About this file

This is a Project Manual and Bidding Documents package for New Freedom Borough, Pennsylvania, for the construction of Wellhouse No. 1 Upgrades. The project includes a 14' X 14' brick masonry addition to the existing wellhouse, duplex ion exchange softening treatment units, an outdoor backup power generator with automatic transfer switch, heating and ventilation improvements, flow metering and control valves with analytical equipment, a tempered water eyewash station, a 4' X 4' vault with access hatch at the entry to a 24-inch chlorine contact pipe, and various piping modifications including a new drain to sanitary. Online sealed bids are due September 2, 2026, at 10:00 a.m. through the PennBid Program. The project is located at 34 S. Front Street, New Freedom, PA 17349, and prospective bidders are required to attend a mandatory pre-bid conference; a site visit is optional and scheduled following the conference. The contract duration is 300 days for substantial completion and 330 days for final completion. Contract times are of the essence, with liquidated damages set at $1,000.00 per day for delays in achieving substantial completion and $500.00 per day for delays beyond that deadline until final completion.

The contract is awarded on a lump sum stipulated price basis to the lowest responsive and responsible bidder. Bid security of 10 percent of the maximum bid price must accompany all bids in the form of a bid bond. Progress payments will be made at 90 percent of work completed (increasing to 95 percent after 50 percent completion) with retainage held until substantial completion, at which point payment increases to 100 percent less an estimate of remaining work. All bids must remain subject to acceptance for 60 days after bid opening. Contractor must subcontract with New Freedom Borough's Systems Integrator, located at 713 Range End Road, Dillsburg, PA 17019, for all instrumentation and controls work and associated systems integration. The Engineer of Record is RK&K, LLP. Bidding documents are available through the designated website https://pennbid.bonfirehum.com, and prospective bidders are urged to register as plan holders to receive all official notifications, addenda, and updates.

View the file

Other files

File Type Posted
2-Bid Drawings - Wellhouse No. 1 Upgrades.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TOC-i

TABLE OF CONTENTS

TITLE PAGE NO.

BIDDING REQUIREMENTS

INSTRUCTIONS TO BIDDERS EJCDC C-200

BIDDING FORMS

BID FORM EJCDC C-410

BID BOND EJCDC C-430

QUALIFICATIONS STATEMENT EJCDC C-451

CONTRACT FORMS

AGREEMENT BETWEEN OWNER AND CONTRACTOR EJCDC C-520

PERFORMANCE BOND EJCDC C-610

PAYMENT BOND EJCDC C-615

CONDITIONS OF THE CONTRACT

STANDARD GENERAL CONDITIONS EJCDC C-700

SUPPLEMENTARY CONDITIONS EJCDC C-800

PREVAILING WAGES PROJECT RATES

TECHNICAL SPECIFICATIONS

DIVISION 1 - GENERAL REQUIREMENTS

Section 01010 – SUMMARY OF WORK 01010–1

Section 01025 – MEASUREMENT AND PAYMENT 01025–1

Section 01025A – PAYMENT APPLICATION FORM 01025A–1

Section 01040 – COORDINATION 01040–1

Section 01200 – PROJECT MEETINGS 01200–1

Section 01300 – SUBMITTALS 01300–1

Section 01400 – QUALITY CONTROL 01400–1

Section 01500 – CONSTRUCTION FACILITIES AND TEMPORARY

CONTROLS

01500–1

Section 01560 – SOIL EROSION AND SEDIMENTATION CONTROL 01560–1

SPECIFICATIONS (Continued) PAGE NO.

