FILE SUMMARY: Wayne Township Park ADA Improvements Project
This is a project manual and bid invitation issued by Schuylkill County, Pennsylvania, on behalf of Wayne Township for construction of ADA-compliant improvements at Wayne Township Park (Summit Station Park). The project scope consists of site preparation, installation of an ADA-accessible fishing deck (8 feet by 10 feet with composite decking and railing), and construction of a 5-foot asphalt access path with associated grading and restoration of disturbed areas. Sealed bids will be received electronically via PennBid until 9:00 a.m. on Wednesday, May 20, 2026, with public opening and display of results online at the same platform. A non-mandatory pre-bid conference will be held on-site on Tuesday, May 5, 2026, at 10:00 a.m. Each bid must be accompanied by a bid bond, certified check, or cashier's check equal to not less than 10 percent of the bid amount, along with a signed non-collusion affidavit. Bids shall remain open for 60 days from opening unless delayed by governmental approval, bond sales, or grant awards, in which case bids remain open for 120 days. The contract term is 60 calendar days for substantial completion and 60 calendar days for final completion and readiness for payment. Liquidated damages are assessed at $500 per calendar day for delays beyond these deadlines.
The project is funded in part by a grant from the U.S. Department of Housing and Urban Development under administration of the Pennsylvania Department of Community and Economic Development. Prevailing wage rates established under the Davis-Bacon Act apply to all work, with required compliance documentation including federal labor standards certifications, public works employment verification forms, non-segregated facilities certifications, and MBE/WBE participation statements. Bidders must demonstrate a minimum of five years of documented experience in comparable work and submit detailed experience questionnaires, subcontractor lists, and qualifications. The contract requires performance and payment bonds each equal to 100 percent of the contract price, comprehensive general liability insurance with minimum coverage of $2,000,000 general aggregate, and property insurance for full replacement cost of the work. Retainage of 10 percent applies until 50 percent completion, reducing to 5 percent thereafter. Contract documents are available electronically at no cost via PennBid or as hard copies for a fee through ARRO Consulting, Inc., the engineer of record.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COUNTY OF SCHUYLKILL
Commonwealth of Pennsylvania
PROJECT MANUAL
For
WAYNE TOWNSHIP
WAYNE TOWNSHIP PARK ADA
IMPROVEMENTS
Engineer�s Project No. 10582.17
(CDBG)
April 2026
ARRO Consulting, Inc.
1239 Centre Turnpike
Orwigsburg, PA 17901
(570) 366-9534
10582.17 - i - ARRO
TABLE OF CONTENTS
TITLE PAGE NO.
BIDDING REQUIREMENTS
Invitation To Bid 00010�1
Instructions To Bidders 00100�1
BIDDING FORMS
Bid Form 00300�1
Bid Bond 00350�1
Experience Questionnaire 00400�1
List Of Proposed Subcontractors 00450�1
Non-Collusion Affidavit 00460-1
Public Works Employment Verification Form 00470-1
Certification of Non-Segregated Facilities 00471-1
Compliance with the Prohibition of Illegal Alien Labor 00472-1
Civil Rights / Discrimination 00473-1
Contractor Integrity Provisions 00474-1
Right to Know Law 00475-1
Compliance with the State Contractor Responsibility Program 00476-1
Provisions Concerning the Americans with Disabilities Act 00477-1
American Recovery and Investment Act of 2009 00478-1
MBE/WBE Contract Solicitation and Commitment Statement 00479-1
CONTRACT FORMS
Statement of Bidder�s Liability 00480-1
Statement of Disposal 00490-1
Agreement 00500�1
Performance Bond 00610�1
Payment Bond 00620-1
10582.17 -ii - ARRO
CONDITIONS OF THE CONTRACT
Commonwealth Of Pennsylvania Requirements 00800A-1
Federal Requirements 00800B-1
Federal Labor Standards 00800C-1
Federal Payroll Certification 00800D-1
SPECIFICATIONS
DIVISION 1 - GENERAL REQUIREMENTS
Section 01010 - Summary of Work 01010-1
Section 01025 � Measurement And Payment 01025�1
Section 01025A � Payment Application Form 01025A�1
Section 01200 - Project Meetings 01200-1
Section 01300 � Submittals 01300�1
Section 01500 � Construction Facilities and Temporary Controls 01500�1
Section 01600 � Materials And Equipment Handling 01600�1
Section 01700 � Contract Closeout 01700�1
DIVISION 2 � SITE WORK
Section 02015 � Protection Of Underground Facilities 02015�1
Section 02210 - Site Grading 02210-1
Section 02260 - Finish Grading 02260-1
Section 02500 - Paving and Surfacing 02500-1
DIVISION 3� CONCRETE
Section 03100 � Concrete Form Work 03100-1
Section 03300 - Cast-In-Place Concrete 03300-1
Exhibits
10582.17 00010-1 ARRO
DOCUMENT 00010
INVITATION TO BID
Sealed Bids for the Wayne Township � Wayne Township Park ADA Improvements project shall be received by the Schuylkill County Board of Commissioners online via PennBid
(https://pennbid.bonfirehub.com/) until 9:00 AM. Wednesday, May 20, 2026 at which time the bids will be publicly opened and the results publicly displayed online at (https://pennbid.bonfirehub.com/). The bid will be awarded at a later date.
Contract Documents for the work are on file and can be obtained electronically on PennBid for no cost. A fee for the documents, postage and handling will be charged to bidders wishing to receive a hard copy which can be ordered via the PennBid portal. A non-mandatory pre-bid conference will be held on site, Tuesday
May 5, 2026 at 10:00 AM.
