This document contains the proposal and specifications for a CIPP sanitary sewer lining and manhole rehabilitation project issued by the Muckinipates Authority in Delaware County, Pennsylvania. The project encompasses the lining of 1,353 linear feet of 18-inch sewer pipe and 2,264 linear feet of 24-inch sewer pipe, along with appurtenant work and manhole rehabilitation. Sealed proposals will be received electronically through PennBid until 11:00 AM on Tuesday, June 23, 2026, at which time they will be publicly opened and read aloud at the offices of H. Gilroy Damon Associates, Inc., located at 1343 Chester Pike, Sharon Hill, PA 19079. All solicitation documents and specifications are available at no cost through PennBid at https://pennbid.bonfirehub.com, though the winning bidder will be required to pay a fee to the platform.
Bids must be accompanied by a certified check or bid bond equal to 10 percent of the total bid amount, made payable to the Muckinipates Authority. The awarded contractor will be required to obtain payment and performance bonds for 100 percent of the contract price, maintain specified insurance coverage as detailed in the bid package, and comply with Pennsylvania prevailing wage rates. No bidder may withdraw their proposal within sixty days following the bid opening date. The Authority reserves the right to reject any or all proposals and to waive any informalities in the bids as deemed in the best interest of the Authority.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2-PROJECT MAP 2026-001.pdf | ||
| 3-SUBCONTRACTOR DECLARATION FORM.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROPOSAL AND SPECIFICATIONS
For The
CIPP LINING AND MANHOLE REHABILITATION
OF PORTIONS OF THE INTERCEPTOR
For
THE MUCKINIPATES AUTHORITY
DELAWARE COUNTY, PA
JUNE 2026
H. GILROY DAMON ASSOCIATES, INC.
Consulting Engineers
Sharon Hill, PA
Phone: 610-583-4100
Fax: 610-583-4140 www.damonengineers.com http://www.damonengineers.com/
NOTICE TO BIDDERS
MUCKINIPATES AUTHORITY
Sealed proposals will be received by the Muckinipates Authority, Delaware County electronically through PennBid™ until 11:00 AM on Tuesday, June 23, 2026 at which time they will be publically opened and read aloud at the offices of H. Gilroy Damon Associates, Inc. 1343 Chester
Pike, Sharon Hill, PA 19079 for the following;
1. Muckinipates Authority CIPP Lining and Manhole Rehabilitation
All documents and solicitation details can be obtained at no cost on PennBid at https://pennbid.bonfirehub.com. The bidder who is awarded the contract will be required to pay a fee to PennBid™. The names of those who have secured plans/specifications may be obtained at
PennBid™.
The bid must be accompanied by a certified check or bid bond in the amount of 10% of the bid, made payable to the Muckinipates Authority.
This project involves lining of 1,353 L.F. of 18-inch sewer, 2,264 L.F. of 24-inch sewer and appurtenant work.
Notice is hereby given to the requirements contained in this Bid Package particularly to the various insurance requirements, PA. Prevailing Wage Rates, and the requirements for a payment and performance bonds for 100% of the contract price.
No bidder may withdraw his bid within sixty (60) days after the actual date of the opening thereof.
The Authority reserves the right to reject any or all proposals and to waive any informality in the bids, as they deem for the best interest of the Authority.
BY: Dennis M. O’Mahony, Secretary
Muckinipates Authority https://pennbid.bonfirehub.com/
INSTRUCTIONS TO BIDDERS
1. RECEIPT AND OPENING OF BIDS: The Muckinipates Authority (herein called the "Owner"), invites bids on the form attached hereto, all blanks of which must be appropriately filled
in. Bids will be received at the office of H. Gilroy Damon Associates, Inc. through PennPID™ until 11:00 o'clock A.M, Tuesday, June 23 , 20 26 , and then at 11:00 A.M. at the offices of H. Gilroy Damon Associates, Inc. publicly opened and read aloud. The envelopes containing the bids must be sealed, addressed to The Muckinipates Authority at 1343 Chester Pike, Sharon Hill, PA 19079 and designated as bid for CIPP lining and Manhole Rehabilitation of portions of the Interceptor sewer.
The Owner may consider informal any bid not prepared and submitted in accordance with the provisions hereof and may waive any informalities or reject any and all bids. Any bid may be withdrawn prior to the above scheduled time for the opening of bids or authorized postponement thereof. Any bid received after the time and date specified shall not be considered. No bidder may withdraw a bid within sixty
(60) days after the actual date of the opening thereof.
2. PREPARATION OF BID: Each bid must be submitted on the prescribed form and accompanied by a Bid
Bond, Certified Check, or Letter of Credit, the Non-collusion Affidavit, and Subcontractor Declaration Form.
All blank spaces for bid prices must be completed, in ink or typewritten, in both words and figures, and the foregoing Certifications must be fully completed and executed when submitted. In case of discrepancies of written words and figures, the prices written in words shall govern.
Each bid must be submitted in a sealed envelope bearing on the outside the name of the bidder, his/her address, and the name of the project for which the bid is submitted. If forwarded by mail, the sealed envelope containing the bid must be enclosed in another envelope addressed as specified in the bid form.
