This Invitation to Bid (IFB) document is issued by the Olathe Housing Authority (OHA) in Kansas for the rehabilitation of two public housing units located at 411 N. Iowa and 413 N. Iowa in Olathe, Kansas. The scope of work includes HVAC system replacement (conversion from downflow to upflow systems with new Goodman equipment or approved equal), gas water heater replacement, plumbing and concrete repairs, interior renovations including painting, flooring installation, electrical improvements, kitchen and bathroom renovations, storm door and window covering installation, and final cleaning and site work to return both units to tenant-ready condition. The bid submission deadline is December 18, 2026, at 10:00 AM CST through the City's Bonfire solicitation portal. Questions regarding the solicitation must be submitted by December 8, 2026, at 5:00 PM CST. Site visits and a pre-proposal conference are available upon request. The contract completion deadline is sixty (60) calendar days from the Notice to Proceed, with liquidated damages assessed at $200.00 per calendar day for delays. Board approval is anticipated in January 2027.
This project is funded through Community Development Block Grant (CDBG) funding from the U.S. Department of Housing and Urban Development (HUD). All contractors must comply with federal, state, and local requirements, including Davis-Bacon wage requirements, Section 3 employment and contracting benchmarks (30 percent of labor hours by Section 3 workers and 5 percent by Targeted Section 3 workers), equal opportunity and nondiscrimination requirements, environmental compliance, and lead-based paint regulations. The OHA will award the contract to the lowest responsive and responsible bidder. A bid guarantee of five percent (5%) of the bid amount and assurance of completion (performance and payment bond, cash escrow, or irrevocable letter of credit) are required. All work is covered by a minimum one-year warranty from the date of final acceptance, with emergency warranty issues to be corrected the same business day they are reported. Insurance documentation, licenses, certifications, and all required federal forms, including HUD-5369-A certifications, Section 3 compliance documentation, and conflict of interest certifications, must be submitted with the bid.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OLATHE HOUSING AUTHORITY
OHA PUBLIC HOUSING REHABILITATION
OLATHE HOUSING AUTHORITY
INVITATION TO BID
OHA PUBLIC HOUSING UNIT REHABILITAION
Invitation to Bid Due December 18, 2026, at 10:00 AM (CST)
The Olathe Housing Authority (OHA) is soliciting bids from qualified contractors for the rehabilitation of two (2) Public Housing units located at 411 N. Iowa and 413 N. Iowa. The work includes HVAC and water heater replacement, plumbing and concrete repairs, interior renovations, electrical improvements, and related site work necessary to return both units to tenant occupancy. All work performed under this contract must comply with all applicable federal, state, and local regulations, including but not limited to, those issued by the U.S. Department of Housing and Urban Development (HUD).
INVITATION TO BID ISSUED November 17, 2026
QUESTIONS DUE December 8, 2026, by 5:00 PM (CST)
SITE VISIT and PRE-PROPOSAL CONFERENCE Available Upon Request
BIDS DUE December 18, 2026, at 10:00 AM (CST)
ANTICIPATED BOARD APPROVAL January, 2027
1. Intent The Olathe Housing Authority (OHA) is soliciting sealed bids from qualified contractors for the rehabilitation of the residential units located at 411 N. Iowa and 413 N. Iowa in Olathe, Kansas.
The selected Contractor shall provide all labor, materials, equipment, supervision, construction services, and incidentals necessary to complete the work described in this Invitation for Bids (IFB). The project includes plumbing, concrete, HVAC, electrical, interior improvements, exterior site work, and final cleaning necessary to return both units to safe, functional, and tenant-ready condition.
Bids shall be submitted through the City's designated Bonfire solicitation portal in accordance with the instructions and deadline identified in the solicitation.
2. Project Background The residential units located at 411 N. Iowa and 413 N. Iowa are currently out of service due to interior slab failure caused by leaking and deteriorated drain piping. Portions of the slab have been removed at 413 N. Iowa, and the majority of the slab has been removed at 411 N. Iowa.