Each bid shall be accompanied by a bidder�s bond, or certified check or cashier�s check, in favor of the
County of Schuylkill in the amount of not less than ten percent. Bidders must also submit with their bids the non-collusion affidavit contained in the bidding documents.
The work generally consists of site preparation and installation of an ADA accessible fishing deck and 5� asphalt access path and associated restoration of disturbed areas. The work locations are more specifically identified in the project manual/bid documents.
Bids shall remain open for sixty (60) days from the date of Bid opening unless award is delayed by a required approval from a governmental agency, the sale of bonds, or the award of a grant or grants, in which event the Bids shall remain open for a period of 120 days from the date of Bid opening. See
Instructions to Bidders for other provisions on the time available for acceptance of Bids.
Prevailing wages established under the Davis-Bacon Act will apply to this contract. The bidding/contract documents contain requirements addressing prevailing labor wage rates, labor standards, nondiscrimination in hiring practices, goals for minority and female participation, MBE and WBE participation.
Qualified Minority and Women Businesses Enterprise (MBE/WBE) are encouraged to respond to this
Invitation to Bid.
As a precondition of being awarded a Contract, Successful Bidder, and its subcontractor(s) are required, to provide confirmation of compliance with Act 127 of 2012, the �Public Works Employment
Verification Act�. All submitted bids shall be accompanied with the Public Works Employment
Verification Form.
Bidders, subcontractors, their workers and any persons providing labor and products to the Project shall be persons lawfully permitted to work in the United States and the Commonwealth of Pennsylvania.
Contractor and its subcontractor(s) shall comply with Federal and Commonwealth of Pennsylvania requirements under �Megan�s Law� in hiring or employing personnel to perform work in this project.
The County hereby reserves the right, which is understood and agreed to by all Bidders, to reject any or all Bids and to waive any omissions, errors, or irregularities in any Bid.
Kim Mashack, Chief Clerk
10582.17 00100-1 ARRO
DOCUMENT 00100
INSTRUCTIONS TO BIDDERS
Article 1 - Defined Terms
1.01 Terms used in these Instructions to Bidders, which are defined in the Standard General
Conditions of the Construction Contract, as prepared by the Engineer's Joint Contract Documents
Committee (Document EJCDC C – 700, 2007 Edition), have the meanings assigned to them in the General Conditions. Additional terms used in these Instructions to Bidders have meanings indicated below, which are applicable to both the singular and plural thereof.
A. Issuing Office – The office from which the Bidding Documents are to be issued and made available for sale, and where the bidding procedures are to be administered.
1. Issuing Office is the office of the Engineer whose name, address and phone number are listed in the Invitation to Bid.
B. Successful Bidder – The lowest, responsible and responsive Bidder to whom Owner (on the basis of Owner's evaluation as hereinafter provided) makes an award.
C. PennBid – Bid management program, which is being used for distribution of contract documents PennBid’s web address is www.PennBid.procureware.com.
Article 2 - Copies of Bidding Documents
2.01 Complete sets of the Bidding Documents may be obtained online at no cost via the
PennBid Program (www.PennBid.procureware.com) OR a hard copy can be obtained by contacting ARRO Consulting at 570-366-9534. A fee for the plans, postage and handling will be charged to bidders wishing to receive the documents by mail.
2.02 Complete sets of Bidding Documents must be used in preparing Bids; neither Owner nor
Engineer assume responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents, or Bidding Documents purchased from sources other than the issuing office.
2.03 Bids from prospective Bidders who have not obtained the Bidding Documents from the issuing office and who have not obtained complete sets of Bidding Documents will not be accepted.
2.04 Copies of Bidding Documents are made available on the above terms only for the purpose of obtaining Bids on the Work and not to confer a license or grant for any other use.
2.05 Digitizing and posting Bidding Documents on the Internet or on websites of prospective
Bidders and other parties, or reproduction of Bidding Documents by others, is not permitted without Engineer’s approval.
10582.17 00100-2 ARRO
Article 3 - Qualifications of Bidders
3.01 To demonstrate qualifications to perform the Work, Bidder shall submit with the Bid the qualification data indicated in the Invitation to Bid, the following Paragraph(s) of Article 3, and the Bid Form. Bidders shall also be prepared to submit, within five calendar days after the Bid opening date, upon Owner’s request, such additional data as may be pertinent to the Project.
3.02 The Bid of out-of-State Bidders and their Subbidder(s), if any, shall contain evidence of qualification to do business in the Commonwealth of Pennsylvania covenant to obtain such qualification prior to and as a condition of award of a Contract.
3.03 To obtain information concerning qualifications of a Bidder, the Owner requires that a completed Experience Questionnaire be submitted on the form included in the Bidding
Documents. Bidder shall include the completed Experience Questionnaire with the Bid.
3.04 It is a requirement of this Contract that successful Bidder provides confirmation of compliance with Act 127 of 2012, by submitting a “Public Works Employment Verification
Form“ (Document 00511) as a pre-condition to being awarded a contract for this Project.
3.05 Submission of financial information is not required with the Bid, but the Owner reserves the right to request such information as part of the Bid evaluation process.
Financial information shall be submitted to Engineer no later than 5 business days following the
Bid Opening date. Documents shall be contained within a sealed envelope marked
“FINANCIAL INFORMATION – CONFIDENTIAL.”
Financial Information of all Bidders will be returned after selection of the apparent low bidder is made.
3.06 It is a requirement of the Contract that Bidders shall have a minimum (5) year, (5) project documented experience in the type of Work required by this Project. Submit required documentation with the Bid.