3. TELEGRAPHIC MODIFICATION: Any bidder may modify his/her bid by telegraphic communication at any time prior to the scheduled closing time for receipt of bids, provided such telegraphic communication is received by the Owner prior to the closing time, and, provided further, the Owner is satisfied that a written confirmation of the telegraphic modification over the signature of the bidder was mailed prior to the closing time. The telegraphic communication should not reveal the bid price, but should provide the addition or subtraction or other modification so that the final prices or terms will not be known by the Owner until the sealed bid is opened. If written confirmation is not received within two days from the closing time, no consideration will be given to the telegraphic modification.
4. METHOD OF BIDDING: The Owner invites unit price/lump sum price bids as indicated in the Bid Form, page.
If the lowest total responsive bid received exceeds the amount of funds available to finance the contract, the
Owner may:
a. Reject all bids;
b. Augment the funds available in an amount sufficient to enable award to the lowest responsive bidder or bidders;
c. Take the base bid less the alternative deductible (if any) as listed on the proposal form as to produce a net amount which is within available funds.
5. QUALIFICATIONS OF BIDDER: The Owner may make such investigations as he/she deems necessary to determine the ability of the bidder to perform the work, and the bidder shall furnish to the Owner all such information and data for this purpose as the Owner may request. The Owner reserves the right to reject any bid if the evidence submitted by, or investigation of, such bidder fails to satisfy the Owner that such bidder is properly qualified to carry out the obligations of the contract and to complete the work contemplated therein. Conditional bids will not be accepted.
6. BID SECURITY: Each bid must be accompanied by cash, certified check of the bidder, or a bid bond prepared on the form of bid bond attached hereto, duly executed by the bidder as principal and having as surety thereon a surety company approved by the Owner. Such cash, checks or bid bonds will be returned to all except the three lowest bidders within three days after the opening of bids, and the remaining cash, checks or bid bonds will be returned promptly after the Owner and the accepted bidder have executed the contract, or, if no award has been made within thirty (30) days after the date of the opening of bids, upon demand of the bidder at any time thereafter, so long as he/she has not been notified of the acceptance of his/her bid.
Attorneys-in-fact who sign bid bonds or contract bonds must file with each bond a certified and effectively dated copy of their power of attorney.
7. LIQUIDATED DAMAGES FOR FAILURE TO ENTER INTO CONTRACT: The successful bidder, upon his/her failure or refusal to execute and deliver the contract and bonds required within ten (10) days after he/she has received notice of the acceptance of his/her bid, shall forfeit to the Owner, as liquidated damages for such failure or refusal, the security deposited with his/her bid.
8. CONDITIONS OF WORK: Each bidder must inform himself/herself fully to the conditions relating to the construction of the project and the employment of labor thereon. Failure to do so will not relieve a successful bidder of his/her obligation to furnish all material and labor necessary to carry out the provisions of his/her contract. Insofar as possible, the contractor in carrying out the work, must employ such methods or means as will not cause any interruption of or interference with the work of any other contractor.
9. OBLIGATION OF BIDDER: At the time of the opening of bids each bidder will be presumed to have inspected the site and to have read and to be thoroughly familiar with the plans and contract documents
(including all addenda). The failure or omission of any bidder to examine any form, instrument or document shall in no way relieve any bidder from any obligation in respect of his/her bid.
10. EXAMINATION OF SITE: Each bidder shall, and is hereby directed to inspect the entire site of the proposed work and judge for himself/herself as to all the circumstances affecting the cost and progress of the work and shall assume all patent and latent risks in connection therewith.
11. SOIL CONDITIONS: Subject to the convenience of the Owners, prospective bidders will be permitted to explore the site by making borings or digging test pits. In such event, the work shall be done at the sole expense and risk of the bidder, and he shall maintain and restore the site to original condition.
The Owner does not guarantee the accuracy of any information or samples which it may have obtained from test borings or otherwise as to the kind, or condition of, the soil that may be encountered in the prosecution of the proposed work, neither does the Owner represent that the plans and specifications drawn are based upon any data so obtained. The Owner does not make any representation as to the soil which may be encountered or of soil or water which underlies the work or is adjacent thereto, including any difficulties that may be due to quicksand, or other unfavorable conditions that may be encountered in the work, whether apparent upon surface inspection or disclosed in the process of carrying forward the work.
12. WORKING FACILITIES: The plans show, in the general manner, the existing structures and the land available for construction purposes. The bidders must satisfy themselves of the conditions and difficulties that may be encountered in the execution of the work at this site.
13. ADDENDA AND INTERPRETATIONS: No official interpretation of the meaning of the plans, specifications or other pre-bid documents will be made to any bidder orally.
Every request for such interpretation should be in writing addressed to
The Engineer and to be given consideration, must be received at least five (5) days prior to the date fixed for the opening of bids. Any and all such interpretations and any supplemental instructions will be in the form of written addenda to the specifications which, if issued, will be mailed by certified mail with return receipt requested to all prospective bidders (at the respective addresses furnished for such purposes), not later than three (3) days prior to the date fixed for the opening of bids. Failure of any bidder to receive any such addendum or interpretation shall not relieve such bidder from any obligation under his/her bid as submitted. All addenda so issued shall become part of the contract documents.
14. WATER SUPPLY: All water for construction purposed, as well as the expense of having water conveyed about the work, must be provided by the Contractor and the cost of this work shall be included in the unit prices stipulated for the various items of the work to be done under this contract.
The source, quality and quantity of water furnished shall at all times be satisfactory to the Engineer.