The purpose of this contract is to rehabilitate both units and return them to service for tenant occupancy. Upon completion and acceptance, both units shall be clean, safe, functional, and ready for tenant move-in.
3. Scope of Work The Contractor shall complete all work described in this solicitation, including the general requirements and unit-specific work identified in the Scope of Work. The scope includes, but is not limited to:
• Exterior site cleanup and maintenance.
• Replacement of existing downflow HVAC systems with new upflow systems.
• Replacement of gas water heaters.
• Underground waste plumbing and water piping improvements.
• Interior concrete slab restoration.
• Interior painting, wall and ceiling repairs, flooring, and finish work.
• Electrical improvements and replacement of specified fixtures and devices.
• Kitchen and bathroom renovations.
• Door, closet, window covering, and other interior improvements.
• Final cleaning and preparation for tenant occupancy.
The Contractor shall verify existing site conditions and include all labor, materials, equipment, and incidental work necessary to provide a complete and functional installation. Work reasonably necessary to complete the described improvements shall be included in the bid, even if every minor installation detail is not individually listed.
4. Contract Time and Completion The Contractor shall complete the project within sixty (60) calendar days of the Notice to Proceed, unless an extension is approved in writing by OHA.
The Contractor shall coordinate the work to minimize delays and complete both units within the established contract period.
Liquidated damages in the amount of $200.00 per calendar day shall apply for each day the project remains incomplete beyond the contract completion date, subject to the terms of the executed contract.
Substantial completion shall mean that the work is sufficiently complete for its intended use, subject to any remaining punch-list items identified by OHA. Final completion requires correction of all punch-list items, completion of all required work, final inspection, and written acceptance by OHA.
5. General Conditions and Contractor Responsibilities The following conditions apply throughout the project:
1. Smoking: Smoking is prohibited on all OHA property.
2. Worker Identification: All workers must carry valid government-issued photo identification while on the property.
3. Working Hours: Normal working hours are Monday through Friday, 7:30 a.m. to 4:00 p.m. Work outside these hours requires prior approval from OHA.
4. Jobsite Maintenance: The jobsite shall be kept clean and safe at all times. The Contractor shall remove construction debris and maintain orderly work areas daily.
5. Property Security: The Contractor is responsible for maintaining the security of the units and securing the property for the duration of the contract.
6. Materials: OHA reserves the right to retain any materials located on site.
7. Change Orders: All changes to the approved scope of work or contract amount must receive prior written approval from OHA. The Contractor shall not proceed with additional or changed work without written authorization.
8. Inspection: OHA reserves the right to inspect the work at any time during the project.
9. Final Acceptance and Payment: Final payment is contingent upon completion of all work, correction of punch-list items, final inspection, and written acceptance by OHA.
10. Wage-Rate Interviews: The Contractor shall make all contractors, subcontractors, and employees available for wage-rate interviews as requested by OHA or its designated representatives.
11. Warranty: All work shall be covered by a minimum one-year warranty from the date of final acceptance.
12. Emergency Warranty Work: Emergency warranty issues shall be corrected or abated the same business day they are reported. The Contractor shall provide contact information for reporting warranty issues.
6. Site Access and Coordination The Contractor shall coordinate site access, work schedules, inspections, and project activities with the OHA-designated representative.
The Contractor shall provide reasonable advance notice when access or coordination is needed and shall ensure that work activities do not create unnecessary hazards or damage to the property.
The Contractor shall be responsible for protecting existing property, completed work, materials, and equipment throughout construction. Any damage caused by the Contractor or its subcontractors shall be repaired at the Contractor's expense.
7. Contractor Qualifications and Responsibility The Contractor shall have the experience, personnel, equipment, licenses, and qualifications necessary to perform the work described in this solicitation.
The Contractor shall ensure that all work is performed by properly qualified personnel and in accordance with applicable building codes, safety requirements, manufacturer instructions, and other applicable laws and regulations.
The Contractor shall be responsible for the work performed by its employees, subcontractors, and suppliers.
