1-RFP 549815 - Attachment B2 Committed Work Capacity.xlsx

XLSX spreadsheet 86 KB Posted

Attached to
CDD - Northwest Activities Center (NWAC) RTU Replacement
Solicitation number
549815
Issued by
Wayne County, Detroit City, Michigan

About this file

This is an Excel-based attachment form for Attachment B2 Committed Work Capacity, created by the City of Detroit Office of Contracting and Procurement on behalf of the Construction and Demolition Department (CDD) in support of an RFP for design-build HVAC upgrade services at Northwest Activities Center. The document requires qualified respondents to document all awarded or in-progress projects assigned to their proposed project manager and superintendent staff. Respondents must complete Tab 2 of the form by entering detailed information for up to five current projects, including project name, description, budget, City of Detroit contract number if applicable, project status, actual or anticipated start and end dates, client information, and committed staff assignments. If respondents have more than five current projects outside of City of Detroit Demolition Department contracts, additional forms must be submitted with reordered column headers.

All committed staff members listed on this form must also appear on the most current Staff Roster submitted with the RFP response; failure to include staff on the roster will render the entire submittal non-responsive. The document must be submitted in Excel format, and any incomplete submissions may result in a determination of non-responsiveness. For each project listed, respondents must document the availability dates for both the project manager and superintendent for new work assignments, with actual or anticipated start and end dates clearly marked with asterisks to ensure transparent capacity planning for the proposed NWAC RTU Replacement project.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tab 1 Instructions_Notes Please read the following instructions and notes in their entirety before completing the attachment. Interested vendors must ask any questions related to this attachment prior to the questions deadline identified in this RFP. Please read the following instructions and notes in their entirety before completing the attachment. Interested vendors must ask any questions related to this attachment prior to the questions deadline identified in this RFP.

Instructions Instructions

On Tab 2., respondents must enter all of the requested information regarding any related project that has been awarded or is in progress. On Tab 2., respondents must enter all of the requested information regarding any awarded or in progress projects that your listed project manger and/or superintendent is assigned to.

If the respondent has more than five (5) current projects awarded or in progress outside of award(s)/contract(s) associated with the City of Detroit Demolition Department, the respondent must use another form and re-title the column headers to read "Project #6", "Project #7", "Project #8", etc.

File Format

Respondents must submit this document in Excel format.

NOTES: Notes

Failure to enter any of the required information may result in a determination that the form is incomplete. Failure to enter any of the required information may result in a determination that the form is incomplete.

Every staff member listed under "Committed Staff Members" must also be documented on the most up to date and current Staff Roster submitted with this RFP. If any committed staff members are not listed on the Staff Roster, the submittal will be considered non-responsive.

Please document actual OR anticipated start/end dates for all lines noted with an asterisk (*). For all rows marked with an asterisk (*), please document actual OR anticipated start/end dates.

File Format: This document must be submitted in Excel format.

&"-,Bold"&14ATTACHMENT B2

CAPACITY

Tab 2 Awarded-In Progress Work

VENDOR NAME:

Project # 1Project # 2Project # 3Project # 4Project # 5
Project Name
Project Description
Project Budget
City of Detroit Contract Number (if applicable)
Project Status
Project Start Date*
Project End Date*
Client
Client Contact Name
Client Contact E-mail
Client Contact Phone
Committed Project Manager Staff
Date Project Manager Staff Available for New Work*
Committed Superintendent Staff
Date Superintendent Staff Available for New Work*

&"-,Bold"&16ATTACHMENT B2

CAPACITY

File details come from the government source that posted it. Updated .