATIONS

11 OF 45 AE421b EXAM ROOM 125 & 126 - ENLARGED FLOOR PLAN AND INTERIOR ELEVATIONS

12 OF 45 A-501 DETAILS

13 OF 45 A-510 INTERIOR SLIDING DOOR DETAILS

14 OF 45 A-601 SCHEDULES, DETAILS, DOOR TYPES & DETAILS

15 OF 45 AW001 SIGNAGE MESSAGE SCHEDULE, IN-04.02, IN-07.02

FIRE

16 OF 45 FX001 FIRE PROTECTION GENERAL NOTES, ABBREVIATIONS & LEGENDS.

17 OF 45 FX101 REFLECTED CEILING PLAN

PLUMBING

18 OF 45 P-001 PLUMBING GENERAL NOTES, ABBREVIATIONS, LEGENDS & SCHEDULE

19 OF 45 PD100 DEMOLITION FLOOR PLAN - PLUMBING FOUNDATION LAYOUT

20 OF 45 PD101 DEMOLITION FLOOR PLAN - PLUMBING LAYOUT

21 OF 45 PD102 DEMOLITION FLOOR PLAN - MEDICAL GAS LAYOUT

22 OF 45 P-100 FLOOR PLAN - PLUMBING FOUNDATION LAYOUT

23 OF 45 P-101 FLOOR PLAN - PLUMBING LAYOUT

Revisions: Date: 1 OF 45

211A

TRUE

NORTH

VA WHITE CITY MEDICAL CENTER

OREGON

1. COORDINATE CONTRACTOR STAGING AREA WITH VA COR

AT THE PRE-CONSTRUCTION MEETING. THIS INCLUDES,

BUT IS NOT LIMITED TO, AREAS TO BE USED FOR

MATERIAL STORAGE, ACCESS FOR MATERIAL DELIVERIES

AND TRANSPORTATION ROUTES TO THE PROJECT AREA.

2. DO NOT STORE PRODUCTS, MATERIALS, TOOLS,

EQUIPMENT, VEHICLES, OR ANY OTHER NON-PERMITTED

ITEMS ON MEDICAL CENTER PROPERTY UNLESS GIVEN

PRIOR APPROVAL BY THE VA COR.

3. A LIMITED AMOUNT OF SUPPLIES MAY BE STORED IN THE

CONSTRUCTION AREA AS LONG AS SAFETY AND

CLEANLINESS ARE NOT COMPROMISED. VA COR HAS

AUTHORITY TO REQUEST RELOCATION OF ANY AND

ALL STORED ITEMS TO A DIFFERENT LOCATION.

4. VERIFY CONTRACTOR STAGING AREA AND MATERIAL /

PRODUCT DELIVERY LOCATION WITH VA COR, PRIOR TO

BRINGING OR DELIVERING ITEMS TO THE MEDICAL

CENTER.

BUILDING WITHIN THE SCOPE OF THIS

PROJECT

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

ENGINEERING DISCIPLINE:

GS101

FACILITY SITE PLAN

SPEES DESIGN BUILD

23830 PACIFIC HIGHWAY S. SUITE 203

KENT, WA 98032

(206) 590-2118

RENOVATE B211A SPECIALTY

CARE

WHITE CITY VA MEDICAL CENTER - WHITE CITY, OR

692-22-102

211A

08/15/2025 MK AJ

CONSTRUCTION

DOCUMENTS

1" = 50'-0"

FACILITY SITE PLAN

LEGEND

GENERAL NOTES

KEY NOTES (THIS SHEET ONLY)

KEY PLAN

TRUE

NORTH

Revisions: Date: 2 OF 45

AB

ABA

AC(T)

ACM

ACW

ADA

ADJ

A/E

AF

AFF

AGG

ALT

ALUM

APPROX

ARCH

ASPH

A/V

BARR

BATH

BB

BLDG

BLK

BLKG

BLW

BM

BMTU

BO

BOC

BOS

BRC

BRKT

BRNG

BTM

BTWN

CAB

CC

CD

CJ

CLG

CLR

CMU

CO

COL

COMP

CONC

CONN

CONST

CONT

COORD

COR

CORR

CS

CT

CTR

CV

AND

ANGLE

AT

CENTERLINE

DEGREES

NUMBER

ANCHOR BOLT

ARCHITECTURAL BARRIERS ACT

ACOUSTICAL CEILING (TILE)

ASBESTOS CONTAINING MATERIAL

ACOUSTICAL WALL

AMERICANS W/ DISABILITIES ACT

ADJACENT

ARCHITECT/ENGINEER

ACCESS FLOOR

ABOVE FINISH FLOOR

AGGREGATE

ALTERNATE

ALUMINUM

APPROXIMATELY

ARCHITECT(URAL)

ASPHALT

AUDIO / VIDEO

BARRIER

BATHROOM

BACKER BOARD

BUILDING

BLOCK

BLOCKING

BELOW

BEAM

BONE MARROW TRANSPLANT UNIT

BOTTOM OF

BOTTOM OF CURB

BOTTOM OF SLAB

BRACE, BRACING

BRACKET

BEARING

BOTTOM

BETWEEN

CABINET

CONTRACTOR FURN, CONTRACTOR INST

CONSTRUCTION/CONTRACT DOCUMENTS

CONTROL JOINT

CEILING

CLEAR(ANCE)

CONCRETE MASONRY UNIT

CONTRACTING OFFICER

COLUMN

COMPOSITION

CONCRETE

CONNECTION

CONSTRUCTION

CONTINUOUS

COORDINATE

CONTRACTING OFFICER REPRESENTATIVE

CORRIDOR

CONCRETE SEALER

CERAMIC TILE

CENTER

CONTRACTOR FURNISHED, VA INSTALLED

HDR

HDWE

HM

HORZ

HPDL

HR

HT

HVAC

ICRA

ID

ILSM

INCL

INST

INSUL

INT

JT

KV

LAM

LAV

LCM

LT

MAT

MAX

MDF

MECH

MEP

MFR

MIN

MISC

MOD

MTL

N N/A

NEG

NO.

NOM

NTS

O.C.

OPNG

OPP

OPT

OVHD

P

PCONC

PCRA

PL

PLAM

PLY(WD)

PNL

PR

PRFB

PS

PT

PTN(S)

PVMT

QTY

HEADER

HARDWARE

HOLLOW METAL

HORIZONTAL

HIGH PRESSURE DECORATIVE LAM

HOUR

HEIGHT

HEATING, VENTILATION & AIR CONDITIONING

INFECTIOUS CONTROL RISK ASSESSMENT

INSIDE DIAMETER OR DIM

INTERIM LIFE SAFETY MEASURES

INCLUDE(D,ING)

INSTALL

INSULATION

INTERIOR

JOINT

KILOVOLT

LAMINATE(D)

LAVATORY

LEAD CONTAINING MATERIAL(S)

LIGHT

MATERIAL(S)

MAXIMUM

MEDIUM-DENSITY FIBREBOARD

MECHANIC(AL)

MECHANICAL, ELECTRICAL, PLUMBING

MANUFACTURE(R)

MINIMUM

MISCELLANEOUS

MODIFIED

METAL

NORTH

NOT APPLICABLE

NEGATIVE

NUMBER

NOMINAL

NOT TO SCALE

ON CENTER(S)

OPENING

OPPOSITE

OPTION(AL)

OVERHEAD

PAINT

PRECAST CONCRETE

PRE-CONSTRUCTION RISK ASSESSMENT

PLATE

PLASTIC LAMINATE

PLYWOOD

PANEL

PAIR

PREFABRICATED

PLASTIC

PRESSURE TREATED

PARTITION(S)

PAVEMENT

QUANTITY

RAD

RCP

REF

REINF

REP

REQ(s,(')D)

RESIL

REV

RF

RM

RMV

RO

S

SCHED

SD

SECT

SF

SFRM

SHG

SHT(G)

SIM

SM

SOW

SPEC

SQ

SS

ST

STDG

STL

STOR

STRUCT

SUSP

SV

SYS

TEMP

T&G

THK

THRESH

TOC

TOS

TPH

TRANS

TS

TYP

UON

VA

VAR

VB

VC

VERT

VIF

VV

W W/

WD

WDW

WGHT

W/O

WP

WR

RADIUS

REFLECTED CEILING PLAN

REFERENCE

REINFORCE(D,ING)

REPRESENTATIVE

REQUIRE(D,S,MENT(S))

RESILIENT

REVERSE

RADIO FREQUENCY / ROOF

ROOM

REMOVE

ROUGH OPENING

SOUTH

SCHEDULE

SCHEMATIC DESIGN

SECTION

SQUARE FEET

SPRAY APPLIED FIRE-RESISTIVE MATERIAL

SHINGLES

SHEET (SHEATHING)

SIMILAR

SEAM

SCOPE OF WORK

SPECIFICATION

SQUARE

STAINLESS STEEL

STAIN

STANDING

STEEL

STORAGE

STRUCTURAL

SUSPENDED

SHEET VINYL

SYSTEM

TEMPORARY

TONGUE AND GROOVE

THICK(NESS)

THRESHOLD

TABLE OF CONTENTS

TOP OF SLAB

TOILET PAPER HOLDER

TRANSITION

TUBE STEEL

TYPICAL

UNLESS OTHERWISE NOTED

VETERANS AFFAIRS

VARIES

VAPOR BARRIER

VA FURNISHED, CONTRACTOR INSTALLED

VERTICAL

VERIFY IN FIELD

VA FURNISHED, VA INSTALLED

WEST

WITH

WOOD

WINDOW

WEIGHT

WITHOUT

WATERPROOF(ING)

WATER RESISTANT

DBL

DC

DD

DEMO

DEPT

DG

DIA

DIM

DWN

DR

DTL

DWG

E

EA

EJ

ELEC

ELEV

ENG

EOC

EOP

EPDM

EQ

EQUIP

ES

ETS

EX(IST)

EXP

EXT

FA

FD

FE(C)

FF

FFB

FFL

FIN

FLASH

FLR

FLRSNT

FNDN

FOC

FOF

FOS

FP

FR

FRM

FT

FTG

FUR

FURN

GA

GALV

GE

G(W)B

GC

GL

GLB

GMU

GOV(T)

