This Request for Bids (RFP) is issued by Letcher County, Kentucky, in cooperation with the Natural Resources Conservation Service (NRCS), for Emergency Watershed Protection streambank stabilization work along Peace Valley Road (DSR-21-05-23-5076-019). The project consists of clearing approximately 300 linear feet of channel debris, stabilizing approximately 120 linear feet of embankment with gabions, and stabilizing approximately 36 linear feet of embankment with steel rail walls across three identified sites. The work includes channel clearing and shaping, installation of steel rail walls and gabion baskets, pollution control measures, and seeding and mulching of disturbed areas. Proposals must be submitted electronically through the DFS Procurement Portal at dfs.bonfirehub.com no later than November 11, 2026 at 2:00 PM EST. A pre-bid site visit is scheduled for a to-be-announced date and time at the Letcher County Fiscal Court office in Whitesburg, Kentucky. Bids will be opened publicly on November 11, 2026 at 3:00 PM, with award scheduled for November 16, 2026 at 10:00 AM during a special call Fiscal Court meeting. The work completion deadline is December 13, 2026, with potential extension to February 2027 subject to approval.
All prices must be all-inclusive and submitted by unit price for 12 identified bid items, including channel clearing and shaping (300 linear feet), seeding and mulching (lump sum), mobilization and demobilization (lump sum), and various materials such as drainfill stone, rock riprap, gabions, steel railroad rail piling, guard rail lagging, and grouting. Successful bidders must provide proof of liability insurance, auto coverage, and workers compensation and must comply with all applicable federal, state, and local laws. Required certifications include non-collusion declarations, debarment certifications, drug-free workplace affidavits, conflict-of-interest statements, and certifications regarding lobbying activities and affirmative steps for minority business participation. The County reserves the right to accept or reject any and all bids and to accept multiple bids and award work per location or per line item. Invoices and work completion documentation must be submitted through erassist.com/submit/dsr019 after contract execution; email submissions are no longer accepted. Bid prices are proposed to remain valid for 180 days.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2-NRCS Letcher County 5076 DSR 019 Peace Valley RFB Addendum 1 as of 10.30.26.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LETCHER COUNTY - DSR-21-05-23-5076-019 - RFP
REQUEST FOR BIDS
FOR
LETCHER COUNTY, KENTUCKY
EMERGENCY WATERSHED PROTECTION
STREAMBANK STABILIZATION
PEACE VALLEY ROAD
DSR-21-05-23-5076-019
PROPOSAL DUE ON 11/11/2026
NO LATER THAN 2:00 PM EST
TABLE OF CONTENTS
I. PURPOSE
II. SCHEDULE
III. POINT OF CONTACT
IV. GENERAL TERMS & INFORMATION
V. PROJECT SCOPE
VI. PROPOSAL EVALUATION CRITERIA
Attachment 1: Certification and Cost Bid Form Attachment 1: Certification and Cost Bid Form
SAMPLE COST PROPOSAL FORM
Attachment 2: NON-COLLUSION DECLARATION Attachment 3: CERTIFICATION REGARDING LOBBYING Attachment 4: FORM 200.321 AFFIRMATIVE STEPS Attachment 5: CERTIFICATION REGARDING DEBARMENT, SUSPENSION, INELIGIBILITY and
VOLUNTARY EXCLUSION
Attachment 6: CONFLICT/NON-CONFLICT OF INTEREST STATEMENT Attachment 7: DRUG-FREE WORKPLACE AFFIDAVIT
APPENDIX A: Construction and Material Specifications APPENDIX B: Drawing Sets
LETCHER COUNTY, KENTUCKY
EWP STREAMBANK STABILIZATION
DSR-21-05-23-5076-019
I. PURPOSE:
Letcher County (hereafter referred to as “County”) is soliciting bids from experienced contractors to provide Streambank Stabilization services near Peace Valley Road as part of the USDA Natural Resources Conservation Service’s (NRCS) Environmental Watershed Protection (EWP) Program, according to NRCS Standard Practices and Specifications and Construction Plans, attached or referenced in Appendices A and B.
The work consists of clearing designated areas by the removal and disposal of trees, logs, stumps, shrubs, brush, and rubbish, and the shaping of the channel.
The work for this project also involves installing steel rail walls and gabion baskets. The planned work will stabilize the channel to lessen flooding hazards in rural areas.
The purpose of this work is to reduce risks to agricultural resources or civil infrastructure by removing obstructions that hinder channel flow or sediment transport in order to restore flow capacity and direction, prevent excessive bank erosion by eddies or redirection of flow, and reduce the undesirable formation of bars and/or minimize blockages by debris.
II. SCHEDULE
A. PRE-BID OPTIONAL SITE VISIT: TBA Date and Time
B. BID SUBMISSION DEADLINE: Wednesday, November 11, 2026 at 2:00 PM EST
C. PUBLIC BID OPENING: Wednesday, November 11, 2026 at 3:00 PM EST
D. in the Judge Executive’s Office
E. MEETING FOR AWARD: Monday, November 16, 2026 at 10:00 AM during a special call Fiscal Court meeting.
F. CURRENT WORK COMPLETE DEADLINE: December 13, 2026 Deadline may be extended to February 2027 depending on extension approval.
III. POINT OF CONTACT:
Points of contact for this Bid: Please copy all contacts on emails.
Terry Adams, Judge: judgeadams@letchercounty.ky.gov
ER Assist Grant Manager: ky-letcher@erassist.com
IV. GENERAL TERMS & INFORMATION:
A. Bids and all required documents must be submitted online to the DFS Procurement Portal
(hereinafter “DFS Portal” or “Portal”) at dfs.bonfirehub.com no later than November 11, 2026 at 2:00 PM EST.