TOC-ii

DIVISION 2 - SITE WORK

Section 02015 – PROTECTION OF UNDERGROUND UTILITIES 02015–1

Section 02100 – CLEARING AND GRUBBING 02100–1

Section 02151 – SHORING 02151–1

Section 02202 – ROCK REMOVAL 02202–1

Section 02210 – SITE GRADING 02210–1

Section 02250 – TRENCH EXCAVATION, BACKFILL AND

COMPACTION

02250–1

Section 02260 – FINISH GRADING 02260–1

Section 02570 – UNDERGROUND PIPING 02570–1

DIVISION 3 - CONCRETE

Section 03100 – CONCRETE FORMWORK 03100–1

Section 03200 – CONCRETE REINFORCEMENT 03200–1

Section 03300 – CAST–IN–PLACE CONCRETE 03300–1

Section 03600 – GROUT 03600–1

DIVISION 4 - MASONRY

Section 04100 – MORTAR 04100–1

Section 04150 – MASONRY ACCESSORIES 04150–1

Section 04200 – UNIT MASONRY 04200–1

DIVISION 5 - METALS

Section 05500 – METAL FABRICATIONS 05500–1

TECHNICAL SPECIFICATIONS

DIVISION 1 - GENERAL REQUIREMENTS

Section 01600 – MATERIALS AND EQUIPMENT 01600–1

Section 01650 – EQUIPMENT, SYSTEMS, AND FACILITY START-UP 01650–1

Section 01650A – EQUIPMENT MANUFACTURER'S CERTIFICATE OF

INSTALLATION, TESTING AND INSTRUCTION

01650A–1

Section 01700 – CONTRACT CLOSEOUT 01700–1

Section 01750 – PRODUCT WARRANTIES 01750–1

TOC-iii

DIVISION 6 – WOOD AND PLASTICS

Section 06100 – ROUGH CARPENTRY 06100–1

DIVISION 7 – THERMAL AND MOISTURE PROTECTION

Section 07190 – VAPOR RETARDERS 07190–1

Section 07200 – INSULATION 07200–1

Section 07900 – JOINT SEALERS 07900–1

DIVISION 8 – DOOR AND WINDOWS

Section 08110 – STEEL DOORS AND FRAMES 08110–1

Section 08330 – COILING DOORS 08330–1

Section 08700 – HARDWARE 08700–1

DIVISION 9 – FINISHES

Section 09250 – WALLBOARD 09250–1

Section 09900 – PAINTING 09900–1

DIVISION 10 – SPECIALTIES

Section 10524 – EMERGENCY SHOWER/EYEWASH STATIONS 10524–1

DIVISION 11 – EQUIPMENT

Section 11340 – WATER SOFTENERS 11340–1

DIVISION 15 – MECHANICAL

Section 15010 – BASIC MECHANICAL REQUIREMENTS 15010–1

Section 15060 – INTERIOR PROCESS PIPING, FITTINGS AND

SPECIALTIES

15060–1

Section 15080 – VALVES AND PIPING SPECIALTIES 15080–1

Section 15090 – SUPPORTS, ANCHORS & SEALS 15090–1

Section 15600 – HEAT GENERATION 15600–1

Section 15800 – AIR DISTRIBUTION 15800–1

TOC-iv

DIVISION 16 - ELECTRICAL

Section 16050 – BASIC ELECTRICAL MATERIALS AND

METHODS

16050–1

Section 16060 – GROUNDING AND BONDING FOR

ELECTRICAL SYSTEMS

16060–1

Section 16073 – HANGERS AND SUPPORTS FOR ELECTRICAL

SYSTEMS

16073–1

Section 16075 – IDENTIFICATION FOR ELECTRICAL

SYSTEMS

16075–1

Section 16120 – LOW-VOLTAGE ELECTRICAL POWER

CONDUCTORS AND CABLES

16120–1

Section 16123 – CONTROL-VOLTAGE ELECTRICAL POWER

CABLES

16123–1

Section 16130 – RACEWAYS AND BOXES FOR ELECTRICAL

SYSTEMS

16130–1

Section 16231 – DIESEL-ENGINE-DRIVEN GENERATOR SETS 16231–1

Section 16415 – TRANSFER SWITCHES 16415–1

Section 16511 – LED INTERIOR LIGHTING 16511–1

Section 16521 – LED EXTERIOR LIGHTING 16521–1

EJCDC® C-200, Instructions to Bidders for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

TOC Page1 of 1

INSTRUCTIONS TO BIDDERS FOR CONSTRUCTION CONTRACT

TABLE OF CONTENTS

Page

Article 1— Defined Terms

Article 2— Bidding Documents

Article 3— Qualifications of Bidders

Article 4— Pre-Bid Conference

Article 5— Site and Other Areas; Existing Site Conditions; Examination of Site; Owner’s Safety Program;

Other Work at the Site

Article 6— Bidder’s Representations and Certifications

Article 7— Interpretations and Addenda

Article 8— Bid Security

Article 9— Contract Times

Article 10— Substitute and “Or Equal” Items

Article 11— Subcontractors, Suppliers, and Others

Article 12— Preparation of Bid

Article 13— Basis of Bid

Article 14— Submittal of Bid

Article 15— Modification and Withdrawal of Bid

Article 16— Opening of Bids

Article 17— Bids to Remain Subject to Acceptance

Article 18— Evaluation of Bids and Award of Contract

Article 19— Bonds and Insurance

Article 20— Signing of Agreement

Article 21— Sales and Use Taxes

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

ARTICLE 1—DEFINED TERMS

1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:

A. Issuing Office—The office from which the Bidding Documents are to be issued, and which registers plan holders. The Issuing Office for this project is New Freedom Borough, 49 East

High Street, New Freedom, PA 17349.

ARTICLE 2—BIDDING DOCUMENTS

2.01 Bidder shall obtain a complete set of Bidding Requirements and proposed Contract Documents

(together, the Bidding Documents). See the Agreement for a list of the Contract Documents. It is

Bidder’s responsibility to determine that it is using a complete set of documents in the preparation of a Bid. Bidder assumes sole responsibility for errors or misinterpretations resulting from the use of incomplete documents, by Bidder itself or by its prospective Subcontractors and Suppliers.

2.02 Bidding Documents are made available for the sole purpose of obtaining Bids for completion of the Project and permission to download or distribution of the Bidding Documents does not confer a license or grant permission or authorization for any other use. Authorization to download documents, or other distribution, includes the right for plan holders to print documents solely for their use, and the use of their prospective Subcontractors and Suppliers, provided the plan holder pays all costs associated with printing or reproduction. Printed documents may not be re-sold under any circumstances.

2.03 Owner has established a Bidding Documents Website as indicated in the Advertisement or invitation to bid. Owner recommends that Bidder register as a plan holder with the Issuing Office at such website, and obtain a complete set of the Bidding Documents from such website. Bidders may rely that sets of Bidding Documents obtained from the Bidding Documents Website are complete, unless an omission is blatant. Registered plan holders will receive Addenda issued by

Owner.

2.04 Plan rooms (including construction information subscription services, and electronic and virtual plan rooms) may distribute the Bidding Documents, or make them available for examination.

Those prospective bidders that obtain an electronic (digital) copy of the Bidding Documents from a plan room are encouraged to register as plan holders from the Bidding Documents Website or

Issuing Office. Owner is not responsible for omissions in Bidding Documents or other documents obtained from plan rooms, or for a Bidder’s failure to obtain Addenda from a plan room.