GYP

DOUBLE

DIRECT CURRENT

DESIGN DEVELOPMENT

DEMOLISH(ION)

DEPARTMENT

DESIGN GUIDE

DIAMETER

DIMENSION

DOWN

DOOR

DETAIL

DRAWING(S)

EAST

EACH

EXPANSION JOINT

ELECTRIC(AL)

ELEVATION OR ELEVATOR

ENGINEER(ING)

EDGE OF CURB

EDGE OF PAVEMENT

ETHYLENE PROPYLENE DIENE TERPOLYMER

EQUAL

EQUIPMENT

EACH SIDE

EXPOSED TO STRUCTURE

EXISTING

EXPANSION

EXTERIOR

FIRE ALARM

FLOOR DRAIN

FIRE EXTINGUISHER (CABINET)

FACTORY FINISH

FINISH FLOOR BREAK

FINISH FLOOR LINE

FINISH(ED)

FLASHING

FLOOR(ING)

FLORESCENT

FOUNDATION

FACE OF CONCRETE

FACE OF FINISH

FACE OF STUDS

FIRE PROOF

FIRE RATED

FRAME

FOOT, FEET

FOOTING

FURRING

FURNISHED

GAGE, GAUGE

GALVANIZED

GENERAL ELECTRIC

GYPSUM (WALL) BOARD

GENERAL CONTRACTOR

GRID LINE

GLUE LAMINATED BEAM

GLASS MASONRY UNIT

GOVERNMENT

GYPSUM BOARD

A101

1 TYP

101.1

A-101

SIM

EXTERIOR ELEVATION

INTERIOR ELEVATION

BUILDING SECTION FLAG

WALL SECTION FLAG

CALLOUT FLAG

VERTICAL GRID LINE

HORIZONTAL GRID LINE

TRUE NORTH ARROW

PROJECT NORTH ARROW

(TRUE NORTH DASHED)

ELEVATION MARKER

KEY NOTE

ROOM TAG (SF OPTIONAL)

CEILING HEIGHT TAG

ROOM NAME

150 SF

A

A-101

SIM

01A

TRUE

NORTH

W1

A-101

PROJECT

NORTH

WALL TAG

FLOOR TAG

ROOF TAG

DOOR TAG

WINDOW TAG

SPECIALTY EQUIPMENT TAG

SIGNAGE TAG

SIGNAGE KEY NOTE

(AW SHEETS ONLY)

SIGNAGE MATERIAL TAG

(AW SHEETS ONLY)

EXISTING TO REMAIN

NEW CONSTRUCTION

TO DEMOLISH

HIDDEN ABOVE OR BELOW

EXISTING DOOR TO REMAIN

EXISTING DOOR TO DEMOLISH

NEW DOOR

1 HR FIRE RATED WALL

SMOKE & 2 HR FIRE RATED WALL

FIRE EXTINGUISHER CABINET

AREA OF WORK / AREA SHOWN

CONSTRUCTION ZONE, ( - - )

PRESSURE

ANTE ROOM, ( - ) PRESSURE

TEMPORARY ICRA BARRIER

TEMPORARY ICRA DOOR

PATH OF TRAVEL

EMERGENCY EGRESS PATHWAY

SEISMIC JOINT

BATT INSULATION

RIGID INSULATION

GYPSUM BOARD, TYPE X

ACOUSTICAL CEILING TILE, 2' x 2'

CONCRETE

STEEL

PLYWOOD, FIRE RATED

EARTH

SUPPLY GRILLE PER MECHANICAL

(SIZE & PROPORTIONS MAY VARY)

RETURN GRILLE PER MECHANICAL

(SIZE & PROPORTIONS MAY VARY)

LIGHTING PER ELECTRICAL

(SIZE & PROPORTIONS MAY VARY)

A-101

A01

D88

A5175SOAP DISH

IN-04.02-01

AFF

GYP ON MTL STUD

9' - 0"

FEC

F-1

R-1

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

ENGINEERING DISCIPLINE:

A-001

ARCHITECTURAL SYMBOLS &

ABBREVIATIONS

SPEES DESIGN BUILD

23830 PACIFIC HIGHWAY S. SUITE 203

KENT, WA 98032

(206) 590-2118

RENOVATE B211A SPECIALTY

CARE

WHITE CITY VA MEDICAL CENTER - WHITE CITY, OR

692-22-102

211A

08/15/2025 MK AK

CONSTRUCTION

DOCUMENTS

SYMBOLS ABBREVIATIONS

GENERAL NOTES

APPLICABLE PUBLICATIONS

1. ALL WORK DONE BY THE CONTRACTOR OR SUB-CONTRACTORS SHALL BE PERFORMED WITH

A HIGH LEVEL OF WORKMANSHIP.

2. MAINTAIN A SAFE, CLEAN CONSTRUCTION ZONE AT ALL TIMES.

3. DO NOT SCALE DRAWINGS.

4. DIMENSIONS ARE NOT ADJUSTABLE UNLESS NOTED WITH A +/- SYMBOL. ONLY NORMAL

INDUSTRY STANDARD TOLERANCES ARE ACCEPTABLE DEVIATIONS FROM DIMENSIONS

INDICATED.

5. ALL DIMENSIONS NOTED AS CLEAR SHALL MAINTAIN THE FULL SPACE INDICATED WITHOUT

ENCROACHMENTS.

6. FURNISH ALL MATERIALS & PRODUCTS TO COMPLY WITH THE CONTRACT DOCUMENTS.

7. ALL VERTICAL HEIGHTS INDICATED ARE FROM THE FINISH FLOOR ELEVATION, UON.

8. ANY AND ALL WALL MOUNTED EQUIPMENT SHALL HAVE BLOCKING IN WALL BEHIND, THIS

INCLUDES BACKING FOR WALL MOUNTED DOOR STOPS. ENSURE THAT ALL REQUIRED

BACKING IS INSTALLED IN WALLS PRIOR TO INSTALLING DRYWALL.

9. IN TOILET ROOMS PROVIDE STAINLESS STEEL FILLER BEHIND ANY MIRRORS AND OTHER

WALL MOUNTED ACCESSORIES WHEN ITEM IS INSTALLED PARTIALLY OVER CERAMIC TILE.

ARCHITECTURAL NOTES

AS AN AGENCY OF THE FEDERAL GOVERNMENT, THE VA IS NOT SUBJECT TO LOCAL IMPOSITIONS OF CODE ENFORCEMENT PROCEDURES ( DRAWING REVIEWS, BUILDING PERMITS, INSPECTIONS, FEES, ETC). THE VA

SHALL FUNCTION AS THE AUTHORITY HAVING JURISDICTION (AHJ).

VA DIRECTIVES, DESIGN MANUALS, MASTER SPECIFICATIONS, VA NATIONAL CAD STANDARD APPLICATION

GUIDE AND OTHER GUIDANCE ON THE TECHNICAL INFORMATION LIBRARY (TIL). SEE ABOVE.

INTERNATIONAL BUILDING CODE (IBC) 2021.

NATIONAL FIRE PROTECTION AGENCY (NFPA) 101 LIFE SAFETY CODE, 2024 ED. NFPA 101 TAKES

PRECEDENCE OVER IBC.

NFPA NATIONAL FIRE CODES, WITH THE EXCEPTION OF NFPA 5000 AND NFPA 900.

OCCUPATIONAL, SAFETY AND HEALTH ADMINISTRATION (OSHA) STANDARDS.

VA SEISMIC DESIGN REQUIREMENTS, H-18-8.

NATIONAL ELECTRICAL CODE (NEC) NFPA 70, 2023.

NFPA 13, 2022 ED., STANDARD FOR THE INSTALLATION OF SPRINKLER SYSTEM.

INTERNATIONAL PLUMBING CODE (IPC), 2022.

NFPA 72, 2022 ED., NATIONAL FIRE ALARM AND SIGNALING CODE.

Revisions: Date: 3 OF 45

L

L

L

L

L

L

L

L

L

OVERHEAD

LIFT

SPRINKER

RISER

D.F. D.F.

D F

SOLID

DISP

FD

FD

RAMP

DN.

DN DN

DN

DN

SHOWN AREA

PROJECT

NORTH

CONSTRUCTION ZONE

TEMPORARY ICRA BARRIER

TEMPORARY ICRA DOOR

OUT OF SCOPE

TEMPORARY ICRA AIR PRESSURE+ ---

TEMPORARILY SEAL EXISTING DOOR FOR DURATION OF

CONSTRUCTION.

TEMPORARY ICRA BARRIER FRAMED TO THE CEILING

ABOVE. CONSTRUCT WITH MTL STUDS AND 5/8" TYPE X

GYP EACH SIDE.

TEMPORARY ICRA DOOR AND FRAME.

1. COMPLY WITH ALL REQS LISTED IN THE INFECTION

CONTROL SECTION OF SPECIFICATION 01 35 26 - SAFETY

REQUIREMENTS.

2. CONSTRUCTION ZONE ENTRANCES AND EXITS SHALL BE

LOCKED AT ALL TIMES UNLESS IN USE BY THE

CONTRACTOR. WHEN IN USE, ACCESS WILL BE

CONTROLLED AND MONITORED BY THE CONTRACTOR.

3. ADHESIVE WALK OFF CONSTRUCTION MATS TO BE USED

AT ALL CONSTRUCTION ZONE AND ANTE ROOM

ENTRANCES AND EXITS.

4. TEMP BARRIERS AND DOORS MAY ONLY BE DEMOLISHED

ONCE GIVEN FINAL APPROVAL BY THE VA COR.

5. ICRA PLAN IS ONLY GIVEN AS A SUGGESTED METHOD,

COORDINATE WITH VA FOR FINAL LAYOUT.

A B C F

ED

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

ENGINEERING DISCIPLINE:

AS101

ICRA PLAN

SPEES DESIGN BUILD

23830 PACIFIC HIGHWAY S. SUITE 203

KENT, WA 98032

(206) 590-2118

RENOVATE B211A SPECIALTY

CARE

WHITE CITY VA MEDICAL CENTER - WHITE CITY, OR

692-22-102

211A

08/15/2025 MK AJ

CONSTRUCTION

DOCUMENTS

LEGEND

GENERAL NOTES

KEY NOTES (THIS SHEET ONLY)

KEY PLAN

PROJECT

NORTH

1/8" = 1'-0"

ICRA PLAN

ICRA NOTES:

CLASS IV

1. BARRIERS MUST BE HARD BARRIERS UNLESS TEMPORARY TO

INSTALL FINAL BARRIER.