B. Submittals received after the closing time will not be accepted. Multiple submittals from the same entity will not be accepted. Submission is electronic only through the DFS Portal. Hard copy bids or offers by telephone, fax, or email will not be accepted.
C. All proposers are encouraged to attend an optional Pre-Bid Meeting and Site Visit scheduled for a to-be-announced date and time at the Letcher County Fiscal Court, 156 Main St STE 107, Whitesburg, KY 41858. No synopsis or summary of the meeting will be provided.
D. Addenda regarding this RFP will be posted to the DFS Portal at dfs.bonfirehub.com. Proposers are responsible for obtaining addenda and are advised to check the website frequently.
E. Questions regarding this RFP are to be submitted to dfs.bonfirehub.com. For questions regarding portal registration or navigation, please email: procurement@erassist.com.
F. All bids must be properly certified by the entity bidding for the work and signed by an officer, director or owner that has authority to bind and commit the Contractor to perform said work and services.
G. Work shall be bid by unit price and all prices shall be all-inclusive and shall include all work required to complete the scope of work according to the Standards, Specifications, and Construction Plans in Appendices A and B, including but not limited to vegetating disturbed areas, traffic control, mobilization and demobilization, contractor quality control, and pollution control measures.
H. Prices offered in the Cost Bid Form by contractor shall be all inclusive and in accordance with the NRCS Standards and Specifications attached in Appendix A and shall not be increased or changed for any reason other than changes requested or approved by Letcher County.
I. The County of Letcher reserves the right to request additional information for any and all prices offered in the Cost Bid Form, including but not limited to a comprehensive breakdown of prices offered.
http://dfs.bonfirehub.com/ mailto:procurement@erassist.com http://dfs.bonfirehub.com/ http://dfs.bonfirehub.com/ mailto:judgeadams@letchercounty.ky.gov mailto:ky-letcher@erassist.com
J. The following forms are provided in this RFP for reference. Proposers must review each form and enter their response as directed in the Portal’s Required Information section. The confirmation or declaration statement for each form for which a response is required is provided in a gray box at the bottom of each form in this document. All responses must be true and accurate and shall be considered the equivalent of a legally-binding electronic signature.
1. Attachment 1: Bid Certification and Cost Bid Form
2. Attachment 2: NON-COLLUSION DECLARATION
3. Attachment 3: CERTIFICATION REGARDING LOBBYING
4. Attachment 4: FORM 200.321 AFFIRMATIVE STEPS
5. Attachment 5: CERTIFICATION REGARDING DEBARMENT, SUSPENSION, INELIGIBILITY and VOLUNTARY EXCLUSION
6. Attachment 6: CONFLICT/NON-CONFLICT OF INTEREST STATEMENT
7. Attachment 7: DRUG-FREE WORKPLACE AFFIDAVIT
K. Costs of preparation of a response to this request for bids are solely those of the proposers. The County assumes no responsibility for any such costs incurred by the proposer. The proposer also agrees that the County bears no responsibility for any costs associated with any administrative or judicial proceedings resulting from the solicitation process.
L. Bids will be opened publicly prior to the award meeting on November 11, 2026 at 3:00 PM in the Judge Executive’s Office.
M. Award is scheduled to occur at a special call of the Letcher County Fiscal Court, 156 Main St STE 107, Whitesburg, KY 41858 on November 16, 2026 at 10:00 AM EST.
N. Successful bidders must provide insurance policies showing proof of liability coverage, auto coverage and workers compensation.
O. Successful bidders, assigns, subcontractors must be compliant with all applicable Federal, State and Local laws.
P. The successful bidder must submit invoices to erassist.com/submit/dsr019. This submission form will not be available until the contract is fully executed. Invoices and work complete photos will no longer be accepted through email.
Q. The County has the right to cancel a solicitation at any time prior to approval of the award by the County.
R. The County of Letcher reserves the right to accept or reject any and all bids, in addition, the County reserves the right to accept multiple bids and award work per location or per line item.
http://erassist.com/submit/DSR019
V. PROJECT SCOPE
A. All work shall be performed as detailed or referenced in the attached NRCS National
Conservation Practice Standards and Specifications and Job Sheets attached hereto in Appendices A and B. The work consists of (1) channel clearing - designated areas by the removal and disposal of trees, logs, stumps, shrubs, brush, and rubbish and the shaping of the channel,
(2) Rail Wall installation - work consists of furnishing, fabricating, and erecting metalwork, including the metal parts and fasteners of the composite structures, (3) Gabions and Gabion Mattresses - The work consists of furnishing, assembling, and installing rock-filled wire-mesh gabions and gabion mattresses, (4) pollution control - work consists of installing measures or performing work to control erosion and minimize the production of sediment and other pollutants to water and air from construction activities, (5) seeding and mulching - work consists of preparing the area for treatment; furnishing and placing seed, sprigs, mulch, fertilizer, inoculant, lime, and other soil amendments; and anchoring mulch in designated areas as specified.
B. Access points for each site are at the coordinates provided (where the stream meets the road) any additional or special instructions regarding site access will be provided at the Pre-Bid meetings.
C. All assigned work shall be performed at the specified location(s) and within the site parameters as determined by NRCS and provided below and in Appendix B. This project contains the following three (3) sites; each having a site ID that correlates to the project map in Appendix B consisting of a number and a letter.