8. Bid Submission Requirements Bids must be submitted electronically through the City's Bonfire solicitation portal before the date and time established in the solicitation.
Bidders are responsible for ensuring that their submissions are complete and received before the deadline. Late submissions will not be accepted.
All questions regarding this solicitation must be submitted through the Bonfire question-and-answer process by the deadline identified in the solicitation. Verbal interpretations or instructions shall not be binding unless issued in writing through an official solicitation addendum.
Bidders shall review all solicitation documents, including attachments and applicable federal funding requirements, before submitting a bid.
9. Bid Evaluation and Award Bids will be evaluated for responsiveness to the solicitation requirements and the responsibility and qualifications of the bidder.
The contract is intended to be awarded to the lowest responsive and responsible bidder whose bid is determined to be in the best interest of OHA, subject to applicable procurement requirements and the availability of funding.
OHA reserves the right to reject any or all bids, waive minor informalities or irregularities, request clarification of information submitted, and make an award in accordance with applicable procurement requirements.
10. Insurance and Contract Requirements The selected Contractor shall provide all insurance documentation, licenses, certifications, and other required contract documents identified in this solicitation before beginning work.
The Contractor shall maintain required insurance coverage throughout the contract period and shall ensure that any subcontractors maintain appropriate coverage as required by the contract.
11. Detailed Scope of Work The Contractor shall furnish all labor, materials, equipment, supervision, and services necessary to complete the following work at both residential units unless otherwise noted.
A. Exterior Site Work – Both Units
1. Remove all trash, debris, and unwanted materials from the property, including the carport.
2. Trim hanging tree limbs at the front corner of 411 N. Iowa and above the carport to provide six (6) feet of clearance.
3. Pressure wash the exterior of the building and carport.
B. HVAC System Replacement – Both Units Existing Conditions and Required Conversion The existing HVAC systems are downflow systems that distribute conditioned air through the slab floor. This configuration shall be abandoned and replaced with new upflow HVAC systems that distribute conditioned air through ceiling supply vents.
The Contractor shall remove, disconnect, or otherwise abandon the existing downflow components as necessary to complete the conversion. The Contractor shall provide and install all equipment, ductwork modifications, connections, and associated components necessary for a complete and operational upflow system in each unit.
Equipment and Installation Requirements Provide and install a new Goodman HVAC system, or approved equal or better, in each unit. Each system shall include:
1. New 80% AFUE gas furnace with a multi-speed blower fan motor.
2. Furnace capacity of 60,000 BTUs.
3. New indoor evaporator coil, 2-ton capacity, with TXV.
4. New matching outdoor condensing unit, 2-ton capacity, 14 SEER, utilizing R32 refrigerant.
5. New refrigerant line set, 3/4-inch x 3/8-inch x 30 feet, between the indoor coil and outdoor condenser.
6. New condensate drain line.
7. Reuse the existing flue through the roof and makeup duct through the ceiling, provided they are suitable for the new installation.
8. Cut ceiling openings as necessary and install new supply vents with louvered registers.
9. New PRO 701 digital thermostat and air filter.
10. New condenser pad, 34 inches x 34 inches x 2 inches.
11. New electrical whip and disconnect box.
Installation and Testing
1. Properly charge each new HVAC system with the required amount of R32 refrigerant.
2. Test and balance each system to verify proper airflow and heating and cooling performance.
3. Verify that all equipment and components are properly installed and operational before project acceptance.
C. Gas Water Heater Replacement – Both Units Remove and replace the existing water heater in each unit. Provide and install:
1. New 40-gallon water heater with 40 MBH input.
2. New expansion tank.
3. New quarter-turn shutoff valve.
4. Replace the roof cap if the existing cap cannot be reused.
All installations shall comply with applicable plumbing and building codes. The Contractor shall test the completed installation for proper operation and leaks.
D. General Interior Improvements – Both Units
1. Painting: Paint all interior walls, ceilings, and doors. OHA will provide paint color numbers for walls, ceilings, doors, and trim. Paint shall be Sherwin-Williams or approved equal.