2.05 Electronic Documents

A. When the Bidding Requirements indicate that electronic (digital) copies of the Bidding

Documents are available, such documents will be made available to the Bidders as Electronic

Documents in the manner specified.

1. Bidding Documents will be provided in Bluebeam or Adobe PDF (Portable Document

Format) (.pdf). It is the intent of the Engineer and Owner that such Electronic

Documents are to be exactly representative of the paper copies of the documents.

However, because the Owner and Engineer cannot totally control the transmission and receipt of Electronic Documents nor the Contractor’s means of reproduction of such

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

documents, the Owner and Engineer cannot and do not guarantee that Electronic

Documents and reproductions prepared from those versions are identical in every manner to the paper copies.

B. Unless otherwise stated in the Bidding Documents, the Bidder may use and rely upon complete sets of Electronic Documents of the Bidding Documents, described in

Paragraph 2.05.A above. However, Bidder assumes all risks associated with differences arising from transmission/receipt of Electronic Documents versions of Bidding Documents and reproductions prepared from those versions and, further, assumes all risks, costs, and responsibility associated with use of the Electronic Documents versions to derive information that is not explicitly contained in printed paper versions of the documents, and for Bidder’s reliance upon such derived information.

ARTICLE 3—QUALIFICATIONS OF BIDDERS

3.01 Bidder is to submit the following information with its Bid to demonstrate Bidder’s qualifications to perform the Work:

A. Written evidence establishing its qualifications such as financial data, previous experience, and present commitments.

B. A written statement that Bidder is authorized to do business in the state where the Project is located, or a written certification that Bidder will obtain such authority prior to the

Effective Date of the Contract.

C. Bidder’s contractor license number, if applicable.

D. Subcontractor and Supplier qualification information.

E. Other required information regarding qualifications.

3.02 A Bidder’s failure to submit required qualification information may disqualify Bidder from receiving an award of the Contract.

3.03 No requirement in this Article 3 to submit information will prejudice the right of Owner to seek additional pertinent information regarding Bidder’s qualifications.

ARTICLE 4—PRE-BID CONFERENCE

4.01 A mandatory pre-bid conference will be held at the time and location indicated in the

Advertisement or invitation to bid. Representatives of Owner and Engineer will be present to discuss the Project. Proposals will not be accepted from Bidders who do not attend the conference. It is each Bidder’s responsibility to sign in at the pre-bid conference to verify its participation. Bidders must sign in using the name of the organization that will be submitting a

Bid. A list of qualified Bidders that attended the pre-bid conference and are eligible to submit a

Bid for this Project will be issued in an Addendum.

4.02 Information presented at the pre-Bid conference does not alter the Contract Documents. Owner will issue Addenda to make any changes to the Contract Documents that result from discussions

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

at the pre-Bid conference. Information presented, and statements made at the pre-bid conference will not be binding or legally effective unless incorporated in an Addendum.

ARTICLE 5—SITE AND OTHER AREAS; EXISTING SITE CONDITIONS; EXAMINATION OF SITE; OWNER’S

SAFETY PROGRAM; OTHER WORK AT THE SITE

5.01 Site and Other Areas

A. The Site is identified in the Bidding Documents. By definition, the Site includes rights-of-way, easements, and other lands furnished by Owner for the use of the Contractor. Any additional lands required for temporary construction facilities, construction equipment, or storage of materials and equipment, and any access needed for such additional lands, are to be obtained and paid for by Contractor.

5.02 Existing Site Conditions

A. Subsurface and Physical Conditions; Hazardous Environmental Conditions

1. The Supplementary Conditions identify the following regarding existing conditions at or adjacent to the Site:

a. Those reports of explorations and tests of subsurface conditions at or adjacent to the Site that contain Technical Data.

b. Those drawings known to Owner of existing physical conditions at or adjacent to the Site, including those drawings depicting existing surface or subsurface structures at or adjacent to the Site (except Underground Facilities), that contain

Technical Data.

c. Reports and drawings known to Owner relating to Hazardous Environmental

Conditions that have been identified at or adjacent to the Site.

d. Technical Data contained in such reports and drawings.

2. Owner will make copies of reports and drawings referenced above available to any

Bidder on request. These reports and drawings are not part of the Contract Documents, but the Technical Data contained therein upon whose accuracy Bidder is entitled to rely, as provided in the General Conditions, has been identified and established in the

Supplementary Conditions. Bidder is responsible for any interpretation or conclusion

Bidder draws from any Technical Data or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.

3. If the Supplementary Conditions do not identify Technical Data, the default definition of

Technical Data set forth in Article 1 of the General Conditions will apply.

B. Underground Facilities: Underground Facilities are shown or indicated on the Drawings, pursuant to Paragraph 5.05 of the General Conditions, and not in the drawings referred to in

Paragraph 5.02.A of these Instructions to Bidders. Information and data regarding the presence or location of Underground Facilities are not intended to be categorized, identified, or defined as Technical Data.

5.03 Other Site-related Documents

A. No other Site-related documents are available.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

5.04 Site Visit and Testing by Bidders

A. Bidder is required to visit the Site and conduct a thorough visual examination of the Site and adjacent areas. During the visit the Bidder must not disturb any ongoing operations at the

Site.

B. An optional Site visit is scheduled following the pre-bid conference. The Site address is 34 S.

Front Street, New Freedom, PA 17349.

