About this file

This Request for Qualifications (RFQ) is issued by Beaver City, Utah for disaster recovery program management and professional engineering services related to the Cottonwood Fire and resulting post-fire flooding, debris flow, and erosion impacts. Beaver City seeks a qualified professional engineering firm or team licensed in Utah to serve as program manager and provide comprehensive engineering services for recovery efforts. The scope of services encompasses recovery program management, funding compliance and cost recovery assistance, engineering and design services, and bidding and construction services for damaged public infrastructure including hydroelectric facilities, water intakes, pipelines, culinary water systems, electrical transmission lines, roads, drainage, culverts, bridges, and stormwater facilities. Written questions are due November 20, 2026 at 5:00 p.m., and Statements of Qualifications must be submitted by November 30, 2026 at 5:00 p.m. to Monte Hawkins, Beaver City Manager. The selection committee will evaluate SOQs by December 4, 2026, with City Council approval and contract execution anticipated on December 8, 2026. Beaver City intends to award one agreement for a five-year term with up to three one-year extensions at the City's discretion. Work will be authorized through individual task orders with no guaranteed minimum volume.

This is a qualifications-based selection under 2 CFR 200.320(b)(2)(iv) and Utah Code Title 63G, with price not used as a selection factor during SOQ evaluation. Beaver City will negotiate fair and reasonable compensation with the highest-ranked firm and perform cost or price analysis as required by 2 CFR 200.324. Services are expected to be funded in whole or in part by federal, state, and/or insurance sources, including FEMA Public Assistance, NRCS Emergency Watershed Protection (EWP), FHWA Emergency Relief, HUD CDBG-DR, Utah state programs, and insurance proceeds. All procurement and contracts must comply with 2 CFR 200.317-200.327 and applicable State of Utah and local procurement requirements. Respondents must be licensed to practice engineering in Utah, maintain professional liability insurance and commercial general liability insurance, and comply with federal contract provisions including debarment certification, Byrd Anti-Lobbying requirements, and applicable federal laws including the Clean Air Act, Federal Water Pollution Control Act, Davis-Bacon Act (if applicable to construction contracts), and Buy America preferences for infrastructure projects. Beaver City encourages participation by small businesses, minority-owned firms, and women-owned business enterprises as subconsultants where feasible.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

30 West 300 North, PO Box 271, Beaver, UT 84713

BEAVER CITY REQUEST FOR QUALIFICATIONS

Disaster Recovery Program Management and Professional Engineering Services Cottonwood Fire and Post-Fire Flood Recovery

Item
Detail
Issue Date
Friday, November 13, 2026
Written Questions Due
Friday, November 20, 2026; 5:00 p.m.
Statements of Qualifications Due
Monday, November 30, 2026; 5:00 p.m. - late submittals will not be considered
Submit To
Monte Hawkins, Beaver City Manager

U3P 30 West 300 North; PO Box 271; Beaver, UT 84713

Issuing Entity
Beaver City

1. Introduction and Purpose Beaver City invites Statements of Qualifications (SOQs) from qualified professional engineering firms and teams licensed to practice in the State of Utah to provide disaster recovery program management and professional engineering services related to the Cottonwood Fire and resulting post-fire flooding, debris flow, and erosion impacts.

Beaver City will appoint evaluators to the selection committee and may issue task orders under the resulting agreement at its discretion. Work will be authorized through individual task orders; there will be no guarantee of a minimum volume of work.

Services are expected to be funded, in whole or in part, by federal, state, and/or insurance sources, which may include FEMA Public Assistance, NRCS Emergency Watershed Protection (EWP), FHWA Emergency Relief, HUD CDBG-DR, Utah state programs, and insurance proceeds. All procurement and resulting contracts will comply with 2 CFR 200.317–200.327 and applicable State of Utah and local procurement requirements.