15. SIGNATURE OF BIDDERS: The firm, corporate or individual name of the bidder must be signed in ink in the space provided for the signatures on the proposed blanks. In the case of a corporation, the title of the officer signing must be stated and such officer must be thereunto duly authorized and the seal of said corporation duly affixed. In the case of a partnership, the signature of at least one of the partners must follow the firm name, using the term "member of the firm". In the case of an individual, use the terms "doing business as", or "sole owner". The bidder shall further state in his proposal the name and address of each person or corporation interested therein.
16. NOTICE OF SPECIAL CONDITIONS: Attention of the bidder is particularly called to those parts of the
General Contract Conditions and other contract documents and specifications which deal with the following:
a. Insurance requirements
b. PA Prevailing Wage rates
c. Requirement for a payment bond and performance bond for 100% of contract price
d. Requirement that all subcontractors be approved by the Owner
e. Time-for-completion and liquidated damages requirements
f. Safety standards
g. Contractor's responsibility to obtain permits
h. Affirmative Action and Equal Opportunity provisions
17. ADDITIONAL OBLIGATIONS UPON CONTRACT AWARD: Upon award of the contract but prior to issuance of the notice to proceed, the contractor shall submit all of the following documents, completed as required:
(a) Acceptance of Notice of Award
(b) Contract
(c) Insurance certificate(s) and/or policy(ies)
(d) Performance & Payment bonds
(e) Contractor's Section 3 Plan
(f) (If over $10,000:) Certification of Bidder Regarding Equal Employment Opportunity
(g) (If over $10,000:) Certification(s) by (all) Proposed Subcontractors Regarding Equal Employment
Opportunity
(h) Certification of Bidder Regarding Section 3 and Segregated Facilities
(i) Certification(s) of (all) Proposed Subcontractor(s) Regarding Section 3 and Segregated Facilities
(j) (If over $100,000:) Certification by Contractor and Subcontractors of Compliance with Clean Air and Water Acts
(k) Contractor's Certification Concerning Labor Standards and Prevailing Wage Requirements
(l) (All) Subcontractor's Certification(s) Concerning labor Standards and Prevailing Wage
Requirements
To the Muckinipates Authority c/o Jeffrey A. Roken, Chairman
1343 Chester Pike
Sharon Hill, PA 19079
Members of the Authority:
The undersigned Bidder hereby offers and proposes to furnish all labor, tools, materials and equipment and to do all the work required to complete the CIPP lining and manhole rehabilitation of portions of the Interceptor Sewer at various locations as shown on the attached drawings, including all work incidental thereto, in as first class workmanlike manner, in strict accordance with the general condition and specifications hereto annexed and to the satisfaction of the Members of the Authority for the following unit price of:
Item
No.
Estimated
Quantities
Unit Price
Total Price
1 1,353 L.F. 18” CIPP Lining $ _________/Per Ft. $ _________________
2 2,264 L.F. 24” CIPP Lining $ _________/Per Ft. $ _________________
3 1 Lateral Reconnection $ _________/Each $ _________________
4 1 Protruding Lateral Removal $ _________/Each $ _________________
5 300 L.F. Heavy Cleaning
And Root Removal
$__________/Per Ft.
6 100 V.F.
Manhole Rehabilitation
$_______/Per Vertical Ft.
Total Bid Price
It is agreed that the Muckinipates Authority reserves the right to increase or diminish the gross amount of work specified. No allowances will be made in case of increase for any sum above prices bid, nor in case of decrease for any real or supposed damage or loss of profit occasioned by such diminution.
If designated as the successful Bidder, the Contractor will begin work on the date specified in the notice to proceed and will complete all work within 90 calendar days. If all work is not completed on time, liquidation damages will be assessed at the rate of $100.00 per additional working day.
WITNESS the hand and seal of the bidder this_________day of_____________A.D. 2026
Company Name and Address:
Signature of Bidder
Telephone Number Title
(SEAL if bid is a Corporation)
SPECIAL CONDITIONS
1. It is the intent of this contract to provide for the CIPP Lining and sanitary manhole rehabilitation.
All work shall be performed as directed, in writing, by the Authority and/or the Engineer.
2. The Contractor shall be required to maintain traffic during the progress of the work, temporary detours or street closing shall be permitted only as deemed necessary by the Engineer with the permission and cooperation of the Police Department. The Contractor shall maintain sufficient barricades, warning signs and warning lights during the construction both day and night in order to insure the safety of the traveling public. The Contractor shall place detour signs as required and shall be responsible for the maintenance and replacement of such warning devices and barricades throughout the course of this contract.
3. Insurance Certificates, as follows, in a form satisfactory to the Authority Solicitor, shall be submitted at the time of executing the contract.
Statutory Workmen’s Compensation.
Public Liability with Contractual Coverage in the amount of $500,000/$1,000,000 and $100,000 respectively.
Cancellation shall not be effective unless the owner is notified in writing 20 days prior to the date of any proposed cancellation.
The Engineer and the Authority shall be named as additional insurers.
4. The successful bidder shall be required to submit to the Authority a record of all equipment, labor and materials used for each order to be gathered together with copies of delivery tickets.
5. The quantities stated on the proposal are only approximate. Payment shall be made on the actual quantity of each unit in the performance of any work as approved by the Engineer.
6. Heavy duty cleaning and root removal shall be paid only when specifically authorized by the
Authority and/or Engineer.