2. CONTAINMENT MUST INCLUDE AN ANTEROOM TO ENSURE

PRESSURE CONTROL. ANTEROOM MUST BE LARGE ENOUGH FOR

EQUIPMENT STAGING, CART CLEANING, WORKERS' PPE AND

CLEANING.

3. WORKER CLOTHING AND/OR PPE MUST BE REMOVED OR CLEAN

AND FREE OF VISIBLE DUST BEFORE LEAVING THE WORK AREA

ANTEROOM. HEPA VACUUMING OF CLOTHING OR USE OF COVER

SUITS IS ACCEPTABLE.

4. WORKERS MUST WEAR SHOE COVERS OR HAVE A METHOD TO

CLEAN SHOES IN ANTEROOM. SHOE COVERS MUST BE REMOVED

PRIOR TO EXITING THE ANTEROOM TO THE OCCUPIED SPACE (NON-

WORK AREA.) DAMAGED SHOE COVERS MUST BE CHANGED

IMMEDIATELY.

WORK AREA CLEANING:

1. CLEAN WORK AREAS INCLUDING ALL ENVIRONMENTAL SURFACES,

HIGH HORIZONTAL SURFACES AND FLOORING MATERIALS.

2. CHECK ALL SUPPLY AND RETURN AIR REGISTERS FOR DUST

ACCUMULATION ON UPPER SURFACES AS WELL AS AIR DIFFUSER

SURFACES.

REMOVAL OF CRITICAL BARRIERS:

1. CRITICAL BARRIERS MUST REMAIN IN PLACE DURING ALL WORK

INVOLVING DRYWALL REMOVAL, CREATION OF DUST AND ACTIVITES

BEYOND SIMPLE TOUCH-UP WORK. THE BARRIER MAY NOT BE

REMOVED UNTIL A WORK AREA CLEANING HAS BEEN PERFORMED.

ADDITIONAL CLEANING MAY BE NEEDED AFTER REMOVAL OF

BARRIER.

2. ALL (PLASTIC OR HARD) BARRIER REMOVAL ACTIVITIES MUST BE

COMPLETED IN A MANNER THAT PREVENTS DUST RELEASE. USE THE

FOLLOWING PRECAUTIONS WHEN REMOVING HARD BARRIERS:

i. CAREFULLY REMOVE SCREWS AND PAINTER TAPE.

ii. IF DUST WILL BE GENERATED DURING SCREW REMOVAL, USE

HAND-HELD HEPA VACUUM.

iii. DRYWALL CUTTING IS PROHIBITED DURING REMOVAL

PROCESS.

iv. CLEAN ALL STUD TRACKS WITH HEPA VACCUM BEFORE

REMOVING OUTER HARD BARRIER.

v. USE A PLASTIC BARRIER TO ENCLOSE AREA IF DUST COULD

BE GENERATED.

NEGATIVE AIR REQUIREMENTS:

1. THE USE OF NEGATIVE AIR MUST BE DESIGNED TO REMOVE

CONTAMINANTS FROM WORK AREA.

2. NEGATIVE AIR DEVICES (FANS, FILTERS, MONITORING AND

DOCUMENTATION EQUIPMENT) MUST REMAIN OPERATIONAL AT ALL

TIMES AND IN PLACE FOR A PERIOD AFTER COMPLETION OF DUST

CREATING ACTIVITIES TO REMOVE CONTAMINANTS FROM THE WORK

AREA AND BEFORE REMOVAL OF CRITICAL BARRIERS.

HVAC SYSTEMS:

1. UPON REMOVAL OF CRITICAL BARRIERS, REMOVE ISOLATION OF

HVAC SYSTEM IN AREAS WHERE WORK IS BEING PERFORMED.

2. VERIFY THAT HVAC SYSTEMS ARE CLEAN AND OPERATIONAL.

3. VERIFY AND DOCUMENT THROUGH A TAB THE HVAC SYSTEMS

MEETS ORIGINAL AIRFLOW AND AIR EXCHANGE DESIGN

SPECIFICATIONS.

WATER SYSTEMS:

1. UNTIL THE POTABLE WATER SYSTEM IS ACTIVATED AND IN USE,

FLUSHING SHALL CONTINUE ATLEAST TWICE PER WEEK IN

ACCORDANCE WITH THE VHA DIRECTIVE 1061.

Revisions: Date: 4 OF 45

L

L

L

L

L

L

L

L

OVERHEAD

LIFT

SPRINKER

RISER

D.F. D.F.

D F

SOLID

DISP

FD

FD

RAMP

DN.

DN DN

DN

DN

SHOWN AREA

PROJECT

NORTH

EMERGENCY EGRESS ROUTE

1 HR FIRE RATED WALL

SMOKE & 2 HR FIRE RATED WALL

FIRE EXTINGUISHER CABINET

PROJECT AREA

FEC

A B C F

ED

FEC

FEC

FEC

FEC

MEDICAL SVC

BATH/SHOWER

144A

CLINICAL SUP

GENERAL

CLINICAL SUP 2

BED

CLINICAL SUP

EKG

CLINICAL SUP

2BED

CLINICAL SUP 2

BED

CLINICAL SUP

LOUNGE

CLINICAL SUP 2

BED

CLINICAL SUP 2

BED

CLINICAL SUP 2

BED

CLINICAL SUP 2

BED

CLINICAL SUP 1

BED

117A

CLINICAL SUP

HALLWAY

CLINICAL SUP

BATH/SHOWER

117B

STAIRWELL

ST1

CLINICAL SUP

HALLWAY

121A

CLINICAL SUP

STORAGE

IT CLOSET

CLINICAL SUP

WORKROOM

CLINICAL SUP

BATH/SHOWER

116B

CLINCIAL SUP

BATH/SHOWER

115A

CLINICAL SUP

BATH/SHOWER

114A

CLINICAL SUP

BATH/SHOWER

113A

CLIICAL SUP

BATH/SHOWER

112A

CLINICAL SUP

BATH/SHOWER

111A

CLINICAL SUP

BATH/SHOWER

110A

CLINICAL SUP

BATH/SHOWER

109A

CLINICAL SUP

BATH/SHOWER

108A

CLINICAL SUP

LOUNGE

CLINICAL SUP

OFFICE/EXA

CLINICAL SUP

BATH/SHOWER

106A

CLINICAL SUP

HAC

CLINICAL SUP

BATH/SHOWER

CLINICAL SUP 2

BED

CLINICAL SUP

BATH/SHOWER

104A

CLINICAL SUP

S/RESTROOM

CLINICAL SUP

1BED

CLINICAL SUP

OFFICE

CLINICAL SUP

BATH/SHOWER

136A

CLINICAL

SUP/BATHROOM

102A

CLINICAL SUP 2

BED

CLINICAL SUP

BATH/SHOWER

138A

CLINICAL SUP 1

BED

CLINICAL SUP 1

BED

139 CLINICAL SUP

BATH/SHOWER

139A

CLINICAL SUP

STORAGE

CLINICAL SUP

S/RESTROOM

CLINICAL SUPP

BATH/SHOWER

142A

CLINICAL SUP

EXAM NURSE

CLINICAL EXAM

NURSE

CLINICAL SUP

BATH/SHOWER

143A

MEDICAL SVC

EXAM_PHYSI

MEDICAL SVC

EXAM_PHYSI

MEDICAL SVC

BATH/SHOWER

145A

FMS MER

146 CLINICAL SUP

BATH/SHOWER

CLINICAL SUP

CORRIDOR

C1

CLINICAL SUP

CORRIDOR

C1W

CLINICAL SUP

SOILED

141 SF

EXAM

146 SF

EXAM

231 SF

CLINICAL SUP

NURSING

STATION

100 SF

OFFICE

92 SF

OFFICE

99 SF

OFFICE

60 SF

PATIENT AREA

133 SF

EXAM

131 SF

EXAM

130 SF

EXAM

46 SF

RESTROOM

105 SF

OFFICE

76 SF

ELECTRICAL

164 SF

EXAM

NO WORK OUTSIDE OF PROJECT AREA, TYP

1. NFPA BUILDING CONSTRUCTION: TYPE II.

2. NFPA OCCUPANCY CLASSIFICATION: BUSINESS.

3. # OF REQ'D EGRESS OPENINGS: 2.

4. 2,225 SF BUSINESS AT 150 SF / OCCUPANT = 15

OCCUPANTS

5. MAX TRAVEL DISTANCE: 300' - 0" (BUSINESS OCCUPANCY)

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

ENGINEERING DISCIPLINE:

AS201

FIRE AND LIFE SAFETY

SPEES DESIGN BUILD

23830 PACIFIC HIGHWAY S. SUITE 203

KENT, WA 98032

(206) 590-2118

RENOVATE B211A SPECIALTY

CARE

WHITE CITY VA MEDICAL CENTER - WHITE CITY, OR

692-22-102

211A

08/15/2025 EM AJ

CONSTRUCTION

DOCUMENTS

LEGEND

GENERAL NOTES

FIRE AND LIFE SAFETY DETAILS

KEY PLAN

PROJECT

NORTH

1/8" = 1'-0"

FIRE & LIFE SAFETY PLAN

1. CORRIDORS AND EGRESS PASSAGEWAYS TO REMAIN

CLEAR AND FREE OF DEBRIS.

2. PROVIDE ANY SIGNAGE FOR ROUTES OF EGRESS

AFFECTED BY CONSTRUCTION ZONES.

3. REPLACEMENT OF CEILING TILES AT THE END OF EACH

SHIFT IS REQIURED FOR WORK AREAS OUTSIDE OF A

RATED CONSTRUCTION BARRIER (IF PROVIDED). IF THE

TILES CANNOT BE REPLACED, THE SPRINKLER SYSTEM

MAY BE CONSIDERED OUT OF SERVICE IN THESE AREAS

AND 1-HOUR FIRE RATED SEPARATION WILL BE

REQUIRED BETWEEN THE CONSTRUCTION AREA AND THE

OCCUPIED PORTIONS OF THE BUILDING.