2. Background The Cottonwood Fire had a limited direct impact on Beaver City's infrastructure, with the primary fire-related damage affecting the power transmission line extending up the canyon to hydro 2. However, the subsequent flooding caused the most significant and widespread damage to the City's infrastructure. Flooding impacted all three of Beaver City's hydroelectric power plants as well as their associated water intakes and pipeline. The City's culinary water system also sustained damage with multiple exposures and breaks in the spring line. These damages have created a need to assess, repair, and restore essential infrastructure to ensure the continued reliability and operation of these critical municipal systems.

Information Available to All Respondents To ensure every respondent has equal access to existing information, Beaver City will make information available to all interested firms upon request. Questions about these materials must be submitted in writing per Section 7.

3. Scope of Services The selected firm or team ("Consultant") will provide professional services related to disaster recovery, as authorized by individual task orders, which may include, but are not limited to, the following.

3.1 Recovery Program Management

1. Serve as program manager for recovery projects, with a dedicated point of contact available to the City and able to be on site within 72 hours of a request or event.

1. Develop work plans, schedules, and budgets for individual projects and the overall recovery program; provide progress reports to the City’s governing body and staff.

1. Advise the City on appropriate project delivery methods (e.g., design-bid-build, design-build, CM/GC) consistent with funding requirements.

1. Coordinate with federal, state, and local agencies, utilities, landowners, and other stakeholders; attend public meetings as requested.

1. Maintain organized electronic project files and documentation, to be delivered to the City upon completion.

3.2 Funding Compliance and Cost Recovery

1. Identify potentially eligible work and funding sources, and assist with applications, project worksheets, damage inventories, and reimbursement requests for FEMA, NRCS, FHWA, HUD, State of Utah, insurance, and other programs.

1. Assign costs to eligible work categories and funding sources to avoid duplication of benefits.

1. Support environmental and historic preservation (EHP) reviews, hazard mitigation proposals, and close-out documentation; assist with appeals as requested.

1. Monitor project funding, prepare financial projections, and support audits.

3.3 Engineering, Design, and Environmental Services

1. Assess and document damage to public infrastructure; post-fire hydrologic and hydraulic analysis; flood and debris-flow risk evaluation.

1. Preliminary and final design, plans, specifications, and engineer’s estimates for repair, replacement, and mitigation of damaged facilities, which may include electrical infrastructure, electrical transmission lines, roads, drainage and culverts, bridges, channels and debris basins, irrigation, culinary water, wastewater, and stormwater facilities.

1. Survey, mapping, GIS, and right-of-way/easement support.

1. Environmental review, permitting (e.g., Clean Water Act Section 404, stream alteration), and agency coordination.

1. Discipline support as needed: geotechnical, structural, water resources, environmental, surveying, architectural.

3.4 Bidding and Construction Services

1. Bidding assistance, pre-bid meetings, and addenda.

1. Construction administration, inspection, submittal and RFI review, pay application and change order review, and as-built documentation.

1. Provide records and testimony related to completed projects if required.

4. Contract Term and Selection Method Beaver City anticipates awarding one agreement for a term of 5 years, with up to three (3) one-year extensions at the City’s discretion.

This is a qualifications-based selection for architectural and engineering services under 2 CFR 200.320(b)(2)(iv), Utah Code Title 63G, and Beaver City Procurement Policy.

Price will not be used as a selection factor. Fee proposals will not be accepted with SOQs. Beaver City will negotiate fair and reasonable compensation with the highest-ranked firm; if negotiations are unsuccessful, the City will terminate negotiations and proceed to the next-ranked firm. The City will perform a cost or price analysis as required by 2 CFR 200.324.

5. Statement of Qualifications Contents SOQs shall not exceed 15 pages, excluding cover letters, tab dividers, and resumes, on 8.5" x 11" pages with a minimum 11-point font. Organize the SOQ as follows:

1. Cover Letter: Summary of qualifications, identification of the proposed program manager and primary contact, and confirmation of availability to begin work upon award.

1. Firm and Team Overview: Firm(s), office location(s), legal structure, and all subconsultants with their roles.

1. Key Personnel: Organizational chart and qualifications of the program manager and key staff, including licenses, relevant experience, and current availability. Resumes may be included in an appendix (2 pages max each).