1. Site 1 : 37.175722, -82.836789
i. Stabilize approximately 120 LF of embankment with Gabions
2. Site 3 : 37.175551, -82.837970
i. Stabilize approximately 36 LF of embankment with Steel Rail Wall
3. Site 4 : 37.17460237451559, -82.83951541295177
i. Clear approximately 300 LF of channel of all debris (300 LF)
Attachment 1: Certification and Cost Bid Form
Proposing Certification: I have carefully examined the Request for Bids and any other documents accompanying or made a part of this Request for Bids.
I hereby propose to furnish the goods or services specified in the Request for Bids at the rates quoted in my Bid. I agree that my Bid will remain in effect for a period of up to one hundred eighty (180) days.
I agree to abide by all conditions of this Bid and understand that a background investigation may be conducted prior to award.
I certify that all information contained in this Bid is truthful to the best of my knowledge and belief. I further certify that I am duly authorized to submit this Bid on behalf of the Proposer as its act and deed and that the Proposer is ready, willing and able to perform if awarded the Contract.
I certify this Bid is made without prior understanding, agreement, connection, discussion, or collusion with any other person, firm or corporation submitting a Bid for the same product or service. I further certify that no officer, employee or agent of County or of any other Proposer has a financial interest in this Bid. I further certify that the undersigned executed this Proposer's Certification with full knowledge and understanding of the matters therein contained and was duly authorized to do so.
DFS Portal Confirmation / Declaration:
By completing and submitting the Cost Bid Form, you are certifying all of the above as well as the prices and data entered in the Cost Bid Form in the DFS Portal. The following Cost Bid Form is provided for reference only.
Attachment 1: Certification and Cost Bid Form
SAMPLE COST PROPOSAL FORM
Emergency Watershed Protection Program - Letcher County
DSR # 21-05-23-5076-019
The prices offered shall be “all-inclusive”, and shall not be increased or changed for any reason other than changes requested or approved by the County and shall conform to the NRCS Standards & Specifications.
Breakdown of costs will be required upon request by the County or NRCS.
This is a Sample Cost Bid Form ONLY. Actual bid prices shall be entered in the Portal. This form is not required but can be submitted. In the case of price discrepancies, the prices in the Portal will prevail.
ITEM # Work/Material Unit Qty Unit Rate Proposed Cost
(extended)
1 Channel Clearing and Shaping LF 300
2 Seeding and Mulching Lump Sum
3 Mobilization and Demobilization
Lump Sum
4 Drainfill, KY DOH #2 Stone TON 28.1
5 Rock Riprap, KYDOH Class III Channel Liner
TON 45
6 Rock Riprap, Class II, Rail Steel Backfill
TON 51
7 Gabions, 1' Reno Mattresses CY 28
8 Gabions CY 64
9 Steel, Railroad Rail Piling, 15’ LF 60
10 Steel, Railroad Rail Piling, 16' LF 112
11 Steel, Guard Rail Lagging SF 460
12 Grouting CY 1.8
Total Cost
Attachment 2: NON-COLLUSION DECLARATION
The bid is not made in the interest of, or on behalf of, any undisclosed person, partnership, company, association, organization, or corporation. The bid is genuine and not collusive or sham.
The bidder has not directly or indirectly induced or solicited any other bidder to put in a false or sham bid. The bidder has not directly or indirectly colluded, conspired, connived, or agreed with any bidder or anyone else to put in a sham bid, or that anyone shall refrain from bidding. The bidder has not in any manner, directly or indirectly, sought by agreement, communication, or conference with anyone to fix the bid price of the bidder or any other bidder, or to fix any overhead, profit, or cost element of the bid price, or of that of any other bidder.
All statements contained in the bid are true. The bidder has not, directly or indirectly, submitted his or her bid price of any breakdown thereof, or the contents thereof, or divulged information or data relative thereto, to any corporation, partnership, company, association, organization, bid depository, or to any member or agent thereof to effectuate a collusive or sham bid, and has not paid, and will not pay, any person or entity for such purpose.
Any person executing this declaration on behalf of a bidder that is a corporation, partnership, joint venture, limited liability company, limited liability partnership, or any other entity, hereby represents that he or she has full power to execute, and does execute, this declaration on behalf of the bidder.
I declare under penalty of perjury under the applicable laws that the foregoing is true and correct.
DFS Portal Confirmation / Declaration:
Do you confirm that you have read the Non-Collusion declaration and therefore declare under penalty of perjury under the applicable laws that the Non-Collusion Declaration is true and correct? (Y/N)
Attachment 3: CERTIFICATION REGARDING LOBBYING
The undersigned certifies that, to the best of their knowledge and belief, that:
1. No Federal appropriated funds have been paid or will be paid, by or on behalf of the undersigned, to any person for influencing or attempting to influence an officer or employee of an agency, a Member of Congress, an officer or employee of Congress, or an employee of a Member of Congress in connection with the awarding of any Federal contract, the making of any Federal grant, the making of any Federal loan, the entering into of any cooperative agreement, and the extension, continuation, renewal, amendment, or modification of any Federal contract, grant, loan, or cooperative agreement.
2. If any funds other than Federal appropriated funds have been paid or will be paid to any person for influencing or attempting to influence an officer or employee of any agency, a Member of Congress, an officer or employee of Congress, or an employee of a Member of Congress in connection with this Federal contract, grant, loan, or cooperative agreement, the undersigned shall complete and submit Standard Form-LLL, “Disclosure Form to Report Lobbying,” in accordance with its instruction.
3. The undersigned shall require that the language of this certification be included in the award document for all subawards at all tiers (including subcontracts, subgrants, and contracts under grants, loans, and cooperative agreements) and that all subrecipients shall certify and disclose accordingly.