Revisions: Date: 5 OF 45

L

L

L

L

L

L

L

L

OVERHEAD

LIFT

SPRINKER

RISER

D.F. D.F.

D F

SOLID

DISP

FD

FD

RAMP

DN.

DN DN

DN

DN

SHOWN AREA

PROJECT

NORTH

DEMOLISH ACT CEILING GRID AND TILES

EXISTING DOOR TO REMAIN

EXISTING DOOR TO DEMOLISH

OUT OF SCOPE

F

E

EXISTING SINK AND

CABINETRY TO REMAIN.

2 3

6 6

EXISTING COLUMNS TO

REMAIN, TYPICAL.

(NO WORK)

DEMOLISH EXISTING RELITE.

SAWCUT AND DEMOLISH CONCRETE SLAB AS REQUIRED

FOR NEW PLUMBING WORK.

DEMOLISH EXISTING CABINETRY AND CASEWORK,

TYPICAL.

DEMOLISH EXISTING PARTITION.

DEMOLISH RAILING, TYPICAL.

DEMOLISH PLUMBING FIXTURES AND ACCESSORIES. SEE

PLUMBING PLANS.

231 SF

CLINICAL SUP

NURSING

STATION

141 SF

CLINICAL SUPPLY

WAITING ROOM

146 SF

CLINICAL SUP

TREATMENT

76 SF

ELECTRICAL

105 SF

CLINICAL SUP

CLEAN

46 SF

RESTROOOM

88 SF

CLINICAL SUP

SOILED

1307 SF

CLINICAL SUP

CORRIDOR

C1W

99 SF

CLINICAL SUP

STORAGE

99 SF

CLINICAL SUP

KITCHEN

100 SF

CLINICAL SUP

COMPUTER

177 SF

CLINICAL SUP

EXAM/TREATMENT

192 SF

CLINICAL SUP

EXAM/TREATMENT

241 SF

CLINICAP SUP

EXAM/TREAT

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

ENGINEERING DISCIPLINE:

AD101

OVERALL DEMO FLOOR PLAN

SPEES DESIGN BUILD

23830 PACIFIC HIGHWAY S. SUITE 203

KENT, WA 98032

(206) 590-2118

RENOVATE B211A SPECIALTY

CARE

WHITE CITY VA MEDICAL CENTER - WHITE CITY, OR

692-22-102

211A

08/15/2025 EM AJ

CONSTRUCTION

DOCUMENTS

LEGEND

KEY NOTES (THIS SHEET ONLY)

KEY PLAN

PROJECT

NORTH

1/4" = 1'-0"

OVERALL DEMO FLOOR PLAN

GENERAL NOTES

1. DEMOLISH EXISTING ACT. PREPARE ROOM FOR NEW ACT

CEILING.

2. DEMOLISH EXISTING WALLS AS REQUIRED FOR

INSTALLATION OF NEW WORK AND ELECTRICALCONDUITS.

3. DEMOLISH FLOORING IN WORK AREA.

4. THE CONTRACTOR SHALL VERIFY ALL EXISTING

CONDITIONS BEFORE BEGINNING OF WORK, ANY

CONFLICTS BETWEEN EXISTING CONDITIONS AND THE

CONTRACT DOCUMENTS SHALL BE BROUGHT IMMEDIATELY

TO THE ATTENTION OF THE COR.

Revisions: Date: 6 OF 45

L

L

L

L

L

L

L

L

OVERHEAD

LIFT

SPRINKER

RISER

D.F. D.F.

D F

SOLID

DISP

FD

FD

RAMP

DN.

DN DN

DN

DN

SHOWN AREA

PROJECT

NORTH

DEMOLISH ACT CEILING GRID AND TILES

EXISTING DOOR TO REMAIN

EXISTING DOOR TO DEMOLISH

OUT OF SCOPE

F

E

4 4

231 SF

CLINICAL SUP

NURSING

STATION

141 SF

CLINICAL SUPPLY

WAITING ROOM

146 SF

CLINICAL SUP

TREATMENT

76 SF

ELECTRICAL

105 SF

CLINICAL SUP

CLEAN

46 SF

RESTROOOM

88 SF

CLINICAL SUP

SOILED

1307 SF

CLINICAL SUP

CORRIDOR

C1W

99 SF

CLINICAL SUP

STORAGE

99 SF

CLINICAL SUP

KITCHEN

100 SF

CLINICAL SUP

COMPUTER

DEMO EXISTING LIGHT.

DEMO EXISTING CURTAIN TRACK.

DEMO EXISTING PATIENT LIFT/

EXISTING CEILING TO REMAIN AT ROOM.

EXISTING CEILING TO REMAIN AT ROOM, REPLACE TILES

AT ALL NEW AND EXISTING ACT CEILINGS.

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

ENGINEERING DISCIPLINE:

AD102

OVERALL DEMO REFLECTED CEILING PLAN

SPEES DESIGN BUILD

23830 PACIFIC HIGHWAY S. SUITE 203

KENT, WA 98032

(206) 590-2118

RENOVATE B211A SPECIALTY

CARE

WHITE CITY VA MEDICAL CENTER - WHITE CITY, OR

692-22-102

211A

08/15/2025 EM AJ

CONSTRUCTION

DOCUMENTS

PROJECT

NORTH

1/4" = 1'-0"

OVERALL DEMO REFLECTED CEILING PLAN

LEGEND

KEY NOTES (THIS SHEET ONLY)

KEY PLAN

GENERAL NOTES

1. REPLACEMENT OF CEILING TILES AT THE END OF EACH

SHIFT IS REQIURED FOR WORK AREAS OUTSIDE OF A RATED

CONSTRUCTION BARRIER (IF PROVIDED). IF THE TILES

CANNOT BE REPLACED, THE SPRINKLER SYSTEM MAY BE

CONSIDERED OUT OF SERVICE IN THESE AREAS AND 1-HOUR

FIRE RATED SEPARATION WILL BE REQUIRED BETWEEN THE

CONSTRUCTION AREA AND THE OCCUPIED PORTIONS OF

THE BUILDING.

Revisions: Date: 7 OF 45

L

L

L

L

L

L

L

L

OVERHEAD

LIFT

SPRINKER

RISER

D.F. D.F.

D F

SOLID

DISP

FD

FD

RAMP

DN.

DN DN

DN

DN

SHOWN AREA

PROJECT

NORTH

1. THE CONTRACTOR SHALL FIELD VERIFY ALL EXISTING

CONDITIONS BEFORE BEGINNING WORK. ANY CONFLICTS

BETWEEN EXISTING CONDITIONS AND THE CONTRACT

DOCUMENTS SHALL BE BROUGHT IMMEDIATELY TO THE

ATTENTION OF THE COR.

2. DIMENSIONS SHOWN ARE FROM GRID LINES TO FACE OF

STUD, CENTERLINE OF STRUCTURAL COLUMNS,

CENTERLINE OF OPENINGS, UON

3. ANY DOORS NOT DIMENSIONED SHALL BE INSTALLED 6"

FROM THE INTERSECTING WALL OR CENTERED ON THE

WALL, UON.

4. ENSURE THAT ALL REQUIRED BACKING IS INSTALLED IN

WALLS PRIOR TO INTALLING DRYWALL.

5. PATCH WALLS WHERE DEMOLISHED FOR INSTALLATION

OF NEW WORK.

6. PROVIDE BACKING AND BLOCKING FOR ALL VV AND CC

PROVIDED ITEMS.

F

E

NO WORK

NO WORK

6' - 6"

/4

100 SF

OFFICE

92 SF

OFFICE

131 SF

EXAM

133 SF

EXAM

130 SF

EXAM

164 SF

EXAM

99 SF

OFFICE

146 SF

EXAM

141 SF

EXAM

60 SF

PATIENT AREA

105 SF

OFFICE

ELECTRICAL

RESTROOM

CLINICAL SUP

SOILED

CLINICAL SUP

CORRIDOR

C1W

CLINICAL SUP

NURSING

STATION

CLINICAL SUP

CORRIDOR

C1W

3" 3"

13' - 3 3/8"

19' - 1 1/8"

7' - 1 1/8"

/8

/8

6"

/8

380 SF

CORRIDOR

C-151

AE421a

AE421a

5 2

100 123

ALIGN

ALIGN

ALIGN

ALIGN

AE421b

AE421b

AE421b

AE421b 7

INFILL RELITE LOCATIONS TO MATCH EXISTING WALLS

AND FINISHES. PAINT ENTIRE EAST WALL WHERE RELITE

INFILLED.

PATCH DOOR LOCATION TO MATCH EXISTING WALL AND

FINISHES. PATCH FLOORING/ COVE AT INFILL, MATCH

EXISTING FLOORING AND PATTERN.

NEW CONCRETE SLAB PATCHING WHERE EXISTING SLAB

DEMOLISHED FOR NEW WORK. PATCH EXISTING VAPOR

BARRIER AND PROVIDE #4 REBAR AT 16 O.C. EACH WAY.

DOWEL INTO EXISTING SLAB 4 INSHES EACH SIDE TO

PREVENT SETTLEMENT. SEE PLUMBING SHEETS FOR

COORDINATION.

INSTALL NEW FLOOR/FINISH.

PAINT ALL WALLS AND CEILING.

INSTALL NEW PLUMBING FIXTURES AND ACCESSORIES.

EXISTING COLUMN TO REMAIN.

EXISTING HANDRAILS TO REMAIN, NO WORK, TYP.

CAP FLOOR DRAIN AND PATCH CONCRETE FLOOR.