1. Relevant Experience: Up to 5 comparable projects completed in the last 10 years involving disaster or post-fire recovery and repair of public infrastructure, including the funding programs involved, the firm’s role, and a client reference (name, title, phone, email).

1. Understanding and Approach: Understanding of the affected region, infrastructure types, and damage types; approach to program management, prioritization, and scheduling; and approach to funding compliance, documentation, and cost recovery across multiple funding sources.

1. Capacity and Responsiveness: Current workload, staff availability, and ability to respond on short notice.

1. Required Forms: Conflict of interest disclosure (Section 8), signed Byrd Anti-Lobbying certification (Attachment A, Item 9), acknowledgment of the federal contract provisions in Attachment A.

6. Evaluation Criteria A selection committee will evaluate SOQs using the following criteria. Beaver City may interview the top firms and may re-score after interviews.

Criterion
Points
Understanding of the region, affected infrastructure, and types of fire- and flood-related damage
30
Qualifications, experience, needed discipline(s) coverage, and availability of the program manager and key personnel
20
Firm and team experience with comparable disaster recovery and public infrastructure projects
20
Approach to funding compliance, documentation, and cost recovery (FEMA, NRCS, FHWA, HUD, state, insurance)
20
Capacity and responsiveness
10
Total
100

7. Schedule, Questions, and Addenda Beaver City intends to complete this procurement on an expedited schedule due to the urgency of post-fire flood risk. Tentative schedule:

Milestone
Date
RFQ issued and advertised
Friday, November 9, 2026
Written questions due
Friday, November 20, 2026; 5:00 p.m.
Answers / addenda issued
Wednesday, November 25, 2026
SOQs due
Monday, November 30, 2026; 5:00 p.m.
Selection / notice of intent to award
Friday, December 4, 2026
Council / Commission approval and contract execution
Tuesday December 8, 2026

Questions must be submitted in writing to Monte Hawkins by the deadline above. Answers will be issued by written addendum to all registered respondents. Oral statements do not modify this RFQ. Contact with City officials or selection committee members about this RFQ, other than the designated contact, is prohibited from issuance until award.

8. Conflict of Interest and Fair Competition Consistent with 2 CFR 200.318(c) and 200.319, respondents must disclose in their SOQ any actual, potential, or apparent organizational or personal conflict of interest, including any prior or current work related to the Cottonwood Fire or its recovery, and describe how any conflict will be avoided or mitigated. Firms that prepared the specifications or RFPs are excluded from competing. Beaver City will make the final determination on any conflict.

9. Federal Requirements Because this work may be federally funded, any agreement resulting from this RFQ will include the required contract provisions of 2 CFR 200.327 and Appendix II to 2 CFR Part 200, additional provisions recommended by FEMA, and any grantor-specific terms. The full text is provided in Attachment A, Federal Contract Provisions. Each provision applies as applicable to the services performed, the contract amount, and the Federal program funding the work. For example, Davis-Bacon prevailing wage requirements are not required under FEMA Public Assistance but are required under HUD CDBG-DR, and they apply to construction contracts.

By submitting an SOQ, each respondent acknowledges these provisions and certifies that:

1. The firm and its proposed subconsultants are not debarred, suspended, or otherwise excluded in SAM.gov (2 CFR Part 180).

1. The firm will submit the signed Byrd Anti-Lobbying certification (31 U.S.C. 1352) with its SOQ.

1. The firm will comply with the provisions of Attachment A, as applicable, and will flow them down to subconsultants where required.

Affirmative steps (2 CFR 200.321): Beaver City encourages participation by small businesses, minority-owned firms, and women’s business enterprises, and encourages prime respondents to take affirmative steps to include such firms as subconsultants where feasible.

10. General Conditions

1. Respondents must be licensed to practice engineering in the State of Utah at the time of submittal.

1. The selected firm must maintain professional liability insurance, commercial general liability insurance, automobile insurance, and workers’ compensation.

1. Beaver City reserves the right to reject any or all SOQs, waive minor irregularities, request clarifications, or cancel this RFQ at any time without liability.