This certification is a material representation of fact upon which reliance was placed when this transaction was made or entered into. Submission of this certification is a prerequisite for making or entering into this transaction imposed by section 1352, title 31 U.S. Code. Any person who fails to file the required certification shall be subject to a civil penalty of not less than $10,000 and not more than $100,000 for each such failure.
DFS Portal Confirmation / Declaration:
Do you, the Contractor, confirm that you have read the Certification Regarding Lobbying form and certify or affirm the truthfulness and accuracy of each statement of its certification and disclosure, if any. In addition, the Contractor understands and agrees that the provisions of 31 U.S.C. Chap. 38, Administrative Remedies for False Claims and Statements, apply to this certification and disclosure, if any. (True/False)
Attachment 4: FORM 200.321 AFFIRMATIVE STEPS
CONTRACTING WITH SMALL AND MINORITY BUSINESSES, WOMEN’S BUSINESS
ENTERPRISES, AND LABOR SURPLUS AREA FIRMS §200.321
The County is required to take all necessary affirmative steps to assure that minority business, women's business enterprises, and labor surplus area firms are used when possible. If contractor uses subcontractors, they are also required to take the following affirmative steps:
1. Placing qualified enterprises on solicitation lists.
2. Assuring that enterprises are solicited whenever they are potential sources.
3. Dividing total requirements when economically feasible into smaller tasks or quantities to permit maximum participation by enterprises.
4. Establishing delivery schedules, where the requirement permits, which encourage participation by enterprises.
5. Using the services and assistance, as appropriate, of such organizations as the Small Business Administration and the Minority Business Development Agency of the Department of Commerce.
DFS Portal Confirmation / Declaration:
Do you confirm that you have read the 200.321 Affirmative Steps Confirmation and agree to take the listed affirmative steps when using subcontractors. (Y/N)
Attachment 5: CERTIFICATION REGARDING DEBARMENT, SUSPENSION, INELIGIBILITY and
VOLUNTARY EXCLUSION
Neither the entity or its principals are presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily excluded from participation by any federal department or agency.
DFS Portal Confirmation / Declaration:
Do you confirm that neither the entity nor its principals are presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily excluded from participation by any federal department or agency? (Y/N)
Attachment 6: CONFLICT/NON-CONFLICT OF INTEREST STATEMENT
To the best of our knowledge the bidder has no potential conflict of interest due to any other clients, contracts, or property interest for this project. [ SELECT YES IF TRUE ]
OR
The bidder, by attachment, submits information which may be a potential conflict of interest due to other clients, contracts, or property interest for this project. [ SELECT NO IF TRUE & UPLOAD
DOCUMENTATION ]
Failure to answer appropriately may result in disqualification of your bid.
DFS Portal Confirmation / Declaration:
Do you confirm that to the best of your knowledge the undersigned proposer has no potential conflict of interest due to any other clients, contracts, or property interest for this project? (Y/N)
If answered no, documentation must be uploaded containing information regarding what may be a potential conflict of interest due to other clients, contracts, or property interest for this project.
Attachment 7: DRUG-FREE WORKPLACE AFFIDAVIT
The undersigned certifies that the responding firm has taken steps to :
1. Publish a statement notifying employees that the unlawful manufacture, distribution, dispensing, possession, or use of a controlled substance is prohibited in the workplace and specifying the actions that will be taken against employees for violations of such prohibition.
2. Inform employees about the dangers of drug abuse in the workplace, the business's policy of maintaining a drug-free workplace, any available drug counseling, rehabilitation, and employee assistance programs, and the penalties that may be imposed upon employees for drug abuse violations.
3. Give each employee engaged in providing the commodities or contractual services that are proposed, a copy of the drug- free workplace statement.
4. In the statement specified in drug-free workplace statement, notify the employees that as a condition of working on the commodities or contractual services that are under bid the employee will abide by the terms of the statement and will notify the employer of any conviction of or plea of guilty or nolo contendere to any violation of any controlled substance law of the United States or any state for a violation occurring in the workplace no later than five (5) days after such conviction.
5. Impose a sanction on or require the satisfactory participation in a drug abuse assistance or rehabilitation program if such is available in the employee's community by any employee who is so convicted.
6. Make a good faith effort to continue to maintain a drug-free workplace through implementation of this section.
I certify that this firm complies fully with the above requirements.
DFS Portal Confirmation / Declaration:
Do you confirm that you have read the Drug-Free Workplace Affidavit and certify that the responding company complies fully with the listed requirements? (Y/N)
- Upload the contractor's Drug Free Workplace Policy
APPENDIX A
NRCS Construction & Material Specifications
KY EWP 5076-019 – Peace Valley Rd 09/2024
5076 Letcher - DSR 21 05 23 5076 019 – Peace Valley Road
EMERGENCY WATERSHED PROTECTION (EWP) STREAMBANK
STABLIZATION PROJECT
with the cooperation of the
Letcher COUNTY FISCAL COURT, Letcher COUNTY, KENTUCKY and the
NATURAL RESOURCES CONSERVATION SERVICE (NRCS)
CONSTRUCTION and MATERIAL SPECIFICATIONS
KY EWP 5076-019 – Peace Valley Rd 09/2024
LIST OF APPLICABLE SPECIFICATIONS
Specifications
• NRCS National Construction Specification 4, Channel Clearing and Shaping
• NRCS National Construction Specification 5, Pollution Control
• NRCS National Construction Specification 6, Seeding, Sprigging, and Mulching
• NRCS National Construction Specification 8, Mobilization and Demobilization
• NRCS National Construction Specification 9, Traffic Control
• NRCS National Construction Specification 11, Removal of Water
• NRCS National Construction Specification 21, Excavation
• NRCS National Construction Specification 23, Earthfill
• NRCS National Construction Specification 24, Drainfill
• NRCS National Construction Specification 61, Rock riprap
• NRCS National Construction Specification 64, Gabions and Gabion Mattresses
• NRCS National Construction Specification 81, Metal Fabrication and Installation
• NRCS National Construction Specification 94, Contractor Quality Control
• NRCS National Construction Specification 95, Geotextile
• NRCS Kentucky Construction Specification 414, Concrete Grouting
MATERIAL SPECIFICATIONS
• NRCS National Material Specification 521, Aggregates for Drainfill and Filters
• NRCS National Material Specification 522, Aggregates for Portland Cement Concrete
• NRCS National Material Specification 523, Rock for Riprap
• NRCS National Material Specification 531, Portland Cement
• NRCS National Material Specification 592, Geotextile
CONSTRUCTION DRAWINGS
Peace Valley Rd 5076-019 UTM sheets 1 through 8
210 H 642 CS 4 (June 2024) 1
Construction Specification 4 — Channel Clearing and
Snagging
Title 210 - Engineering Part 642 – Specifications for Construction Contracts Subpart B – National Construction Specifications June 2024
A. Scope
1. The work consists of clearing designated areas by the removal and disposal of trees, logs, stumps, shrubs, brush, and rubbish and the shaping of the channel.