7. The Contractor shall provide temporary access to all manholes as necessary to perform the work.
Any areas disturbed shall be stabilized and restored to pre-work conditions.
8. The Contractor shall be responsible for obtaining water for their use.
9. The Contractor shall submit a detailed plan for bypass pumping.
AGREEMENT
THIS AGREEMENT made this__________day of______________, 2026 by and between______________________________herinafter called the “Contractor” and the Muckinipates
Authority hereinafter called the “Owner”.
WITNESSETH, that the Contractor and the Owner for the considerations stated herein mutually agree as follows:
1. Statement of Work
The Contractor shall furnish all supervision, technical personnel, labor, materials, machinery, tools, equipment and services, including utility and transportation services, and perform and complete all work required for the construction of improvements embraced in the project: CIPP lining and Manhole
Rehabilitation of Portions of Interceptor Sewer in strict accordance with the Contract Documents including all work incidental thereto.
ARTICLE 2. The Contractor Price
The Owner will pay the Contractor for the total quantities of work performed at the unit prices stipulated in the bid for the respective items of work completed for the sum not to exceed_____________(dollars) subject to additions and deductions as provided in Article 14 of the General Contractor Conditions hereof.
ARTICLE 3. Contract
The executed contract documents shall consist of the following:
a. This agreement
b. Signed copy of Bid
c. Perfomance and Payment Bonds
d. General Conditions
e. Technical Specifications and Drawings
It is further agreed that all work will be completed within 60 calendar days from the date specified in order to proceed.
This Agreement, together with other documents enumerated in this ARTICLE 3, which said other documents are as fully a part of the Contract as if hereto attached or herein repeated, forms the contract between parties hereto. In the event that any provision in any component part of this contract conflicts with any provision of any other component part, the provision of the component part first enumerated in this ARTICLE 3 shall govern, except as otherwise specifically stated.
IN WITNESS WHEREOF, the parties of this AGREEMENT have set their hands and seals the day and year first above written.
Contractor
ATTESTED BY:
___________________________ By_________________________
Title
SEAL DUNS Number
Central Contractor Registration No.
ACCEPTED ON_______________
Date
ATTESTED BY: MUCKINIPATES AUTHORITY
____________________________ BY_________________________
Dennis M. O’Mahony Jeffrey A. Roken
SEAL
COMMONWEALTH OF PENNSYLVANIA
PUBLIC WORKS EMPLOYMENT VERIFICATION FORM
Date _______________________
Business or Organization Name (Employer)_________________________________________________
Address _____________________________________________________________________________
City _____________________________________ State_____________ Zip Code ________________
Contractor {dzōŎƻƴǘNJŀŎǘƻNJ όŎƘŜŎƪ ƻƴŜύ
Contracting Public Body _______________________________________________________________
Contract/Project No ___________________________________________________________________
Project Description ____________________________________________________________________
Project Location ______________________________________________________________________
As a contractor/subcontractor for the above referenced public works contract, I hereby affirm that as of the above date, our company is in compliance with the Public Works Employment Verification Act
(‘the Act’) through utilization of the federal E‐Verify Program (EVP) operated by the United States
Department of Homeland Security. To the best of my/our knowledge, all employees hired post
January 1, 2013 are authorized to work in the United States.
It is also agreed to that all public works contractors/subcontractors will utilize the federal EVP to verify the employment eligibility of each new hire within five (5) business days of the employee start date throughout the duration of the public works contract. Documentation confirming the use of the federal EVP upon each new hire shall be maintained in the event of an investigation or audit.
I, _________________________, authorized representative of the company above, attest that the information contained in this verification form is true and correct and understand that the submission of false or misleading information in connection with the above verification shall be subject to sanctions provided by law.
Authorized Representative Signature
SPECIFICATIONS FOR CURED IN PLACE PIPE LINER
PART 1 – GENERAL
1. Intent of Specifications
A. It is the intent of this section of these Specifications to provide for the reconstruction of sewer pipelines and conduits by the installation of a resin-impregnated flexible tube that is either inverted or pulled into the original pipeline/conduit and expanded to fit tightly against said pipeline by the use of water or air pressure.
The resin system shall then be cured by elevating the temperature of the fluid (water/air used for the inflation to a sufficient enough level for the indicators in the resin to effect a thermosetting reaction or by applying ultraviolet light to obtain the desired cure.
B. These specifications, and the accompanying plans, are intended to require and include all work and material necessary and proper for the work contemplated. In case, by inadvertence or otherwise, the plans or specifications omit to require some work or material necessary for that purpose, the Contractor shall, nevertheless, be required to provide the same so that the work may be complete according to the true intent and purpose of the plans and specifications.
C. The Contractor agrees that he has satisfied himself by his own investigation and research regarding all the conditions affecting the work to be done and labor and material needed, and that his conclusion to execute this Contract is based on such investigation and research, and not the estimate of the quantities or other information prepared by the Engineer, and that he will make no claim against the Owner because any of the estimates, tests or representatives of any kind affecting the work made by any agent of the Owner maybe prove to be an r
2. Description of Work
A. The work of this section includes, but is not limited to, rehabilitation of the existing sanitary pipe by installation of a cured-in-place pipe liner. The process shall result in a self-supporting, continuous, tight fitting, watertight seal with the existing sewer main. Included in the work is cutting out of existing laterals.