3.07 Failure, or refusal, to submit documentation required by the Invitation to Bid, this Article
3, and the Bid Form will be reason for rejection of the Bid. Following are additional reasons for rejection of the Bid:
A. Failure to submit the Bid and other Bidding Documents, on the forms included in the Project Manual.
B. Failure to sign the Bid Form or any of the required affidavits and other documents attached to it.
C. Failure to furnish the required Bid Security.
D. Failure to include a unit/lump sum price for each item on the Bid Form, including
Alternates.
10582.17 00100-3 ARRO
E. The inclusion by Bidder of conditions or qualifications not provided for in the
Bidding Requirements and Bidding Documents.
F. Submission of incomplete Bid Form or other required documents.
G. If the Bid Form contains any omissions, erasures, alterations, additions not called for, or irregularities of any other kind.
H. If any bid prices are obviously unbalanced.
I. When applicable, non-attendance at a mandatory pre-bid meeting and if applicable, site visit.
J. Debarment by a Commonwealth agency, political subdivision, or Federal agency.
K. Having been declared in default on prior projects.
Article 4 - Examination of Contract Documents and Site
4.01 It is the responsibility of each Bidder before submitting a Bid:
A. To examine thoroughly the Bidding Documents;
B. To visit the site and become familiar with and satisfy Bidder as to the general, local and site conditions that may affect cost, progress, performance or furnishing of the Work;
C. To consider federal, state, and local Laws and Regulations that may affect cost, progress, performance or furnishing of the Work;
D. To study and carefully correlate Bidder's knowledge and observations with the
Bidding Documents and such other related data; and
E. To promptly notify Engineer of all conflicts, errors, ambiguities or discrepancies which Bidder has discovered in or between the Bidding Documents.
F. Obtain such additional or supplementary examinations, investigations, explorations, tests studies, and data concerning conditions (surface, subsurface, and Underground Facilities) at or contiguous to the site or otherwise which may affect cost, progress, performance, or furnishing of the Work or which relate to any aspect of the means, methods, techniques, sequences or procedures of construction to be employed by Bidder and safety precautions and programs incident thereto or which Bidder deems necessary to determine its Bid for performing and furnishing the Work in accordance with the time, price, and other terms and conditions of the Contract Documents.
1. Bidder shall be responsible for restoration of areas disturbed due to supplementary examinations, investigations, explorations, and tests
10582.17 00100-4 ARRO
concerning existing aboveground and underground conditions at, or contiguous to the Site.
4.02 Refer to the Supplementary Conditions for identification of:
A. Those reports of explorations and tests of subsurface conditions at or contiguous to the site.
B. Those drawings of physical conditions in or relating to existing surface and subsurface structures (except Underground Facilities) which are at or contiguous to the site.
C. To the extent provided in the Supplementary Conditions, Owner will make copies of such data available to any Bidder requesting them. These data are for information only and are not part of the Bidding Documents.
4.03 Information and data shown or indicated in the Bidding Documents with respect to existing Underground Facilities at or contiguous to the site is based upon information and data furnished to Owner and Engineer by owners of such Underground Facilities or others, and
Owner and Engineer do not assume responsibility for the accuracy or completeness thereof unless it is expressly provided otherwise in the Supplementary Conditions.
4.04 Provisions concerning responsibilities for the adequacy of data furnished to prospective
Bidders with respect to subsurface conditions, other physical conditions and Underground
Facilities, and possible changes in the Contract Documents due to differing or unanticipated conditions appear in Article 4, Paragraphs 4.02, 4.03, and 4.04 of the General Conditions, as amended by the Supplementary Conditions.
4.05 On request, Owner will provide each Bidder access to the site to conduct such examinations, investigations, explorations, tests, and studies as each Bidder deems necessary for submission of a Bid.
A. To gain access to the site of the proposed Work, contact the office of the engineer.
4.06 Refer to Section 01010 – SUMMARY OF WORK for the identification of the general nature of work to be performed at the site by Owner or others (such as utilities and other prime contractors) that relates to the work for which a Bid is to be submitted.
4.07 Refer to Paragraph SC-6.13.C of the Supplementary Conditions for information on Safety and Protection at the site, as it relates to Owner’s safety programs, if any.
4.08 The submission of a Bid will constitute an incontrovertible representation by Bidder that
Bidder has complied with every requirement of this Article 4, that without exception the Bid is premised upon performing and furnishing the Work required by the Bidding Documents and applying the specific means, methods, techniques, sequences or procedures of construction (if any) that may be shown or indicated or expressly required by the Bidding Documents, that
Bidder has given Engineer written notice of all conflicts, errors, ambiguities and discrepancies that Bidder has discovered in the Bidding Documents and the written resolutions thereof by
10582.17 00100-5 ARRO
Engineer is acceptable to Bidder, and that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performing and furnishing the
Work.
4.09 The provisions of this Article 4 do not apply to Hazardous Environmental Conditions at the site; provisions concerning these conditions appear in Article 4, Paragraph 4.06 of the
General Conditions.
Article 5 - Availability of Lands for Work
5.01 The lands upon which the Work is to be performed, rights-of-way and easements for temporary or permanent access, and other lands designated for use by Contractor in performing the Work are identified in the Bidding Documents. All additional lands and access required for temporary construction facilities, or storage of construction equipment and of Products to be incorporated in the Work shall be obtained and paid for by Contractor. Easements for permanent structures or permanent changes in existing facilities will be obtained and paid for by Owner, unless otherwise provided in the Bidding Documents.
Article 6 - Interpretations and Addenda
6.01 All questions about the meaning or intent of the Bidding Documents shall be submitted in writing on PennBID. Interpretations, or clarifications, considered necessary by Engineer in response to such questions, will be provided to all bidders. Questions received later than ten calendar days prior to the date for opening of Bids, or the deadline, if any, indicated on the
Invitation to Bid, may not be answered. Only questions submitted to and answered in writing on PennBID or by written Addenda will be binding. Oral statements, interpretations, or clarifications will not be binding, or legally effective. Neither the Owner nor the Engineer shall be responsible for the failure of any Bidder to receive notice of or to read the Addenda posted by the Engineer.