B. Protection of Existing Vegetation
1. Protect trees and other vegetation designated to remain undisturbed from damage throughout the duration of the construction period. Any damages resulting from the contractor’s operations or neglect must be repaired by the contractor.
2. Earthfill, stockpiling of materials, vehicle or equipment parking, and excessive foot or vehicle traffic must not be allowed within the drip line of vegetation designated to remain in place. Vegetation damaged by any of these or similar actions must be replaced with viable vegetation of the same species, similar condition, and like size unless otherwise approved by the contracting officer.
3. Any cuts, skins, scrapes, or bruises to the bark of the vegetation must be carefully trimmed and local nursery-accepted procedures must be used to seal damaged bark.
4. Any limbs or branches 0.5 inch or larger in diameter that are broken, severed, or otherwise seriously damaged during construction must be cut off at the base of the damaged limb or branch, flush with the adjacent limb or tree trunk.
5. All roots 1 inch or larger in diameter that are cut, broken, or otherwise severed during channel shaping must have the ends smoothly cut perpendicular to the root. Roots exposed during channel shaping operations must be covered with moist soil as soon as possible to prevent them from drying out.
C. Marking
1. The limits of the areas to be cleared and shaped are marked by stakes, flags, paint, tree markings, or other suitable methods or as specified in Section H of this specification or will be shown on the drawings. Trees to remain standing, undisturbed, and uninjured are designated by special markings.
D. Clearing
1. Trees and other vegetation marked for clearing must be cut off as near the ground surface as conventional tools and equipment normally permit. All trees not
210 H 642 CS 4 (June 2024) 2 marked for preservation and all snags, logs, brush, shrubs, stumps, and rubbish must be cleared from within the area limits identified.
E. Disposal
1. Dispose of all woody material, vegetation, and rubbish resulting from clearing from designated areas at the locations and in a manner shown on the drawings or as specified in Section H of this specification.
F. Shaping
1. Shape the channel bottom and side slopes as shown on the drawings. The resulting shaped channel surface must be reasonably smooth. Remove and dispose material excavated during the channel-shaping operation from the channel as specified in Section H of this specification.
G. Measurement and Payment
1. Method 1. For items of work for which specific unit prices are established by the contract, the designated cleared and shaped area is measured and area is determined to the nearest 0.1 acre. Payment for clearing and shaping is made at the contract unit price for the item and constitutes full compensation for all labor, equipment, tools, applicable permits and associated fees for burning and disposal of refuse, and all other items necessary and incidental to the satisfactory completion of the work.
2. Method 2. For items of work for which specific unit prices are established by the contract, the length of the cleared and shaped channel designated is measured to the nearest 100 feet. Payment for clearing and shaping is made at the contract unit price for the item and constitutes full compensation for all labor, equipment, tools, applicable permits and associated fees for burning and disposal of refuse, and all other items necessary and incidental to the satisfactory performance of the work.
3. Method 3. For items of work for which specific unit prices are established by the contract, the cleared and shaped areas is measured, and area is determined to the nearest 0.1 acre. The designated cleared and shaped areas is determined from the measured width at representative sections and the distance between the sections.
Payment for clearing and shaping is made at the contract unit price for the item and constitutes full compensation for all labor, equipment, tools, applicable permits and associated fees for burning and disposal of refuse, and all other items necessary and incidental to the satisfactory completion of the work.
4. Method 4. For items of work for which specific lump sum prices are established by the contract, the extent of clearing and shaping is not measured or determined for payment. Payment for clearing and shaping is made at the contract lump sum price for the item and constitutes full compensation for all labor, equipment, tools, applicable permits and associated fees for burning and disposal of refuse, and all other items necessary and incidental to the satisfactory completion of the work.
5. All Methods. The following provisions apply to all methods of measurement and payment. Compensation for any item of work described in the contract but not listed in the bid schedule is included in the payment for the item of work to which
210 H 642 CS 4 (June 2024) 3 it is made subsidiary. Such items and items to which they have been made subsidiary are identified in Section H of this specification.
H. Items of Work and Construction Details
KY EWP 5076-019 – Peace Valley Rd 4
Items of work to be performed in conformance with this specification and the construction details are:
a) Bid Item 1, Channel Clearing and Shaping
1) This item consists of all work necessary to remove and dispose of accumulated sediment, woody debris and any man-made debris as necessary to restore pre-storm flow capacity.