B. Location of sewer pipeline work is shown on the drawing.
C. Maintenance and protection of traffic is included in the work.
D. Work includes cleaning and videotaping the existing sewer lines.
E. Bypass pumping of sewage flows is included in the work.
F. The Contractor shall be responsible for providing water necessary for the work.
3. Site Conditions
A. Prior to all work, the Contractor shall carefully inspect the area for “present” existing conditions.
B. The Contractor shall verify existing pipeline diameters and lengths prior to ordering materials.
4. Compliance with Standards
A. All work and materials shall conform to these specifications.
5. Maintaining Traffic
A. The Contractor shall so carry his work that traffic will be maintained as reasonably as possible.
B. Driveways to properties shall be kept on at all times, except in areas where work is in actual progress.
C. Access to fire hydrants shall be maintained.
6. Precautions to be Taken
A. The Contractor shall erect barricades, lights and provide such warnings as may be necessary to protect injury to persons and property or damage to the work.
B. The Contractor shall carry out his operations in strict accordance with all OSHA and manufacturers’ safety requirements.
7. Notices
A. Prior to starting work, the Contractor shall notify the Townships and serve notices to the property owners of the intended day of work.
B. The Contractor shall notify the Engineer at all times when he is working and he shall give his personal supervision to the faithful prosecution of the work in case of his absence, he shall have a competent representative of field superintendent on the work who shall follow, without delay, all instructions of the
Engineer or his assistants in the prosecution and completion of the work.
8. Referenced Documents
This Specification references ASTM D5813 (Standard Specification for Cured-In-Place Thermosetting Resin
Sewer Pipe) ASTM F1216 (Standard Practice for Rehabilitation of Existing Pipelines and Conduits by the
Inversion and Curing of a Resin-Impregnated Tube), and ASTM F1743 (Standard Practice for Rehabilitation of
Existing Pipelines and Conduits by Pulled-In-Place Installation of Cured-In-Place Thermosetting Resin Pipe.
9. Qualification Requirements
A. The system proposed (materials, methods, workmanship) must be proven through previous successful installations to an extent and nature satisfactory to the Owner and the Engineer that is commensurate with the size of the project being proposed. Since CIPP is intended to have a 50-year design life, only products deemed to have this performance will be accepted. All products and installers must be pre-approved prior to the formal opening of proposals.
Products and Installers seeking approval must meet all of the following criteria to be deemed commercialy acceptable:
For a Product to be considered Commercially Proven, a minimum of 250,000 linear feet and/or 1,000 line sections must have been successfully installed. The Manufacturer (Licensor) shall have completed sufficient enough testing to document that the materials and the method(s) of installation proposed will produce the desired long-term performance.
For an Installer to be considered Commercially Proven, the Installer must satisfy all insurance, financial, and bonding requirements of the Owner, and must have at least three years active experience in the commercial installation of the product bid.
The installers key personnel shall have at least 100,000 linear feet and/or 300 line sections of successful experience (included in this experience shall be a sufficient quantity of installations in the sizes proposed for this project). The installer shall be “ISO” certified to demonstrate that he/she has a similar quality assurance system in place.
Documentation for products and installers seeking pre-approved status must be submitted no less than two weeks prior to the proposal date to allow time for adequate consideration. The Owner will advise of acceptance (or rejection) a minimum of three days prior to due date. All required submittals must be satisfactory to the Owner.
10. Submittals
A. The Contractor shall submit the following information:
1. Manufacturer’s certification that the materials to be used meet the referenced standards and these specifications.
2. License or certificate verifying Manufacturer’s / Licensor’s approval of the installer.
3. Proposed equipment and procedures for accomplishing the work.
4. Lining Manufacturer’s product data and instructions for resin and catalyst system.
5. Design Calculations for wall thickness designs.
6. Written certificate of compliance with the manufacturer’s standards and specifications for all materials shall be submitted.
7. Two (2) copies of pre-construction videos of the pipe after cleaning and root removal, but prior to lining and two (2) copies of the post-construction videos of the pipe after lining shall be supplied by the Contractor.
PART 2 – PRODUCTS
1. General
A. The final product shall be a self-supporting, continuous pipe between each manhole, free of defects, watertight, designed to provide flow equivalent to that of the existing pipe and designed to withstand the loads of surface and subsurface conditions above the pipe.
B. The final product shall be sealed to the existing manholes. The sealing material shall be compatible with that of the liner such that a watertight connection can be made. Contractor shall place grout at the manhole connections on all sides of the pipe and shall provide a smooth transition from the channel to the linear at each manhole.
C. All lateral connections must be “cut out” within two (2) hours of the installation of the pipe lining to provide partial flow. Laterals shall be fully “cut out” and brushed immediately following the partial “cut out” of the laterals.
D. The tube shall consist of one or more layers of a flexible needled felt or an equivalent nonwoven or woven material, or a combination of nonwoven and woven materials, capable of carrying resin and withstanding the installation pressures and curing temperatures. The tube should be compatible with the resin system to be used on this project. The materials should be able to stretch to fit irregular pipe sections and negotiate bends.
E. The tube should be fabricated to a size that, when installed, will tightly fit the internal circumference and the length of the original conduit. Allowances should be made for the longitudinal and circumferential stretching that occurs during placement of the tube.
F. The tube shall be uniform in thickness and when subjected to the installation pressures will meet or exceed the designed finish wall thickness.