C. Bidders visiting the Site are required to arrange their own transportation to the Site.

D. All access to the Site other than during a regularly scheduled Site visit must be coordinated through the following Owner contact for visiting the Site: Jake Smith, 717-887-6497, publicworks@newfreedomboro.org. Bidder must conduct the required Site visit during normal working hours.

E. Bidder is not required to conduct any subsurface testing, or exhaustive investigations of Site conditions.

F. On request, and to the extent Owner has control over the Site, and schedule permitting, the

Owner will provide Bidder general access to the Site to conduct such additional examinations, investigations, explorations, tests, and studies as Bidder deems necessary for preparing and submitting a successful Bid. Owner will not have any obligation to grant such access if doing so is not practical because of existing operations, security or safety concerns, or restraints on Owner’s authority regarding the Site. Bidder is responsible for establishing access needed to reach specific selected test sites.

G. Bidder must comply with all applicable Laws and Regulations regarding excavation and location of utilities, obtain all permits, and comply with all terms and conditions established by Owner or by property owners or other entities controlling the Site with respect to schedule, access, existing operations, security, liability insurance, and applicable safety programs.

H. Bidder must fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies.

ARTICLE 6—BIDDER’S REPRESENTATIONS AND CERTIFICATIONS

6.01 Express Representations and Certifications in Bid Form, Agreement

A. The Bid Form that each Bidder will submit contains express representations regarding the

Bidder’s examination of Project documentation, Site visit, and preparation of the Bid, and certifications regarding lack of collusion or fraud in connection with the Bid. Bidder should review these representations and certifications, and assure that Bidder can make the representations and certifications in good faith, before executing and submitting its Bid.

B. If Bidder is awarded the Contract, Bidder (as Contractor) will make similar express representations and certifications when it executes the Agreement.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

ARTICLE 7—INTERPRETATIONS AND ADDENDA

7.01 Bidder shall submit all questions about the meaning or intent of the Bidding Documents to

Engineer in writing. Contact information and submittal procedures for such questions are as follows:

A. All questions must be submitted via the PennBid Bidding Documents Website

(https://pennbid.bonfirehub.com).

7.02 Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda delivered to all registered plan holders. Questions received less than seven days prior to the date for opening of Bids may not be answered.

7.03 Only responses set forth in an Addendum or the questions and answers tab on the PennBid site for the project will be binding. Oral and other interpretations or clarifications will be without legal effect.

ARTICLE 8—BID SECURITY

8.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of 10 percent of Bidder’s maximum Bid price (determined by adding the base bid and all alternates) and in the form of a Bid bond issued by a surety meeting the requirements of Paragraph 6.01 of the General

Conditions. Such Bid bond will be issued in the form included in the Bidding Documents.

8.02 The Bid security of the apparent Successful Bidder will be retained until Owner awards the contract to such Bidder, and such Bidder has executed the Contract, furnished the required

Contract security, and met the other conditions of the Notice of Award, whereupon the Bid security will be released. If the Successful Bidder fails to execute and deliver the Contract and furnish the required Contract security within 15 days after the Notice of Award, Owner may consider Bidder to be in default, annul the Notice of Award, and the Bid security of that Bidder will be forfeited, in whole in the case of a penal sum bid bond, and to the extent of Owner’s damages in the case of a damages-form bond. Such forfeiture will be Owner’s exclusive remedy if

Bidder defaults.

8.03 The Bid security of other Bidders that Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of 7 days after the Effective Date of the

Contract or 61 days after the Bid opening, whereupon Bid security furnished by such Bidders will be released.

8.04 Bid security of other Bidders that Owner believes do not have a reasonable chance of receiving the award will be released within 7 days after the Bid opening.

ARTICLE 9—CONTRACT TIMES

9.01 The number of days within which, or the dates by which, the Work is to be (a) substantially completed and (b) ready for final payment, and (c) Milestones (if any) are to be achieved, are set forth in the Agreement.

9.02 Provisions for liquidated damages, if any, for failure to timely attain a Milestone, Substantial

Completion, or completion of the Work in readiness for final payment, are set forth in the

Agreement.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

ARTICLE 10—SUBSTITUTE AND “OR EQUAL” ITEMS

10.01 The Contract for the Work, as awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents without consideration during the bidding and Contract award process of possible substitute or “or-equal” items. In cases in which the Contract allows the Contractor to request that Engineer authorize the use of a substitute or “or-equal” item of material or equipment, application for such acceptance may not be made to and will not be considered by Engineer until after the Effective Date of the Contract.

10.02 All prices that Bidder sets forth in its Bid will be based on the presumption that the Contractor will furnish the materials and equipment specified or described in the Bidding Documents, as supplemented by Addenda. Any assumptions regarding the possibility of post-Bid approvals of

“or-equal” or substitution requests are made at Bidder’s sole risk.

ARTICLE 11—SUBCONTRACTORS, SUPPLIERS, AND OTHERS

11.01 A Bidder must be prepared to retain specific Subcontractors and Suppliers for the performance of the Work if required to do so by the Bidding Documents or in the Specifications. If a prospective

Bidder objects to retaining any such Subcontractor or Supplier and the concern is not relieved by an Addendum, then the prospective Bidder should refrain from submitting a Bid.

11.02 The Contractor must subcontract with New Freedom Borough’s Systems Integrator; 713 Range

End Road, Dillsburg, PA 17019; (717) 432-5511; for the following work:

A. All instrumentation and controls work, and associated systems integration.

ARTICLE 12—PREPARATION OF BID

12.01 The Bid Form is included with the Bidding Documents.

A. All blanks on the Bid Form must be completed in ink and the Bid Form signed in ink. Erasures or alterations must be initialed in ink by the person signing the Bid Form. A Bid price must be indicated for each section, Bid item, alternate, adjustment unit price item, and unit price item listed therein.

