About this file
This document set comprises the bidding requirements and contract forms for the City of Orem, Utah's Well #1R Development Project, with Hansen, Allen & Luce, Inc. serving as the project engineer and geologist. The project involves dual swab development and test pumping of a production well using a cable tool rig, with simultaneous swabbing and pumping to maximize well efficiency while recording static water level, pumping water level, flow rate, and sand production. The well features anticipated 20-inch diameter casing with approximately 300 feet of screen to an anticipated depth of 800 feet. The pre-bid conference is scheduled for 3:00 PM on October 8, 2026, at the City of Orem Public Works Building located at 1450 West 550 North, Orem, Utah 84057, with attendance strongly recommended. Bids will be received via the Utah Public Procurement Portal (U3P/Bonfire) until 3:00 PM local time on October 22, 2026. The contract specifies substantial completion within 90 days and final completion within 120 days of the notice to proceed.
Evaluation criteria weight qualifications, experience, and references at 60 percent; cost at 15 percent; and scheduling and availability at 25 percent. The bid schedule includes seven line items: mobilization/demobilization, dual swab well development (300 hours at hourly rate), furnish and install test pump equipment with 5,000 gpm capacity set at 350-foot depth, well development and pump testing (160 hours at hourly rate), well disinfection, well bailing (8 hours at hourly rate), and video well log, all submitted on a unit price basis. Liquidated damages are assessed at $200 per day for delays beyond substantial completion and final payment dates. No bid security is required, though a 5 percent bid bond was initially referenced in the advertisement. A 95 percent progress payment with 5 percent retainage applies during construction, increasing to 97.5 percent upon substantial completion. The City of Orem reserves the right to reject any or all bids submitted. Bidding documents are available in electronic PDF format from the engineer on or after September 30, 2026, with questions directed to Scott Greenhalgh, P.G., Project Geologist, at Hansen, Allen & Luce, Inc.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CITY OF OREM
WELL #1R
DEVELOPMENT PROJECT
CONTRACT DOCUMENTS
September 2026
09/2026 INSIDE COVER
119.11.100 PAGE 00 00 01 - 1
City of Orem
Well #1R Development Project
BIDDING DOCUMENTS
Project Geologist
HANSEN, ALLEN, & LUCE, INC.
Consultants/Engineers 859 W. South Jordan Pkwy, Ste. 200
South Jordan, UT 84095
(801) 566-5599
10/2/2026
09/2026 INSIDE COVER
119.11.100 PAGE 00 00 01 - 2
THIS PAGE INTENTIONALLY LEFT BLANK
09/2026 TABLE OF CONTENTS
119.11.100 PAGE 00 00 03 - 1
TABLE OF CONTENTS
SECTION PAGE(S)
00 00 01 Inside Cover ........................................................................................ 00 00 01 - 1 to 2 00 00 03 Table of Contents ................................................................................ 00 00 03 - 1 to 2
PART 1 - BIDDING REQUIREMENTS
00 00 30 Advertisement for Bid ........................................................................ 00 00 30 - 1 to 2 00 10 00 Instructions to Bidders ....................................................................... 00 10 00 - 1 to 10 00 30 00 Bid Form ........................................................................................... 00 30 00 - 1 to 6
PART 2 - CONTRACT FORMS
00 51 00 Notice of Award ................................................................................. 00 51 00 - 1 to 2 00 52 00 Agreement ........................................................................................ 00 52 00 - 1 to 8 00 53 00 Change Order ................................................................................... 00 53 00 - 1 to 2 00 55 00 Notice to Proceed.............................................................................. 00 55 00 - 1 to 2 00 62 50 Certificate of Substantial Completion................................................. 00 62 50 - 1 to 2
PART 3 - CONTRACT CONDITIONS
00 70 00 General Conditions ........................................................................... 00 70 00 - 1 to 70 00 80 00 Supplementary Conditions ................................................................ 00 80 00 - 1 to 10
PART 4 - TECHNICAL SPECIFICATIONS
DIVISION 1 - GENERAL REQUIREMENTS
01 11 00 Summary of Work ............................................................................... 01 11 00 - 1 to 2 01 14 00 Contractor Use of Premises ................................................................ 01 14 00 - 1 to 2 01 22 00 Measurement and Payment ................................................................ 01 22 00 - 1 to 4 01 32 00 Progress Schedules ............................................................................ 01 32 00 - 1 to 2 01 33 00 Submittal Procedures .......................................................................... 01 33 00 - 1 to 4 01 41 26 Permit Requirements .......................................................................... 01 41 26 - 1 to 2 01 45 00 Quality Control .................................................................................... 01 45 00 - 1 to 2 01 50 00 Temporary Construction Utilities ......................................................... 01 50 00 - 1 to 4 01 71 13 Mobilization ......................................................................................... 01 71 13 - 1 to 4 01 71 33 Protection of Existing Facilities ............................................................ 01 71 33 - 1 to 4 01 77 00 Project Closeout .................................................................................. 01 77 00 - 1 to 2
DIVISION 02 - NOT USED
DIVISION 03 – NOT USED
DIVISIONS 04 THROUGH 32 - NOT USED
TABLE OF CONTENTS (CONTD)
SECTION PAGE(S)
09/2026 TABLE OF CONTENTS
119.11.100 PAGE 00 00 03 - 2
DIVISION 33 - UTILITIES
33 21 55 Well Development ............................................................................... 33 21 55 - 1 to 6 33 21 60 Well Disinfection ................................................................................. 33 21 60 - 1 to 2
DIVISIONS 34 THROUGH 48 - NOT USED
FIGURES
Figure 1. Orem Well #1R Location Map Figure 2. Orem Well #1R Preliminary Well Schematic
PART 1
BIDDING REQUIREMENTS
09/2026 ADVERTISEMENT FOR BID
119.11.100 PAGE 00 00 30 - 1
DOCUMENT 00 00 30
ADVERTISEMENT FOR BID
CITY OF OREM
56 North State Orem, UT 84057
Bids will be received by Orem City via the Utah Public Procurement Portal (U3P (Bonfire) - link below) for the OREM CITY WELL #1R DEVELOPMENT PROJECT until 3:00 p.m. (local time) , October 22, 2026.