1. Beaver City will not reimburse any costs incurred in preparing SOQs or attending interviews.

1. SOQs become public records subject to the Utah Government Records Access and Management Act (GRAMA). Respondents must clearly mark any information claimed as protected confidential business information.

1. Beaver City will evaluate SOQs without discrimination on the basis of race, color, religion, sex, national origin, age, disability, or any other protected status.

11. Contact Monte Hawkins Beaver City Manager 435-438-2451 monteh@beavercityut.gov

Attachment A: Federal Contract Provisions The following provisions apply to contracts made under a federal award. Part 1 lists the provisions required by 2 CFR 200.327 and Appendix II to 2 CFR Part 200. Part 2 lists additional provisions recommended by FEMA. Each provision applies as applicable to the services performed, the contract amount, and the Federal program(s) funding the work.

PART 1: REQUIRED CONTRACT PROVISIONS (2 CFR 200.327, APPENDIX II)

1. Remedies for Breach Contracts for more than the simplified acquisition threshold, which is the inflation adjusted amount determined by the Civilian Agency Acquisition Council and the Defense Acquisition Regulations Council (Councils) as authorized by 41 U.S.C. 1908, must address administrative, contractual, or legal remedies in instances where contractors violate or breach contract terms, and provide for such sanctions and penalties as appropriate.

In the event the Consultant fails to perform its obligations or materially violates any provision of this Agreement, Beaver City may issue written notice identifying the deficiency and requiring corrective action within ten (10) calendar days, or such other reasonable period specified in the notice. If the Consultant fails to correct the deficiency within the specified period, the City may exercise any remedy available under this Agreement or applicable law, including:

1. Requiring correction or re-performance of deficient services at no additional cost;

1. Withholding payment for deficient or unaccepted services;

1. Suspending affected services or authorization of additional work;

1. Terminating the Agreement or applicable Task Order for cause pursuant to Section 2; or

1. Recovering damages or pursuing other appropriate contractual or legal remedies, subject to applicable law.

Beaver City may take immediate action when necessary to protect public health, safety, property, or other substantial interests. Remedies shall be proportionate to the breach and consistent with applicable law.

2. Termination for Cause and for Convenience Beaver City may terminate this Agreement, in whole or in part, without cause upon thirty (30) calendar days’ written notice to the Consultant. Upon receipt of notice, the Consultant shall discontinue the affected services as directed, take reasonable measures to minimize further costs, and deliver completed work products and work in progress for which payment is made. The Consultant shall be compensated for satisfactorily performed services through the effective termination date, together with reasonable, documented, unavoidable termination costs authorized under this Agreement. Settlement of partially completed fixed-price deliverables shall be based on documented work performed and an equitable allocation of the agreed contract price. The Consultant shall not be entitled to anticipated profits on unperformed services.

3. Equal Employment Opportunity Except as otherwise provided under 41 CFR Part 60, all contracts that meet the definition of “federally assisted construction contract” in 41 CFR Part 60-1.3 must include the equal opportunity clause provided under 41 CFR 60-1.4(b), in accordance with Executive Order 11246, “Equal Employment Opportunity” (30 FR 12319, 12935, 3 CFR Part, 1964-1965 Comp., p. 339), as amended by Executive Order 11375, “Amending Executive Order 11246 Relating to Equal Employment Opportunity,” and implementing regulations at 41 CFR part 60, “Office of Federal Contract Compliance Programs, Equal Employment Opportunity, Department of Labor.”

4. Davis-Bacon Act and Copeland "Anti-Kickback" Act Davis-Bacon Act, as amended (40 U.S.C. 3141-3148). When required by Federal program legislation, all prime construction contracts in excess of $2,000 awarded by non-Federal entities must include a provision for compliance with the Davis-Bacon Act (40 U.S.C. 3141-3144, and 3146-3148) as supplemented by Department of Labor regulations (29 CFR Part 5, “Labor Standards Provisions Applicable to Contracts Covering Federally Financed and Assisted Construction”). In accordance with the statute, contractors must be required to pay wages to laborers and mechanics at a rate not less than the prevailing wages specified in a wage determination made by the Secretary of Labor. In addition, contractors must be required to pay wages not less than once a week. The non-Federal entity must place a copy of the current prevailing wage determination issued by the Department of Labor in each solicitation. The decision to award a contract or subcontract must be conditioned upon the acceptance of the wage determination. The non-Federal entity must report all suspected or reported violations to the Federal awarding agency.