G. Any plastic film applied to the tube on what will become the interior wall of the finished CIPP shall be compatible with the resin system used, translucent enough that the resin is clearly visible, and shall be firmly bonded to the felt material.
H. The tube shall be marked for distance at regular intervals along its entire length, not to exceed 5 feet. Such markings shall also include the lining manufacturer’s name or identifying symbol.
I. The Resin System. The resin system shall be a corrosion resistant polyester, vinyl ester, or epoxy and catalyst system that when property cured meets the minimum requirements given herein or those that are to be utilized in the design of the CIPP for this project.
2. Structural Requirements
A. The design thickness of the linear shall be arrived at using standard engineering methodology. ASTM F1216, Appendix X1, has such an acceptable methodology that may be used where applicable. The long-term flexural modulus to be used in the design shall be verified through testing. The long-term modulus shall not exceed 50% of the short-term value for the resin system unless the tube contains reinforcements. In the event that a reinforced tube is utilized, the long-term flexural modulus shall be the percentage of the short-term modulus as determined by the above referenced testing.
B. The layers of the finished CIPP shall be uniformly bonded. It shall not be possible to separate any two layers with a probe or point of a knife blade so that the layers separate cleanly or such that the knife blade moves freely between the layers. If separation of the layers occurs during testing of the field samples, new samples will be cut from the work. Any reoccurrence may be the cause for rejection of the work.
C. The finished CIPP shall fit tightly to the host pipeline at all observable points and shall meet or exceed the minimum thickness established by the design process. The materials properties of the finished CIPP shall meet or exceed the following structural standards:
ASTM Polyester Filled Vinyl Ester
Property Test
Method
System Polyester System
Flexural Strength D790 4,500 psi 4,500 psi 5,000 psi
Flexural Modulus (Initial) D790 250,000 psi 400,000 psi 300,000 psi
Flexural Modulus (50 yr) D790 125,000 psi 200,000 psi 150,000 psi
Tensile Strength D638 3,000 psi 3,000 psi 4,000 psi
D. CIPP Thickness
1. The required structural CIPP wall thickness shall be based, as a minimum:
a. In accordance with ASTM F2019, Appendix X1, Design considerations for a fully deteriorated or partially deteriorated host pipe, for a circular host pipe with 10% ovality or less.
b. A safety factor of 2
c. A minimum service life of 50 years under continuous service
d. A modulus of soil reaction of 950 psi
e. A soil density of 120 lbs/in
f. A Poisson’s ratio of 0.3
g. An enhancement factor of 7
h. A groundwater elevation over the pipe equivalent to surface grade
i. Ovality for each segment as applicable
j. Live loads for each segment as applicable
k. Soil depth for each segment as applicable
PART 3 – INSTALLATION
1. Cured in Place Pipe
A. The CIPP shall be installed in accordance with the practices given in ASTM F1216 (for direct inversion installations) or ASTM F1743 (for pulled-in-place installations). The quantity of resin used for the tube’s impregnation shall be sufficient to fill the volume of air voids in the tube with additional allowances being made for polymerization shrinkage and the anticipated loss of any resin through cracks and irregularities in the original pipe wall. A vacuum impregnation shall be used in conjunction with a roller system to achieve a uniform distribution of the resin throughout the tube.
B. Temperature gauges shall be placed at the upstream and downstream ends of the reach being lined to monitor the pressurized fluid’s (air or water) temperature. In addition to monitoring the temperature inside the tube, temperature gauges shall be placed between the host pipe and the liner at as many points as is practical to record the heating that takes place on the outside of the liner.
Curing the resin system shall be as per the Manufacturer (Licensor) of the CIPP product. The temperatures achieved and the duration of holding the pressurized fluid at those temperatures shall be per the Manufacturer’s (Licensor’s) established procedures.
C. Experienced personnel trained in locating breaks, obstacles, and service connections by close circuit television shall perform inspection of the pipelines. The interior of the pipeline shall be carefully inspected to determine the location of any conditions that may prevent proper installation of the CIPP into pipelines, and it shall be noted so that these conditions may be corrected. A videotape and suitable log shall be kept for later reference by the Owner.
D. It shall be the responsibility of the Contractor to clear the line of obstructions such as solids and roots that will prevent the insertion of CIPP. If pre-installation inspection reveals an obstruction such as protruding service connection, dropped joint, or a collapse that will prevent the installation process, and it cannot be removed by conventional sewer cleaning equipment, then the Contractor shall make a point repair excavation to uncover and remove or repair the obstruction. Such excavation shall be approved, in writing, by the Engineer prior to the commencement of the work and shall be considered as a separate pay item.
E. Lining of the pipe shall be performed in accordance with the pipe liner manufacturer’s instructions. Any additional repairs to the existing main required prior to installation of the liner such that the liner may be properly installed shall be performed by the Contractor.
F. All access to the sanitary sewer main shall be through existing manholes. No alterations or modifications to the manholes are permitted. No excavation shall be performed without the approval of the Owner.
G. All equipment and materials required for installation of the liner including water, power, etc. shall be provided by the Contractor.
H. The new liner pipe shall be continuous over its entire length between manholes and be free as practical from visual defects, such as foreign inclusions and pinholes.
I. The liner shall fit tightly within the existing pipe. Should a tight fit not be obtained, the Contractor shall remove and dispose of the liner and replace it with a new liner at no additional cost.