Description and Scope of Work: Dual Swab Development and Test Pumping of a production well (Well #1R) using a Cable Tool Rig. The well will be swabbed and pumped simultaneously to maximize the efficiency of the well while recording parameters such as:
static water level, pumping water level, flow rate while pumping and sand production. The anticipated construction of the well is 20-inch diameter casing, with approximately 300 feet of screen, to an anticipated depth of 800 feet. Figure 1 shows the location and site plan of the well. Figure 2 shows the anticipated well design, and Figure 3 shows the well-head completion.
A PRE-BID CONFERENCE will be held at 3:00 PM on October 8, 2026, at the City of Orem Public Works Building located at 1450 West 550 North, Orem, UT 84057. Attendance at the pre-bid conference is strongly recommended.
All questions related to the project shall be directed to the ENGINEER/GEOLOGIST on or before October 21, 2026.
HANSEN, ALLEN & LUCE, INC.
859 W. South Jordan Pkwy, Ste 200 South Jordan, Utah 84095 Attention: Scott Greenhalgh, P.G., Project Geologist Phone: 801-995-0324 Email: scottg@HALengineers.com
BIDDING DOCUMENTS may be obtained in electronic PDF format from the ENGINEER on or after September 30, 2026.
A five percent (5%) Bid Bond will be required.
City of Orem reserves the right to reject any or all bids submitted.
09/2026 ADVERTISEMENT FOR BID
119.11.100 PAGE 00 00 30 - 2
09/2026 INSTRUCTIONS TO BIDDERS
119.11.100 00 10 00-1
DOCUMENT 00 10 00
INSTRUCTIONS TO BIDDERS
ARTICLE 1 - DEFINED TERMS
1.01 Terms used in these Instructions to Bidders will have the meanings indicated in the
General Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:
A. Issuing Office--The office from which the Bidding Documents are to be issued and where the bidding procedures are to be administered.
ARTICLE 2 - COPIES OF BIDDING DOCUMENTS
2.01 Complete sets of the Bidding Documents may be obtained from the Issuing Office.
2.02 Complete sets of Bidding Documents must be used in preparing Bids; neither Owner nor
Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents.
2.03 Owner and Engineer in making copies of Bidding Documents available on the above terms do so only for the purpose of obtaining Bids for the Work and do not confer a license or grant for any other use.
ARTICLE 3 - NOT USED
ARTICLE 4 - EXAMINATION OF BIDDING DOCUMENTS, OTHER RELATED DATA, AND
SITE
4.01 Subsurface and Physical Conditions
A. The Supplementary Conditions identify:
1. Those reports of explorations and tests of subsurface conditions at or contiguous to the Site that Engineer has used in preparing the Bidding Documents.
2. Those drawings of physical conditions in or relating to existing surface and subsurface structures at or contiguous to the Site (except Underground Facilities) that Engineer has used in preparing the Bidding Documents.
B. Copies of reports and drawings referenced in paragraph 4.01.A will be made available by Owner to any Bidder on request. Those reports and drawings are not part of the Contract Documents, but the “technical data” contained therein upon which Bidder is entitled to rely as provided in paragraph 5.03 of the General Conditions has been identified and established in paragraph 5.03 of the Supplementary Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any “technical data” or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.
119.11.100 00 10 00-2
4.02 Underground Facilities
A. Information and data shown or indicated in the Bidding Documents with respect to existing Underground Facilities at or contiguous to the Site is based upon information and data furnished to Owner and Engineer by owners of such Underground Facilities, including Owner, or others.
4.03 Hazardous Environmental Condition
A. The Supplementary Conditions identify those reports and drawings relating to a Hazardous Environmental Condition identified at the Site, if any, that ENGINEER has used in preparing the Bidding Documents.
B. Copies of reports and drawings referenced in paragraph 4.03.A will be made available by Owner to any Bidder on request. Those reports and drawings are not part of the Contract Documents, but the “technical data” contained therein upon which Bidder is entitled to rely as provided in paragraph 5.03 of the General Conditions has been identified and established in paragraph 4.06 of the Supplementary Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any “technical data” or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.
4.04 Provisions concerning responsibilities for the adequacy of data furnished to prospective
Bidders with respect to subsurface conditions, other physical conditions and Underground Facilities, and possible changes in the Bidding Documents due to differing or unanticipated conditions appear in paragraphs 5.03, 5.04, and 5.05 of the General Conditions.
Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to a Hazardous Environmental Condition at the Site, if any, and possible changes in the Contract Documents due to any Hazardous Environmental Condition uncovered or revealed at the Site which was not shown or indicated in the Drawings or Specifications or identified in the Contract Documents to be within the scope of the Work appear in paragraph 5.03 of the General Conditions.
4.05 On request, Owner will provide Bidder access to the Site to conduct such examinations, investigations, explorations, tests, and studies as Bidder deems necessary for submission of a Bid. Bidder shall fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies. Bidder shall comply with all applicable Laws and Regulations relative to locating of excavation and utility.
4.06 Additional Owner Provided Information:
A. Reference is made to Article 7 of the Supplementary Conditions for the identification of the general nature of other work that is to be performed at the Site by Owner or others (such as utilities and other prime contractors) that relates to the Work contemplated by these Bidding Documents. On request, Owner will provide to each Bidder for examination access to or copies of Contract Documents (other than portions thereof related to price) for such other work.
119.11.100 00 10 00-3
B. Paragraph 7.13.G of the General Conditions states that if an Owner safety program exists it will be noted in the Supplementary Conditions.
4.07 It is the responsibility of each Bidder before submitting a Bid to:
A. Examine and carefully study the Bidding Documents, the other related data identified in the Bidding Documents, and any Addenda;
B. Visit the Site and become familiar with and satisfy Bidder as to the general, local, and
Site conditions that may affect cost, progress, and performance of the Work;
C. Become familiar with and satisfy Bidder as to all Federal, State, and local Laws and
Regulations that may affect cost, progress, or performance of the Work;
D. Carefully study all: (1) reports of explorations and tests of subsurface conditions at or contiguous to the Site and all drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the Site (except Underground Facilities) which have been identified in the Supplementary Conditions as provided in paragraph 5.03 of the General Conditions, and (2) reports and drawings of Hazardous Environmental Conditions at the Site which have been identified in the Supplementary Conditions as provided in paragraph 5.06 of the General Conditions;
E. Obtain and carefully study (or accept consequences for not doing so) all additional or supplementary examinations, investigations, explorations, tests, studies, and data concerning conditions (surface, subsurface, and Underground Facilities) at or contiguous to the Site which may affect cost, progress, or performance of the Work or which relate to any aspect of the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, including applying any specific means, methods, techniques, sequences, and procedures of construction expressly required by the Bidding Documents, and safety precautions and programs incident thereto;
F. Agree at the time of submitting its Bid that no further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of its Bid for performance of the Work at the price(s) bid and within the times and in accordance with the other terms and conditions of the Bidding Documents;
G. Become aware of the general nature of the work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents;
H. Correlate the information known to Bidder, information and observations obtained from visits to the Site, reports and drawings identified in the Bidding Documents, and all additional examinations, investigations, explorations, tests, studies, and data with the Bidding Documents;
I. Promptly give Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder discovers in the Bidding Documents and confirm that the written resolution thereof by Engineer is acceptable to Bidder; and
119.11.100 00 10 00-4
J. Determine that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance of the Work.
4.08 The submission of a Bid will constitute an incontrovertible representation by Bidder that
Bidder has complied with every requirement of this Article 4, that without exception the Bid is premised upon performing and furnishing the Work required by the Bidding Documents and applying any specific means, methods, techniques, sequences, and procedures of construction that may be shown or indicated or expressly required by the Bidding Documents, that Bidder has given Engineer written notice of all conflicts, errors, ambiguities, and discrepancies that Bidder has discovered in Bidding Documents and the written resolutions thereof by Engineer are acceptable to Bidder, and that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performing and furnishing the Work.
ARTICLE 5 - PRE-BID CONFERENCE
5.01 A Pre-Bid conference will be held at 3:00 PM on October 8, 2026, at the City of Orem
Public Works Building located at 1450 West 550 North, Orem, UT 84057.
Representatives of OWNER and ENGINEER will be present to discuss the Project.
Attendance at the Pre-Bid conference is strongly recommended. ENGINEER will transmit to all prospective Bidders of record such Addenda as ENGINEER considers necessary in response to questions arising at the conference. Oral statements may not be relied upon and will not be binding or legally effective.
ARTICLE 6 - SITE AND OTHER AREAS
6.01 The Site is identified in the Bidding Documents. Easements for permanent structures or permanent changes in existing facilities are to be obtained and paid for by Owner unless otherwise provided in the Bidding Documents. All additional lands and access thereto required for temporary construction facilities, construction equipment, or storage of materials and equipment to be incorporated in the Work are to be obtained and paid for by Contractor.
ARTICLE 7 - INTERPRETATIONS AND ADDENDA
7.01 All questions about the meaning or intent of the Bidding Documents are to be submitted to
Engineer in writing. Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda mailed or delivered to all parties recorded by Engineer as having received the Bidding Documents. Questions received less than five days prior to the date for opening of Bids may not be answered. Only questions answered by Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect.
7.02 Addenda may be issued to clarify, correct, or change the Bidding Documents as deemed advisable by Owner or Engineer.
ARTICLE 8 - BID SECURITY
8.01 No Bid Security Required.
119.11.100 00 10 00-5
ARTICLE 9 - CONTRACT TIMES
9.01 The number of days within which, or the dates by which, the Work is to be substantially completed and ready for final payment are set forth in the Agreement.