The contracts must also include a provision for compliance with the Copeland “Anti-Kickback” Act (40 U.S.C. 3145), as supplemented by Department of Labor regulations (29 CFR Part 3, “Contractors and Subcontractors on Public Building or Public Work Financed in Whole or in Part by Loans or Grants from the United States”). The Act provides that each contractor or subrecipient must be prohibited from inducing, by any means, any person employed in the construction, completion, or repair of public work, to give up any part of the compensation to which he or she is otherwise entitled. The non-Federal entity must report all suspected or reported violations to the Federal awarding agency.

5. Contract Work Hours and Safety Standards Act Contract Work Hours and Safety Standards Act (40 U.S.C. 3701-3708). Where applicable, all contracts awarded by the non-Federal entity in excess of $100,000 that involve the employment of mechanics or laborers must include a provision for compliance with 40 U.S.C. 3702 and 3704, as supplemented by Department of Labor regulations (29 CFR Part 5). Under 40 U.S.C. 3702 of the Act, each contractor must be required to compute the wages of every mechanic and laborer on the basis of a standard work week of 40 hours. Work in excess of the standard work week is permissible provided that the worker is compensated at a rate of not less than one and a half times the basic rate of pay for all hours worked in excess of 40 hours in the work week. The requirements of 40 U.S.C. 3704 are applicable to construction work and provide that no laborer or mechanic must be required to work in surroundings or under working conditions which are unsanitary, hazardous or dangerous. These requirements do not apply to the purchases of supplies or materials or articles ordinarily available on the open market, or contracts for transportation or transmission of intelligence.

6. Rights to Inventions Made Under a Contract or Agreement If the Federal award meets the definition of “funding agreement” under 37 CFR § 401.2 (a) and the recipient or subrecipient wishes to enter into a contract with a small business firm or nonprofit organization regarding the substitution of parties, assignment or performance of experimental, developmental, or research work under that “funding agreement,” the recipient or subrecipient must comply with the requirements of 37 CFR Part 401, “Rights to Inventions Made by Nonprofit Organizations and Small Business Firms Under Government Grants, Contracts and Cooperative Agreements,” and any implementing regulations issued by the awarding agency.

7. Clean Air Act and Federal Water Pollution Control Act Clean Air Act (42 U.S.C. 7401-7671q.) and the Federal Water Pollution Control Act (33 U.S.C. 1251-1387), as amended—Contracts and subgrants of amounts in excess of $150,000 must contain a provision that requires the non-Federal award to agree to comply with all applicable standards, orders or regulations issued pursuant to the Clean Air Act (42 U.S.C. 7401-7671q) and the Federal Water Pollution Control Act as amended (33 U.S.C. 1251-1387). Violations must be reported to the Federal awarding agency and the Regional Office of the Environmental Protection Agency (EPA).

8. Debarment and Suspension Debarment and Suspension (Executive Orders 12549 and 12689)—A contract award (see 2 CFR 180.220) must not be made to parties listed on the governmentwide exclusions in the System for Award Management (SAM), in accordance with the OMB guidelines at 2 CFR 180 that implement Executive Orders 12549 (3 CFR part 1986 Comp., p. 189) and 12689 (3 CFR part 1989 Comp., p. 235), “Debarment and Suspension.” SAM Exclusions contains the names of parties debarred, suspended, or otherwise excluded by agencies, as well as parties declared ineligible under statutory or regulatory authority other than Executive Order 12549.