J. A watertight fit shall be obtained at the manhole connections and at the laterals. A resin material compatible with the liner may be installed such that a watertight seal may be obtained. The liner shall be cut to fit flush with the inside wall of the manhole. The area between the liner and the channel shall be grouted to provide a smooth transition from the manhole to the liner.
K. All later connections shall be “cut out” and deburred such that the lateral may return to normal operation
L. A final videotape inspection of the line shall be performed by the Contractor. One (1) copy of the video shall be provided to the Engineer for review. Should any defects, flaws, or deformities be found, they shall be remedied by the Contractor at no additional cost to the Owner.
2. Bypass Pumping
A. Maintain commercial and residential sewer service during the installation process, if necessary to properly complete the work, the Contractor may interrupt flow from services. The Contractor has the sole responsibility of notifying the public of the work to be done. Each home or business connected to the sewer must be informed via written notice a day prior (24 hours) to work being commenced. The
Contractor must also leave contact information so the public may call with questions or concerns about the project. Upon completion of the work, immediately reinstate all services and notify the property owner(s) that service is again available. The Contractor also assumes all responsibility for blockages, back-ups or damages caused to public or private property as a result of the interruption of service called by the Contractor’s actions.
B. Bypass pumping systems shall be used and operated in accordance with NASSCO Specifications. The bypass pumping system capacity must be sized to meet all potential flows. The Contractor will be held solely responsible for any damage caused by flooding and will take care to avoid this occurrence. The system must be kept in service for each section until that section is completed and ready to return to service. The Contractor is responsible for all installation, operation and maintenance of the system.
Manpower, fuel, and necessary utilities required by the systems must be provided and paid for by the
Contractor. Standby pumping must be available and achieved by backing pumps size for size. This will allow for one hundred percent (100%) backup capacity in case of emergency situations or equipment malfunction. Bypass sewage from individual laterals if needed.
3. Clean Up
A. The Contractor shall, at all times, keep the work area free from accumulation of waste material or rubbish caused by employees or work. Before the work will be considered as having been completed, the
Contractor shall clean and remove from the work areas and adjacent property, all surplus and discarded material, equipment and temporary structures and shall leave the project “Broom Clean”.
4. Testing
A. The Contractor shall, at his expense, provide a pipe “coupon” specimen from each run of pipe for testing by an approved laboratory.
B. The Contractor shall, at his expense, within 14 days of completion, provide a closed circuit television camera videotape of each of the new liner pipelines.
C. Correct all defects discovered during the television inspection before Conditional Acceptance. After the defects are corrected, repeat the post-construction inspection for that sewer line.
PART 4 – PAYMENT
1. General
A. All work shall be paid for at the contract lump sum price specified in the proposal, for each lined sewer pipeline, complete in place, as specified, which price will include all work, materials, equipment and testing thereto and the satisfactory disposal of all unsuitable and surplus materials.
B. Removal of protruding service connections shall be paid for at the contract unit price specified in the proposal, for each connection, which price shall include any additional close circuit T.V. inspections required and the satisfactory removal of the protruding pipe materials.
C. Reconnections of active service connections shall be paid for at the contract unit price specified in the proposal, for each reconnection, which price shall include the satisfactory removal of the pipe materials.
D. Heavy duty cleaning shall be paid for at the contract unit price specified in the proposal upon acceptance by the Engineer.
2. ACCEPTANCE
A. Acceptance of the CIPP shall be based on the Engineer’s evaluation of the post-construction inspection video, and laboratory test results for the installed pipe samples, which shall demonstrate:
1. Compliance with the required CIPP physical properties and thickness.
2. Observed groundwater infiltration of the liner is zero.
3. All active service connections are open and clear.
4. There is no evidence of excessive wrinkles, splits, cracks, breaks, lifts, kinks, scalds, blisters, delaminations, crazing or other defects in the linear.
B. If any device liner is discovered after it has been installed, it shall be removed and replaced with either a sound liner or a new pipe at no additional cost to the Owner. The Contractor shall be responsible for costs of additional testing required to confirm compliance with these requirements. Obtain approval of the Engineer for method of repair, which may require field or workshop demonstration.
C. For liners with defects, if the Contractor elects to excavate and repair defects in the liner, cut and remove the defective section of liner plus the host pipe to a minimum of two feet beyond each end of the defective liner. Use SDR 35 PVC, or approved equal, to replace the removed liner and host pipe. Align invert of point repair with invert of CIPP. On either side of the proposed repair, carefully remove the host pipe from around the existing sound liner to expose a minimum of five inches of sound liner or as needed for repair coupling. Use stainless steel shielded flexible repair couplings custom-fabricated specifically to fit the outside diameter of the host pipe and CIPP to assure a watertight connection. Haunch all exposed liner and new PVC pipe to the springline with pipe bedding material. Cover with concrete all exposed liner and repair couplings a minimum of six inches on either side of the pipe from the springline to six inches above the pipe. Place AASHTO #57 bedding, as approved by the Engineer a minimum of eight inches on either side of pipe from the springline of new PVC pipe to eight inches above the pipe.