B. If the Bid Form expressly indicates that submitting pricing on a specific alternate item is optional, and Bidder elects to not furnish pricing for such optional alternate item, then Bidder may enter the words “No Bid” or “Not Applicable.”

12.02 If Bidder has obtained the Bidding Documents as Electronic Documents, then Bidder shall prepare its Bid on a paper copy of the Bid Form printed from the Electronic Documents version of the

Bidding Documents. The printed copy of the Bid Form must be clearly legible, printed on 8½ inch by 11-inch paper and as closely identical in appearance to the Electronic Document version of the

Bid Form as may be practical. The Owner reserves the right to accept Bid Forms which nominally vary in appearance from the original paper version of the Bid Form, providing that all required information and submittals are included with the Bid.

12.03 A Bid by a corporation must be executed in the corporate name by a corporate officer (whose title must appear under the signature), accompanied by evidence of authority to sign. The corporate address and state of incorporation must be shown.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

12.04 A Bid by a partnership must be executed in the partnership name and signed by a partner (whose title must appear under the signature), accompanied by evidence of authority to sign. The official address of the partnership must be shown.

12.05 A Bid by a limited liability company must be executed in the name of the firm by a member or other authorized person and accompanied by evidence of authority to sign. The state of formation of the firm and the official address of the firm must be shown.

12.06 A Bid by an individual must show the Bidder’s name and official address.

12.07 A Bid by a joint venture must be executed by an authorized representative of each joint venturer in the manner indicated on the Bid Form. The joint venture must have been formally established prior to submittal of a Bid, and the official address of the joint venture must be shown.

12.08 All names must be printed in ink below the signatures.

12.09 The Bid must contain an acknowledgment of receipt of all Addenda, the numbers of which must be filled in on the Bid Form.

12.10 Postal and e-mail addresses and telephone number for communications regarding the Bid must be shown.

12.11 The Bid must contain evidence of Bidder’s authority to do business in the state where the Project is located, or Bidder must certify in writing that it will obtain such authority within the time for acceptance of Bids and attach such certification to the Bid.

ARTICLE 13—BASIS OF BID

13.01 Lump Sum

A. Bidders must submit a Bid on a lump sum basis as set forth in the Bid Form.

13.02 Allowances

A. For cash allowances the Bid price must include such amounts as the Bidder deems proper for

Contractor's overhead, costs, profit, and other expenses on account of cash allowances, if any, named in the Contract Documents, in accordance with Paragraph 13.02.B of the General

Conditions.

ARTICLE 14—SUBMITTAL OF BID

14.01 The Bidding Documents include one separate unbound copy of the Bid Form, and, if required, the

Bid Bond Form. The unbound copy of the Bid Form is to be completed and submitted with the Bid security and the other documents required to be submitted under the terms of Article 2 of the

Bid Form.

14.02 A Bid must be received no later than the date and time prescribed and at the place indicated in the Advertisement or invitation to bid and must be accompanied by the Bid security and other required documents.

14.03 Bids received after the date and time prescribed for the opening of bids, or not submitted at the correct location or in the designated manner, will not be accepted and will be returned to the

Bidder unopened.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

ARTICLE 15—MODIFICATION AND WITHDRAWAL OF BID

15.01 An unopened Bid may be withdrawn prior to Bid opening by using PennBid’s “Recall Bid” function.

15.02 If a Bidder wishes to modify its Bid prior to Bid opening, Bidder must withdraw its initial Bid in the manner specified in Paragraph 15.01 and submit a new Bid prior to the date and time for the opening of Bids.

15.03 Withdrawal of Bid after Bids are opened shall only be allowed in accordance with Pennsylvania’s

Public Contract Bid Withdrawal Law (73 P.S. § 1601 et seq.).

ARTICLE 16—OPENING OF BIDS

16.01 Bids will be “opened” at the time and place indicated in the advertisement or invitation to bid and, unless obviously non-responsive, made publicly viewable on PennBid. An abstract of the amounts of the base Bids and major alternates, if any, will be made available to Bidders after the opening of Bids.

ARTICLE 17—BIDS TO REMAIN SUBJECT TO ACCEPTANCE

17.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.

ARTICLE 18—EVALUATION OF BIDS AND AWARD OF CONTRACT

18.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner also reserves the right to waive all minor

Bid informalities not involving price, time, or changes in the Work.

18.02 Owner will reject the Bid of any Bidder that Owner finds, after reasonable inquiry and evaluation, to not be responsible.

18.03 If Bidder purports to add terms or conditions to its Bid, takes exception to any provision of the

Bidding Documents, or attempts to alter the contents of the Contract Documents for purposes of the Bid, whether in the Bid itself or in a separate communication to Owner or Engineer, then

Owner will reject the Bid as nonresponsive.

18.04 If Owner awards the contract for the Work, such award will be to the responsible Bidder submitting the lowest responsive Bid.

18.05 In evaluating Bids, Owner will consider whether the Bids comply with the prescribed requirements, and such alternates, unit prices, and other data, as may be requested in the Bid

Form or prior to the Notice of Award.

18.06 In evaluating whether a Bidder is responsible, Owner will consider the qualifications of the Bidder and may consider the qualifications and experience of Subcontractors and Suppliers proposed for

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

those portions of the Work for which the identity of Subcontractors and Suppliers must be submitted as provided in the Bidding Documents.