9. Byrd Anti-Lobbying Amendment Byrd Anti-Lobbying Amendment (31 U.S.C. 1352)—Contractors that apply or bid for an award exceeding $100,000 must file the required certification. Each tier certifies to the tier above that it will not and has not used Federal appropriated funds to pay any person or organization for influencing or attempting to influence an officer or employee of any agency, a member of Congress, officer or employee of Congress, or an employee of a member of Congress in connection with obtaining any Federal contract, grant or any other award covered by 31 U.S.C. 1352. Each tier must also disclose any lobbying with non-Federal funds that takes place in connection with obtaining any Federal award. Such disclosures are forwarded from tier to tier up to the non-Federal award.

10. Procurement of Recovered Materials (2 CFR 200.323)

(a) A recipient or subrecipient that is a State agency or agency of a political subdivision of a State and its contractors must comply with section 6002 of the Solid Waste Disposal Act, as amended by the Resource Conservation and Recovery Act of 1976 as amended, 42 U.S.C. 6962. The requirements of Section 6002 include procuring only items designated in the guidelines of the Environmental Protection Agency (EPA) at 40 CFR part 247 that contain the highest percentage of recovered materials practicable, consistent with maintaining a satisfactory level of competition, where the purchase price of the item exceeds $10,000 or the value of the quantity acquired during the preceding fiscal year exceeded $10,000; procuring solid waste management services in a manner that maximizes energy and resource recovery; and establishing an affirmative procurement program for procurement of recovered materials identified in the EPA guidelines.

(b) The recipient or subrecipient should, to the greatest extent practicable and consistent with law, purchase, acquire, or use products and services that can be reused, refurbished, or recycled; contain recycled content, are biobased, or are energy and water efficient; and are sustainable. This may include purchasing compostable items and other products and services that reduce the use of single-use plastic products. See Executive Order 14057, section 101, Policy.

11. Prohibition on Certain Telecommunications and Video Surveillance Equipment or Services (2 CFR 200.216)

(a) Recipients and subrecipients are prohibited from obligating or expending loan or grant funds to:

(1) Procure or obtain covered telecommunications equipment or services;

(2) Extend or renew a contract to procure or obtain covered telecommunications equipment or services; or

(3) Enter into a contract (or extend or renew a contract) to procure or obtain covered telecommunications equipment or services.

(b) As described in section 889 of Public Law 115-232, “covered telecommunications equipment or services” means any of the following:

(1) Telecommunications equipment produced by Huawei Technologies Company or ZTE Corporation (or any subsidiary or affiliate of such entities);

(2) For the purpose of public safety, security of government facilities, physical security surveillance of critical infrastructure, and other national security purposes, video surveillance and telecommunications equipment produced by Hytera Communications Corporation, Hangzhou Hikvision Digital Technology Company, or Dahua Technology Company (or any subsidiary or affiliate of such entities);

(3) Telecommunications or video surveillance services provided by such entities or using such equipment;

(4) Telecommunications or video surveillance equipment or services produced or provided by an entity that the Secretary of Defense, in consultation with the Director of the National Intelligence or the Director of the Federal Bureau of Investigation, reasonably believes to be an entity owned or controlled by, or otherwise connected to, the government of a covered foreign country;

(c) For the purposes of this section, “covered telecommunications equipment or services” also include systems that use covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system.

(d) In implementing the prohibition under section 889 of Public Law 115-232, heads of executive agencies administering loan, grant, or subsidy programs must prioritize available funding and technical support to assist affected businesses, institutions, and organizations as is reasonably necessary for those affected entities to transition from covered telecommunications equipment or services, to procure replacement equipment or services, and to ensure that communications service to users and customers is sustained.

(e) When the recipient or subrecipient accepts a loan or grant, it is certifying that it will comply with the prohibition on covered telecommunications equipment and services in this section. The recipient or subrecipient is not required to certify that funds will not be expended on covered telecommunications equipment or services beyond the certification provided upon accepting the loan or grant and those provided upon submitting payment requests and financial reports.

(f) For additional information, see section 889 of Public Law 115-232 and § 200.471.