OUT OF SCOPE

EXISTING DOOR TO REMAIN

NEW DOOR

WALL TAG (SEE WALL SCHEDULE ON

SCHEDULES SHEET)

DOOR TAG (SEE DOOR SCHEDULE ON

SCHEDULES SHEET)

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

ENGINEERING DISCIPLINE:

AE101

OVERALL FLOOR PLAN

SPEES DESIGN BUILD

23830 PACIFIC HIGHWAY S. SUITE 203

KENT, WA 98032

(206) 590-2118

RENOVATE B211A SPECIALTY

CARE

WHITE CITY VA MEDICAL CENTER - WHITE CITY, OR

692-22-102

211A

08/15/2025 EM AJ

CONSTRUCTION

DOCUMENTS

PROJECT

NORTH

LEGEND

GENERAL NOTES

KEY PLAN

1/4" = 1'-0"

OVERALL FLOOR PLAN

KEY NOTES (THIS SHEET ONLY)

NEW ROOM SCHEDULE

ROOM # NAME

PROGRAM

NET

DESIGNED

NET

100 EXAM 125 NSF 141 SF

123 EXAM 125 NSF 146 SF

124 EXAM 125 NSF 131 SF

125 EXAM 125 NSF 133 SF

126 EXAM 125 NSF 130 SF

129 OFFICE 100 NSF 105 SF

133 EXAM 125 NSF 164 SF

134 OFFICE 100 NSF 99 SF

135 OFFICE 100 NSF 100 SF

149 PATIENT

AREA

- 60 SF

150 OFFICE 100 NSF 92 SF

Revisions: Date: 8 OF 45

L

L

L

L

L

L

L

L

OVERHEAD

LIFT

SPRINKER

RISER

D.F. D.F.

D F

SOLID

DISP

FD

FD

RAMP

DN.

DN DN

DN

DN

WAP

WAP

PP

WAP

WAP

PP

SHOWN AREA

PROJECT

NORTH

2x4 ACOUSTICAL CEILING TILE

GYPSUM BOARD ON METAL STUDS

SUPPLY GRILLE PER MECHANICAL

(SIZE & PROPORTION MAY VARY)

LIGHT FIXTURE PER ELECTRICAL

RETURN GRILLE PER MECHANICAL

(SIZE & PROPORTION MAY VARY)

EXHAUST GRILLE PER MECHANICAL

(SIZE & PROPORTION MAY VARY)

F

E

CLINICAL SUP

NURSING

STATION

CLINICAL SUP

CORRIDOR

C1W

CLINICAL SUP

CORRIDOR

C1W

CLINICAL SUP

SOILED

RESTROOM

ELECTRICAL

EXAM

EXAM

EXAM

OFFICE

OFFICE

OFFICE

EXAM

CORRIDOR

C-151

EXAM

EXAM

PATIENT AREA

F

E

2 24

AFF

ACT 2x4

8' - 6"

AFF

ACT 2x4

8' - 6"

AFF

ACT 2x4

8' - 6"

AFF

ACT 2x4

8' - 6"

AFF

ACT 2x4

8' - 6"

AFF

ACT 2x4

8' - 6"

AFF

ACT 2x4

8' - 6"

F

E F

E

NEW ACT CEILINGS AT 8'-6", TYPICAL IN PROJECT AREA,

ALL ROOMS WHERE EXISTING ACT DEMOLISHED, EXCEPT

WHERE NOTED.

REPLACE ACT CEILING TILES AT EXISTING CEILING GRIDS

NOTED TO REMAIN.

EXISTING CEILINGS OUTSIDE OF WORK AREA, NO WORK.

EXISTING GWB CEILING, PAINT.

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

ENGINEERING DISCIPLINE:

AC101

OVERALL REFLECTED CEILING PLAN

SPEES DESIGN BUILD

23830 PACIFIC HIGHWAY S. SUITE 203

KENT, WA 98032

(206) 590-2118

RENOVATE B211A SPECIALTY

CARE

WHITE CITY VA MEDICAL CENTER - WHITE CITY, OR

692-22-102

211A

08/15/2025 MK AJ

CONSTRUCTION

DOCUMENTS

PROJECT

NORTH

1/4" = 1'-0"

OVERALL REFLECTED CEILING PLAN

KEY NOTES (THIS SHEET ONLY)

LEGEND

GENERAL NOTES

KEY PLAN

1. THE CONTRACTOR SHALL VERIFY ALL EXISTING

CONDITIONS BEFORE BEGINNING OF WORK, ANY

CONFLICTS BETWEEN EXISTING CONDITIONS AND THE

CONTRACT DOCUMENTS SHALL BE BROUGHT IMMEDIATELY

TO THE ATTENTION OF THE COR.

Revisions: Date: 9 OF 45

J

D Mo

J

D Mo

F

A5107

GLOVE

DISPENSER

A5080

PAPER TOWEL

DISPENSER

A5108

SHARPS

DISPOSAL

M1803 WORKSTATIONM1804

DUAL MONITOR

MOUNT

F2010 WASTE BASKET

M0506 TV

M9025 EXAM BED

A1066 MIRROR

F0206 BARIATRIC CHAIRA5145

GARMENT

HOOK

F2310

MAGAZINE

RACK

A5075

SOAP

DISPENSER

A5180

PRIVACY

CURTAIN

TRACK

F0340 STOOL

131 SF

EXAM

AE421a

5 2

F

F

F

LEVEL 1

0' - 0"

M0506TV A1066 MIRROR

F2010 WASTE BASKET

M1804

DUAL MONITOR

MOUNT

M1803 WORKSTATION

F0206 BARIATRIC CHAIR

M9025 EXAM BED

F0340 STOOL INTEGRAL COVE BASE, TYP

F3200 CLOCK

LEVEL 1

0' - 0"

A1066 MIRROR F2310 MAGAZINE RACK

A5180

PRIVACY CURTAIN

TRACK

F0206 BARIATRIC CHAIRM9025 EXAM BED

A5145 GARMENT HOOK

INTEGRAL COVE BASE, TYP

LEVEL 1

0' - 0"

A5075

SOAP

DISPENSER

A5108

SHARPS

DISPOSAL

M1803WORKSTATION

M0506 TV

M9025 EXAM BED

F2010 WASTE BASKET

F3200 CLOCK

F0340STOOL

M1804

DUAL MONITOR

MOUNT

INTEGRAL COVE BASE, TYP

LEVEL 1

0' - 0"

A5108

SHARPS

DISPOSAL

A5107

GLOVE

DISPENSER

A5080

PAPER TOWEL

DISPENSER

A5075

SOAP

DISPENSER

F2310

MAGAZINE

RACK

A5180

PRIVACY

CURTAIN

TRACK

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

ENGINEERING DISCIPLINE:

AE421a

EXAM ROOM 124 - ENLARGED FLOOR PLAN

AND INTERIOR ELEVATIONS

SPEES DESIGN BUILD

23830 PACIFIC HIGHWAY S. SUITE 203

KENT, WA 98032

(206) 590-2118

RENOVATE B211A SPECIALTY

CARE

WHITE CITY VA MEDICAL CENTER - WHITE CITY, OR

692-22-102

211A

08/15/2025 EM AJ

CONSTRUCTION

DOCUMENTS

GENERAL NOTES

1. ALL WALL MOUNTED EQUIPMENT SHALL HAVE METQAL

BLOCKING IN WALL BEHIND. THIS INCLUDES BACKING FOR

WALL MOUNTED DOOR STOPS, DISPENSES, PHONES,

GARMENT HOOKS, ETC. ENSURE THAT ALL REQUIRED

BACKING IS INSTALLED PRIOR TO INSTALLING DRYWALL.

SEE TYPICAL BLOCKING DETAIL.

2. SEE SIGNAGE SHEET FOR SIGNAGE LOCATION PLAN,

MESSAGE SCHEDULE, AND SIGN TYPES.

1/2" = 1'-0"

EXAM ROOM 124 - ENLARGED FLOOR PLAN

1/2" = 1'-0"

EXAM ROOM 124 - INTERIOR EAST ELEV

1/2" = 1'-0"

EXAM ROOM 124 - INTERIOR SOUTH ELEV

1/2" = 1'-0"

EXAM ROOM 124 - INTERIOR NORTH ELEV

1/2" = 1'-0"

EXAM ROOM 124 - INTERIOR WEST ELEV

PROJECT

NORTH

EQUIPMENT SCHEDULE

MARK

FURN /

INST

BY DESCRIPTION COMMENTS

A1066 CC MIRROR A HIGH QUALITY 1/4" POLISHED FLOAT GLASS MIRROR 36X18, FRAMED IN A ONE-PIECE, BRIGHT POLISHED, STAINLESS STEEL CHANNEL FRAME WITH 90° MITERED CORNERS. ALL EDGES OF THE MIRROR ARE PROTECTED BY ABSORBING FILLER STRIPS.

MIRROR HAS A GALVANIZED STEEL BACK WITH INTEGRAL HORIZONTAL HANGING BRACKETS AND WALL HANGER FOR CONCEALED MOUNTING. FOR MOUNTING ABOVE SINGLE WALL MOUNTED LAVATORIES LOCATED IN TOILET AREAS, DOCTORS EXAMINATION OFFICES, ETC. MAY ALSO BE USED ABOVE DOUBLE LAVATORIES, EITHER WALL OR COUNTERTOP MOUNTED, FOUND IN RESTROOM

AREAS.

A5075 VV SOAP DISPENSER DISPOSABLE SOAP DISPENSER. ONE-HANDED DISPENSING OPERATION. DESIGNED TO ACCOMMODATE DISPOSABLE SOAP

CARTRIDGE AND VALVE.

A5080 VV PAPER TOWEL

DISPENSER

A SURFACE MOUNTED, SATIN FINISH STAINLESS STEEL, SINGLE-FOLD, PAPER TOWEL DISPENSER. DISPENSER FEATURES: TUMBLER LOCK; FRONT HINGED AT BOTTOM; AND REFILL INDICATOR SLOT. MINIMUM CAPACITY 400 SINGLE-FOLD PAPER TOWELS. FOR

GENERAL PURPOSE USE THROUGHOUT THE FACILITY.

A5082 VV PAPER TOWEL

DISPENSER

PAPER TOWEL DISPENSER

A5107 VV GLOVE DISPENSER EXAMINATION GLOVE DISPENSER BOX FOR WALL MOUNTING. FABRICATED OF EITHER COLD ROLLED STEEL WITH A WHITE BAKED ENAMEL FINISH, PLASTIC OR ACRYLIC. PROVIDED WITH WALL BRACKET TO FACILITATE MOUNTING AND DEMOUNTING.