6.02 Addenda may also be issued to modify the Bidding Documents as deemed advisable by Owner or Engineer.
Article 7 - Bid Security
7.01 Each Bid shall be accompanied by Bid security made payable to Owner in an amount of ten (10%) percent of Bidder's maximum Bid price and in the form of a certified or bank check, an irrevocable letter of credit, or a Bid Bond (on form attached) issued by a surety meeting the requirements of Paragraphs 5.01, 5.02, and 5.03 of the General Conditions.
A. All instruments of Bid security shall be valid and remain in effect for the entire period that the Bids remain open.
B. Substitute Bid Bond forms are not acceptable.
10582.17 00100-6 ARRO
7.02 The Bid security and financial information (if any) of the three apparent lowest responsive and responsible Bidders must remain in effect until the Successful Bidder has furnished the required Performance and Payment Bonds, and Insurance Certificate, and
Successful Bidder and Owner have executed the Agreement.
7.03 Owner may annul the Notice of Intent to Award, if the apparent Successful Bidder fails or refuses to execute and deliver to the Owner the Agreement, together with the required
Performance and Payment Bonds or other forms of security, and Insurance Certificate, within the number of calendar days specified in the Notice of Intent to Award. Bidder shall be considered in Default, and the full amount of its Bid Security shall be forfeited.
Article 8 - Contract Time
8.01 The number of calendar days within which, or the date by which the Work shall be substantially completed (the Contract Time) are set forth in the Agreement.
Article 9 - Liquidated and Other Damages
9.01 Provisions for liquidated and other damages, if any, are set forth in the Agreement.
Article 10 - Substitutions and “Or Equal” Items
10.01 Bids shall be based on Products and methods covered in the Specifications and shown on the Drawings. When a Product specification includes the name or names of manufacturer(s), Bids shall be based on a Product which: (1) meets all Specification requirements; and (2) is produced by one of the manufacturers specifically named in the Specifications for that particular
Product.
A. Requests for substitutions, “or Equal” for Products or methods other than those specified in the Project Manual, will not be considered prior to the Bid opening date. Refer to Supplementary Conditions Paragraphs SC-6.05.A through SC-6.05.L for procedures to be used in making, and costs to
Contractor associated with, such requests after award of the Contract.
Article 11 - Subcontractors
11.01 Article 6, Paragraph 6.06.B of the General Conditions, as amended by Paragraph
SC-6.06.B.1 of the Supplementary Conditions, sets forth requirements as to the approval of
Subcontractors.
11.02 The Bidder shall submit, with the Bid, a list of proposed Subcontractors on the form supplied with the Bidding Documents.
Article 12 - Bid Form
12.01 The Bid Form and other required Bidding Documents are contained within the Project
Manual. Bids must be submitted on forms bound in these documents or on duplicates provided
10582.17 00100-7 ARRO
by the Engineer (or Issuing Office); substitute Documents are not acceptable. If the forms bound within the Project Manual are used for the originals, they must be removed from the Project
Manual for enclosing in the Bid envelope.
A. All blank spaces for Bid prices must be completed in ink or by typewriter and the
Bid Form signed in ink. Erasures or alterations shall be initialed in ink by the person signing the Bid Form. The Bid price of each item on the Bid Form must be stated in numerals and in words. Subject to the Owner's right to correct a Bidder's mathematical totals, a discrepancy between the word and numeral for a particular item will be resolved in favor of the word; corrections to the mathematical totals shall be signed and dated by the person making the correction. When Owner corrects mathematical errors, it shall strike the wrong total with a RED line, so that the original total remains visible.
12.02 The Bid of an individual must be signed by the individual personally; the individual’s signature must be witnessed; and the individual’s business address and any business trade name must be stated. The Bid of a partnership must state the names and addresses of all partners, and the partnership business name and address; and it must be signed by all general partners, with the signatures witnessed. The Bid of a corporation must show the State of incorporation and the principal office address, and must be signed by the President or Vice President, with the corporate seal affixed, attested by the Secretary or Assistant Secretary. Bids by limited liability companies must be executed in the limited liability company name and signed by all members.
The state of formation and official address of the limited liability company must be shown below the signature lines.
12.03 All names must be typed or printed below the signature.
12.04 The Bid shall contain an acknowledgement of receipt of all Addenda (the numbers and dates of which must be filled in on the Bid Form).
12.05 The address, e-mail, telephone number, and fax number of Bidder, and the name, e-mail, and telephone number of the individual to whom communications regarding the Bid are to be directed, must be shown.
12.06 The Bid Form may call for lump sum prices, unit prices, or a combination of both.
A. If the Bid form calls for lump sum prices, the Bidder shall state a single lump sum price for the entire Work, or single lump sum prices for each portion of the Work, subject to a lump sum price as set forth in the Bid form, as applicable. Any such lump sum price or prices shall include all the work described in the Contract
Documents as being part of the Work.
B. If the Bid Form calls for unit prices, the Bidder shall state a single unit price for each item to be furnished or work to be done as set forth in the Bid Form. The
Bid Form indicates, opposite each item for which a unit price is required, the
Engineer’s estimated quantity of units of such items which will be required in the prosecution of the Work; and the Bidder shall state in the space provided in the
10582.17 00100-8 ARRO
Bid Form the total price for such items, as computed by multiplying such estimated quantity of units of such item by the unit price bid.
12.07 Bid prices shall be all inclusive and shall include, if applicable, all taxes of whatever nature applicable to the Work.