2) In Section B, Protection of Existing Vegetation:
a. Trimming or treatment of cuts, scrapes or bruises to bark or limbs is not required.
b. Limbs or branches 3 inches or larger in diameter that are broken, severed, or otherwise seriously damaged during construction shall be cut off at the base of the damaged limb or branch flush with the adjacent limb or tree trunk.
3) In Section C, Marking, the upstream and downstream extents for channel clearing and shaping will be located by either paint markings on the adjacent roadway, or survey flags as deemed appropriate by site conditions. Trees to remain standing or to otherwise not be disturbed during construction will be marked with paint of survey ribbon.
4) In Section D, Clearing, tree clearing/removal:
a. The removal or adverse impacts to all existing trees, shrubs or other native vegetation shall be avoided and minimized to the extent possible. In general, trees and shrub removal should be targeted for removal only when they inhibit construction, cause a safety hazard within the work limits, or are already felled, severely dislodged or down.
b. Trees that exhibit exfoliating bark characteristics such as shell and shagbark hickories, white oak species; or dead and dying trees with exfoliating bark, broken tree tops, splintered or split areas; trees with cavities or hollowed areas shall not be removed unless
(a) above applies.
c. When possible and feasible all required tree removal shall occur between November 15th and March 31st and will not require NRCS State Biologist prior approval. Tree removal from April 1 to November 14th will require prior approval from the NRCS State Biologist and be marked for retention or removal by an NRCS representative. Trees and shrubs less than 3 inches in diameter may be removed any time of year.
d. If the construction activity occurs in proximity to a known Indiana and/or northern long-eared bat maternity colony or hibernaculum area, any tree removal will require prior approval from the NRCS State Biologist (regardless of time of year) and be marked for removal or retention by an NRCS representative prior to implementation.
e. NRCS will designate any needed ingress and egress, access points, or work areas in woodland and mark trees for removal or retention by an NRCS representative prior to construction.
f. If additional tree removal is required during construction, all the criteria listed above is required.
KY EWP 5076-019 – Peace Valley Rd 5
g. NRCS inspectors will ensure that sponsors and contractors adhere to the above requirements by inspecting the site prior to any work and by making site visits every day or every other day once work has commenced.
5) In Section D, Clearing, stream debris removal/clearing:
a. The use of construction equipment, green concrete, pesticides or other pollutants including fuel and oil products within flowing streams or natural waterbodies during construction activities is prohibited. Plan and install appropriate measures to minimize sediment and turbidity during construction or debris removal.
b. During construction activities, appropriate measures shall be implemented to ensure that the transport of excess nutrients, sediments, pesticides or toxic substances to streams, wetlands and adjacent waterbodies does not occur.
c. Construction activities along the streams and within riparian corridors will be performed only to the minimum level needed to effectively extract targeted debris from the stream.
Tree removal must be performed as outlined above (4).
d. Man-made or natural debris of salvageable value to sponsor or landowner shall be moved, disposed of, or secured in a manner agreeable to sponsor, landowner, Insurance provider, contractor and as determined by the Government Representative. Examples would be marketable timber or damaged autos.
e. Man-made debris dislodged from blockage removal shall be secured and removed from the work area.
6) In Section E, Disposal, manmade debris as removed will be disposed of at an approved landfill. Sediment and woody debris will be disposed of at a location of the project sponsor’s discretion. This disposal area will be outside of the 100 year flood plain. Burning of woody debris on-site will not be permitted.
7) In Section F, Shaping, areas disturbed during the removal process, including banks and access routes, shall be regraded to slopes and grades that are consistent with the surrounding area.
8) In Section G, Measurement and Payment, Method 2 shall apply. Such payment shall constitute full payment for related subsidiary items:
a) Construction Specification 5, Pollution Control
b) Construction Specification 9, Traffic Control
c) Construction Specification 94, Contractor Quality Control
210 H 642 CS 5 (June 2024) 1
Construction Specification 5 — Pollution Control
Title 210 – Engineering Part 642 – Specifications for Construction Contracts
1. The work consists of installing measures or performing work to control erosion and minimize the production of sediment and other pollutants to water and air from construction activities.
2. The following BioPreferred® product categories are applicable to this specification:
a. Mulch and compost materials
b. Erosion control materials
c. Fertilizers
d. Dust suppressants
e. Agricultural spray adjuvants
B. Material
1. Silt fence conform to the requirement of Materials Specification 592, Geotextile.
All other material furnished meet the requirements of the material specifications listed in Section G of this specification.
2. Erosion and Sediment Control Measures and Works. The measures and works includes, but are not limited to, the following:
a. Staging of Earthwork Activities. Scheduling the excavation and moving of soil materials to minimize the size of areas disturbed and unprotected from erosion for the shortest reasonable time.
b. Seeding. Seeding to protect disturbed areas occur as soon as reasonably possible following completion of that earthwork activity.
c. Mulching. Mulching to provide temporary protection of the soil surface from erosion.
d. Diversions. Diversions to divert water from work areas and to collect water from work areas for treatment and safe disposition. These are temporary and must be removed and the area restored to its near-original condition when the diversions are no longer required or when permanent measures are installed.
e. Stream Crossings. Culverts or bridges where equipment must cross streams.
These are temporary must and be removed and the area restored to its near-original condition when the crossings are no longer required or when permanent measures are installed.
f. Sediment Basins. Sediment basins for collecting, settling, and eliminating sediment from eroding areas that impact properties and streams below the
210 H 642 CS 5 (June 2024) 2 construction sites. These basins are temporary and must be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.
g. Sediment Filters. Straw bale filters or geotextile sediment fences for trapping sediment from areas with limited runoff. Sediment filters must be properly anchored to prevent erosion under or around them. Silt fences must be installed and maintained in accordance with ASTM D6462. These filters are temporary and must be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.
h. Waterways. Waterways for the safe disposal of runoff from fields, diversions, and other structures or measures. These works are temporary and must be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.
i. Other. Additional protection measures as specified in Section G of this specification or required by the federal, state, or local government.