2. Wall and Ceiling Repairs: Repair all wall and ceiling surfaces as necessary to provide a smooth, finished surface ready for painting.
3. Flooring: Install new 6-inch x 36-inch glue-down LVT plank flooring in each room. OHA will provide a sample color for the Contractor to reasonably match. Install 4-inch cove base throughout each unit.
4. Plumbing Shutoff Valves: Install new shutoff valves at all wet locations, including the main shutoff.
5. Laundry Connections: Install new washing machine supply boxes with hot and cold shutoff valves.
Upgrade the drain line behind the wall to 2 inches.
6. Electrical Devices: Replace all GFCI outlets and install new GFCI protection as required by code. Install new duplex outlets, toggle switches, and cover plates. Install dedicated outlets for appliances located within six (6) feet of a water source, as required by applicable code. All devices and cover plates shall be white.
7. Doors and Wall Repairs: Adjust all interior and exterior doors to latch properly. Install door stops.
Remove existing round wall protectors and repair affected wall surfaces.
8. 411 N. Iowa – Attic Access- Close the existing attic access opening in the bedroom closet. Install sheetrock and finish the ceiling surface to match the surrounding area.
413 N. Iowa – Attic Access- Rebuild the attic access openings in the bedroom closets.
9. Sound Insulation: Insulate the adjoining bathroom wall for sound reduction.
10. Storm Doors: Install new Emco Light White Vinyl Retractable Storm Doors at the front and rear entry doors, or approved equal or better.
11. Window Coverings: Install new 1-inch vinyl cordless mini-blinds at each window.
12. Light Bulbs: Install new light bulbs in each fixture.
13. Insulation: Replace insulation as needed to complete the project.
E. Kitchen Improvements – Both Units
1. Sand and apply a clear coat finish to existing kitchen cabinets.
2. Install new Formica kitchen countertops.
3. Install new 1/3 HP garbage disposal.
4. Install new kitchen faucet and supply lines.
5. OHA will supply the refrigerator and stove. The Contractor shall coordinate with OHA regarding placement and installation as needed.
F. Bedroom Improvements – Both Units
1. Install a new closet pole at 70 inches in height, with two metal support brackets and one continuous shelf across the entire closet.
2. Relocate the smoke detector to four (4) inches away from the wall at the bedroom door, as permitted by applicable code and manufacturer requirements.
G. Underground Waste Plumbing and Water Piping – Both Units
1. Excavate and grade the underground areas as necessary to prepare for installation of new waste piping.
2. Excavate the area around the combination main through the foundation.
3. Rough-in and install all new underground waste piping.
4. Install new poly piping for hot and cold water underground and rough in connections to the kitchen, bathroom, and laundry areas.
5. Grade and bed all new piping in accordance with applicable plumbing codes and installation requirements.
6. Backfill excavated areas using salvaged soil and additional gravel as necessary.
The Contractor shall coordinate underground plumbing work with the concrete slab restoration work to ensure that all piping is properly installed, inspected as required, and ready for slab placement.
H. Concrete Interior Slab Restoration – Both Units
1. Remove debris and prepare all areas necessary for placement of the missing concrete slab sections.
2. Place a four (4)-inch layer of crushed stone or gravel and compact the material.
3. Epoxy #4 rebar into the existing slab at 16-inch intervals.
4. Raise interior walls to ceiling truss height before concrete placement, as necessary to complete the work.
5. Secure wall bottom plates to the new concrete slab.
All concrete work shall be completed in accordance with applicable building codes and accepted construction practices. The Contractor shall coordinate concrete placement with plumbing installation and required inspections.
I. Bathroom Improvements – Both Units
1. Demolish the existing bathroom finishes, including wall tile. Replace with new sheetrock and mud/tape to match the existing wall finish.
2. Install a new bathtub and tub surround.
3. Install two (2) grab bars. Provide appropriate backing or structural support before installing the tub surround to ensure secure attachment.