12.08 Owner may be exempt from sales and use taxes for certain items to be incorporated into the Work. Each Bidder shall obtain legal advice to determine how and to what extent the
Contractor may utilize the Owner’s tax exemption. Owner will provide, at the Contractor’s request, documentation required to obtain applicable tax exemptions.
12.09 Submission of prices for all Alternates, if any, is mandatory.
Article 13 – Submission of Bids
13.01 Bids shall be submitted no later than the date and time, and at the place indicated in the
Invitation to Bid. Bids submitted by means other than via the PennBid program will not be accepted.
13.02 Documents to be submitted along with the Bid are specified on the Bid Form. Use loose forms included with the Project Manual or duplicate copies provided by the Engineer. If the forms bound within the Project Manual are used, the forms must be removed from the documents for enclosing in the Bid.
13.03 The Bidder is solely responsible for delivering the Bid to the Owner at the location, and by the time of the Bid opening, designated in the Invitation to Bid. No officer, employee, or agent of the Owner is authorized to accept receipt of a Bid on behalf of the Owner at any other time or place and the Owner shall have no responsibility for the receipt of mailed Bids or Bids delivered otherwise than to the Bid opening location as mentioned previously.
13.04 COMPLIANCE WITH FEDERAL, STATE, AND LOCAL LAWS
Attention of Bidders is particularly called to the necessity of complying with all Federal, State, and Local Laws and regulations.
Article 14 - Modification and Withdrawal of Bids
14.01 Bids may be modified or withdrawn at any time prior to the Bid opening.
14.02 After the Bid opening, Bidder may withdraw its Bid, without forfeiture of Bid security, if
Bidder submits credible evidence that there is an error in its Bid and such error was a clerical mistake as opposed to a judgement mistake and was due to an unintentional arithmetical error or an unintentional omission of a substantial quantity of the Work; provided: (1) notice of claim of the right to withdraw Bid is made in writing to the Owner within two business days after opening of Bids; and (2) the withdrawal of the Bid will not result in the awarding of the Contract on another Bid of the same Bidder, Bidder's partner, or a corporation, or business venture owned by
Bidder, or in which Bidder has a substantial interest. A Bidder who is permitted to withdraw its
Bid shall not supply any Products or labor to, or perform any subcontract, or other work, for any entity awarded a Contract, or subcontract for performance of the Work for which the withdrawn
10582.17 00100-9 ARRO
Bid was submitted. If Bidder fails or refuses to submit credible evidence for withdrawing its
Bid, within the time specified above, Bidder shall forfeit the entire amount of its Bid security.
15.01 Bids will be opened and (unless obviously non-responsive) read aloud publicly at the time and place set forth in the Invitation to Bid.
15.02 An abstract of the amounts of Base Bids and major Alternates (if any) will be made available to Bidders after the opening of Bids.
Article 16 - Bids to Remain Subject to Acceptance
16.01 Bids shall remain open for a period of 60 days from the date of Bid opening unless award is delayed by a required approval from a governmental agency, the sale of bonds, or the award of a grant or grants, in which event the Bids shall remain open for a period of 120 days from the date of Bid opening. The Owner will either award the Contract within the applicable time period or reject all Bids, returning the Bid security to the Bidders. Thirty-day extensions of the date for the award may be made by the mutual written consent of the Owner and the apparent Successful
Bidder.
Article 17 - Award of Contract
17.01 Owner reserves the right, without limitation, to reject any or all Bids, which are nonconforming, nonresponsive, unbalanced or conditional, and to reject the Bid of any Bidder, if
Owner believes that it would not be in the best interest of the Project to make an award to that
Bidder, whether because the Bidder is unqualified or of doubtful financial ability, or fails to meet any other pertinent standard or criteria established by Owner. Owner also reserves the right to waive all irregularities not involving price, time, or changes in the Work and to negotiate contract terms with the Successful Bidder.
17.02 The Owner will correct discrepancies in Bidder’s mathematical totals. Discrepancies in the multiplication of units of Work and unit prices will be resolved in favor of the unit prices.
Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum. Discrepancies between words and figures will be resolved in favor of the words.
17.03 In evaluating Bids, Owner will consider the qualifications of Bidders, if the Bids comply or do not comply with the prescribed requirements, and such Alternates, unit prices, and other data, as may be listed on the Bid Form, or as may be requested by Owner prior to the Notice of
Intent to Award.
17.04 In evaluating Bids Owner may consider the qualifications and experience of
Subcontractors, Suppliers, and other persons and organizations proposed for those portions of the
Work of which Owner, prior to Notice of Intent to Award, requests their identity. Owner also may consider, where applicable, the operating costs, maintenance requirements, performance data, and guarantees of major items of materials and equipment proposed for incorporation in the
Work when such data are required to be submitted prior to the Notice of Intent to Award.
10582.17 00100-10 ARRO
17.05 In evaluating Bids Owner may conduct such investigations, as Owner deems necessary, to assist in the evaluation of any Bid and to establish the responsibility, qualifications, legal status and financial ability of Bidders, proposed Subcontractors, Suppliers and other persons and organizations, to perform and furnish the Work in accordance with the Contract Documents to
Owner's satisfaction within the prescribed time.
17.06 If the Contract is to be awarded, it will be awarded to the lowest responsible, responsive
Bidder whose evaluation by Owner indicates to Owner that the award will be in the best interests of the Project.
17.07 If the Contract is to be awarded, Owner will give the apparent Successful Bidder a Notice of Intent to Award within the time limits prescribed in Article 16.
17.08 Bidders may be required by Owner, prior to and as a condition of Contract award, to execute and sign documents related to financing of the Project.
