1-Security RFP CCRRA.pdf
PDF 428 KB Posted
- Solicitation number
- Not on record
- Issued by
- Centre County, Pennsylvania
About this file
This is a Request for Proposal (RFP) issued by the Centre County Recycling & Refuse Authority (CCRRA) in Pennsylvania for the supply and installation of a comprehensive security camera system upgrade and video management system across all Authority facilities. The project involves replacing and installing approximately 28 cameras of various types, including PTZ cameras, 360-degree cameras, thermal cameras, license plate recognition (LPR) cameras, varifocal turret cameras, and associated network infrastructure. The scope spans four primary locations: the Main Building, Transfer Station/Building C, Scale House, and Building E—the Recycling Plant. Key deliverables include replacing a 32-channel Network Video Recorder with a 64-channel unit, installing multiple network switches, running CAT6 cabling, and providing end-user training and ongoing maintenance. The RFP was issued on June 26, 2026, with an optional pre-bid meeting scheduled for July 8, 2026, at 10:00 AM at 253 Transfer Road, Bellefonte, PA 16823. The deadline for vendor questions is July 17, 2026, at Noon, and proposals must be submitted by July 24, 2026, at Noon via Penn Bid. Vendor selection is scheduled for July 28, 2026, with substantial completion required no later than October 31, 2026.
Proposals will be evaluated based on technical compliance, vendor experience and reputation, project timeline feasibility, and the quality of support and warranty terms offered. All proposed equipment must meet specified technical requirements, including NDAA Section 889 compliance, and vendors proposing systems other than the basis-of-design system must submit complete documentation demonstrating compliance. The RFP requires detailed pricing breakdowns inclusive of equipment, installation, training, and maintenance fees, along with warranty and support term descriptions. Inquiries and proposal submissions should be directed to Patrick R. Burke, P.E., Senior Project Manager at Entech Engineering, Inc., at pburke@entecheng.com or 570-274-0294. The Authority reserves the right to reject any or all proposals and waive technicalities in selecting the proposal deemed most advantageous.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Centre County Recycle & Refuse Authority
REQUEST FOR PROPOSAL
Security Camera System Upgrade & Installation
1. Introduction
The Centre County Recycling & Refuse Authority (Authority or CCRRA) invites qualified vendors to submit proposals via Penn Bid for the supply and installation of a comprehensive security camera and video management system. The referenced system is intended as a basis of design, and approved equal systems will be considered by the Engineer. This initiative is intended to strengthen safety protocols, enhance surveillance capabilities, and modernize existing infrastructure across all Authority facilities.
2. Project Objectives
The Authority seeks to achieve the following goals through this engagement:
• Enhance security monitoring coverage of critical operational areas.
• Improve fire prevention and overall site safety.
• Establish a multi-tier video management platform providing a minimum of thirty (30) days of accessible, high-quality recorded footage.
3. Scope of Work
3.1 Main Building
• Replace the existing 32-channel Network Video Recorder (NVR) with one (1) 64-channel NVR to accommodate all site cameras.
• Replace the following exterior cameras:
• One (1) PTZ camera
• One (1) 360° camera
• One (1) 180° camera
• One (1) license plate recognition (LPR) camera
• Utilize the existing point-to-point (PT-to-PT) link on the main building, which services three (3) light poles located near the public recycling bins.
• Install four (4) cameras along the front drive, consisting of: one (1) PTZ, one (1) LPR, one (1) 360°, and one (1) 180° camera — with two cameras mounted on a single pole, one positioned over the recycling area, and one facing the front of the main building.
• Each light pole includes a NEMA-rated enclosure with an integrated network switch.
3.2 Transfer Station / Building C
• Install one (1) new 8MP varifocal/zoomable camera overlooking the lower lot, replacing an existing camera that is over ten (10) years old.
• Within the transfer building:
• Replace three (3) existing thermal cameras.
• Install one (1) new thermal camera near the loading bay.
• Replace one (1) non-thermal, low-resolution camera with one (1) 8MP turret camera.
• Install one (1) additional thermal camera on the opposite wall of the transfer station.
• Install one (1) 24-port network switch.
3.3 Scale House
• Remove the existing rooftop camera and replace it with one (1) four-lens 360° camera mounted at the building corner.
• Replace the existing inbound LPR camera mounted on the post at the Scale House.
• On the outbound scale post, remove one (1) of the two existing cameras and replace with one (1) license plate recognition (LPR) camera.
• Install one (1) new varifocal/zoomable camera on the rear of the Scale House, providing coverage of the shop building on the hill.
• Install one (1) 8-port network switch. (Note: The client has confirmed that new fiber infrastructure is already available at the Scale House.)
• Run all new CAT6 cables as required.
3.4 Building E – Recycling Plant
• Existing infrastructure consists of CAT6 cabling throughout.
• Install one (1) 24-port network switch.
Replace nine (9) existing thermal cameras.
• Replace two (2) existing turret cameras currently positioned to overlook machinery.
• Add thermal camera to loading bay #5.
• Replace 1 – 8MP varifocal lens camera to overlook processing loading bays.
• Supply Ubiquiti remote TV viewer.