4. Install a new shower cartridge, shower spout, and showerhead.
5. Install a new high-efficiency, gravity-flush toilet with elongated bowl and chair-height seating.
6. Install a new exhaust fan equal to or better than the existing fan.
7. Wire the exhaust fan and bathroom light so both fixtures turn on simultaneously.
8. Install new bathroom accessories, including a towel bar and toilet paper holder.
J. Unit-Specific Work – 411 N. Iowa In addition to the work identified for both units, complete the following:
1. Install a new 30-inch range hood.
2. Demolish the kitchen ceiling and repair or replace it to match the surrounding area. Replace insulation as needed.
3. Rescreen one window screen.
4. Replace all interior doors and casing with new six-panel doors and split-jamb casing.
5. Remove the door separating the hallway from the laundry area and convert the opening to a cased opening.
6. Install new door hardware matching the existing hardware type. Install a privacy knob on the bathroom door.
7. Remove the bedroom ceiling fan and install a new 15-inch flush-mount light fixture matching the style used in the unit.
8. Reinstall all base cabinets and securely fasten upper cabinets.
K. Unit-Specific Work – 413 N. Iowa In addition to the work identified for both units:
1. Relocate the utility closet drain to a position just behind the door to improve accessibility.
L. Final Cleaning – Both Units Upon completion of all construction and installation work, the Contractor shall thoroughly clean both units and leave them in a clean, sanitary, and move-in-ready condition.
Final cleaning shall include, at a minimum:
1. Remove all remaining trash, abandoned items, and debris from the units, patios or balconies, storage areas, and exterior entry areas immediately adjacent to the units.
2. Clean and disinfect all kitchen surfaces, including countertops, cabinets inside and out, sinks, fixtures, appliances, range hood, refrigerator, oven, and floors.
3. Clean and disinfect bathrooms, including toilets, tubs and showers, sinks, vanities, mirrors, fixtures, exhaust grilles, cabinets, and floors.
4. Dust and wipe all horizontal and vertical surfaces, including doors, trim, baseboards, window sills, blinds, vents, light fixtures, ceiling fans, and closet shelving.
5. Shop-vacuum confined areas, including closets and floor edges.
6. Sweep and wet-mop all hard-surface flooring using appropriate cleaning products.
7. Clean interior windows, including inside and outside surfaces, window tracks, mirrors, and accessible glass and reflective surfaces.
8. Remove cobwebs and clean accessible wall surfaces.
9. Secure all doors and windows upon completion.
10. Notify the Facilities and Housing Maintenance Supervisor of any deficiencies identified during final cleaning or inspection.
Both units shall be delivered clean, sanitary, safe, functional, and ready for tenant occupancy.
12. Inspection and Acceptance OHA or its designated representative may inspect the work throughout the project. The Contractor shall correct any deficient, incomplete, or nonconforming work identified during inspections at no additional cost to OHA.
Upon notification that the work is complete, the Contractor shall coordinate a final inspection with OHA. Any punch-list items shall be corrected before final acceptance.
Final acceptance will be provided in writing by OHA after all required work has been completed and accepted.
13. Warranty The Contractor shall provide a minimum one-year warranty covering all labor, materials, workmanship, and installed equipment, beginning on the date of final written acceptance.
The Contractor shall correct warranty deficiencies at no additional cost to OHA. Emergency warranty work shall be corrected or abated the same business day it is reported.
14. Federal Funding Requirements This project is funded in whole or in part through Community Development Block Grant (CDBG) funding. The Contractor shall comply with all applicable federal, state, and local requirements associated with the funding and performance of this contract.
The federal funding requirements, certifications, and applicable contract provisions are included in the attachments following this section. These requirements are incorporated into the solicitation and, upon award, the resulting contract.
ATTACHMENTS
Instructions for HUD and OHA Required Forms As part of this RFP a list of forms is provided below. Each respondent is responsible for reviewing, completing, and submitting all forms designated as Return. Failure to complete and return required forms may render a proposal non-responsive.