17.09 More than one bid from an individual, partnership, corporation, or an association under the same name or different names will not be considered. Reasonable grounds for believing that the Bidder is interested in more than one Bid for the same Work will cause the rejection of all
Bids in which such Bidder is interested. Any or all Bids will be rejected if there is any reason for believing that collusion exists among any of the Bidders; participants in such collusion will not be considered in future bidding.
17.10 Alternates, if any, will be considered and selected by Owner and the prices for the selected Alternates will be added to or deducted from the Base Bid price to arrive at an adjusted
Bid price. Owner reserves the right to reject or select Alternates regardless of price attached to such Alternates. The adjusted Bid price will be used in comparing Bids and will be the basis for determining the "lowest" of all responsible, responsive Bidders.
17.11 Successful Bidder and its subcontractors shall submit Employment Verification Forms, in accordance with the PA “Public Works Employment Verification Act” (Act 127 of 2012), prior to and as a condition of award of a contract.
Article 18 - Contract Bonds and Insurance
18.01 Article 5 of the General Conditions sets forth Owner's requirements as to Performance and Payment Bonds to be provided by the Contractor. When the apparent Successful Bidder delivers the signed Agreement to Owner, it must be accompanied by the required Performance and Payment Bonds, each in the amount of one hundred percent (100%) of the Contract Price, on the forms provided in the Bidding Documents. Substitute Bond forms are not acceptable.
18.02 Article 5 of the General Conditions and the Supplementary Conditions set forth Owner's requirements as to insurance to be carried by the Contractor. When the apparent Successful
Bidder delivers the signed Agreement to the Owner, it must be accompanied by the required insurance certificate on the latest version of the Acord 25 Certificate of Insurance form. All policies of insurance shown on the Certificate of Insurance shall not be cancelled or materially changed until thirty days prior notice has been given by Contractor to Owner and Engineer and
10582.17 00100-11 ARRO
to each additional insured, and shall contain waiver provisions in accordance with General
Conditions, Paragraph 5.07.
Article 19 - Signing of Agreement
19.01 When Owner gives a Notice of Intent to Award to the apparent Successful Bidder, it will be accompanied by four unsigned counterparts each of the Agreement (each with a copy of the
Bid submission and, if applicable, the List of Proposed Subcontractors attached), Performance and Payment Bonds, or other forms of financial security. Apparent Successful Bidder shall sign and deliver to the Owner, within the calendar days specified in the Notice of Intent to Award, all counterparts of the Agreement accompanied by the executed Performance and Payment Bonds
(with a Power-of-Attorney certificate attached to each), or other forms of financial security and four originals of the required insurance certificate(s).
A. Successful Bidder(s)/Contractor(s) shall be responsible for all costs resulting from reviewing by Engineer, or others, of non-conforming, or incomplete Contract
Document submissions prior to execution of an Agreement. Costs shall be deducted by Change Order from Contractor’s first Application for Payment.
19.02 If the Owner finds the documents submitted by the apparent Successful Bidder acceptable, it will, within ten (10) calendar days after receipt of such documents, complete the signing of the Agreement and submit two fully executed counterparts and accompanying documents to the Contractor.
19.03 If the Owner elects to issue a Notice to Proceed, such notice will accompany the fully executed copies of the Agreement. If a Notice to Proceed is not issued, the Contract Times will commence to run as specified in General Conditions, Paragraph 2.03, as amended by
Supplementary Conditions Paragraph SC-2.03.
19.04 Owner may annul the Intent to Award, if the apparent Successful Bidder fails or refuses to execute and deliver to the Owner the Agreement, together with the required Performance and
Payment Bonds, Insurance Certificate, and any other required Contract Document(s), within the number of calendar days specified in the Notice of Intent to Award; Bidder shall be considered in
Default, and the full amount of its Bid Bond shall be forfeited.
Article 20.0 - Pre-Bid Meeting and Site Visit
20.01 A pre-bid meeting and site visit will be held at the time and place set forth in the
Invitation to Bid. Engineer will transmit to all prospective Bidders present at the pre-bid meeting and site visit such Addenda, as Engineer considers necessary in response to questions arising at the meeting. Attendance at the pre-bid meeting and site visit is not mandatory.
END OF INSTRUCTIONS TO BIDDERS
10582.17 00300-1 ARRO
DOCUMENT 00300
BID FORM
BIDDER (Name and Address MUST be shown on this page):
PROJECT IDENTIFICATION: Wayne Township � Wayne Township Park ADA Improvements
CONTRACT IDENTIFICATION: General Construction
THIS BID IS SUBMITTED TO: County of Schuylkill 401 North Second Street Pottsville, PA 17901-2025
1. The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Owner in the form included in the Bidding Documents to perform and furnish all Work as specified or indicated in the Bidding Documents for the Contract Price and within the Contract Time(s) and in accordance with the other terms and conditions of the Bidding Documents.
2. Bidder accepts all of the terms and conditions of the Invitation to Bid and Instructions to Bidders, including without limitation those dealing with the disposition of Bid security. This Bid will remain subject to acceptance for a period of 60 days from the date of Bid opening unless award is delayed by a required approval from a governmental agency, the sale of bonds, or the award of a grant, or grants, in which event the Bids shall remain open for a period of 120 days from the date of Bid opening. Thirty-day extensions of the date for the award may be made by the mutual written consent of the Owner and the apparent Successful Bidder. Bidder agrees, if required by Owner prior to and as a condition of Contract award, to execute and sign any documents related to financing of the Project. Bidder will sign and submit the Agreement with the Bonds and other documents required by the Bidding Documents within 15 days after the date of Owner's Notice of Intent to Award.
3. In submitting this Bid, Bidder represents, as more fully set forth in the Agreement, that:
3.1 Bidder has examined copies of all the Bidding Documents and of the following Addenda (receipt of all which is hereby acknowledged):
Date Number
10582.17 00300-2 ARRO
3.2 Bidder has visited the site and has become familiar with and is satisfied as to the general, local, and site conditions that may affect cost, progress, performance, and furnishing of the Work;
3.3 Bidder is familiar with and is satisfied as to all federal, state, and local Laws and Regulations that may affect cost, progress, performance, and furnishing of the Work.
3.4 Bidder has carefully studied any available reports of explorations and tests of subsurface conditions at or contiguous to the site and all drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the site (except Underground Facilities) which have been identified in Paragraph SC-4.02 of the Supplementary Conditions as provided in Paragraph 4.02 of the General Conditions. Bidder acknowledges that any such reports and drawings are not Bidding Documents or Contract Documents and may not be complete for Bidder's purposes. Bidder acknowledges that Owner and Engineer do not assume responsibility for the accuracy or completeness of information and data shown or indicated in the Bidding Documents with respect to Underground Facilities at or contiguous to the site. Bidder has obtained and carefully studied (or assumes responsibility for having done so) such additional or supplementary examinations, investigations, explorations, tests, studies and data concerning conditions (surface, subsurface, and Underground Facilities) at or contiguous to the site or otherwise which may affect cost progress, performance, or furnishing of the Work or which relate to any aspect of the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder and safety precautions and programs incident thereto. Bidder does not consider that any additional examinations, investigations, explorations, tests, studies, or data are necessary for the determination of this Bid for performance and furnishing of the Work in accordance with the times, price, and other terms and conditions of the Bidding Documents and Contract Documents.
3.5 Bidder is aware of the general nature of Work to be performed by Owner and others at the site that relates to Work for which this Bid is submitted as indicated in the Bidding Documents and Contract Documents.
3.6 Bidder has correlated the information known to Bidder, information and observations obtained from visits to the site, reports and drawings identified in the Bidding Documents and Contract Documents and all additional examinations, investigations, explorations, tests, studies, and data with the Bidding Documents and Contract Documents.
3.7 Bidder has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents and Contract Documents and the written resolution thereof by Engineer is acceptable to Bidder, and the Bidding Documents and Contract Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performing and furnishing the Work for which this Bid is submitted.
3.8 This Bid is genuine and not made in the interest of or on behalf of any undisclosed person, firm, or corporation and is not submitted in conformity with any agreement or
10582.17 00300-3 ARRO
rules of any group, association, organization, or corporation; Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid;
Bidder has not solicited or induced any person, firm or corporation to refrain from bidding; and Bidder has not sought by collusion to obtain for itself any advantage over any other Bidder or over Owner.
4. Bidder shall complete the Work for the following lump sum prices. Stipulated prices shown on the Bid Form shall be all inclusive. They shall include furnishing all labor, superintendence, necessary equipment, utilities and facilities, furnishing and installing all Products described in the Drawings and Specifications, performing all work necessary for, or incidental to completing the Work, Contractor�s overhead, profit and burden costs and performing all other obligations imposed by the Agreement. Refer to Section 01025 for description of pay items.
Description Unit
Estimated
Quantity
Bid Unit
Price ($)
Extended
Price In
Figures ($)
1. Mobilization/Demobilization LS 1 $_________ $__________
2. Construction of ADA Compliant Fishing Deck
LS 1 $_________ $__________
3. Excavation / Grading for Access Path (8� Depth)
SY 65 $_________ $__________
4. 2A Coarse Aggregate, 6� Depth SY 65 $_________ $__________
5. 9.5MM, 2.0� Depth SY 65 $_________ $__________
Total of Items 1 through 4: BID PRICE (Figures): $___________________________________
BID PRICE (Words):
Quantities given above are not guaranteed. Final payment will be based on actual quantities.
Any difference between estimated and final quantities, increases in market value of Products and services, or complexity of work will not be considered reason for increase of unit prices.
5. Bidder agrees that the Work will be substantially complete on or before the dates or within the number of calendar days indicated in the Agreement; and accepts the provisions of the Agreement as to liquidated and other damages in the event of failure to complete the Work on time.
6. The following documents are attached to and made a condition of this Bid:
6.1 Required Bid Security in the form of _________________________________
6.2 Experience Questionnaire; Document 00400.
10582.17 00300-4 ARRO
6.3 List of Proposed Subcontractors; Document 00450.
6.4 Affidavit of Non-Collusion; Document 00460.
6.5 Bidder�s and Its Subcontractor(s) Employment Verification Form: Document 00470.
6.6 Certification of Non-Segregated Facilities; Document 00471.
6.7 Compliance with the Prohibition of Illegal Alien Labor; Document 00472.
6.8 Civil Rights / Discrimination; Document 00473.
6.9 Contractor Integrity Provisions; Document; 00474.
6.10 Right to Know Law; Document 00475
6.11 Compliance with the State Contractor Responsibility Program; Document 00476
6.12 Provisions Concerning the Americans with Disabilities Act; Document 00477
6.13 American Recovery and Investment Act of 2009; Document 00478
6.14 MBE/WBE Contract Solicitation and Commitment Statement; Document 00479
6.15 Evidence of Bidder's and its Subbidder(s) qualification to do business in the Commonwealth of Pennsylvania or covenant to obtain such qualification prior to and as a condition of award of the Contract (for PA - to be provided if Bidder/Subbidder is out of State)
7. Communications concerning this Bid will be addressed to (Bidder's Contact Person):
Phone: ( )
Fax: ( )
Company Email Address:
8. The terms used in this Bid are defined and have the meanings assigned to them in the General Conditions, as may be amended by the Supplementary Conditions, included as part of the Bidding Documents.
9. Bidder acknowledges that the Bid Price is based on Products and methods described and named in the Drawings and Specifications.