18.07 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders and any proposed Subcontractors or Suppliers.

ARTICLE 19—BONDS AND INSURANCE

19.01 Article 6 of the General Conditions, as may be modified by the Supplementary Conditions, sets forth Owner’s requirements as to performance and payment bonds, other required bonds (if any), and insurance. When the Successful Bidder delivers the executed Agreement to Owner, it must be accompanied by required bonds and insurance documentation.

19.02 Article 8, Bid Security, of these Instructions, addresses any requirements for providing bid bonds as part of the bidding process.

ARTICLE 20—SIGNING OF AGREEMENT

20.01 When Owner issues a Notice of Award to the Successful Bidder, it will be accompanied by the unexecuted counterparts of the Agreement along with the other Contract Documents as identified in the Agreement. Within 15 days thereafter, Successful Bidder must execute and deliver the required number of counterparts of the Agreement and any bonds and insurance documentation required to be delivered by the Contract Documents to Owner. Within 10 days thereafter, Owner will deliver one fully executed counterpart of the Agreement to Successful

Bidder, together with printed and electronic copies of the Contract Documents as stated in

Paragraph 2.02 of the General Conditions.

ARTICLE 21—SALES AND USE TAXES

21.01 Owner is exempt from payment of sales and compensating use taxes of the Commonwealth of

Pennsylvania and of cities and counties thereof on materials to be incorporated into the Work.

Refer to Paragraph SC-7.10 of the Supplementary Conditions for additional information.

EJCDC® C-410, Bid Form for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

BID FORM FOR CONSTRUCTION CONTRACT

The terms used in this Bid with initial capital letters have the meanings stated in the Instructions to

Bidders, the General Conditions, and the Supplementary Conditions.

ARTICLE 1—OWNER AND BIDDER

1.01 This Bid is submitted to: New Freedom Borough, 49 East High Street, New Freedom, PA 17349.

1.02 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents.

ARTICLE 2—ATTACHMENTS TO THIS BID

2.01 The following documents are submitted with and made a condition of this Bid:

A. Required Bid security;

B. List of Proposed Subcontractors;

C. List of Proposed Suppliers;

D. Evidence of authority to do business in the state of the Project; or a written covenant to obtain such authority within the time for acceptance of Bids and;

E. Required Bidder Qualification Statement with supporting data.

ARTICLE 3—BASIS OF BID—LUMP SUM BID AND UNIT PRICES

3.01 Lump Sum Bids

A. Bidder will complete the Work in accordance with the Contract Documents for the following lump sum (stipulated) price:

1. Lump Sum Price (Single Lump Sum)

Lump Sum Bid Price $

ARTICLE 4—TIME OF COMPLETION

4.01 Bidder agrees that the Work will be substantially complete and will be completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before the dates or within the number of calendar days indicated in the Agreement.

4.02 Bidder accepts the provisions of the Agreement as to liquidated damages.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

ARTICLE 5—BIDDER’S ACKNOWLEDGEMENTS: ACCEPTANCE PERIOD, INSTRUCTIONS, AND RECEIPT OF

ADDENDA

5.01 Bid Acceptance Period

A. This Bid will remain subject to acceptance for 60 days after the Bid opening, or for such longer period of time that Bidder may agree to in writing upon request of Owner.

5.02 Instructions to Bidders

A. Bidder accepts all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing with the disposition of Bid security.

5.03 Receipt of Addenda

A. Bidder hereby acknowledges receipt of the following Addenda:

Addendum Number Addendum Date

ARTICLE 6—BIDDER’S REPRESENTATIONS AND CERTIFICATIONS

6.01 Bidder’s Representations

A. In submitting this Bid, Bidder represents the following:

1. Bidder has examined and carefully studied the Bidding Documents, including Addenda.

2. Bidder has visited the Site, conducted a thorough visual examination of the Site and adjacent areas, and become familiar with the general, local, and Site conditions that may affect cost, progress, and performance of the Work.

3. Bidder is familiar with all Laws and Regulations that may affect cost, progress, and performance of the Work.

4. Bidder has considered the information known to Bidder itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; and the Bidding Documents; with respect to the effect of such information and observations on (a) the cost, progress, and performance of the Work; (b) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, if selected as Contractor; and

(c) Bidder’s (Contractor’s) safety precautions and programs.

5. Based on the information and observations referred to in the preceding paragraph, Bidder agrees that no further examinations, investigations, explorations, tests, studies, or data are necessary for the performance of the Work at the Contract Price, within the Contract

Times, and in accordance with the other terms and conditions of the Contract.

6. Bidder is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

7. Bidder has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents, and of discrepancies between Site conditions and the Contract Documents, and the written resolution thereof by Engineer is acceptable to Contractor.

8. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.

9. The submission of this Bid constitutes an incontrovertible representation by Bidder that without exception the Bid and all prices in the Bid are premised upon performing and furnishing the Work required by the Bidding Documents.

6.02 Bidder’s Certifications

A. The Bidder certifies the following:

1. This Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any collusive agreement or rules of any group, association, organization, or corporation.

2. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid.

3. Bidder has not solicited or induced any individual or entity to refrain from bidding.

4. Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract. For the purposes of this Paragraph 6.02.A:

a. Corrupt practice means the offering, giving, receiving, or soliciting of anything of value likely to influence the action of a public official in the bidding process.

b. Fraudulent practice means an intentional misrepresentation of facts made (a) to influence the bidding process to the detriment of Owner, (b) to establish bid prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition.

c. Collusive practice means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish bid prices at artificial, non-competitive levels.

d. Coercive practice means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

BIDDER hereby submits this Bid as set forth above:

Bidder:

(typed or printed name of organization)

By:

(individual’s signature)

Name:

(typed or printed)

Title:

(typed or printed)

Date:

(typed or printed)

If Bidder is a corporation, a partnership, or a joint venture, attach evidence of authority to sign.