ARTICLE 10 - LIQUIDATED DAMAGES
10.01 Provisions for liquidated damages are set forth in the Agreement.
ARTICLE 11 - SUBSTITUTE AND “OR-EQUAL” ITEMS
11.01 The Contract, if awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents without consideration of possible substitute or “or-equal” items. Whenever it is specified or described in the Bidding Documents that a substitute or “or-equal” item of material or equipment may be furnished or used by CONTRACTOR if acceptable to ENGINEER, application for such acceptance will not be considered by ENGINEER until after the Effective Date of the Agreement. The procedure for submission of any such application by CONTRACTOR and consideration by ENGINEER is set forth in the General Conditions and may be supplemented in the General Requirements.
ARTICLE 12 - SUBCONTRACTORS, SUPPLIERS, AND OTHERS
12.01 If the Supplementary Conditions require the identity of certain Subcontractors, Suppliers, individuals, or entities to be submitted to Owner in advance of a specified date prior to the Effective Date of the Agreement, the apparent Successful Bidder, and any other Bidder so requested, shall within five days after Bid opening, submit to Owner a list of all such Subcontractors, Suppliers, individuals, or entities proposed for those portions of the Work for which such identification is required. Such list shall be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor, Supplier, individual, or entity if requested by Owner. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor, Supplier, individual, or entity, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit a substitute, without an increase in the Bid.
12.02 If apparent Successful Bidder declines to make any such substitution, Owner may award the Contract to the next lowest responsible Bidder that proposes to use acceptable Subcontractors, Suppliers, individuals, or entities. Declining to make requested substitutions will not constitute grounds for forfeiture of the Bid security of any Bidder.
Any Subcontractor, Supplier, individual, or entity so listed and against which Owner and Engineer makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Engineer subject to revocation of such acceptance after the Effective Date of the Agreement as provided in paragraph 6.06 of the General Conditions.
12.03 Contractor shall not be required to employ any Subcontractor, Supplier, individual, or entity against whom Contractor has reasonable objection.
119.11.100 00 10 00-6
ARTICLE 13 - PREPARATION OF BID
13.01 The Bid form is included with the Bidding Documents. Additional copies may be obtained from Engineer.
13.02 All blanks on the Bid form shall be completed in ink and the Bid signed in ink. Erasures or alterations shall be initialed in ink by the person signing the Bid From. A Bid price shall be indicated for each Bid item listed therein, or the words “No Bid,” “No Change,” or “Not Applicable” entered.
13.03 A Bid by a corporation shall be executed in the corporate name by the president or a vice-president or other corporate officer accompanied by evidence of authority to sign.
The corporate seal shall be affixed and attested by the secretary or an assistant secretary. The corporate address and state of incorporation shall be provided on the Bid Form.
13.04 A Bid by a partnership shall be executed in the partnership name and signed by a partner
(whose title must appear under the signature), accompanied by evidence of authority to sign. The official address of the partnership shall be provided on the Bid Form.
13.05 A Bid by a limited liability company shall be executed in the name of the firm by a member and accompanied by evidence of authority to sign. The state of formation of the firm and the official address of the firm shall be shown.
13.06 A Bid by an individual shall show the Bidder’s name and business address.
13.07 A Bid by a joint venture shall be executed by each joint venturer in the manner indicated on the Bid form. The official address of the joint venture must be provided on the Bid
13.08 All names shall be printed in ink below the signatures.
13.09 The Bid shall contain an acknowledgment of receipt of all Addenda, the numbers and dates of which shall be filled in on the Bid form.
13.10 The postal and email addresses and telephone number for communication regarding the
Bid shall be shown.
13.11 The Bid shall contain evidence of Bidder’s authority and qualification to do business in the state or locality where the Project is located or Bidder shall covenant in writing to obtain such qualification prior to award of the Contract and attach such covenant to the Bid. Bidder’s state contractor license number, if any, shall also be shown on the Bid
ARTICLE 14 - BASIS OF BID; COMPARSION OF BIDS
14.01 Unit Price
A. Bidders shall submit a Bid on a unit price basis for each item of Work listed in the Bid schedule.
119.11.100 00 10 00-7
B. The total of all bid prices will be the sum of the products of the estimated quantity of each item and the corresponding unit price. The final quantities and Contract Price will be determined in accordance with paragraph 13.03 of the General Conditions.
A. Discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum. Discrepancies between words and figures will be resolved in favor of the words.
14.02 Allowances
A. For cash allowances the Bid price shall include such amounts as the Bidder deems proper for Contractor's overhead, costs, profit, and other expenses on account of cash allowances, if any, named in the Contract Documents, in accordance with Paragraph 13.02.B of the General Conditions.
ARTICLE 15 - SUBMITTAL OF BID
15.01 The Bid Form is to be completed and submitted with all the attachments outlined in
Article 7 of the Bid Form.
15.02 A Bid shall be submitted no later than the date and time prescribed and in the manner indicated in the Advertisement for Bids and shall be in electronic PDF format submitted by email with “Orem City Well #1R Development Project” as the subject line of the email.
The Bid shall include the name and address of Bidder, the Bid security, and other required documents. If a Bid is sent by mail or other delivery system, the sealed envelope containing the Bid shall be enclosed in a separate envelope plainly marked on the outside with the notation “BID ENCLOSED” and shall be addressed to the ENGINEER at the address listed in the Advertisement for Bids for the Engineer. When using the mail or other delivery system, the Bidder is totally responsible for the mail or other delivery system delivering the Bid at the place and prior to the time indicated in the Advertisement for Bid. A mailed Bid shall be addressed to Owner at address in Article
1.01 of Bid Form.
ARTICLE 16 - MODIFICATION AND WITHDRAWAL OF BID
16.01 A Bid may be modified or withdrawn by an appropriate document duly executed in the manner that a Bid must be executed and delivered to the place where Bids are to be submitted prior to the date and time for the opening of Bids.
16.02 If within 24 hours after Bids are opened any Bidder files a duly signed written notice with
Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the preparation of its Bid, that Bidder may withdraw its Bid, and the Bid security will be returned. Thereafter, if the Work is rebid or negotiated, that Bidder will be disqualified from further bidding on the Work.
This provision to withdraw a Bid without forfeiting the Bid security does not apply to Bidder’s errors in judgment in preparing the Bid.
119.11.100 00 10 00-8
ARTICLE 17 - OPENING OF BIDS
17.01 Bids will be opened at the time and place indicated in the Advertisement for Bids. An abstract of the amounts of the Bids and major alternates, if any, will be made available to Bidders after the opening of Bids.
ARTICLE 18 - BIDS TO REMAIN SUBJECT TO ACCEPTANCE
18.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, at its sole discretion, release any Bid and return the Bid security prior to the end of this period.
ARTICLE 19 - EVALUATION OF BIDS AND AWARD OF CONTRACT
19.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner further reserves the right to reject the Bid of any Bidder whom it finds, after reasonable inquiry and evaluation, to be non-responsible. Owner also reserves the right to waive all informalities not involving price, time, or changes in the Work and to negotiate contract terms with the Successful Bidder.
19.02 More than one Bid for the same Work from an individual or entity under the same or different names will not be considered. Reasonable grounds for believing that any Bidder has an interest in more than one Bid for the Work may be cause for disqualification of that Bidder and the rejection of all Bids in which that Bidder has an interest.
19.03 In evaluating Bids, Owner will consider whether or not the Bids comply with the prescribed requirements, and such alternates, unit prices and other data, as may be requested in the Bid Form or prior to the Notice of Award.
19.04 In evaluating Bidders, Owner will consider the qualifications of Bidders and may consider the qualifications and experience of Subcontractors, Suppliers, and other individuals or entities proposed for those portions of the Work for which the identity of Subcontractors, Suppliers, and other individuals or entities must be submitted as provided in the Supplementary Conditions.
19.05 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders, proposed Subcontractors, Suppliers, individuals, or entities to perform the Work in accordance with the contract Documents.
19.06 If the Contract is to be awarded, Owner will award the Contract to the responsible Bidder whose Bid, conforming with all the material terms and conditions of the Instructions to Bidders, is lowest, price and other factors considered. If detailed in the bid form, factors such as discounts, transportation costs, and life cycle costs may be used to determine which bidder, if any, is to be offered the award.
119.11.100 00 10 00-9
ARTICLE 20 - SIGNING OF AGREEMENT
21.01 When Owner gives a Notice of Award to the Successful Bidder, it shall be accompanied by the required number of unsigned counterparts of the Agreement with the other Contract Documents which are identified in the Agreement as attached thereto. Within 15 days thereafter, Successful Bidder shall sign and deliver the required number of counterparts of the Agreement and attached documents to Owner. Within ten days thereafter, Owner shall deliver one fully signed counterpart to Successful Bidder with a complete set of the Drawings with appropriate identification.
- END OF SECTION -
119.11.100 00 10 00-10
09/2026 BID FORM
119.11.100 00 30 00-1
DOCUMENT 00 30 30
BID FORM
Project Identification: CITY OF OREM – WELL #1R DEVELOPMENT PROJECT
Contract Identification and Number:
ARTICLE 1 - BID RECIPIENT
1.01 This Bid Is Submitted To: CITY OF OREM
56 N State St.
Orem, UT 84057
1.02 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an
Agreement with Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in the Bid and in accordance with the other terms and conditions of the Bidding Documents.
ARTICLE 2 - BIDDER’S ACKNOWLEDGMENTS
2.01 Bidder accepts all of the terms and conditions of the Advertisement and Instructions to
Bidders, including without limitations those dealing with the dispositions of Bid security.
The Bid will remain subject to acceptance for 60 days after the Bid opening, or for such longer period of time that Bidder may agree to in writing upon request of Owner.
ARTICLE 3 - BIDDER’S REPRESENTATIONS
3.01 In submitting this Bid, Bidder represents that:
A. Bidder has examined and carefully studied the Bidding Documents, the other related data identified in the Bidding Documents, and the following Addenda, receipt of which is hereby acknowledged:
Addendum No. Addendum Date
B. Bidder has visited the Site and become familiar with and is satisfied as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work.
C. Bidder is familiar with and is satisfied as to all Federal, state, and local Laws and
Regulations that may affect cost, progress, and performance of the Work.
D. Bidder has carefully studied all: (1) reports of explorations and tests of subsurface conditions at or contiguous to the Site and all drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the Site (except Underground Facilities) which have been identified in GC-5.03(A)(1), and (2) reports
119.11.100 00 30 00-2 and drawings of Hazard Environmental Conditions, if any, at the Site that have been identified in GC-5.03(A)(2) as containing reliable “technical data.”
E. Bidder has considered the information known to Bidder; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Site-related reports and drawings identified in the Bidding Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, including applying the specific means, methods, techniques, sequences, and procedures of construction expressly required by the Bidding Documents; and (3) Bidder’s safety precautions and programs.
F. Based on the information and observations referred to in Paragraph 3.01.E above, Bidder does not consider that any further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of this Bid for performance of the Work at the price(s) bid and within the times and in accordance with the other terms and conditions of the Bidding Documents.
G. Bidder is aware of the general nature of the Work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents.
H. Bidder has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents, and the written resolution thereof by Engineer is acceptable to Bidder.
I. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance of the Work for which this Bid is submitted.
J. Bidder will submit written evidence of its authority to do business in the State or other jurisdiction where the Project is located not later than the date of its execution of the Agreement.
ARTICLE 4 - BIDDER’S CERTIFICATION
4.01 Bidder further represents that:
A. This Bid is genuine and not made in the interest of or on the behalf of any undisclosed individual or entity and is not submitted in conformity with any agreement or rules of any group, association, organization, or corporation;
B. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid;
C. Bidder has not solicited or induced any individual or entity to refrain from bidding; and
D. Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract. For the purposes of this Paragraph 4.01.D:
1. “corrupt practice” means the offering, giving, receiving, or soliciting of anything of value likely to influence the action of a public official in the bidding process;
119.11.100 00 30 00-3
2. “fraudulent practice” means an intentional misrepresentation of facts made (a) to influence the bidding process to the detriment of Owner, (b) to establish bid prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition;
3. “collusive practice” means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish bid prices at artificial, non-competitive levels; and
4. “coercive practice” means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.
ARTICLE 5 - BASIS OF BID
5.01 Bidder will complete the Work in accordance with the Contract Documents for the following price(s):
City of Orem – Well #1R
BID SCHEDULE A
Description Qty Unit Unit Bid Amount
Total Bid Amount
A.1 Mobilization/Demobilization 1 L.S. $ $
A.2 Dual Swab Well Development with Cable Tool Rig 300 HRS $ $
A.3 Furnish and Install Test Pump Equipment with 5,000 gpm Capacity Set at 350 Foot Depth 1 L.S. $ $
A.4 Well Development, Step and Constant Rate Pump Tests 160 HRS $ $
A.5 Well Disinfection 1 L.S. $ $ A.6 Well Bailing 8 HRS $ $ A.7 Video Well Log 1 L.S. $ $
BID SCHEDULE A TOTAL: $
5.02 Evaluation of Bids:
A. Evaluation Criteria:
1. Qualifications, Experience and References – 60%
2. Cost – 15%
3. Scheduling/Availability – 25%
B. The OWNER also reserves the right to reject all bids
119.11.100 00 30 00-4
Unit Prices have been computed in accordance with paragraph 13.03.B of the General Conditions.
Bidder acknowledges that estimated quantities are not guaranteed, and are solely for the purpose of comparison of Bids, and final payment for all Unit Price Bid items will be based on actual quantities, determined as provided in the contract Documents.
ARTICLE 6 - TIME OF COMPLETION
6.01 Bidder agrees that the Work will be substantially complete and will be completed and ready for final payment in accordance with paragraph 15.06 of the General Conditions on or before the dates or within the number of calendar days indicated in the Agreement.
6.02 Bidder accepts the provisions of the Agreement as to liquidated damage.
ARTICLE 7 - ATTACHMENTS TO THIS BID
7.01 The following documents are attached to and made a condition of the Bid:
A. Evidence of authority to do business in the state or jurisdiction of the Project; or a written covenant to obtain such license within the time frame for acceptance of Bids.
B. Preliminary baseline project schedule including, but not limited to the following:
1. Notice to Proceed.
2. Dual Swab while pumping.
3. Test Pumping while surging.
4. Step & Constant Rate Tests.
5. Well Bailing.
6. Video Log.
ARTICLE 8 - DEFINED TERMS
8.01 The terms used in this Bid with the initial capital letters have the meanings indicated in the
Instructions to Bidders, the General Conditions, and the Supplementary Conditions.
119.11.100 00 30 00-5
ARTICLE 9 - BID SUBMITTAL
9.01 This Bid is submitted by:
If Bidder is:
An Individual
Name (typed or printed): ____________________________________________________
By: _____________________________________________________________________ (Individual’s signature)
Doing business as:
A Partnership
Partnership Name: _________________________________________________________
By: _____________________________________________________________________ (Signature of general partner -- attach evidence of authority to sign)
Name (typed or printed):
A Corporation
Corporation Name:
State or Jurisdiction of Incorporation: ______________________________
Type (General Business, Profession, Service, Limited Liability):
By: ___________________________________________________________________ (Signature -- attach evidence of authority to sign)
Name (typed or printed):
Title: ____________________________________________
Attest ____________________________________________________________ (Signature of Corporate Secretary)
Date of Qualification to do business in ____________ [State or other jurisdiction where Project is located] is ___/___/______
SEAL,
if required by State
SEAL,
if required by State
CORPORATE
if required by State
119.11.100 00 30 00-6
A Joint Venture
Name of Joint Venture:
First Joint Venture Name: ____________________________________________________
By: ____________________________________________________________________ (Signature of joint venture partner -- attach evidence of authority to sign)
Name (typed or printed):
Title: ____________________________________________
Second Joint Venture Name:
By: ____________________________________________________________________ (Signature of joint venture partner -- attach evidence of authority to sign)
Name (typed or printed):
Title: ____________________________________________
(Each joint venturer must sign. The manner of signing for each individual, partnership, and corporation that is party to the venture should be in the manner indicated above.)
Bidder’s Business address: __________________________________________________
Business Phone No. (_____)______________
Business FAX No. (_____)_____________
Business E-Mail Address
State Contractor License No. ____________________________________. (If applicable)
Employer’s Tax ID No. _______________________________________
Phone and FAX Numbers, and Address for receipt of official communications, if different from Business contact information:
9.02 Bid submitted on ______________________________, 20___.
by State
SEAL,
by State
PART 2
CONTRACT FORMS
EJCDC C-510 Notice of Award Prepared by the Engineers Joint Contract Documents Committee and endorsed by the Construction Specifications Institute.
DOCUMENT 00 51 00
NOTICE OF AWARD
Date: __________________
Project: City of Orem – Well #1R Development Project
Owner: City of Orem Owner's Contract No.:
Contract: Engineer's Project No.: 119.11.100
Bidder:
Bidder's Address: [send Notice of Award Certified Mail, Return Receipt Requested]
You are notified that your Bid dated for the above Contract has been considered. You are the Successful Bidder and are awarded a Contract for
[Indicate total Work, alternates, or sections of Work awarded.]
The Contract Price of your Contract is Dollars ($ ).
Three copies of the proposed Contract Documents (except Drawings) accompany this Notice of Award.
Drawings will be delivered separately or otherwise made available to you immediately.
You must comply with the following conditions precedent within 15 days of the date you receive this Notice of Award.
1. Deliver to the Owner three fully executed counterparts of the Contract Documents.
2. Deliver with the executed Contract Documents the Contract security [Bonds] as specified in the Instructions to Bidders (Article 20), General Conditions (Paragraph 6.01), and Supplementary Conditions (Paragraph SC-6.03).
3. Other conditions precedent:
Failure to comply with these conditions within the time specified will entitle Owner to consider you in default, annul this Notice of Award, and declare your Bid security forfeited.
Within ten days after you comply with the above conditions, Owner will return to you one fully executed counterpart of the Contract Documents.
City of Orem Owner By:
Authorized Signature
Title
Copy to Engineer
EJCDC C-510 Notice of Award Prepared by the Engineers Joint Contract Documents Committee and endorsed by the Construction Specifications Institute.
EJCDC® C-520, Agreement between Owner and Contractor for Construction Contract (Stipulated Price).
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
DOCUMENT 00 52 00
AGREEMENT
This Agreement is by and between City of Orem (“Owner”) and (“Contractor”).
Terms used in this Agreement have the meanings stated in the General Conditions and the Supplementary Conditions.
Owner and Contractor hereby agree as follows:
ARTICLE 1—WORK
1.01 CONTRACTOR SHALL COMPLETE ALL WORK AS SPECIFIED OR INDICATED IN
THE CONTRACT DOCUMENTS. THE WORK IS GENERALLY DESCRIBED AS
FOLLOWS:
Description and Scope of Work: Dual Swab Development and Test Pumping of a production well (Well #1R) using a Cable Tool Rig. The well will be swabbed and pumped simultaneously to maximize the efficiency of the well while recording parameters such as:
static water level, pumping water level, flow rate while pumping and sand production. The anticipated construction of the well is 20-inch diameter casing, with approximately 300 feet of screen, to an anticipated depth of 800 feet. Figure 1 shows the location and site plan of the well. Figure 2 shows the anticipated well design, and Figure 3 shows the well-head completion.
ARTICLE 2—THE PROJECT
2.01 The Project, of which the Work under the Contract Documents is a part, is generally described as follows: City of Orem – Well #1R Development Project.
ARTICLE 3—ENGINEER
3.01 The Owner has retained Hansen, Allen & Luce, Inc. (“Engineer”) to act as Owner’s representative, assume all duties and responsibilities of Engineer, and have the rights and authority assigned to Engineer in the Contract.
3.02 The part of the Project that pertains to the Work has been designed by Engineer.
ARTICLE 4—CONTRACT TIMES
4.01 Time is of the Essence
A. All time limits for Milestones, if any, Substantial Completion, and completion and readiness for final payment as stated in the Contract Documents are of the essence of the Contract.
4.02 Contract Times: Dates
A. The Work will be substantially complete within 90 Days and completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before within 120 Days.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
4.03 Liquidated Damages
A. Contractor and Owner recognize that time is of the essence as stated in
Paragraph 4.01 above and that Owner will suffer financial and other losses if the Work is not completed and Milestones not achieved within the Contract Times, as duly modified. The parties also recognize the delays, expense, and difficulties involved in proving, in a legal or arbitration proceeding, the actual loss suffered by Owner if the Work is not completed on time. Accordingly, instead of requiring any such proof, Owner and Contractor agree that as liquidated damages for delay (but not as a penalty):
1. Substantial Completion: Contractor shall pay Owner $200.00 for each day that expires after the time (as duly adjusted pursuant to the Contract) specified above for Substantial Completion, until the Work is substantially complete.
2. Completion of Remaining Work: After Substantial Completion, if Contractor shall neglect, refuse, or fail to complete the remaining Work within the Contract Times (as duly adjusted pursuant to the Contract) for completion and readiness for final payment, Contractor shall pay Owner $200.00 for each day that expires after such time until the Work is completed and ready for final payment.
3. Liquidated damages for failing to timely attain Milestones, Substantial Completion, and final completion are not additive, and will not be imposed concurrently.
B. If Owner recovers liquidated damages for a delay in completion by Contractor, then such liquidated damages are Owner’s sole and exclusive remedy for such delay, and Owner is precluded from recovering any other damages, whether actual, direct, excess, or consequential, for such delay, except for special damages (if any) specified in this Agreement.
ARTICLE 5—CONTRACT PRICE
5.01 Owner shall pay Contractor for completion of the Work in accordance with the Contract Documents, the amounts that follow, subject to adjustment under the Contract:
A. For all Work, at the prices stated in Contractor’s Bid, attached hereto as an exhibit.
All specific cash allowances are included in the above price in accordance with Paragraph 13.02 of the General Conditions.
ARTICLE 6—PAYMENT PROCEDURES
6.01 Submittal and Processing of Payments
A. Contractor shall submit Applications for Payment in accordance with Article 15 of the
General Conditions. Applications for Payment will be processed by Engineer as provided in the General Conditions.
6.02 Progress Payments; Retainage
A. Owner shall make progress payments on the basis of Contractor’s Applications for
Payment on or about the 30th day of each month during performance of the Work as provided in Paragraph 6.02.A.1 below, provided that such Applications for Payment have been submitted in a timely manner and otherwise meet the requirements of the Contract. All such payments will be measured by the Schedule of Values established as provided in the General Conditions (and in the case of Unit Price Work based on
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
the number of units completed) or, in the event there is no Schedule of Values, as provided elsewhere in the Contract.
1. Prior to Substantial Completion, progress payments will be made in an amount equal to the percentage indicated below but, in each case, less the aggregate of payments previously made and less such amounts as Owner may withhold, including but not limited to liquidated damages, in accordance with the Contract.
a. 95 percent of the value of the Work completed (with the balance being retainage).
1) If 50 percent or more of the Work has been completed, as determined by Engineer, and if the character and progress of the Work have been satisfactory to Owner and Engineer, then as long as the character and progress of the Work remain satisfactory to Owner and Engineer, there will be no additional retainage; and
b. 95 percent of cost of materials and equipment not incorporated in the Work (with the balance being retainage).
B. Upon Substantial Completion, Owner shall pay an amount sufficient to increase total payments to Contractor to 97.5 percent of the Work completed, less such amounts set off by Owner pursuant to Paragraph 15.01.E of the General Conditions, and less 100 percent of Engineer’s estimate of the value of Work to be completed or corrected as shown on the punch list of items to be completed or corrected prior to final payment.
6.03 Final Payment
A. Upon final completion and acceptance of the Work, Owner shall pay the remainder of the Contract Price in accordance with Paragraph 15.06 of the General Conditions.
6.04 Consent of Surety
A. Owner will not make final payment, or return or release retainage at Substantial Completion or any other time, unless Contractor submits written consent of the surety to such payment, return, or release.
6.05 Interest
A. All amounts not paid when due will bear a maximum interest rate of up to or equal to
Owner’s maximum interest rate, but in no case greater than 4 percent per annum.
ARTICLE 7—CONTRACT DOCUMENTS
7.01 Contents
A. The Contract Documents consist of all of the following:
1. This Agreement.
2. General Conditions.
3. Supplementary Conditions.
4. Specifications as listed in the table of contents of the project manual (copy of list attached).
5. Drawings (Well Schematics) with each sheet bearing the following general title:
City of Orem – Well #1R Drilling Project.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
6. Drawings listed on the attached sheet index.
7. Addenda (numbers to , inclusive).
8. Exhibits to this Agreement (enumerated as follows):
a.
9. The following which may be delivered or issued on or after the Effective Date of the Contract and are not attached hereto:
a. Notice of Award.
b. Notice to Proceed.
c. Work Change Directives.
d. Change Orders.
e. Field Orders.
f. Warranty Bond, if any.
B. The Contract Documents listed in Paragraph 7.01.A are attached to this Agreement (except as expressly noted otherwise above).
C. There are no Contract Documents other than those listed above in this Article 7.
D. The Contract Documents may only be amended, modified, or supplemented as provided in the Contract.
ARTICLE 8—REPRESENTATIONS, CERTIFICATIONS, AND STIPULATIONS
8.01 Contractor’s Representations
A. In order to induce Owner to enter into this Contract, Contractor makes the following representations:
1. Contractor has examined and carefully studied the Contract Documents, including
Addenda.
2. Contractor has visited the Site, conducted a thorough visual examination of the
Site and adjacent areas, and become familiar with the general, local, and Site conditions that may affect cost, progress, and performance of the Work.
3. Contractor is familiar with all Laws and Regulations…