12. Domestic Preferences for Procurements (2 CFR 200.322)

(a) The recipient or subrecipient should, to the greatest extent practicable and consistent with law, provide a preference for the purchase, acquisition, or use of goods, products, or materials produced in the United States (including but not limited to iron, aluminum, steel, cement, and other manufactured products). The requirements of this section must be included in all subawards, contracts, and purchase orders under Federal awards.

(b) For purposes of this section:

(1) “Produced in the United States” means, for iron and steel products, that all manufacturing processes, from the initial melting stage through the application of coatings, occurred in the United States.

(2) “Manufactured products” means items and construction materials composed in whole or in part of non-ferrous metals such as aluminum; plastics and polymer-based products such as polyvinyl chloride pipe; aggregates such as concrete; glass, including optical fiber; and lumber.

(c) Federal agencies providing Federal financial assistance for infrastructure projects must implement the Buy America preferences set forth in 2 CFR part 184.

PART 2: ADDITIONAL PROVISIONS

13. Access to Records The following access to records requirements apply to this contract:

(1) The Consultant agrees to provide the Entities, the FEMA Administrator, the Comptroller General of the United States, or any of their authorized representatives access to any books, documents, papers, and records of the Consultant which are directly pertinent to this contract for the purposes of making audits, examinations, excerpts, and transcriptions.

(2) The Consultant agrees to permit any of the foregoing parties to reproduce by any means whatsoever or to copy excerpts and transcriptions as reasonably needed.

(3) The Consultant agrees to provide the FEMA Administrator or his authorized representatives access to construction or other work sites pertaining to the work being completed under the contract.

14. Changes and Modifications To be allowable under a FEMA award, the cost of any contract change, modification, amendment, addendum, change order, or constructive change must be necessary, allocable, within the scope of the award, reasonable for the scope of work, and otherwise allowable. FEMA recommends that recipients and subrecipients include a changes clause in the contract that describes how, if at all, changes can be made by either party to alter the method, price, or schedule of the work without breaching the contract. The language of the clause may differ depending on the nature of the contract and the end-item procured.

15. DHS Seal, Logo, and Flag The Consultant shall not use the DHS seal(s), logos, crests, or reproductions of flags or likenesses of DHS agency officials without specific FEMA pre-approval.

16. Compliance with Federal Law, Regulations, and Executive Orders This is an acknowledgement that FEMA financial assistance will be used to fund the contract. The Consultant will comply with all applicable federal law, regulations, executive orders, FEMA policies, procedures, and directives.

17. No Obligation by the Federal Government The Federal Government is not a party to this contract and is not subject to any obligations or liabilities to the non-Federal entity, contractor, or any other party pertaining to any matter resulting from the contract.

18. Program Fraud and False or Fraudulent Statements or Related Acts The Consultant acknowledges that 31 U.S.C. Chap. 38 (Administrative Remedies for False Claims and Statements) applies to the Consultant’s actions pertaining to this contract.

19. Copyright and Data Rights 2 C.F.R. § 200.315 concerns intangible property and requires that a recipient or subrecipient provide certain licenses with respect to copyright to the federal agency. 2 C.F.R. § 200.315(b) provides “a royalty-free, nonexclusive and irrevocable right to reproduce, publish, or otherwise use [any work that is subject to copyright] for federal purposes, and to authorize others to do so” to the federal agency. 2 C.F.R. § 200.315(d) provides to the Federal Government the rights to “obtain, reproduce, publish, or otherwise use” data produced under a federal award and to authorize others to do the same.

20. Build America, Buy America Act (BABAA) for A/E Contracts In accordance with BABAA requirements, FEMA must ensure that no federal financial assistance for infrastructure projects is awarded unless all of the iron, steel, manufactured products, and construction materials used in the project are produced in the United States. Although A/E professional services are not considered infrastructure, FEMA recommends that A/E contracts under FEMA grants that are subject to BABAA include a statement requiring contractors and subcontractors to implement a Buy America Preference in their planning and design of an infrastructure project. The Consultant and its subconsultants shall implement a Buy America preference, consistent with the Build America, Buy America Act and 2 CFR part 184, in the planning and design of any infrastructure project funded in whole or in part under this Agreement.