Attest:

(individual’s signature)

Name:

(typed or printed)

Title:

(typed or printed)

Date:

Address for giving notices:

Bidder’s Contact:

Name:

(typed or printed)

Title:

(typed or printed)

Phone:

Email:

Address:

EJCDC® C-430, Bid Bond (Penal Sum Form).

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

BID BOND (PENAL SUM FORM)

Bidder Surety

Name: _________________________________ Name: _________________________________

Address (principal place of business): Address (principal place of business):

Owner Bid

Name: New Freedom Borough Project (name and location):

Address (principal place of business): Wellhouse No. 1 Upgrades

34 S. Front Street

New Freedom, PA 17349 49 East High Street

New Freedom, PA 17349

Bid Due Date: September 2, 2026

Bond

Penal Sum: 10% of the Bid Amount

Date of Bond: ____________________

Surety and Bidder, intending to be legally bound hereby, subject to the terms set forth in this Bid Bond, do each cause this Bid Bond to be duly executed by an authorized officer, agent, or representative.

Bidder Surety

(Full formal name of Bidder) (Full formal name of Surety) (corporate seal)

By: By:

(Signature) (Signature) (Attach Power of Attorney)

Name: Name:

(Printed or typed) (Printed or typed)

Title: Title:

Attest: Attest:

(Signature) (Signature)

Name: Name:

(Printed or typed) (Printed or typed)

Title: Title:

Notes: (1) Note: Addresses are to be used for giving any required notice. (2) Provide execution by any additional parties, such as joint venturers, if necessary.

EJCDC® C-430, Bid Bond (Penal Sum Form).

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

1. Bidder and Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors, and assigns to pay to Owner upon default of Bidder the penal sum set forth on the face of this Bond.

Payment of the penal sum is the extent of Bidder’s and Surety’s liability. Recovery of such penal sum under the terms of this Bond will be Owner’s sole and exclusive remedy upon default of Bidder.

2. Default of Bidder occurs upon the failure of Bidder to deliver within the time required by the Bidding

Documents (or any extension thereof agreed to in writing by Owner) the executed Agreement required by the Bidding Documents and any performance and payment bonds required by the Bidding Documents.

3. This obligation will be null and void if:

3.1. Owner accepts Bidder’s Bid and Bidder delivers within the time required by the Bidding Documents

(or any extension thereof agreed to in writing by Owner) the executed Agreement required by the

Bidding Documents and any performance and payment bonds required by the Bidding Documents, or

3.2. All Bids are rejected by Owner, or

3.3. Owner fails to issue a Notice of Award to Bidder within the time specified in the Bidding Documents

(or any extension thereof agreed to in writing by Bidder and, if applicable, consented to by Surety when required by Paragraph 5 hereof).

4. Payment under this Bond will be due and payable upon default of Bidder and within 30 calendar days after receipt by Bidder and Surety of written notice of default from Owner, which notice will be given with reasonable promptness, identifying this Bond and the Project and including a statement of the amount due.

5. Surety waives notice of any and all defenses based on or arising out of any time extension to issue Notice of Award agreed to in writing by Owner and Bidder, provided that the total time for issuing Notice of Award including extensions does not in the aggregate exceed 120 days from the Bid due date without Surety’s written consent.

6. No suit or action will be commenced under this Bond prior to 30 calendar days after the notice of default required in Paragraph 4 above is received by Bidder and Surety, and in no case later than one year after the Bid due date.

7. Any suit or action under this Bond will be commenced only in a court of competent jurisdiction located in the state in which the Project is located.

8. Notices required hereunder must be in writing and sent to Bidder and Surety at their respective addresses shown on the face of this Bond. Such notices may be sent by personal delivery, commercial courier, or by

United States Postal Service registered or certified mail, return receipt requested, postage pre-paid, and will be deemed to be effective upon receipt by the party concerned.

9. Surety shall cause to be attached to this Bond a current and effective Power of Attorney evidencing the authority of the officer, agent, or representative who executed this Bond on behalf of Surety to execute, seal, and deliver such Bond and bind the Surety thereby.

10. This Bond is intended to conform to all applicable statutory requirements. Any applicable requirement of any applicable statute that has been omitted from this Bond will be deemed to be included herein as if set forth at length. If any provision of this Bond conflicts with any applicable statute, then the provision of said statute governs and the remainder of this Bond that is not in conflict therewith continues in full force and effect.

11. The term “Bid” as used herein includes a Bid, offer, or proposal as applicable.

EJCDC C-451, Qualifications Statement.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

ARTICLE 1—GENERAL INFORMATION

1.01 Provide contact information for the Business:

Legal Name of Business:

Corporate Office

Name: Phone number:

Title: Email address:

Business address of corporate office:

Local Office

Name: Phone number:

Title: Email address:

Business address of local office:

1.02 Provide information on the Business’s organizational structure:

Form of Business: ☐ Sole Proprietorship ☐ Partnership ☐ Corporation

☐ Limited Liability Company ☐ Joint Venture comprised of the following companies:

1.

2.

3.

Provide a separate Qualification Statement for each Joint Venturer.