A5108 VV SHARPS DISPOSAL A CONTAINER FOR COLLECTING AND TRANSPORTING SYRINGES AND OTHER SHARPS FOR DECONTAMINATION AND DISPOSAL.

AVAILABLE IN 2 GALLON AND 8 GALLON WITH LOCKING ROTOR. COMPLIES WITH OSHA REGULATIONS FOR HANDLING SHARPS.

A5145 CC GARMENT HOOK A SURFACE MOUNTED, SATIN FINISH STAINLESS STEEL, DOUBLE GARMENT HOOK. EQUIPPED WITH A CONCEALED MOUNTING BRACKET THAT IS SECURED TO A CONCEALED WALL PLATE. FOR GENERAL PURPOSE USE THROUGHOUT THE FACILITY TO HANG

VARIOUS ITEMS OF APPAREL.

A5180 CC PRIVACY CURTAIN

TRACK

SURFACE MOUNTED CUBICLE TRACK, WITH CURTAIN. TRACK CONSTRUCTED OF THICK EXTRUDED ALUMINUM. EQUIPPED WITH SELF LUBRICATING CARRIERS, BEADED DROP CHAIN HOOKS, AND FLAME RESISTANT CURTAIN. TO INCLUDE REMOVABLE END CAPS.

DESIGNED TO BE SUSPENDED AROUND PATIENT AREAS WHERE PRIVACY IS NEEDED. PRICE LISTED IS PER FOOT OF THE TRACK, CURTAINS TO BE PRICED PER QUOTE.

F0206 VV BARIATRIC CHAIR A BARIATRIC SIDE CHAIR WITH ARMS FOR USE IN A WAITING ROOM, LOBBY OR OTHER PATIENT AREA. CHAIR WILL HAVE A PADDED

SEAT AND BACK AND HAVE A CAPACITY OF 800 POUNDS.

F0340 VV STAFF STOOL SELF ADJUSTING STOOL. CONSISTS OF A FOAM PADDED UPHOLSTERED SEAT WITH ATTACHED FOOT REST FOR ADDED COMFORT.

MOUNTED ON SWIVEL CASTERS. DESIGNED FOR DOCTOR'S USE DURING EXAMINATIONS.

F2010 VV WASTE BASKET "STEP-ON" WASTEPAPER BASKET WITH INNER LINER AND FOOR PEDAL ACTIVATED FLIP TOP.

F2310 VV MAGAZINE RACK WALL MOUNTED PAMPHLET RACK UP TO 12 (TWELVE) PAMPHLET HOLDING POCKETS. UNIT IS USED TO STORE AND DISPLAY

EDUCATIONAL PAMPHLETS.

F3200 VV CLOCK CLOCK, 12" DIAMETER. ROUND SURFACE, EASY TO READ NUMBERS WITH SWEEP SECOND HAND. WALL MOUNTED UNIT FOR USE WHEN IMPRACTICAL TO INSTALL A FULLY SYNCHRONIZED CLOCK SYSTEM. BATTERY OPERATED, (BATTERIES NOT INCLUDED).

M0506 VV FLAT SCREEN TV. FLAT SCREEN TELEVISION WITH APPROXIMATELY 32'" TO 40' DIAGONAL SCREEN SIZE. THE TV WILL HAVE BUILT-IN SPEAKERS, NTSC TUNER, A 16:9 WIDE SCREEN ASPECT RATIO, A MINIMUM OF 1280 X 768 RESOLUTION AND A REMOTE CONTROL.

M1803 VV WORKSTATION A WALL MOUNTED RETRACTABLE WORK STATION. WORK STATION IS USED AS A COMPUTER STATION IN TREATMENT ROOMS, EXAM

ROOMS AND AREAS WHERE PHYSICAL SPACE IS LIMITED.

M1804 VV DUAL MONITOR

MOUNT

WALL MOUNTED DUAL MONITOR MOUNT.

M9025 VV EXAM BED TABLE, EXAMINATION/TREATMENT WITH CABINET. CABINET TYPE EXAM TABLE WITH THREE SECTION UPHOLSTERED TOP ADJUSTABLE TO A FULL CHAIR POSITION. CONCEALED HEEL STIRRUPS, DUAL OUTLETS, DRAWERS, AND STORAGE SPACE WITH OPTIONAL ARMBOARD. UNIT IS DESIGNED FOR GENERAL USE IN EXAMINATION/TREATMENT ROOMS.

Revisions: Date: 10 OF 45

J

D Mo

J

D Mo

J

FS

D Mo a

J

FS

D Mo a

F

AE421b

F0340 STOOL

M9025 EXAM BED

M0506 TV

F2010 WASTE BASKET

M1803 WORKSTATIONM1804

DUAL MONITOR

MOUNT

A5108

SHARPS

DISPOSAL

A5080

PAPER TOWEL

DISPENSER

A5075

SOAP

DISPENSER

A5107

GLOVE

DISPENSER

A5180

PRIVACY

CURTAIN

TRACK

F2310

MAGAZINE

RACK

A5145

GARMENT

HOOK

F0206 BARIATRIC CHAIR

A1066 MIRROR

133 SF

EXAM

FFF

LEVEL 1

0' - 0"

F2010

WASTE

BASKET

M0506TV

F3200 CLOCK

M9025 EXAM BED

A1066 MIRROR

M1803WORKSTATION

M1804

DUAL MONITOR

MOUNT

F0340 STOOL

F0206 BARIATRIC CHAIR

INTEGRAL COVE BASE, TYP

LEVEL 1

0' - 0"

LEVEL 1

0' - 0"

LEVEL 1

0' - 0"

A1066MIRROR

M9025EXAM BED

F0206 BARIATRIC CHAIR

A5145

GARMENT

HOOK F2310 MAGAZINE RACK

A5180

PRIVACY CURTAIN

TRACK

INTEGRAL COVE BASE, TYP

LEVEL 1

0' - 0"

LEVEL 1

0' - 0"

LEVEL 1

0' - 0"

F3200 CLOCK

M0506 TV

M1803WORKSTATION

M1804

DUAL MONITOR

MOUNT

F2010 WASTE BASKET

M9025 EXAM BED

F0340STOOL

A5108

SHARPS

DISPOSAL

A5075

SOAP

DISPENSER

INTEGRAL COVE BASE, TYP

LEVEL 1

0' - 0"

LEVEL 1

0' - 0"

LEVEL 1

0' - 0"

A5107 GLOVE DISPENSER

A5080

PAPER TOWEL

DISPENSER

A5108 SHARPS DISPOSAL

A5075

SOAP

DISPENSER

F2310

MAGAZINE

RACK

A5180

PRIVACY

CURTAIN

TRACK

LEVEL 1

0' - 0"

LEVEL 1

0' - 0"

F

AE421b

130 SF

EXAM

126 AE421b 7

A5108

SHARPS

DISPOSAL

M1804

DUAL MONITOR

MOUNT

A5080

PAPER TOWEL

DISPENSER

A5107

GLOVE

DISPENSER

A5075

SOAP

DISPENSER

A5180

PRIVACY

CURTAIN

TRACK

F2310

MAGAZINE

RACK

A5145

GARMENT

HOOK

F0206 BARIATRIC CHAIR

A1066 MIRROR

F0340 STOOL

M9025 EXAM BED

M0506 TV

F2010 WASTE BASKET

M1803 WORKSTATION FFF

LEVEL 1

0' - 0"

F3200 CLOCK

M0506TV

M1804

DUAL MONITOR

MOUNT

F2010

WASTE

BASKET

F0340 STOOL

M9025 EXAM BED

F0206 BARIATRIC CHAIR

A1066 MIRROR

INTEGRAL COVE BASE, TYP

M1803WORKSTATION

LEVEL 1

0' - 0"

LEVEL 1

0' - 0"

LEVEL 1

0' - 0"

A1066MIRROR

M9025EXAM BED

A5145

GARMENT

HOOK F2310 MAGAZINE RACK

A5180

PRIVACY CURTAIN

TRACK

F0206 BARIATRIC CHAIR INTEGRAL COVE BASE, TYP

LEVEL 1

0' - 0"

LEVEL 1

0' - 0"

LEVEL 1

0' - 0"

F3200 CLOCK

M0506 TV

M9025 EXAM BED

M1804

DUAL MONITOR

MOUNT

M1803WORKSTATION

A5108

SHARPS

DISPOSAL

A5075

SOAP

DISPENSER

F0340STOOL

F2010 WASTE BASKET

INTEGRAL COVE BASE, TYP

LEVEL 1

0' - 0"

LEVEL 1

0' - 0"

LEVEL 1

0' - 0"

A5180

PRIVACY

CURTAIN

TRACK

F2310

MAGAZINE

RACK

A5075

SOAP

DISPENSER

A5108 SHARPS DISPOSAL

A5080

PAPER TOWEL

DISPENSER

A5107 GLOVE DISPENSER

LEVEL 1

0' - 0"

LEVEL 1

0' - 0"

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

ENGINEERING DISCIPLINE:

AE421b

EXAM ROOM 125 & 126 - ENLARGED FLOOR

PLAN AND INTERIOR ELEVATIONS

SPEES DESIGN BUILD

23830 PACIFIC HIGHWAY S. SUITE 203

KENT, WA 98032

(206) 590-2118

RENOVATE B211A SPECIALTY

CARE

WHITE CITY VA MEDICAL CENTER - WHITE CITY, OR

692-22-102

211A

08/15/2025 EM AJ

CONSTRUCTION

DOCUMENTS

1/2" = 1'-0"

EXAM ROOM 125 - ENLARGED FLOOR PLAN

PROJECT

NORTH

1/2" = 1'-0"

EXAM ROOM 125 - INTERIOR EAST ELEV

1/2" = 1'-0"

EXAM ROOM 125 - INTERIOR SOUTH ELEV

1/2" = 1'-0"

EXAM ROOM 125 - INTERIOR NORTH ELEV

1/2" = 1'-0"

EXAM ROOM 125 - INTERIOR WEST ELEV

1/2" = 1'-0"

EXAM ROOM 126 - ENLARGED FLOOR PLAN

1/2" = 1'-0"

EXAM ROOM 126 - INTERIOR EAST ELEV

1/2" = 1'-0"

EXAM ROOM 126 - INTERIOR SOUTH ELEV

1/2" = 1'-0"

EXAM ROOM 126 - INTERIOR NORTH ELEV

1/2" = 1'-0"

EXAM ROOM 126 - INTERIOR WEST ELEV

PROJECT

NORTH

Revisions: Date: 11 OF 45

VERTICAL WALL STUDS

@ 16" OR 24" OC

CUT HORIZONTAL

FASTENER FROM STUD

FASTEN AT BOTH ENDS

WITH MIN 4 TAPPING

SCREWS

WALL FINISH

ISOMETRIC VIEW

PLAN VIEW

GENERAL NOTES:

1. CONTRACTOR SHALL COORDINATE LOCATIONS OF

HORIZONTAL FASTENERS.