10. Bidder certifies that (s)he visited the site on_________, ____________, 20__.
INTENDING TO BE LEGALLY BOUND, the undersigned submits the forgoing Bid this ___ day of _________________, 20__.
10582.17 00300-5 ARRO
(If Bidder is an Individual)
Signature of Witness Signature of Individual
Trading and doing business as:
Name of Business
Address of Business
(If Bidder is a Limited Liability Company � All Members Must Sign)
Name of Company
Address of Company
Signature of Witness Signature of Member
Signature of Witness Signature of Member
10582.17 00300-6 ARRO
(If Bidder is a Partnership - All General Partners Must Sign)
Name of Partnership
Address of Partnership
Signature of Witness Signature of Partner
Signature of Witness Signature of Partner
Signature of Witness Signature of Partner
(If Bidder is a Corporation)
Attest:
Name of Corporation
Signature of Secretary or Assistant Secretary
Address of Principal Office
(Corporate Seal) State of Incorporation
Signature of President or Vice President
Type or print name below each signature.
State here the names and addresses of all members, if a limited liability, or partners, if a partnership, or of three principal officers, if a corporation.
END OF BID FORM
10582.17 00350-1 ARRO
DOCUMENT 00350
BID BOND
BIDDER (Name and Address): SURETY (Name and Address):
OWNER (Name and Address): County of Schuylkill
401 North Second Street
Pottsville, PA 17901-2025
Project Bid Date:
Project Identification: Wayne Township � Wayne Township Park ADA
Improvements
Contract Identification: General Construction
BOND
Date:
Amount:
1. Bidder and Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors and assigns to pay to Owner upon default of Bidder the full face amount of this Bond.
2. Default of Bidder shall occur upon the failure of Bidder to deliver within the time required by the Bidding Documents, the executed Agreement required by the Bidding Documents, and any Performance Bonds, Payment Bonds, Certificates of Insurance, or other documents required by the Bidding Documents and Contract Documents.
3. This obligation shall be null and void if:
3.1 Owner accepts Bidder's Bid and Bidder delivers within the time required by the
Bidding Documents (or any extension thereof agreed to in writing by Owner) the executed Agreement required by the Bidding Documents and any Performance
Bonds, Payment Bonds, Certificates of Insurance, or other documents required by the
Bidding Documents and Contract Documents, or
3.2 All Bids are rejected by Owner, or
10582.17 00350-2 ARRO
3.3 Owner fails to issue a Notice of Award to Bidder within the time specified in the
Bidding Documents (or any extension thereof).
4. Payment under this Bond will be due and payable upon default of Bidder and within 30 calendar days after receipt of Bidder and Surety of written notice of default from Owner, which notice will be given with reasonable promptness, identifying this Bond and the Project and including a statement of the amount due.
5. Surety waives notice of and any and all defenses based on or arising out of any time extension to issue Notice of Award, provided that the time for issuing Notice of Award shall not in the aggregate exceed 120 days from Bid opening date without Surety's written consent.
6. No suit or action shall be commenced under this Bond prior to 30 calendar days after the notice of default required in paragraph 4 above is received by Bidder and Surety, and in no case later than one year after Bid opening date.
7. Any suit or action under this Bond shall be commenced only in a court of competent jurisdiction located in the state in which the Project is located.
8. Notice required hereunder shall be in writing and sent to Bidder and Surety at their respective addresses shown on the first page of this Bond. Such notices may be sent by personal delivery, commercial courier or by United States Registered or Certified Mail, return receipt requested, postage pre-paid, and shall be deemed to be effective upon receipt by the party concerned.
9. Surety shall cause to be attached to this Bond a current and effective Power of Attorney evidencing the authority of the officer, agent or representative who executed this Bond on behalf of Surety to execute, seal and deliver such Bond and bind the surety thereby.
10. This Bond is intended to conform to all applicable statutory requirements. Any applicable requirement of any applicable statute that has been omitted from this Bond shall be deemed to be included herein as if set forth at length. If any provision of the Bond conflicts with any applicable provision of any applicable statute, then the provision of said statute shall govern and the remainder of this Bond that is not in conflict therewith shall continue in full force and effect.
11. The terms used in this Bid Bond which are defined in the General Conditions have the meaning assigned to them in the General Conditions.
10582.17 00350-3 ARRO
(If Bidder is an Individual)
Signature of Witness Signature of Individual
Trading and doing business as:
Name of Business
Address of Business
(If Bidder is a Limited Liability Company � All Members Must Sign)
Name of Company
Address of Company
Signature of Witness Signature of Member
10582.17 00350-4 ARRO
(If Bidder is a Partnership - All General Partners Must Sign)
Name of Partnership
Address of Partnership
Signature of Witness Signature of Partner
Signature of Witness Signature of Partner
Signature of Witness Signature of Partner
(If Bidder is a Corporation)
Attest:
Name of Corporation
Signature of Secretary or
Assistant Secretary
Address of Principal Office
(Corporate Seal) State of Incorporation
Signature of
President or Vice President
Type or print name below each signature.
10582.17 00350-5 ARRO
(Corporation Surety)
Name of Corporation
Address of Office
Signature of Witness Signature of Attorney-in-fact
Attach an appropriate power of attorney, dated as of the same date as the Bond, evidencing the authority of the Attorney-in-fact to act in behalf of the corporation.
Type or print name below each signature.
NOTE: Substitute Bid Bond Form is not acceptable. Failure to submit Bond on this form will be reason for rejection of Bid.
END OF BID BOND
10582.17 00400-1 ARRO
DOCUMENT 00400
EXPERIENCE QUESTIONNAIRE
PROJECT IDENTIFICATION : Wayne…