Date Business was formed: State in which Business was formed:

Is this Business authorized to operate in the Project location? ☐ Yes ☐ No ☐ Pending

1.03 Identify all businesses that own Business in whole or in part (25% or greater), or that are wholly or partly (25% or greater) owned by Business:

Name of business: Affiliation:

Address:

Name of business: Affiliation:

Address:

Name of business: Affiliation:

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

1.04 Provide information regarding the Business’s officers, partners, and limits of authority.

Name: Title:

Authorized to sign contracts: ☐ Yes ☐ No Limit of Authority: $

Name: Title:

Authorized to sign contracts: ☐ Yes ☐ No Limit of Authority: $

Name: Title:

Authorized to sign contracts: ☐ Yes ☐ No Limit of Authority: $

Name: Title:

ARTICLE 2—LICENSING

2.01 Provide information regarding licensure for Business:

Name of License:

Licensing Agency:

License No: Expiration Date:

Name of License:

Licensing Agency:

License No: Expiration Date:

ARTICLE 3—DIVERSE BUSINESS CERTIFICATIONS

3.01 Provide information regarding Business’s Diverse Business Certification, if any. Provide evidence of current certification.

Certification Certifying Agency Certification

Date

☐ Disadvantaged Business Enterprise

☐ Minority Business Enterprise

☐ Woman-Owned Business Enterprise

☐ Small Business Enterprise

☐ Disabled Business Enterprise

☐ Veteran-Owned Business Enterprise

☐ Service-Disabled Veteran-Owned Business

☐ HUBZone Business (Historically

Underutilized) Business

☐ Other

☐ None

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

ARTICLE 4—SAFETY

4.01 Provide information regarding Business’s safety organization and safety performance.

Name of Business’s Safety Officer:

Safety Certifications

Certification Name Issuing Agency Expiration

4.02 Provide Worker’s Compensation Insurance Experience Modification Rate (EMR), Total Recordable

Frequency Rate (TRFR) for incidents, and Total Number of Recorded Manhours (MH) for the last

3 years and the EMR, TRFR, and MH history for the last 3 years of any proposed Subcontractor(s) that will provide Work valued at 10% or more of the Contract Price. Provide documentation of the EMR history for Business and Subcontractor(s).

Year

Company EMR TRFR MH EMR TRFR MH EMR TRFR MH

ARTICLE 5—FINANCIAL

5.01 Provide information regarding the Business’s financial stability. Provide the most recent audited financial statement, and if such audited financial statement is not current, also provide the most current financial statement.

Financial Institution:

Business address:

Date of Business’s most recent financial statement: ☐ Attached

Date of Business’s most recent audited financial statement: ☐ Attached

Financial indicators from the most recent financial statement

Contractor’s Current Ratio (Current Assets ÷ Current Liabilities)

Contractor’s Quick Ratio ((Cash and Cash Equivalents + Accounts Receivable +

Short Term Investments) ÷ Current Liabilities)

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

ARTICLE 6—SURETY INFORMATION

6.01 Provide information regarding the surety company that will issue required bonds on behalf of the

Business, including but not limited to performance and payment bonds.

Surety Name:

Surety is a corporation organized and existing under the laws of the state of:

Is surety authorized to provide surety bonds in the Project location? ☐ Yes ☐ No

Is surety listed in “Companies Holding Certificates of Authority as Acceptable Sureties on

Federal Bonds and as Acceptable Reinsuring Companies” published in Department Circular 570

(as amended) by the Bureau of the Fiscal Service, U.S. Department of the Treasury?

☐ Yes ☐ No

Mailing Address

(principal place of business):

Physical Address

Phone (main): Phone (claims):

ARTICLE 7—INSURANCE

7.01 Provide information regarding Business’s insurance company(s), including but not limited to its

Commercial General Liability carrier. Provide information for each provider.

Name of insurance provider, and type of policy (CLE, auto, etc.):

Insurance Provider Type of Policy (Coverage Provided)

Are providers licensed or authorized to issue policies in the Project location? ☐ Yes ☐ No

Does provider have an A.M. Best Rating of A-VII or better? ☐ Yes ☐ No

Mailing Address

Physical Address

Phone (main): Phone (claims):

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

ARTICLE 8—CONSTRUCTION EXPERIENCE

8.01 Provide information that will identify the overall size and capacity of the Business.

Average number of current full-time employees:

Estimate of revenue for the current year:

Estimate of revenue for the previous year:

8.02 Provide information regarding the Business’s previous contracting experience.

Years of experience with projects like the proposed project:

As a general contractor: As a joint venturer:

Has Business, or a predecessor in interest, or an affiliate identified in Paragraph 1.03:

Been disqualified as a bidder by any local, state, or federal agency within the last 5 years?

☐ Yes ☐ No

Been barred from contracting by any local, state, or federal agency within the last 5 years?

☐ Yes ☐ No

Been released from a bid in the past 5 years? ☐ Yes ☐ No

Defaulted on a project or failed to complete any contract awarded to it? ☐ Yes ☐ No

Refused to construct or refused to provide materials defined in the contract documents or in a change order? ☐ Yes ☐ No

Been a party to any currently pending litigation or arbitration? ☐ Yes ☐ No

Provide full details in a separate attachment if the response to any of these questions is Yes.

8.03 List all projects currently under contract in Schedule A and provide indicated information.

8.04 List a minimum of three and a maximum of six projects completed in the last 5 years in Schedule B and provide indicated information to demonstrate the Business’s experience with projects similar in type and cost of construction.

8.05 In Schedule C, provide information on key individuals whom…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .