Summary: East Martello Historic Masonry Restoration RFP
This Request for Proposals (RFP) is issued by Monroe County Board of County Commissioners in Florida for the repair and repointing of existing historic masonry brick at Fort East Martello Tower, a fully functioning museum open to the public seven days a week. The project scope requires the contractor to match existing brick and mortar exactly while adhering to the Secretary of the Interior's Standards for Rehabilitation. The contractor must prepare additional construction documents for review, approval, and permitting by the City of Key West Building Department and Historic Architectural Review Commission (HARC), with all permitting fees the contractor's responsibility. A non-mandatory pre-proposal conference is scheduled for May 5, 2026, at 11:00 a.m. at the East Martello Tower. Proposals are due by 3:00 p.m. on June 4, 2026, via the Bonfire electronic bidding platform. The Selection Committee Meeting is anticipated for June 16, 2026, with Board of County Commissioners Award on July 15, 2026. The Notice to Proceed and Pre-Construction Meeting are anticipated for August 3, 2026, with substantial completion required by March 31, 2027—a 240-calendar-day performance period. The museum must remain operational during construction, requiring the contractor to minimize public impact, coordinate with the Key West Art and Historical Society, and maintain limited work hours of Monday through Friday, 8:00 a.m. to 5:00 p.m., unless written approval for schedule modifications is obtained with 72 hours' notice.
The contract is awarded on a stipulated-sum basis with unit prices for repointing existing brick masonry and replacing existing brick masonry on a per-square-foot basis. A bid bond equal to five percent of the maximum bid price is required, and a Public Construction Bond equal to the contract cost is mandated unless the contract amount is $200,000 or less. Insurance requirements include Workers' Compensation with statutory limits, Employers' Liability of $1,000,000, General Liability of $500,000 combined single limit, and Vehicle Liability of $300,000 combined single limit. The contractor must name Monroe County Board of County Commissioners as an additional insured on all policies except Workers' Compensation. Liquidated damages are assessed based on contract amount and days of delay, ranging from $50 to $3,500 per day depending on the contract size and delay period. The evaluation criteria include relevant experience (25 points), project approach and quality control (15 points), staffing and project team (25 points), and overall proposal including price (35 points). Local business preference of 2.5 percent is available for qualifying Monroe County-based vendors, with an additional 2.5 percent if 50 percent or more of work is subcontracted to local businesses. The county reserves the right to reject any and all proposals and to waive irregularities in the bidding process.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 3-Specifications.pdf | ||
| 2-Drawings.pdf | ||
| 4-Legal Notice.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MONROE COUNTY
BOARD OF COUNTY COMMISSIONERS
REQUEST FOR PROPOSALS
FOR
EAST MARTELLO HISTORIC MASONRY
RESTORATION
BOARD OF COUNTY COMMISSIONERS
Mayor Michelle Lincoln, District 2 Mayor Pro Tem David Rice, District 4
Craig Cates, District 1 James K. Scholl, District 3
Holly Merrill Raschein, District 5
COUNTY ADMINISTRATOR
Christine Hurley
Clerk of the Circuit Court Facilities & Project Management Director Kevin Madok William DeSantis
April 2026
PREPARED BY:
Monroe County Department of Facilities and Project Management
East Martello Historic Masonry Restoration
TABLE OF CONTENTS Page 2 of 222
Contents
SECTION 00030
SECTION 00100
SUMMARY OF THE WORK
SECTION 00110
INSTRUCTIONS TO PROPOSERS
SECTION 00120
PROPOSAL FORM
SECTION 00130
INSURANCE REQUIREMENTS AND FORMS
SECTION 00140
PRE-PROPOSAL SUBSTITUTIONS
SECTION 00200
SITE SURVEY
SECTION 00350
MILESTONE SCHEDULE/LIQUIDATED DAMAGES
SECTION 00500
AGREEMENT
SECTION 00750
GENERAL CONDITIONS OF THE CONTRACT
SECTION 00970
PROJECT SAFETY AND HEALTH PLAN
SECTION 00980
CONTRACTOR QUALITY CONTROL PLAN
SECTION 01015
CONTRACTOR’S USE OF PREMISES
SECTION 01027
APPLICATION FOR PAYMENT
SECTION 01030
ALTERNATES
SECTION 01040
PROJECT COORDINATION
TABLE OF CONTENTS Page 3 of 222
SECTION 01045
CUTTING AND PATCHING
SECTION 01050
FIELD ENGINEERING
SECTION 01200
PROJECT MEETINGS
SECTION 01301
SUBMITTALS
SECTION 01310
PROGRESS SCHEDULES
SECTION 01370
SCHEDULE OF VALUES
SECTION 01385
DAILY CONSTRUCTION REPORTS
SECTION 01395
REQUEST FOR INFORMATION (RFI)
SECTION 01410
TESTING LABORATORY SERVICES
SECTION 01421
REFERENCE STANDARDS AND DEFINITIONS
SECTION 01500
TEMPORARY FACILITIES
SECTION 01520
CONSTRUCTION AIDS
SECTION 01550
ACCESS ROADS AND PARKING AREAS
SECTION 01560
TEMPORARY CONTROLS
SECTION 01590
FIELD OFFICES AND SHEDS
SECTION 01595
CONSTRUCTION CLEANING
SECTION 01600
TABLE OF CONTENTS Page 4 of 222
MATERIAL AND EQUIPMENT
SECTION 01630
POST-CONTRACT SUBSTITUTIONS
SECTION 01640
PRODUCT HANDLING
SECTION 01700
CONTRACT CLOSEOUT
SECTION 01710
FINAL CLEANING
SECTION 01720
PROJECT RECORD DOCUMENTS
SECTION 01730
OPERATION AND MAINTENANCE DATA
SECTION 01740
WARRANTIES
NOTICE OF CALLING FOR PROPOSALS 00030- Page 5 of 222
SECTION 00030
NOTICE OF REQUEST FOR COMPETITIVE SOLICITATIONS
NOTICE IS HEREBY GIVEN that on Thursday, June 4, 2026, at 3:00 P .M., the Monroe County Purchasing Office will receive and open sealed responses for the following:
Monroe County, Florida
Pursuant to F.S. § 50.0211(3)(a), all published competitive solicitation notices can be viewed at:
www.floridapublicnotices.com, a searchable Statewide repository for all published legal notices.
Requirements for submission and the selection criteria may be requested from the County’s electronic bidding platform at https://monroecounty-fl.bonfirehub.com OR www.monroecounty-fl.gov/BonfireBids.
The Public Record is available upon request.
Monroe County Purchasing Department receives bids via the Bonfire electronic bidding platform. Please do not e m a i l , mail or attempt to deliver in person any sealed bids. Emailed/mailed/physically delivered bids/proposals/responses WILL NOT be accepted.
The Monroe County Purchasing Department hereby directs that bids be submitted via the Bonfire electronic bidding platform at https://monroecounty-fl.bonfirehub.com, no later than 3:00 P.M . on Thursday, June 4, 2026. There is no cost to the bidder to use the Bonfire platform.
Please d o no t submit your confidential financial information as part of your proposal. There are separate uploads for each set of documents, including confidential financial information. All proposals will be made public on the platform after an intended decision or 30 days, whichever is earlier, unless the bids/proposals are rejected in accordance with F.S. 119.071. If your proposal document includes financial information, that information will not be considered confidential and will be available and viewable to the public in accordance with public records law. In the event of a discrepancy between the bid amount on the Proposal Form and the bid amount entered in Bonfire, the bid amount listed in the “Proposal Form” provided by Monroe County in the RFP is the amount that will be utilized by the County when considering the bid proposal. The County reserves the right to waive any proposal/bid irregularity.
The bid opening for this solicitation will be held virtually, via the internet, at 3 : 0 0 P . M . , on Thursday, June 4, 2026. You may call in by phone or internet using the following:
Join Zoom Meeting https://mcbocc.zoom.us/j/4509326156
Meeting ID: 4509326156 One tap mobile:
+16465189805,,4509326156# US (New York) +16699006833,,4509326156# US (San Jose)
Dial by your location:
+1 646 518 9805 US (New York) +1 669 900 6833 US (San Jose)
Publication Dates Keys Citizen: Sat., 04/25/2026 Keys Weekly: Thur., 04/30/2026
News Barometer: Fri., 05/01/2026 End of Section 00030
SUMMARY OF THE WORK 00100- Page 6 of 222
SECTION 00100
SUMMARY OF THE WORK
A NON-MANDATORY Pre-Proposal Conference shall be held on Tuesday, May 5, 2026, at 11:00am at the East Martello Tower located at 3501 South Roosevelt Boulevard., Key West, Florida. Although the meeting is not mandatory, it is highly recommended that all bidders be in attendance.
1. General Project Intent
The intent of the Drawings and Specifications is to describe the materials and methods of construction required for the performance of the work. In general, it is intended that the drawings shall delineate the detailed extent of the work. Drawings, Specifications, and Contract documents are complimentary, and what is required by one shall be as binding as if required by all.
2. Scope of Work
The Contractor is required to provide a complete job as contemplated by the drawings and specifications, which are a part of this bid package. The Contractor shall furnish all labor, supervision, materials, power, tools, equipment, supplies, permits and any other means of construction necessary or proper for performing and completing the Scope of Work, unless otherwise specifically stated. The Contractor shall supply all of the needed materials and hardware to complete the project and properly dispose of debris.
The Project Scope of Work includes the repair and repointing of existing historic masonry brick at Fort East Martello Tower. The Contractor is to match existing brick and mortar exactly.
The Contractor shall follow the attached Schematic Drawings and Specifications from Bender & Associates Architects, P.A.
A list of Qualified Bidders can be found in the attached Specifications. Other Contractors may bid but are subject to review of their qualifications and experience with historic masonry projects as stated in Section 04210 of the Specifications.
Any and all City of Key West Building Department and Historic Architectural Review Commission (HARC) approvals and permitting shall be the responsibility of the Contractor, including permitting fees. The attached drawings are schematic only and are not for construction. It will be the responsibility of the Contractor to prepare and supply the necessary additional construction documents required for review, approval, and permitting of the work.
The East Martello Tower is a fully functioning museum open to the public seven (7) days a week. The museum shall remain open to the public during execution of the work. The Contractor shall complete the work with as minimal impact to the public who may be utilizing other areas and features within the museum during construction. As such, the Contractor should plan the staging of materials and work areas with safety of the public in mind. The Work area shall be cordoned off from the public with safety barriers. Work areas and laydown areas must be cleaned and secured at the end of every workday. The
SUMMARY OF THE WORK 00100- Page 7 of 222
Contractor must also coordinate construction activities with the Key West Art and Historical Society (KWAHS) who manage the property and museum.
The work of this project involves a significant historic site. All work activities must be undertaken with sufficient care to protect this historic resource and must be supervised by personnel who are familiar with the Secretary of Interior’s Standards for Rehabilitation. All work must comply with the Secretary of the Interior’s Standards for Rehabilitation.
Award of this RFP will be determined by selection-based criteria. See Section 00110, Paragraph 5.8 for ranking criteria and required format for submission of Proposals.
3. Milestone Dates
The Contractor shall note the following special milestone dates.
1. Proposal Documents Available 04/25/26
2. Pre-Proposal Conference 05/05/26
3. Last Day to Submit RFI’s 05/22/26
4. Proposal Due Date 06/04/26
5. Selection Committee Meeting (Anticipated) 06/16/26
5. BOCC Award Date (Anticipated) 07/15/26
6. Notice to Proceed & Pre-Construction Meeting (Anticipated) 08/03/26
7. Substantial Completion (Anticipated) 03/31/27
4. Permits
The Contractor will be responsible to obtain all necessary permits and approvals for the work from the City of Key West Building Department, the City of Key West Historic Architectural Review Commission (HARC), and any other permitting or regulatory agencies as applicable.
5. Special Provisions
The following Special Provisions are intended to clarify the Scope of Work, or highlight features of the work, or modify, change, add to, or delete from the General Scope of this Proposal Package.
1. All licenses required in order to perform the Scope of Work in the specified locations shall be procured and maintained by the Contractor and his/her subcontractors. The Contractor shall submit copies to the Department of Facilities and Project Management prior to issuance of the Notice to Proceed. The Contractor’s license shall accompany the proposal.
2. The Contractor shall require that the Florida Licensed Architect/Engineer of Record obtain and maintain the following insurance coverage:
SUMMARY OF THE WORK 00100- Page 8 of 222
Employer’s Liability $100,000 Bodily Injury by Accident $500,000 Bodily Injury by Disease, policy limits $100,000 Bodily Injury by Disease, each employee
General Liability $300,000 Combined Single Limit
Vehicle Liability $100,000 Combined Single Limit
If split limits are preferred:
$50,000 per Person $100,000 per Occurrence $25,000 Property Damage
Architect Errors & Omissions $1,000,000 per Occurrence / $3,000,000 Aggregate
3. The Contractor shall review attached drawings and specifications prepared by Bender & Associates, Architects P.A.:
a. Schematic Design Drawings titled East Martello Historic Masonry
Restoration dated 01/13/26; pages A1, A2, A3, A4, A5, A6, and A7.
b. Specifications for East Martello Historic Masonry Restoration dated January 2026; 31 pages total.
4. The Contractor shall review the General Requirements for additional responsibilities required in order to perform this Work.
5. If, in the event of conflicting or overlapping requirements in any area of the proposal documents, technical specifications, or drawings, the most stringent condition shall be proposed and constructed. The Contractor shall notify the Department of Facilities and Project Management, in any event, in order to not compromise the Owner's right to make appropriate decisions.
6. The Contractor shall maintain As-Built Drawings, (Record Drawings per Section
01720, Project Record Documents), of his/her work progression.
7. The Contractor shall not store materials, tools or debris inside the building without written permission. The Contractor shall take all means necessary to contain dust and debris as an integral part of the work. The Contractor shall provide suitable storage containers and be responsible for disposal off-site of all debris and trash.
8. Construction shall be conducted in such a manner as to cause the least possible interruption to normal County business. Necessary access to and from adjacent buildings and the parking area shall be provided at all times.
9. The Contractor needs to be aware of the facility, its vendors and staff with unusual schedules and plan accordingly. Coordination of each day’s work shall be done in advance with approval from the County. All spaces interior and exterior shall be cleaned and returned to normal work period/day.
SUMMARY OF THE WORK 00100- Page 9 of 222
10. The Contractor shall coordinate with the Owner’s representative on available hours for Job Site access. Job site will have limited Monday-Friday 8:00AM–5:00PM work hours. Any change to the agreed upon schedule must be obtained in writing by Monroe County Department of Facilities and Project Management with a minimum of seventy-two (72) hours advanced notice.
11. Weather intrusion and unauthorized access to the Project Site due to construction activities shall be prevented by the Contractor’s careful scheduling of work, or other means satisfactory to the Owner.
12. Special Project Signs; Notice of Work on Facility:
Ten (10) Days prior to start of construction, the Contractor shall mount an additional project sign on a 3’x4’ sheet of plywood. The Contractor shall securely fasten the sign to the building or posts set in the ground as approved by the Department of Facilities and Project Management. A design provided by or approved by the Department of Facilities and Project Management shall include, but not necessarily be limited to: the Project Name; the Construction start date;
Construction duration; portions of the facility/site to be closed and/or under construction; the Owner’s name; the Contractor’s name, address, and telephone number, and the Architect’s name, address, and telephone number.
13. Monroe County Department of Facilities and Project Management Temporary Facilities: N/A
14. Additional special provisions such as:
Unit Price #1: Price per square foot to repoint existing brick masonry.
Unit Price #2: Price per square foot to replace existing masonry.
15. Information shown on the Drawings is assembled from numerous record information sources and may be inaccurate or incomplete. The Contractor shall make such field visits or investigations as are necessary to prepare an accurate and complete bid. Claims for extra work or expense after bid closing, which are due to reasonably foreseeable circumstances, shall be denied and shall remain the sole risk and expense of the Contractor. Field measured dimensions shall be obtained by the Contractor prior to placing orders for fabrications or prefabricated materials. Adjustments, delays, re-fabrications, or replacement materials due to inaccurate information are the sole responsibility of the Contractor.
16. The contract shall require a Public Construction bond equal to the contract cost.
The bond must be issued by a surety company with an A.M. Best rating of A: VII or better, that is licensed to conduct business in the State of Florida and that has an agent for service of process within the State of Florida. The Contractor shall provide a certified copy of the recorded payment and/or performance bond to the Owner pursuant to Section 255.05, Florida Statutes. A Public Construction Bond is not required for construction contracts of Two Hundred Thousand and 00/100 ($200,000.00) Dollars or less.
SUMMARY OF THE WORK 00100- Page 10 of 222
6. Protection
1. The Contractor shall use every available precaution to provide for the safety of the property owner, visitors to the site, and all connected with the work under the Contract.
2. All existing facilities, both above and below ground, shall be protected and maintained free of damage. Existing facilities shall remain operating during the period of construction unless otherwise permitted. All access roadways must remain open to traffic unless otherwise permitted.
3. Barricades shall be erected to fence off all construction areas from operations personnel and the general public. Fence posts shall have bases that eliminate the need to penetrate the ground for support.
7. Safety Requirements
1. All application, material handling, and associated equipment shall conform to and be operated in conformance with OSHA safety requirements.
2. The Contractor shall:
a. Comply with all Federal, State, Local and Owner Fire and Life Safety requirements.
b. Advise the Owner whenever work is expected to be hazardous to owner employees and/or operations.
c. Maintain a crewman as a floor area guard whenever roof and or decking is being repaired or replaced.
d. Maintain proper fire extinguisher within easy access whenever power tools, roofing kettles, and torches are being used.
8. Housekeeping
1. The Contractor shall keep materials neat and orderly.
2. The Contractor shall remove scrap, waste, and debris from project area daily.
3. Maintenance of clean conditions while work is in progress and cleanup when work is completed shall be in strict accordance with the "General Conditions" of this contract.
4. The Contractor shall maintain Fire protection during construction.
5. Housekeeping by the Contractor is required on a daily basis.
End of Section 00100
PROPOSAL FORM 00120- Page 11 of 222
SECTION 00110
INSTRUCTIONS TO PROPOSERS
To be considered, Proposals must be made in accordance with these Instructions to Proposers.
ARTICLE 1
DEFINITIONS
1.1 Terms used in these Instructions to Proposers, which are defined in the General
Conditions, shall have the same meanings or definitions as assigned to them in the General Conditions.
1.2 A Proposal, Bid, or Response is a complete and properly signed proposal to do the Work for the sums stated therein, including any Owner Options or Alternates stipulated therein, and submitted in accordance with the Proposal Documents. In this Request for Proposals, the word “Bid” is used interchangeably for “Proposal” or “Response”.
1.3 Addenda are written or graphic instruments issued by the Owner, its agents, employees or consultants prior to the receipt of Proposals, which modify or interpret the Proposal Documents by additions, deletions, clarifications, or corrections.
1.4 Allowance is a given amount to be included in the Proposer’s proposal. From this
Allowance, payments will be made to the vendor for the specified service or project. If the Contractor is responsible for making payments, he/she will be reimbursed for the payments to the vendor via presentation of invoices in his/her monthly payment application. Allowance includes labor, materials, installations, permits, etc.
1.5 Alternate Proposal (or Alternate) is an amount stated in the Proposal to be added to or deducted from the amount of the Base Proposal if the corresponding change in the Work, as described in the Proposal Documents, is accepted by Owner.
1.6 Architect/Engineer is the Architect or Engineer hired by the County to design the project.
1.7 Base Proposal is the sum stated in the Proposal for which the Proposer offers to perform the Work described in the Proposal Documents as the base, to which may be added or from which Work may be deleted for sums stated in an Alternate Proposal or Owner Option Proposals.
1.8 Proposer is a person or entity who submits a Proposal to the solicitation.
1.9 Proposal Documents include the Notice of Calling for Proposal, Instructions to
Proposers, Proposal, Pre-Proposal Substitutions, Scope of Work, Milestone Schedule and other sample Proposal and contract forms and the proposed Contract Documents including any addenda issued prior to receipt of Proposals. The Contract Documents consist of this Agreement, Conditions of the Contract (General, Supplementary and other Conditions), Drawings, Specifications, Proposal Documents, Addenda issued prior to execution of this Agreement, together with the response to RFP and all required insurance and license and certification documentation, and Modifications issued after execution of this Agreement. The Contract represents the entire and integrated agreement between
PROPOSAL FORM 00120- Page 12 of 222 the parties hereto and supersedes prior negotiations, representations or agreements, either written or oral.
1.10 Local Business means, as specifically defined in Monroe County Code Section 2-349(b), the vendor has a valid receipt of the business tax paid as issued by Monroe County Tax Collector at least one (1) year prior to the notice of request for bids or proposals for the business to provide the goods, services or construction to be purchased, and a physical business address located within Monroe County from which the vendor operates or performs business on a day-to-day basis that is a substantial component of the goods or services being offered to Monroe County. The physical business address must be registered with the Florida Department of State as its principal place of business for at least one (1) year prior to the notice of request for bids or proposals. Post Office Boxes are not verifiable and shall not be used for the purpose of establishing a physical address.
1.11 “Owner” is synonymous with “Monroe County”.
1.12 “Perform” means to comply fully with the specified or implied requirements of the
Contract.
1.13 “Provide” means “furnish and install”. Wherever “provide” or “furnish and install” are used, this shall mean the purchase and complete installation, and all purchasing requirements and procedures, as per the specified or implied requirements of the Contract.
1.14 Sub-bidder is a person or entity who submits a bid to a Proposer for materials or labor for a portion of the Work.
1.15 “Unit Price” means an amount stated in the Proposal as a price per unit of measurement for materials or services as described in the Proposal Documents or in the proposed contract documents. Unit prices shall apply to change orders.
RANKING CRITERA
The Ranking Criteria and maximum points scoring values allowed in each criteria category of this solicitation are as follows:
Tab 1 Relevant Experience 25 points Tab 2 Project Approach and Quality Control 15 points Tab 3 Staffing and Project Team 25 points
Tab 4 Overall Proposal (including price) 35 points Tab 5 County Forms Yes/No
Tab 6 Financial Information and Litigation Yes/No
Total possible points 100 points
ARTICLE 2
COPIES OF PROPOSAL DOCUMENTS
2.1 Proposers may obtain complete sets of the Proposal Documents from the County’s electronic bidding platform at https://monroecounty-fl.bonfirehub.com OR www.monroecounty-fl.gov/BonfireBids.
PROPOSAL FORM 00120- Page 13 of 222
2.2 Proposers shall use complete sets of Proposal Documents in preparing Proposals.
Neither the Owner nor the Department of Facilities and Project Management, nor their agents, nor the Architect/Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Proposal Documents.
2.3 Submitted Proposals MUST include an Insurance Agent Statement and a completed
Insurance Checklist, and all forms and requirements as called for in the Request for Proposals. Failure to include all necessary forms and licenses will result in a non-responsive proposal.
ARTICLE 3
EXAMINATION OF PROPOSAL DOCUMENTS AND SITE
3.1 Before Submitting a Proposal:
3.1.1 Each Proposer shall thoroughly examine all the Proposal Documents.
3.1.2 Each Proposer shall visit the site to familiarize himself/herself with local conditions that may in any manner affect the cost, progress, or performance of the Work.
3.1.3 Ignorance on the part of the Proposer shall in no way relieve him/her of the obligations and responsibilities assumed under this Proposal.
3.1.4 Should a Proposer find discrepancies, ambiguities in, or omissions from the Proposal
Documents, or should he/she be in doubt as to their meaning, he/she shall at once notify the Owner via the County’s electronic bidding platform at https://monroecounty-fl.bonfirehub.com OR www.monroecounty-fl.gov/BonfireBids.
3.2 The lands upon which the Work is to be performed, rights-of-way for access thereto and other lands designated for use by the Contractors in performing the Work are identified in the General Requirements or Drawings.
3.3 Each Proposer shall study and carefully correlate his/her observations with the Proposal
Documents.
3.4 The submission of a Proposal will constitute a representation by the Proposer that he/she has complied with every requirement of Article 3 and that the Proposal Documents are sufficient in scope and detail to indicate and convey understanding of all terms and conditions for performance of the Work.
ARTICLE 4
INTERPRETATION AND CORRECTION OF PROPOSAL DOCUMENTS
4.1 Proposers and Sub-proposers shall promptly notify the Director of the Department of
Facilities and Project Management in writing of any ambiguity, inconsistency or error that they may discover upon examination of the Proposal Documents or of the site and local conditions.
PROPOSAL FORM 00120- Page 14 of 222
4.2 Proposers and Sub-proposers requiring clarification or interpretation of the Proposal Documents shall submit their questions in writing to the Director of the Department of Facilities and Project Management no later than ten (10) business days prior to the date for receipt of Proposals (See Subsection 3.1.4). Any answer, interpretation, correction or change of the Proposal Documents will be accomplished by Addenda. Copies of Addenda will be made available for inspection at the County’s electronic bidding platform at https://monroecounty-fl.bonfirehub.com OR www.monroecounty-fl.gov/BonfireBids.
Interpretations, corrections, or changes of the Proposal Documents made in any other manner will not be binding, and Proposers shall not rely upon such interpretations, corrections, and changes. Oral and other interpretations or clarifications will be without legal effect.
ARTICLE 5
PROPOSAL PROCEDURE
5.1 FORM AND STYLE OF PROPOSAL
5.1.1 The Proposal shall be submitted on the forms included in Section 00110 of these Proposal
Documents with the exception of the Proposal Security, which may be submitted in alternate forms as described in Subsection 5.3.1 of these Instructions to Proposers. Each of the forms in Section 00110 must be properly filled out, executed, and submitted as the Proposal.
5.1.2 All blanks on the Proposal Form shall be filled in with ink or by typewriter or word processor.
5.1.3 Where so indicated on the Proposal Form, sums shall be expressed in both words and figures and, in case of discrepancy between the two, the amount written in words shall govern. Failure to comply with this requirement shall constitute a non-responsive proposal.
5.1.4 Any interlineation, alteration, or erasure must be initialed by the signer of the Proposal.
5.1.5 All requested Alternates shall be proposed. If no change in the Base Proposal is required, enter "No Change". Failure to comply with this requirement shall constitute a non-responsive proposal.
5.1.6 All requested Allowances shall be proposed. Failure to comply with this requirement shall constitute a non-responsive proposal.
5.1.7 The Proposer is required to submit a copy of the appropriate and current Contractor’s license (Monroe County or State) as part of the Proposal.
5.2 ADDENDA
5.2.1 Each Proposer shall ascertain prior to submitting his/her Proposal that he/she has received all Addenda issued, and he/she shall acknowledge their receipt in his/her Proposal. However, in case any Proposer fails to acknowledge receipt of such Addenda, his/her Proposal will nevertheless be construed as if it had been received and acknowledged, and the submission of the Proposal will constitute acknowledgement of
PROPOSAL FORM 00120- Page 15 of 222 receipt of the Addenda. It is the responsibility of each Proposer to verify that he/she has received all Addenda issued before Proposals are opened.
5.2.2 No Addenda will be issued later than five (5) business days prior to the date for receipt of Proposals except for an Addendum withdrawing the Request for Proposals or one which includes postponement of the date for receipt of Proposals.
5.2.3 Copies of Addenda will be made available for inspection where Proposal Documents are on file for that purpose. See Section 4.2 above.
5.3 PROPOSAL SECURITY
5.3.1 Each proposal shall be accompanied by a Proposal Security in the amount equal to five percent (5%) of the Proposer’s maximum bid price by way of a bid bond from a surety insurer authorized to do business in Florida as a surety or any method permitted in Section 255.051, Florida Statutes, as amended (certified check, cashier’s check, treasurer’s check or bank draft of any national or state bank). If the security is in the form of a check or draft, it shall be made payable to Monroe County BOCC.
Proposals submitted pursuant to the electronic bidding process set forth in Section 00030 (Notice of Calling for Proposals) shall include electronic copies of the Proposal Security identified above. Only an original Proposal Security in the form of a certified check, cashier’s check, treasurer’s check or bank draft of any national or state bank shall be submitted contemporaneously through the United States Postal Service or by means of a commercial delivery service to: Monroe County Board of County Commissioners, c/o Purchasing Department; 1100 Simonton Street, Room 2-213; Key West, Florida 33040.
All other forms of a bid bond (e.g., a surety bid bond) shall only be submitted electronically.
5.3.2 The Proposal Security constitutes a pledge and guarantee by the Proposer that the
Proposer will enter into a Contract with the Owner on the terms stated in his Proposal and the solicitation documents and will furnish a certified copy of the recorded performance bond, as described in the General and Supplementary Conditions of this contract if the Proposer is the successful bidder. Bid securities may remain in the custody of the County OMB for up to ninety (90) days from the bid opening date or until forfeited or released. The bid security of the successful bidder shall be returned to the bidder after (a) the bidder executes the contract, (b) furnishes a good and sufficient certified copy of the recorded performance bond, payment bond, and required proof of insurance as may be required in the contract documents, and (c) commences performance of the contract. If, after the Board of County Commissioners accepts the bid to a competitive solicitation, the successful bidder refuses or is unable to execute the contract to provide the required contract bonds or proof of insurance, or commence performance, the County may annul the Notice of Award, and the bid security will be forfeited to, and become the property of, the County as liquidated damages for the County’s loss of bargain. A public construction bond is not required on construction contracts of Two Hundred Thousand and 00/100 ($200,000.00) Dollars or less.
5.3.3 The Proposal Security of any Proposer may be retained by the County set forth in
Subsection 5.3.2 above, or for up to ninety (90) days from the date when all Proposals have been rejected.
PROPOSAL FORM 00120- Page 16 of 222
5.4 SCHEDULING, MANPOWER REQUIREMENTS, AND PERMITS
5.4.1 The overall schedule for construction is shown in the Proposal Documents "Milestone
Schedule" at Section 00350.
5.4.2 The Contractor will be required to provide adequate manpower and equipment in order to meet the requirements of the schedule.
5.4.3 The Proposer shall ascertain the necessity for all permits, impact fees, inspections, testing and survey (and fees required by same) required by Federal, State, Municipal or Utility bodies having jurisdiction over the project. The Proposer shall include in his/her proposal the cost of all such permits, impact fees, inspections, testing, and surveys for the project site/building. The Contractor shall be required to secure all such permits, impact fees, inspections, testing, surveys, and to provide all installation and permitting, required for the execution of this Contract. The County will assess County building permit and County impact fees. The Contractor shall be responsible for any and all building permit costs or impact fees required for the substantial completion of this project.
5.4.4 The Contractor shall be responsible for securing and paying for all testing services of an independent testing laboratory to perform specified inspections and testing as indicated in Technical Specification Sections and as required by the contract or governing authorities.
The Contractor shall include the cost of all inspection and testing fees in his bid proposal.
5.5 SUBMISSION OF PROPOSALS
5.5.1 Proposals shall be submitted to Monroe County at the designated location not later than the time and date for receipt of Proposals indicated in the Notice of Calling for Proposals, or any extension thereof made by Addendum. Bonfire will not allow any Proposals to be uploaded after the time and date for receipt of Proposals. Proposals received after the time and date for receipt of Proposals will not be considered.
5.5.2 The Monroe County Purchasing Department receives bids via the Bonfire electronic bidding platform. Please do not email, mail or attempt to deliver in person any sealed bids. Emailed/mailed/physically delivered bids/proposals/responses WILL NOT be accepted.
The Monroe County Purchasing Department hereby directs that bids be submitted via the Bonfire electronic bidding platform at https://monroecounty-fl.bonfirehub.com, no later than 3:00 P.M. on Thursday, June 4, 2026. There is no cost to the bidder to use the Bonfire platform.
Please do not submit your confidential financial information as part of your proposal.
There are separate uploads for each set of documents, including confidential financial information. All proposals will be made public on the platform after an intended decision or 30 days, whichever is earlier, unless the bids/proposals are rejected in accordance with Subsection 119.071(1)(b)(3), Florida Statutes. If your proposal document includes financial information, that information will not be considered confidential and will be available and viewable to the public in accordance with public records law.
PROPOSAL FORM 00120- Page 17 of 222
In the event of a discrepancy between the bid amount on the Proposal Form and the bid amount entered into Bonfire, the bid amount listed in the proposal documents is the amount that will be utilized by staff when considering the bid proposal. The County reserves the right to waive any proposal/bid irregularity.
The bid opening for this solicitation will be held virtually via the internet at 3 pm on Thursday, June 4, 2026. You may call in via phone or internet using the following:
Join Zoom Meeting https://mcbocc.zoom.us/j/4509326156
Meeting ID: 450 932 6156
One tap mobile +16465189805,,4509326156# US (New York) +16699006833,,4509326156# US (San Jose)
Dial by your location +1 646 518 9805 US (New York) +1 669 900 6833 US (San Jose)
5.5.3 The Proposer shall assume full responsibility for timely delivery at the location designated for receipt of Proposals.
5.5.4 Oral, telephonic, telegraphic, and faxed Proposals are invalid and will not receive consideration.
5.6 MODIFICATION AND WITHDRAWAL OF PROPOSALS
5.6.1 A Proposal may not be modified, withdrawn, or canceled by the Proposer during the stipulated time period following the time and date designated for the receipt of Proposals, except as provided in Section 5.7 (Right to Claim Error in Proposal) and each Proposer so agrees in submitting his/her Proposal.
5.6.2 Prior to the time and date designated for receipt of Proposals, any Proposal submitted may be modified by removing the existing proposal from Bonfire and uploading a new, complete proposal. The new submission shall comply with the requirements for the original proposal.
5.6.3 Proposals may be withdrawn on Bonfire prior to the time and date designated for the receipt of Proposals. Withdrawn Proposals may be resubmitted on Bonfire up to the time designated for the receipt of Proposals provided that they are then fully in conformance with these Instructions to Proposers.
5.6.4 If required, the Proposal Security shall be in an amount equal to five percent (5%) of the of the modified proposal price. See Subsection 5.3.1 for description of the form of the Proposal Security.
5.6.5 Conditional, modified, or qualified proposals will be rejected. Proposers are to comply with the instructions on the proposal forms and not make any changes thereto.
PROPOSAL FORM 00120- Page 18 of 222
5.7 RIGHT TO CLAIM ERROR IN PROPOSAL
5.7.1 Each Proposer's original work papers, documents, and materials used in preparation of the proposal shall be enclosed in an envelope and marked clearly as to contents, must be received by Monroe County Purchasing Department no later than twenty-four (24) hours after the time and date for receipt of Proposals, or any extension thereof made by Addendum. Additionally, Proposers shall submit by email copies of their original work papers, documents, and materials used in preparation of the proposal to Monroe County Purchasing Department no later than twenty-four (24) hours after the time and date for receipt of Proposals, or any extension thereof made by Addendum. The contents of the email shall be clearly marked in the subject line of the email. Proposers who fail to submit their original work papers, documents, and materials used in the preparation of the proposal, as provided herein, waive all rights to claim error in the Proposal.
5.7.2 Owner will review documents submitted within the designated time frame for the purpose of determining the validity of the Proposer’s claim.
5.7.3 Following review of the Proposer's claim at the election of the Owner, the Owner may:
a. Allow the Proposer to withdraw the Proposal and the Owner retains the Proposal Security.
b. Allow the Proposer to withdraw the Proposal and the Owner returns the Proposal Security.
c. Allow the Proposer to enter into contract for the proposed Work at the original Proposal price.
5.8 CONTENT OF SUBMISSION FOR RANKING CRITERIA
The following information, at a minimum, shall be included in the Submittal:
Tab 1. Relevant Experience, References and Past Performance on Similar Projects
Each Proposer shall provide a list of past projects that are the same or similar to the size and scope of the proposed project.
The list should include the information below:
Name and full address of referenced project and organization.
Name and telephone number of contact person for contract.
Date of initiation and completion of contract for referenced project.
Brief summary of the project and services including a comparison to services sought by this RFP.
Original budget and time frame for the project and whether the project was completed on time and within budget.
The Contractor must provide a list of all projects that it has completed similar in budget and in scope to the project for the last ten (10) years. The Contractor shall highlight previous projects completed on historic brick masonry structures.
PROPOSAL FORM 00120- Page 19 of 222
If the Contractor is not already on the Qualified Bidders list as found in the attached Specifications, the Contractor shall provide sufficient information for the Owner to make a reasonable assessment and determination of this category including written references or the name and current contact information.
Tab 2. Project Approach and Quality Control
The Proposer shall provide a listing of the construction and quality control services, with specific descriptions that will be offered under the Agreement. The Proposer should briefly describe any programs and tools used to manage and control deliveries, inspections, logistics, and daily progress for the project.
Tab 3. Staffing for this Project
The Proposer shall describe the composition and structure of the firm (sole proprietorship, corporation, partnership, joint venture) and include names of persons with an interest in the firm.
The Proposer shall include a list of the proposed staff that will perform the work required if awarded this contract. An organizational chart should be included in this section. The Proposer shall also include a resume for each member of the project team identifying his/her role on the team and any qualifications relevant to the assigned position. Include in this section the location of the main office and the location of the office proposed to work on this project.
Personnel identified in this proposal are to be assigned as proposed and are committed to performing services under this Agreement. Personnel changes will require written approval from the County. Previously approved staff, whose performance is unsatisfactory, shall be replaced by the Contractor within one (1) week of County notification.
The Proposer shall include the name and contact information of the Florida Licensed Architect and/or Engineer Consultant or Firm they have engaged to provide design services for the project. The Proposer shall include a list of past projects that are the same or similar to size and scope of the proposed project that the Licensed Architect and/or Engineer of Record has completed- paying special attention to those projects of a historic nature (specifically the repair and restoration of brick structures) or those projects requiring historic preservation commission approval.
Tab 4. Overall Proposal (including Bid Price)
The Proposer shall provide a total cost for complete construction of this project. The Proposer shall produce descriptions and evidence of previous and proper construction work, along with proper licensing to perform the services as required, in Section 00120 of this RFP. Any exclusions or exceptions to the requirements and Scope of Work in this RFP will not be accepted.
Tab 5. County Forms
PROPOSAL FORM 00120- Page 20 of 222
Proposer shall complete all required forms and validate they have proper licensing to perform the services described herein. Copies of all professional and occupational licenses shall be included in section 00120 of this RFP.
Tab 6. Financial Information and Litigation
Provide answers to all questions, forms, and backup information as requested under Paragraph 1, Section 00120 of this RFP.
ARTICLE 6
CONSIDERATION OF PROPOSALS
6.1 OPENING OF PROPOSALS
6.1.1 The properly identified Proposals received on time will be opened at the Monroe County
Purchasing Department. The public is permitted to be present via a virtually held bid opening as specified in Subsection 5.5.2.
6.1.2 Any Proposal not received by the Purchasing Department on or before the deadline for receipt of proposals designated in the Notice of Calling for Proposals will not be opened.
6.2 PROPOSALS TO REMAIN OPEN
6.2.1 All Proposals shall remain open and valid for ninety (90) days after the date designated for receipt of Proposals.
6.2.2 The Owner may, at its sole discretion, release any Proposal and return the Proposal
Security before the ninety (90) days period has elapsed.
6.3 AWARD OF CONTRACT
6.3.1 The Owner reserves the right to reject any and all proposals, or any part of a proposal.
The Owner reserves the right to waive variations from the specifications that do not render the proposal non-conforming, to re-advertise for competitive solicitations, or to abandon the project, purchase of goods, or request for competitive solicitations. The Owner retains the right to disregard non-conformities, non-responsive proposals or conditional proposals in the best interest of the County.
6.3.2 In evaluating Proposals, the Owner shall consider the qualifications of the proposers and whether or not the Proposals comply with the prescribed requirements in the Proposal Documents.
6.3.3 The Owner shall have the right to accept alternates in any order or combination and to determine the low proposer on the basis of the sum of the Base Proposal plus Alternates selected by the Owner. The Owner reserves the right to reject any or all Alternates in the selection process as is deemed necessary to keep the project within budget.
PROPOSAL FORM 00120- Page 21 of 222
6.3.4 The Owner may consider the qualifications and experience of subcontractors and/or other entities (including those who are to furnish materials, or equipment fabricated to a special design) proposed for each of the principal portions of the Work as identified in the Proposal Documents. Proposers shall submit their listing of subcontractors. A Proposed Subcontractor Listing Form supplied by the Owner is to be completed for this purpose.
6.3.5 Where legally acceptable the Owner shall consider preference to local businesses in making a purchase or awarding a contract which meet the criteria for a local business as defined by Section 2-349 of the Monroe County Code.
6.3.6 Individuals or firms which meet all the criteria in Section 2-349 of the Monroe County Code and are a conforming and responsible proposer shall receive local preference and shall be given an amount not to exceed two and one-half percent (2.5%) of the lowest non-local responsive and responsible proposer. Total proposal price shall include the base proposal and all alternatives or options to the base proposal which are part of the proposal and being recommended for award by the appropriate authority.
6.3.7 If the Local Business subcontracts fifty percent (50%) or more of the goods, services or construction to other “Local Businesses” which meet all of the criteria in Section 2-349 of the Monroe County Code, an additional two and one-half percent (2.5%) preference will be given of the lowest nonlocal responsive and responsible proposer.
6.3.8 The application of local preference may be waived upon written recommendation by the
Owner and approval by the Monroe County Board of County Commissioners at the time of Award of Contract. Waiver of the application of the local preference is based upon analysis of the marketplace and in consideration of the special or unique quality of goods, services, or professional services sought to be purchased by the Owner.
6.3.9 The Owner may conduct such investigations, as deemed necessary to assist in the evaluation of any Proposal and to establish the responsibility, qualifications, and financial ability of the Proposers, proposed subcontractors, and other persons or organizations to do the Work in accordance with the Contract Documents to the Owner's satisfaction within the prescribed time.
6.3.10 The Owner reserves the right to request any additional information related to the financial qualifications, technical competence, the ability to satisfactorily perform within the contract time constraints, or other information the department deems necessary to enable the department and Board of County Commissioners to determine if the person responding is responsible.
6.3.11 The Owner reserves the right to reject the Proposal of any Proposer who does not pass any such evaluation to its satisfaction.
6.3.12 If the Contract is awarded, it will be awarded to the lowest, conforming responsible, responsive Proposer, with consideration to local businesses.
6.3.13 If the Contract is to be awarded, the Owner will issue the Notice of Award to the successful
Proposer within ninety (90) days after the date of receipt of proposals. The Owner reserves the right to return all Proposals, not make any awards, and cancel the Project. The Owner reserves the right not to accept any proposals and advertise another RFP for the job.
PROPOSAL FORM 00120- Page 22 of 222
6.3.14 The Owner is tax exempt and reserves the right to purchase directly various construction materials and equipment that may be a part of the Contract. If the Owner elects to make a particular purchase, the Owner will, via a Purchase Contract, purchase the materials and equipment, and the Contractor shall assist the Owner in the preparation of these Purchase Contracts, including providing to the Owner appropriate tax credits. The Contractor agrees that the amount of the purchase and the appropriate tax credit will be the subject of a deductive change order in recognition of the fact that the purchase and taxes were computed into the contractor’s costs.
6.3.15 Tie Breaker Procedure: In the event the same competitive solicitation amounts are received from two (2) or more responders who are considered by the BOCC to be equally qualified and responsive or when two (2) or more responders are equal in rank and score, and only one (1) of the responders has a principal place of business in Monroe County, FL, the award shall be to the responder who has a principal place of business located in Monroe County, FL, except where prohibited by federally or state funded contracts.
Otherwise, the tie will be resolved by draw from an opaque container.
6.3.16 Protest Procedure: Any Bidder/Respondent/Proposer who claims to be adversely affected by the decision or intended decision to award a contract shall submit in writing a notice of protest which must be received by the County within seventy-two (72) hours or three (3) business days, whichever is less, after the posting of the Notice of Decision or Intended Decision on the electronic bidding platform or posting of the Notice of Decision or Intended Decision on the Monroe County Board of County Commissioners’ agenda, whichever occurs first. Additionally, a formal written protest must be submitted in writing and must be received by the County Attorney’s Office seventy-two (72) hours or three (3) business days prior to the Board of County Commissioner’s meeting date in which the award of contract by the Board of County Commissioners will be heard. The only opportunity to address protest claims is before the BOCC at the designated public meeting in which the agenda item awarding the contract is heard. In accordance with the Rules of Debate as set forth in the Monroe County Board of County Commissioners Administrative Procedures, the Bidder/Respondent/Proposer that filed the protest is responsible for providing the Clerk with his/her name and residence prior to the agenda item to award the contract being called in order to preserve their opportunity to be heard on this matter. An individual has three (3) minutes to address the Commission and a person representing an organization has five (5) minutes to address the Commission. The BOCC decision to award the contract is final and at its sole discretion.