General Guidance:
• Use the most current versions of the HUD forms provided in this RFP package.
• Where a signature is required, forms must be signed by an authorized representative of the Respondent.
• Notarization is required when included in the document.
• Forms marked Read-Only are for reference only and do not require return.
• If any form is incomplete or missing, OHA reserves the right to request clarification; however, such requests may not be made if the omission is material.
Attachment # Return Read-Only
A Vendor Response Form X B Federal Funding and CDBG Contract Provisions X
C Section 3 Compliance and Participation Form X D Conflicts of Interest Certification X
E Non-Collusive/Non-Identity of Interest Affidavit X
F HUD-5369: Instructions to Bidders for Contracts X
G HUD-5369-A: Representations, Certifications and Other Statements of Bidders (Construction)
X
H HUD-5370: General Conditions for Construction Contracts X I HUD-50070: Certification for a Drug-Free Workplace X
J HUD-50071: Certification of Payments to Influence Federal Transactions
X
K HUD-2992: Certification Regarding Debarment and Suspension X
L Olathe Housing Authority Instructions: General Terms and Conditions
X
M Bid Bond Form X
N Insurance Requirements X
O Sample Standard Agreement X
P Davis Bacon Wages X
VENDOR RESPONSE FORM
Attachment A
Proposer Information:
Legal Name of Company: ___________________________________________________________________________
Doing Business As (if different): ______________________________________________________________________
Federal Tax ID Number: _____________________________________________________________________________
UEI # (Unique Entity Identifier, formerly DUNS): _______________________________________________________
Address: __________________________________________________________________________________________
City, State, Zip Code: _______________________________________________________________________________
Contract Person: ___________________________________________________________________________________
Title: ______________________________________________________________________________________________
Phone number: ____________________________________________________________________________________
Email address: _____________________________________________________________________________________
Website: __________________________________________________________________________________________
Company Structure and Experience:
Type of Legal Entity (Check one):
[ ] Corporation [ ] Limited Liability Company (LLC) [ ] Partnership [ ] Sole Proprietorship [ ] Other (Specify): ____________________________________________________
State of Formation/Incorporation: _________________________________________
Date Company Established (MM/DD/YYYY): ________________________________
Acknowledgement and Certifications:
1. Acknowledgement of Addenda: The undersigned Proposer acknowledges receipt of the following Addenda to this Request for Proposal:
Addendum No. ______ Dated: ____________ Addendum No. ______ Dated: ____________ Addendum No. ______ Dated: ____________ (If no Addenda have been issued, please state "None". If more space is needed, please attach a separate sheet.)
2. General Certification: I hereby certify that the above information is true and correct to the best of my knowledge. I also certify that I hold the authority to contract with the Olathe Housing Authority and that this Proposal, including all required forms and attachments, is submitted in full understanding and acceptance of all terms, conditions, and requirements set forth in this Request for Proposal.
Firm Name: ____________________________________________________
Authorized Representative Name (Printed): _________________________
Authorized Representative Signature: _____________________________
Title: ________________________________________________________
Date: ________________________________________________________
Attachment B
FEDERAL FUNDING AND CDBG CONTRACT PROVISIONS
The Contractor shall comply with all applicable federal, state, and local laws, regulations, requirements, and conditions governing the use of Community Development Block Grant (CDBG) funds for this project. The following provisions are incorporated into the contract and shall apply to the Contractor and all subcontractors performing work under this agreement.
1. Federal Funding Requirements This project is funded, in whole or in part, through the U.S. Department of Housing and Urban Development (HUD) Community Development Block Grant (CDBG) program.
The Contractor acknowledges that federal funding requirements apply to this project and agrees to comply with all applicable federal statutes, regulations, executive orders, and grant conditions.
The Contractor shall ensure that all subcontractors are informed of and comply with applicable federal requirements.
2. Equal Opportunity and Nondiscrimination The Contractor shall comply with all applicable federal civil rights and nondiscrimination requirements, including but not limited to:
• Title VI of the Civil Rights Act of 1964.