C. Chemical Pollution
1. The contractor must provide watertight tanks or barrels or construct a sump sealed with plastic sheets to collect and temporarily contain chemical pollutants, such as drained lubricating or transmission fluids, grease, soaps, concrete mixer wash water, or asphalt, produced as a by-product from the construction activities.
Dispose of pollutants in accordance with appropriate state and federal regulations.
At the completion of the construction work, remove tanks, barrels, and sumps and restore the area to its original condition as specified in Section H of this specification. Sump removal must be conducted without causing pollution.
2. Sanitary facilities, such as chemical toilets, and septic tanks must not be located next to live streams, wells, or springs. They must be located at a distance sufficient to prevent contamination of any water source. At the completion of construction activities, facilities must be disposed of without causing pollution as specified in Section H of this specification.
D. Air Pollution
1. The burning of brush or slash and the disposal of other materials must adhere to state and local regulations.
2. Fire prevention measures must be taken to prevent the start or spreading of wildfires that may result from project activities. Firebreaks or guards must be constructed and maintained at locations shown on the drawings.
3. All public access or haul roads used by the contractor during construction of the project must be sprinkled or otherwise treated to fully suppress dust. All dust control methods must ensure safe construction operations at all times. If chemical dust suppressants are applied, the material must be a commercially available product specifically designed for dust suppression, and the application must follow the manufacturer’s requirements and recommendations. A copy of the product data sheet and manufacturer’s recommended application procedures must be provided to the engineer 5 working days before the first application.
210 H 642 CS 5 (June 2024) 3
E. Maintenance, Removal, and Restoration
1. All pollution-control measures and temporary works must be adequately maintained in a functional condition for the duration of the construction period.
Remove all temporary measures and restore the site to near-original condition.
F. Measurement and Payment
1. Method 1. For items of work for which specific unit prices are established in the contract, each item is measured to the nearest unit applicable. Payment for each item is made at the contract unit price for that item. For water or chemical suppressant items used for dust control for which items of work are established in Section H of this specification, measurement for payment will not include water or chemical suppressants that are used inappropriately or excessively. Such payment will constitute full compensation for the completion of the work.
2. Method 2. For items of work for which lump-sum prices are established in the contract, payment is made as the work proceeds and is supported by invoices presented by the contractor that reflect actual costs. If the total of all progress payments is less than the lump-sum contract price for this item, the balance remaining for this item will be included in the final contract payment. Payment of the lump-sum contract price will constitute full compensation for completion of the work.
3. Method 3. For items of work for which lump-sum prices are established in the contract, payment will be prorated and provided in equal amounts on each monthly progress payment estimate. The number of months used for prorating must be the number estimated to complete the work as outlined in the contractor’s approved construction schedule. The final month’s prorate amount will be provided with the final contract payment. Payment as described will constitute full compensation for completion of the work.
4. All Methods. The following provisions apply to all methods of measurement and payment. Compensation for any item of work described in the contract but not listed in the bid schedule is included in the payment for the item of work to which it is made subsidiary. Such items, and the items to which they are made subsidiary, are identified in Section H of this specification.
G. Items of Work and Construction Details
KY EWP 5076-019 – Peace Valley Road 4
Items of work to be performed in conformance with this specification and the construction details are:
a) Subsidiary Item, Pollution Control
1) This item shall consist of all the work necessary to control erosion and sediment pollution, chemical pollution and air pollution.
2) This item also consists of removal of water including but not limited to general dewatering, pumping, diversion and temporary embankments to exclude water from all work sites.
3) The Contractor’s scheduling shall be made in a manner that will reduce adverse environmental effects. Construction scheduling shall be revised when significant pollution can result due to his planned construction schedule.
4) The Contractor shall perform work in a manner that will reduce erosion and minimize sediments and other pollutants to the water and streams and create a minimum of air pollution consistent with standard construction operations.
5) To the maximum extent practicable, all in-stream work under this contract shall be performed during conditions of low flow.
6) Measures shall be taken to prevent and control spills of fuels, lubricants, or other materials used in construction from entering the stream, drainage way, or water body.
7) Should evidence of stream use or jurisdictional wetland impairment and/ or violations of water quality standards occur as a result of this activity either from a spill or other forms of water pollution the Kentucky Division of Water shall be notified immediately and physical, chemical, or biological examination of the water course shall be conducted and reported. In such case(s), additional facilities or alternative measures may be required.
8) In Section D, Air Pollution, as necessary to control dust, water or other dust suppressors shall be applied to prevent excessively dusty conditions along haul and access roads.
9) In Section F, Measurement and Payment, no method shall apply. Full compensation for the completion of this item of work shall be included in the payment for:
a) Bid Item 5, Rock Riprap, Class III Channel Liner.
b) Bid Item 6, Rock Riprap, Class II, Rail Steel Backfill
c) Bid Item 7, Gabions, 1’ Reno Mattresses
d) Bid Item 8, Gabions
e) Bid Item 9, Steel, Railroad Rail Piling, 15’
f) Bid Item 10, Steel, Railroad Rail Piling, 16’
g) Bid Item 11, Steel, Guard Rail Lagging
h) Bid Item 12, Grouting
210 H 642 CS 6 (June 2024) 1
Construction Specification 6 — Seeding, Sprigging, and
Mulching
Title 210 - Engineering Part 642 – Specifications for Construction Contracts
1. The work consists of preparing the area for treatment; furnishing and placing seed, sprigs, mulch, fertilizer, inoculant, lime, and other soil amendments; and anchoring mulch in designated areas as specified.