D. If the Contractor elects to repair defects in the liner using trenchless methods, remove the defective sections of liner for the full circumference to a minimum of six inches beyond each of the defective liner or as approved by the Engineer. Install a cured-in-place point repair that is comparable to the short and long-term material properties of the existing liner and must have the appropriate thickness to withstand the criteria for that particular liner. A minimum of twelve inches of overlap is required on either end of the repair. Should the proposed cured-in-place point repair reduce the inside diameter of pipe to an unacceptable diameter
SPECIFICATIONS FOR MANHOLE REHABILITATION
PART 1 – GENERAL
1.1 DESCRIPTION
A. Work Included - The project consists of the rehabilitation of various sanitary sewer manholes within the limits of the proposed lining work as shown on the plans.
B. The rehabilitation of manholes shall be accomplished by the application or installation of rehabilitation components either individually or together. These may include grouts, protective coatings, a variety of linings, that, when installed, shall protect the manhole structure, seal it from I & I, and provide chemical resistance for the length of time specified. The Contractor is responsible for the accurate and complete installation, and warranty of each manhole rehabilitation.
C. Related Work – Documents affecting work of this Section include, but are not necessarily limited to, General Conditions, and Supplementary Conditions, of these Specifications.
1.2 SCOPE
A. Manhole Rehabilitation - Work shall include but not be limited to stopping all leaks, filling voids, repairing brick work and placing a coating to entire interior surface of manhole to provide a waterproof sealant system.
1.3 GENERAL REQUIREMENTS
A. Traffic Control/Protection – The Contractor shall provide adequate traffic control in accordance with PA
DOT standards. Contractor shall be responsible for coordinating of school traffic. Road closures must be approved in advance by the Township. At the end of the workday, work area shall be properly cleaned and protected with operational lighted barricades. No trench shall be left open. The work area shall be protected with safety fence and lighted barricades. All materials shall be stockpiled to maintain adequate vehicular traffic (minimum 16’wide passage) and pedestrian traffic. Access to all driveways shall be maintained.
B. Tree Removal/Trimming – The contractor shall not remove or trim any trees without having approval of the Municipality.
C. Erosion Control – The Contractor shall install and maintain all erosion control measures. Any necessary trench dewatering shall be pumped into a sediment filter bag prior to discharge.
D. Notification of Residents – The contractor shall notify residents by distributing notices prior to start of work.
E. Incidental Work – Any work not expressly shown in the form of proposal, but required for completion of the project, shall be considered incidental.
F. Permits/Contractor License - Permits and construction license for construction activities will be required for all contractors and subcontractors at the contractor and subcontractor expense.
G. Safety Precautions – It shall be the Contractor’s sole responsibility to ensure that all safety regulations are met. The Contractor shall appoint a safety officer to monitor these operations.
H. Sanitary Sewer Operation – It shall be the Contractor’s sole responsibility to ensure that the sanitary sewer operation be maintained at all times.
1.4 SUBMITTALS
A. Product data submittals required for all rehabilitation systems proposed for installation under this contract shall include:
1. Material type and manufacturer to be used including: catalog data sheets, ASTM references, material composition, manufacturers recommended specifications, component physical properties and chemical resistance.
2. Manufacturer’s detailed description of the recommended procedures for handling and storing materials including a proposed method for monitoring temperatures of the storage location, if applicable to the specific material.
3. Manufacturers detailed description of the recommended material installation/application process including mixing, additives, set time, cure time (return to service) and all equipment required for quality product delivery.
4. Technical data sheet describing each rehabilitation component to be applied/installed, stating the expected longevity of the component in a wastewater environment. Data shall be based on independent third-party tests.
5. Manufacturer’s detailed description of all required field-testing processes and procedures. (PWS)
6. Copies of independent testing performed on the rehabilitation component, indicating that the product meets the requirements as specified in these contract documents and the manufacturer’s design.
7. Technical data sheet and project specific data for manhole repair materials to be used in conjunction with each rehabilitation component(s) including application cure time and surface preparation procedures.
8. Certification that backup installation equipment is available on the job site or can be delivered to the job site by the morning of the next business day.
9. Shipping information including: (Jobsite)
a. Shipped item, including manufacturer, stock and lot number.
b. Date shipped including origination and delivery locations.
c. Shipping method and carrier.
d. All shipping, storage and safety requirements including MSDS documents.
e. Date delivered to project site including name and signature of receiver.
10. By-Pass Pumping Plan, if applicable.
11. Traffic Control Plan, if applicable.
12. Certified statement, from the manufacturer, that the contractor/installer is an approved installer with certificates of completed training for each crew member involved in each rehabilitation component.
This requirement shall comply with the specific SYSTEM requirements specified in the contract documents. (PWS)
13. For each manhole rehabilitation, a complete and accurate record of all installed/applied shall be prepared by the Contractor. The record shall include identifying manhole number, location, quantities of rehabilitation components installed.
14. Submittal of all quality assurance documentation and test reports (After Rehabilitation Completion)
15. Compensation for all work required for product submittals and the submittal of a By-Pass
Pumping Plan and a Traffic Control Plan shall be included in the manhole rehabilitation item contained in the Bid Proposal.
16. Refer to section 1.1F for design requirements.
PART 2 – REHABILITATION COMPONENT SYSTEM PRODUCTS
A. The SYSTEM’S defined herein included those identified as commercially accepted methods for manhole rehabilitation. Methods or products not defined herein must be pre-approved by the Owner before use on this project under these specifications.
2.2 CEMENTITIOUS MANHOLE RESTORATION
A. REFERENCES ASTM F2414-03 Standard Practice for Sealing Sewer manholes Using Chemical
Grouting
B. CHEMICAL GROUT TYPES
1. The Contractor shall…