2. ALL WALL MOUNTED EQUIPMENT SHALL HAVE METAL

BLOCKING IN WALL BEHIND. ENSURE ALL REQUIRED

BACKING IS INSTALLED PRIOR TO INSTALLING GYP.

BLOCKING AT

TOP & BOTTOM

1/4" PLY BACK WITH

PLAM FINISH

RECESSED ADJUSTABLE

SHELF STANDARDS, TYP

3/4" PLY ADJUSTABLE SHELF

WITH PLAM FINISH

3/4" PLY END OR DIVIDER

PANEL WITH PLAM FINISH

FACE OF WALL

3/4" PLY BOTTOM WITH

PLAM FINISH

3/4" PLY DOOR WITH

PLAM EA SIDE

4" x 3/8" DIA

WIRE PULL

1' - 3"

3/4" x 2-1/2" BLOCKING

ANCHORED TO IN-WALL

BLOCKING, TYP

SDSF COUNTERTOP & BACKSPLASH

4" x 3/8" DIA WIRE PULL

3/4" PLY DOOR WITH

PLAM FINISH EA SIDE

3/4" PLY TOE KICK WITH

PLAM FINISH & BASE

3/4" x 2-1/2"

BLOCKING, TYP

3/4" PLY BOTTOM WITH

PLAM FINISH

2x4 PRESSURE

TREATED FRAME

BLOCKING AT TOP &

BOTTOM OF CABINET

1/4" PLY BACK WITH

PLAM FINISH

3/4" PLY END OR DIVIDER

PANEL WITH PLAM FINISH

FACE OF WALL

3/4" PLY FAUX

DRAWER FRONT

WITH PLAM FINISH

PIPING PER PLUMBING

3"

3/4" x 1-1/2" PLY FRAME

WITH PLAM FINISH, TYP

DROP-IN SINK & FACUET

PER PLUMBING

2' - 0"

SDSF COUNTERTOP & BACKSPLASH

4" x 3/8" DIA

WIRE PULL, TYP

3/4" PLY TOE KICK

WITH PLAM FINISH

& BASE

3/4" PLY BOTTOM WITH

PLAM FINISH

2x4 PRESSURE

TREATED FRAME

BLOCKING AT TOP &

BOTTOM OF CABINET

1/4" PLY BACK WITH

PLAM FINISH

3/4" PLY END OR DIVIDER

PANEL WITH PLAM FINISH

FACE OF WALL

1/2" PLY DRAWER

FRONT WITH PLAM

FINISH, TYP

1/2" PLY DRAWER BACK,

SIDES & BOTTOM WITH

PLAM FINISH, TYP

2' - 0"

E Q

E Q

E Q

E Q

3"

DRAWER SLIDE, TYP

3/4" x 2-1/2"

BLOCKING, TYP

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

ENGINEERING DISCIPLINE:

A-501

DETAILS

SPEES DESIGN BUILD

23830 PACIFIC HIGHWAY S. SUITE 203

KENT, WA 98032

(206) 590-2118

RENOVATE B211A SPECIALTY

CARE

WHITE CITY VA MEDICAL CENTER - WHITE CITY, OR

692-22-102

211A

08/15/2025 MK AJ

CONSTRUCTION

DOCUMENTS

GENERAL NOTES

1. ALL WALL MOUNTED EQUIPMENT SHALL HAVE BLOCKING IN

WALL BEHIND. THIS INCLUDES BACKING FOR WALL

MOUNTED DOOR STOPS, DISPENSERS, PHONES, ETC.

ENSURE THAT ALL REQUIRED BACKING IS INSTALLED

PRIOR TO INSTALLING DRYWALL. SEE TYPICAL BLOCKING

DETAIL.

TYPICAL BLOCKING DETAIL

1 1/2" = 1'-0"

PLAM WALL CABINET DETAIL

1 1/2" = 1'-0"

PLAM BASE CABINET DETAIL - SINK & DOOR

1 1/2" = 1'-0"

PLAM BASE CABINET DETAIL - 4 EQ DRAWERS

Revisions: Date: 12 OF 45

PERSPECTIVE 1 -FRONT PERSPECTIVE 2 -BACK

FRAME OPTIONAL KEY CYLINDER

12" BACK TO BACK LADDER

PULL

OPTIONAL THUMB TURN

12" BACK TO BACK LADDER

PULL

FRAME

2" CLEAR OPENING 5" DOOR OVERHANG

SLAB

1 1/2" MINIMUM CLEARANCE

TRACK

FINISHED FRAME

/4

C L E

A R

O P

E N

H E

IG

H

T

2"

1/2" 2 1/2"

1 1/2" MINIMUM CLEARANCE

/4

TRACK

DOOR

1 3/4"

/4

2 1/2"

WALL WALL

3' - 4"

DOOR

1 3/4" METAL STUD

WALL

WOOD BLOCKING

BY OTHERS

/4

2 3/4"

1/4"

5/8" 3 5/8" 5/8"

4 7/8"

SERENITY DOUBLE

SOUND SEAL SYSTEM 2

/4

2"

/4

2"

METAL STUD

WALL

SERENITY DOUBLE

SOUND SEAL SYSTEM

DOOR

2"

/4

/2

METAL STUD

WALL

SERENITY

SOUND SEAL

DOOR

1"

A-510

Sim

A-510

Sim

OPEN DOOR VIEW CLOSED DOOR VIEW

A-510

5 Sim

A-510

8 Sim

A-510

6 Sim

A-510

7 Sim

DOOR

CONCEALED FLOOR GUIDE

OPTIONAL KEY CYLINDER OPTIONAL PRIVAVY

INDICATOR

OPTIONAL THUMB TURN

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

ENGINEERING DISCIPLINE:

A-510

INTERIOR SLIDING DOOR DETAILS

SPEES DESIGN BUILD

23830 PACIFIC HIGHWAY S. SUITE 203

KENT, WA 98032

(206) 590-2118

RENOVATE B211A SPECIALTY

CARE

WHITE CITY VA MEDICAL CENTER - WHITE CITY, OR

692-22-102

211A

08/15/2025 MK AJ

CONSTRUCTION

DOCUMENTS

6" = 1'-0"

PERSPECTIVE VIEWS

1" = 1'-0"

FRONT VIEWS

1" = 1'-0"

VIEW A-A

1" = 1'-0"

VIEW B-B

6" = 1'-0"

DETAIL 01

6" = 1'-0"

DETAIL 02

6" = 1'-0"

DETAIL 04

6" = 1'-0"

DETAIL 03

1 1/2" = 1'-0"

DOOR HANDLES

3" = 1'-0"

12" BACK TO BACK LADDER PULL

3" = 1'-0"

SMALL MORTISE LOCK

Revisions: Date: 13 OF 45

A(C)T ACOUSTICAL CEILING TILE

GWB GYPSUM WALLBOARD

P PAINT

SV SHEET VINYL

LVT LUXURY VINYL TILE

RB RESILIENT BASE

FINISH ABBREVIATIONS

9" 4"

DOOR HEIGHTS AND WIDTHS PER SCHEDULE

GLAZING

SURFACE SLIDING

DOOR HEIGHTS AND WIDTHS PER SCHEDULE

MTL DOOR

FRAME

SHIM AS

REQ'D

RUNNER

BETWEEN

STUDS

1/2"

CONST

JOINT

SEE NOTE 1

VERTICAL STUDS @ 2'-0" MAX. W/

GYPSUM WALL BOARD. 1'-4" W/ GYPSUM

LATH & PLASTER DOUBLE STUDS FOR

SUPPORTING CONC. BACKER BOARD

PROVIDE CONTINUOUS BRACING

WHEN STUDS EXCEED 10'-0" AND

ARE FINISHED BOTH SIDES

JAMB ANCHOR CLIPS 3 PER

SIDE - COORDINATE W/

HINGE REINFORCEMENT

NOTE 1: OMIT BRACE WHEN 'D' DIMENSION

IS LESS THAN 2'-0" FOR GYP. WALL BOARD

OR 16" FOR PLASTER PARTITION

ELEVATION AT DOOR FRAME

DETAIL D

JAMB ANCHORS

(FURNISHED W/ FRAME)

DETAIL C

FRAME FACE

MIN

US 3/16"

E Q

E Q

D

E Q

E Q

V A

R

IE

S S

E E

D O

O R

S C

H E

D

VARIES SEE DOOR SCHED

DETAIL B

A A

1/2" M

IN

5/8" M

AX

FRAME FACE

MIN

US 3/16"

/4

M

IN

STUD

W

IDTH

/4

M

IN

JAMB DEPTH

MINUS 3/16"

STUD

W

IDTH

1/2"

DETAIL D, TYP

M A

X

DETAIL B

PROVIDE SOUND

DEADENING WHERE

REQUIRED

/8

SECTION A

DOUBLE STUDS JAMB ANCHOR

GYPSUM WALL

BOARD PANELS

CONTROL JOINT

ISOMETRIC OF CONSTRUCT JOINT

/4

M

IN

DETAIL C

SANITARY

STOP

MTL DOOR FRAME

MTL ANCHOR CLIP

SHIM AS

REQ'D

CRIPPLE STUD, DO NOT

ANCHOR TO BEARING STUD

1/2" M

IN

CAULK ALL

AROUND

ADJUSTABLE

ANCHOR

STANDARD FRAME

EXPOSED MASONRY OR BRICK

1/2"

S.F.T.U.

NOMINAL

CMU OR 1/2"

FRAMES IN MASONRY PARTITION

CASING BEAD

ADJUSTABLE

ANCHOR

STANDARD FRAME

MASONRY BLOCK PLASTERED

GROUT

5/8"

S.F.T.U.

NOMINAL

CMU OR 7/8"

PLASTER ON

METAL LATH

CAULK ALL

AROUND

GROUT

CERAMIC TILE

ADJUSTABLE

ANCHOR

STANDARD FRAME

MASONRY BLOCK WITH CERAMIC TILE FINISH

GROUT

SETTING BED

CAULK ALL

AROUND

1/2"

S.F.T.U.

NOMINAL

CMU OR 3/4"

*** FRAME WIDTH FOR NOMINAL MASONRY

4 3/4" W/ 4" CMU

6 3/4" W/ 6" CMU

8 3/4" W/ 8" CMU

METAL STUD AND PLASTER FINISH

FRAMES WITH METAL STUD

AND PLASTER PARTITIONS

GAUGE AS

SPECIFIED

ADD RETURN ON

FRAME WHERE

DRYWALL FINISH

IS REQUIRED

STANDARD DOOR FRAME

FRAMES IN METAL STUD PARTITIONS

CERAMIC TILE

FINISH WHERE

REQUIRED

CAULK ALL

AROUND BOTH

SIDES

STANDARD FRAME

FOR DRYWALL

JAMB ANCHORS

DOUBLE STUDS

BACK TO BACK

DRYWALL, THICKNESS

SINGLE OR DOUBLE AS

REQUIRED

FRAMES IN MASONRY PARTITION

FACED WITH GWB

STANDARD FRAME

ADJUSTABLE

ANCHORS

GROUT

CAULK ALL

AROUND

CERAMIC TILE

FINISH WHERE

REQUIRED

TILE FINISH

FRAME AT CONCRETE WALLS

DOUBLE EGRESS DOOR FRAME

PLAN

JAMB 'B'

HEAD 'A'

NOTE: SHOWING SWING OF

DOUBLE EGRESS DOORS

A B

C

A C

B

NOTE: SHOWING SWING OF

DOUBLE EGRESS DOORS

DOOR

DOOR

DOOR STOP (BEYOND)

PLATE WELDED

TO FRAME

/2

"2 1/2" MIN

+/- 1/4"

/4

7/8"

08 11 13-01

METAL STUDS

PER STD DTL 3/4"

1/4"

7/8"

08 11 13-01

MTL STUDS

PER STD DTL 11/16"

1/4"

1/4"

1/4"

CAULK ALL

AROUND

CASING BEAD

WHERE PLASTER

IS REQUIRED

CONCRETE

GROUT

VENEER

PLASTER ON

PLASTER BASE

TROWEL CUT

AT FRAME

EDGES

ANCHOR

STANDARD

FRAME

CONVENTIONAL

PLASTER

GYP LATH

CERAMIC TILE

CAULK BOTH

SIDES

ANCHOR

STANDARD

FRAME

CERAMIC TILE

GWB

CEMENT

BACKER BOARD

PIPE SEPARATORS

WELDED TO PLATE

F.H. CSK.

EXP. BOLT

THROAT OPENING = PARTITION

WIDTH + 1/8" MIN

1/2" 1/2"

/8

1 15/16"VARIESVARIES

TYPE 'X' GYP

STEEL STUD FRAMING WITH FIBER GLASS

SOUND BATT INSULATION

TYPE 'X' GYP

5/8"

5/8" 3 5/8"

5/8"

STRUCTURE ABV

"FINISH CLG

GA FILE NO.

WP 1052

50-54 STC

(2 LAYERS)

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

ENGINEERING DISCIPLINE:

A-601

SCHEDULES, DETAILS, DOOR TYPES &

DETAILS

SPEES DESIGN BUILD

23830 PACIFIC HIGHWAY S. SUITE 203

KENT, WA 98032

(206) 590-2118

RENOVATE B211A SPECIALTY

CARE

WHITE CITY VA MEDICAL CENTER - WHITE CITY, OR

692-22-102

211A

08/15/2025 EM AJ

CONSTRUCTION

DOCUMENTS

ROOM FINISH SCHEDULE

ROOM

ROOM

NAME

CEILING FLOOR

MAT

BASE WAINSCOT WALL

COMMENTSMAT FIN MAT HT MAT HT MAT FIN

100 EXAM AT SV SV 4" - - GWB P

123 EXAM AT P SV SV 4" - - GWB P

124 EXAM AT SV SV 4" - - GWB P

125 EXAM AT SV SV 4" - - GWB P

126 EXAM AT SV SV 4" - - GWB P

129 OFFICE AT LVT PLANK RB 4'

4"

- - GWB P

130 RESTROOM EX P SV SV 4" - - GWB P

133 EXAM AT SV SV 4" - - GWB P

134 OFFICE AT LVT PLANK RB 4" - - GWB P

135 OFFICE AT LVT PLANK RB 4" - - GWB P

149 PATIENT AREA AT LVT PLANK RB GWB P

150 OFFICE AT LVT PLANK RB 4" - - GWB P

C-151 CORRIDOR AT LVT PLANK RB 4" - - GWB P MATCH EXISTING CONDITIONS AT CORRIDOR

DOOR SCHEDULE

MARK ROOM #

ROOM

NAME

DOOR SIZE DOOR

TYPE

GLAZING

TYPE

HW

SET

MATERIAL FIRE

RATING COMMENTSWIDTH HT THK DOOR FRAME

100 100 EXAM 4' - 0" 7' - 0" 0' - 1 3/4" 6 - SDH1 WOOD METAL -- SLIDING DOOR 42" NET CLEAR OPENING

123 123 EXAM 4' - 0" 7' - 0" 0' - 1 3/4" 6 - SDH1 WOOD METAL -- SLIDING DOOR 42" NET CLEAR OPENING

124 124 EXAM 4' - 0" 7' - 0" 0' - 1 3/4" 6 - SDH1 WOOD METAL -- SLIDING DOOR 42" NET CLEAR OPENING

125 125 EXAM 4' - 0" 7' - 0" 0' - 1 3/4" 6 - SDH1 WOOD METAL -- SLIDING DOOR 42" NET CLEAR OPENING

126 126 EXAM 4' - 0" 7' - 0" 0' - 1 3/4" 6 - SDH1 WOOD METAL -- SLIDING DOOR 42" NET CLEAR OPENING

133 133 EXAM 4' - 0" 7' - 0" 0' - 1 3/4" 6 - SDH1 WOOD METAL -- SLIDING DOOR 42" NET CLEAR OPENING

135 135 OFFICE 3' - 0" 6' - 8" 0' - 1 3/4" 1 TEMPERED 3E WOOD METAL --

149 149 PATIENT AREA 4' - 0" 7' - 0" 0' - 1 3/4" 6 - SDH1 WOOD METAL -- SLIDING DOOR 42" NET CLEAR OPENING

150 150 OFFICE 3' - 0" 6' - 8" 0' - 1 3/4" 1 TEMPERED 3E WOOD METAL --

1/4" = 1'-0"

DOOR TYPES

3/4" = 1'-0"

PARTITION FRAMING AT DOORS

3" = 1'-0"

INTERIOR DOOR FRAMES

1" = 1'-0"

WALL TYPES

Revisions: Date: 14 OF 45

F

E

AE421a

5 2

AE421b

AE421b 7

IN-04.02-04

IN-04.02-05

IN-04.02-02

IN-04.02-03

IN-04.02-09

IN-04.02-06

IN-04.02-08

IN-04.02-07

EXAM

EXAM

EXAM

EXAM

EXAM

EXAM

PATIENT AREA

OFFICE

OFFICE

OFFICE

CLINICAL SUP

NURSING

STATION

IN-04.02-01

OFFICE

ELECTRICAL

RESTROOM

CLINICAL SUP

SOILED

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

ENGINEERING DISCIPLINE:

AW001

SIGNAGE MESSAGE SCHEDULE, IN-04.02,

IN-07.02

SPEES DESIGN BUILD

23830 PACIFIC HIGHWAY S. SUITE 203

KENT, WA 98032

(206) 590-2118

RENOVATE B211A SPECIALTY

CARE

WHITE CITY VA MEDICAL CENTER - WHITE CITY, OR

692-22-102

211A

08/15/2025 MK AJ

CONSTRUCTION

DOCUMENTS

1/4" = 1'-0"

LEVEL 1 - SIGNAGE LOCATION PLAN

PROJECT

NORTH

6" = 1'-0"

IN-04.02 - ROOM IDENTIFICATION

GENERAL NOTES

1. CONTRACTOR TO MATCH EXISTING SIGNAGE AT THE VA

MEDICAL CENTER.

SIGNAGE MESSAGE SCHEDULE

MARK ROOM # ROOM NAME MESSAGE NOTES

IN-04.02-01 135 OFFICE Office

IN-04.02-02 150 OFFICE Office

IN-04.02-03 124 EXAM Exam

IN-04.02-04 100 EXAM Exam

IN-04.02-05 123 EXAM Exam

IN-04.02-06 125 EXAM Exam

IN-04.02-07 126 EXAM Exam

IN-04.02-08 133 EXAM Exam

IN-04.02-09 149 PATIENT AREA Patient Area

Revisions: Date: 15 OF 45

FIRE PROTECTION WET

FIRE PROTECTION PRE-ACTION

PIPING SYSTEMS

FPW

FPPA

PIPING SYMBOLS

PL4

PL7

A

26-P 3

DETAIL NUMBER

DRAWING NUMBER WHERE SHOWN

SECTION LETTER

TYPICAL UNIT NO.

BUILDING NO. WHERE EQUIPMENT IS LOCATED.

PUMP NO. 3 IN BUILDING NO. 26

EQUIPMENT ABBREVIATION (PUMP)

DRAWING NUMBER WHERE DRAWN

FIRE PROTECTION DRYFPD

FIRE PROTECTION OTHERFPO

ABBREVIATIONS

CONTINUATION

DROP IN PIPE

ELBOW

TEE

UNION

TOP CONNECTION

BOTTOM CONNECTION

TOP…