2. The following BioPreferred® product categories are applicable to this specification:
a. Mulch and compost materials
b. Erosion control materials
c. Fertilizers
d. Agricultural spray adjuvants
B. Material
1. Seed.
a. All seed must conform to the current rules and regulations of the state where it is being used and must be from the latest crop available. It must meet or exceed the standard for purity and germination listed in Section G.
b. Seed must be labeled in accordance with the state laws and the U.S.
Department of Agriculture rules and regulations under the Federal Seed Act in effect on the date of invitations for bids. Bag tag figures are evidence of purity and germination. No seed will be accepted with a test date of more than 9 months before the delivery date to the site.
c. Seed that has become wet, moldy, or otherwise damaged in transit or storage will not be accepted. The percent of noxious weed seed allowable must be as defined in the current state laws relating to agricultural seeds. Each type of seed must be delivered in separate sealed containers and fully tagged unless an exception is granted in writing by the contracting officer.
2. Fertilizer. Unless otherwise specified, the fertilizer must be a commercial-grade fertilizer. It must meet the standard for grade and quality specified by state law.
Where fertilizer is furnished from bulk storage, the contractor must furnish a supplier’s certification of analysis and weight. When required by the contract, a representative sample of the fertilizer must be furnished to the contracting officer for chemical analysis.
210 H 642 CS 6 (June 2024) 2
3. Inoculants. The inoculant for treating legume seeds must be a pure culture of nitrogen-fixing bacteria prepared specifically for the species and must not be used later than the date indicated on the container or as otherwise specified. A mixing medium, as recommended by the manufacturer, must be used to bond the inoculant to the seed. Two times the amount of the inoculant recommended by the manufacturer must be used (unless seed is applied using a hydraulic seeder; then four times the amount must be used). Seed must be sown within 24 hours of treatment and must not remain in the hydraulic seeder longer than 4 hours.
4. Lime and Other Soil Amendments. Lime must consist of standard ground agriculture limestone or approved equivalent. Standard ground agriculture limestone is defined as ground limestone meeting current requirements of the state’s Department of Agriculture. Other soil amendments must meet quality criteria and application requirements specified in Section G.
5. Mulch Tackifiers. Asphalt emulsion tackifiers must conform to the requirements of ASTM D977, Specification for Emulsified Asphalt. The emulsified asphalt may be rapid setting, medium setting, or slow setting. Non-asphaltic tackifiers required because of environmental considerations must be as specified in Section G.
6. Straw Mulch Material. Straw mulch must consist of wheat, barley, oat or rye straw, hay, grass cut from native grasses, or other plants as specified in Section G.
The mulch material must be air-dried reasonably light in color and must not be musty, moldy, caked, or otherwise of low quality. The use of mulch that contains noxious weeds is not permitted. The contractor must provide a method satisfactory to the contracting officer for determining weight of mulch furnished.
7. Other Mulch Materials. Mulching materials, such as wood cellulose fiber mulch, mulch tackifiers, synthetic fiber mulch, netting, and mesh may be required for specialized locations and conditions. These materials, when specified, must be accompanied by the manufacturer’s recommendations for methods of application.
C. Seeding Mixtures, Sod, Sprigs, and Dates of Planting
1. The application rate per acre for seed mixtures, sprigs, or sod and the date of seeding or planting must be as shown on the plans or as specified in Section G.
D. Seedbed Preparation and Treatment
1. Dress areas to be treated to a smooth, firm surface. On sites where equipment can operate on slopes safely, adequately loosen and smooth the seedbed (4 to 6 inches deep). Depending on soil and moisture conditions, disking, cultipacking, or both, may be necessary to properly prepare a seedbed. Where equipment cannot operate safely, prepare the seedbed by methods like scarifying, providing a roughened soil surface by hand so that broadcast seed will remain in place.
2. If seeding is to be accomplished immediately following construction operations, seedbed preparation may not be required except on a compacted, polished, or freshly cut soil surface.
210 H 642 CS 6 (June 2024) 3
3. Rocks larger than 6 inches in diameter, trash, weeds, and other debris that will interfere with seeding or maintenance operations must be removed or disposed of as specified in Section G.
4. Discontinue seedbed preparation when soil moisture conditions are not suitable for the preparation of a satisfactory seedbed as determined by the responsible engineer.
E. Seeding, Sprigging, Fertilizing, Mulching, and Stabilizing
1. Perform all seeding or sprigging operations in such a manner that the seed or sprigs are applied in the specified quantities uniformly in the designated areas.
The method and rate of seed application must be as specified in Section G. Unless otherwise specified, seeding or sprigging must be accomplished within 2 days after final grading is completed and approved.
2. Apply fertilizer, lime, and other soil amendments as specified in Section G. When specified, the fertilizer and soil amendments must be thoroughly incorporated into the soil immediately following surface application.
3. The rate, amount, and kind of mulching or mesh must be as specified in Section G. Apply mulches uniformly to the designated areas. They must be applied to areas seeded not later than 2 working days after seeding has been performed.
Stabilize straw mulch material within 24 hours of application using a mulch crimper or equivalent anchoring tool or by a suitable tackifier. When the mulch crimper or equivalent anchoring tool is used, it must have straight blades and be the type manufactured expressly for and capable of firmly punching the mulch into the soil. Where the equipment can be safely operated, it must be operated on the contour.