4. Technical Specifications
All proposed equipment shall meet or exceed the following specifications:
Basis of Design and Approved Equals: References to a specific manufacturer, product line, or configuration are intended to establish the minimum basis of design, performance, compatibility, and functional requirements only. Proposed equal systems shall be submitted with the bid/proposal, including manufacturer names, model numbers, product data sheets, a compliance matrix, NDAA compliance documentation, and a list of any deviations from the specified requirements. Acceptance of any proposed equal shall be as determined by the Engineer.
Category Specification
Basis-of-Design Camera System
3 × Turret 8MP Fixed; 3 × LPR; 1 × 12MP Fisheye; 1 × 5MP PTZ Active Deterrence; 15 × Thermal; 1 × 5MP multi-Sensor 360°; 1 × Panoramic Dual- Sensor; 3 × 8MP Varifocal Turret
Field of View 180°, 360°, varifocal lens, and LPR configurations as specified
Connectivity Wired, Power over Ethernet (PoE)
Recording System
NVR-based with a minimum of thirty (30) days of storage retention
Software Features
Motion detection, automated alert notifications, remote viewing access
Category Specification
Compliance
Full adherence to applicable industry standards and regulations. All proposed video management system (VMS) components, cameras, network video recorders (NVRs), and associated networking equipment shall be NDAA Section 889 compliant.
5. Proposal Submission Requirements
Vendors responding to this RFP shall provide the following documentation:
Procurement Compliance: All proposals shall be prepared and submitted in accordance with applicable Pennsylvania municipal procurement requirements and the requirements of this RFP. Bidders are responsible for submitting complete information for any proposed equal with their bid/proposal; substitutions or proposed equals not submitted with the bid/proposal may be rejected as non-responsive, at the discretion of the Authority and Engineer.
1. Company Overview — Summary of organizational background and demonstrated experience with comparable projects.
2. Technical Proposal — Detailed product specifications and documentation confirming compliance with stated requirements.
3. Approved Equal Documentation - If proposing a system other than the basis-of-design system, provide complete documentation with the bid/proposal demonstrating that the proposed system meets or exceeds the specified requirements. The Engineer shall determine whether proposed equals are acceptable.
4. Pricing Breakdown — Itemized costs inclusive of equipment, installation, end-user training, and ongoing maintenance fees.
5. Warranty & Support Terms — Description of warranty coverage and post-installation support offerings.
6. Project Timeline — Estimated schedule from purchase order issuance through full system commissioning.
6. Evaluation Criteria
Proposals will be evaluated on the following basis:
Criterion Consideration
Technical Compliance
Degree to which the proposal meets all specified technical requirements.
Vendor Experience & Reputation
Demonstrated history with security system projects of similar scope.
Project Timeline Reasonableness and feasibility of the proposed implementation schedule. Preferred substantial completion no later than 10/31/2026.
Support & Warranty Terms
Quality and comprehensiveness of post-installation service offerings.
7. Key Dates
Milestone Date
RFP Issuance June 26,2026
Optional Pre-Bid Meeting
Deadline for Vendor Questions
July 8, 2026 (10:00 AM)
July 17, 2026 (Noon)
Proposal Submission Deadline July 24, 2026 (Noon)
Evaluation & Vendor Selection July 28, 2026
8. Optional Pre-Bid Meeting
Bidders are encouraged, but not required, to attend a pre-bid meeting on-site to familiarize themselves with the project location on Wednesday, July 8, at 10:00 AM. The meeting will be held in the Authority’s Board Room located at 253 Transfer Road, Bellefonte, PA 16823.
9. Contact Information
All inquiries and proposal submissions should be directed to:
Patrick R. Burke, P.E.
Senior Project Manager
Entech Engineering, Inc.
pburke@entecheng.com
570-274-0294
The Authority reserves the right to reject any or all proposals, waive technicalities, and select the proposal deemed most advantageous to the Authority.
CCRRA Proposed Camera Locations (See Location Maps)
1. 5mp PTZ camera (mounted on light post)
2. 360-degree camera (mounted on light post)
3. 180- degree camera (mounted on light post)
4. LPR Camera (mounted on light post)
5. Thermal camera Transfer tipping floor
6. Thermal camera Transfer tipping floor
7. Thermal camera Transfer tipping floor
8. 8mp turret citizens drop off area
9. Thermal camera Transfer tipping floor
10. Thermal camera Transfer tipping floor
11. 8mp varifocal/zoomable camera Transfer Bay 1 overlooking lower lot
12. Thermal camera Processing lower level
13. Thermal camera Processing lower level
14. Thermal camera Processing lower level
15. 8mp Fixed turret camera over Processing baler
16. 8mp Fixed turret camera over Processing baler/belt
17. 8mp varifocal lens overlooking Processing loading bays
18. Thermal camera Loading Bay 5
19. Thermal camera Bldg. E tipping area
20. Thermal camera Bldg. E tipping area
21. Thermal camera Processing upper level
22. Thermal camera Recycling tipping floor area
23. Thermal camera Processing upper level
24. Thermal camera Recycling tipping floor area
25. LPR camera mounted on outbound scale post
26. 8mp Varifocal/zoomable camera (mount on rear of Scale House)
27. Four-lens 360-degree camera (mount on front of Scale House)
28. LPR camera mount on inbound scale post
| Security RFP_CCRRA |
| camera location aerial photos |
File details come from the government source that posted it. Updated .