• Section 109 of the Housing and Community Development Act of 1974.
• Section 504 of the Rehabilitation Act of 1973.
• The Americans with Disabilities Act, as applicable.
• The Age Discrimination Act of 1975.
• The Fair Housing Act.
The Contractor shall not discriminate against any person on the basis of race, color, national origin, religion, sex, disability, or age in connection with the performance of this contract, as applicable under the governing laws and regulations.
3. Conflict of Interest The Contractor shall disclose any actual or potential conflict of interest involving the Contractor, its employees, agents, subcontractors, or any person associated with the project.
The Contractor shall not engage in activities that create an actual or apparent conflict of interest in the performance of this contract.
Any potential conflict shall be reported promptly to the Olathe Housing Authority.
4. Suspension and Debarment The Contractor certifies that neither the Contractor nor its principals are currently suspended, debarred, declared ineligible, or voluntarily excluded from participation in federally assisted programs.
The Contractor shall notify the Olathe Housing Authority immediately if its eligibility status changes during the performance of this contract.
The Contractor shall not knowingly subcontract with any party that is suspended, debarred, or otherwise excluded from federally assisted transactions.
5. Anti-Lobbying Requirements The Contractor shall comply with the Byrd Anti-Lobbying Amendment (31 U.S.C. 1352) and applicable federal regulations.
For covered contracts exceeding $100,000, the Contractor shall certify that no federal appropriated funds have been or will be used to pay any person or organization to influence or attempt to influence a federal agency, member of Congress, or congressional employee in connection with obtaining this award.
Any required disclosure of lobbying activities conducted with non-federal funds shall be submitted using the applicable federal disclosure form.
6. Environmental Compliance The Contractor shall comply with all environmental requirements and conditions applicable to the project under the CDBG program.
The Contractor shall:
• Comply with applicable federal, state, and local environmental laws and regulations.
• Properly handle, store, transport, and dispose of construction materials and waste.
• Immediately notify the Olathe Housing Authority of any discovery of hazardous materials, suspected contamination, or environmental concerns.
• Follow all environmental mitigation measures and project-specific conditions communicated by the
Olathe Housing Authority.
No construction activities may begin until the Olathe Housing Authority has issued authorization to proceed and confirmed that all required environmental approvals and conditions have been satisfied.
7. Lead-Based Paint Requirements The Contractor shall comply with applicable federal, state, and local lead-based paint requirements, including applicable HUD regulations under 24 CFR Part 35 and EPA regulations under 40 CFR Part 745.
Where applicable, the Contractor shall:
• Maintain required EPA Renovation, Repair and Painting (RRP) certification.
• Use appropriately trained and certified personnel.
• Follow required lead-safe work practices.
• Properly contain, handle, and dispose of lead-containing materials and debris.
• Provide required documentation of inspections, testing, clearance, and completed work.
The Contractor shall not disturb suspected lead-based paint materials without first following applicable notification, evaluation, and safety requirements.
8. Access to Records and Audit Requirements
The Contractor shall maintain accurate records, invoices, receipts, payroll documentation when applicable, subcontractor records, and other supporting documentation related to the performance and payment of this contract.
The Contractor shall provide access to relevant project records to the Olathe Housing Authority, the City of Olathe, HUD, the U.S. Comptroller General, and other authorized federal, state, or local representatives upon reasonable request.
The Contractor shall cooperate with any audit, monitoring, inspection, or review related to this project.
9. Record Retention The Contractor shall retain project records for the period required by applicable federal regulations and the contract.
Records shall be maintained in a manner that allows the Olathe Housing Authority and authorized representatives to verify project costs, payments, compliance, and completion.
10. Termination for Cause or Convenience The Olathe Housing Authority may terminate this contract for cause or convenience in accordance with the terms of the executed agreement and applicable federal requirements.
Termination for cause may occur when the Contractor fails to perform required work, violates contract requirements, or otherwise fails to meet its contractual obligations.
Termination for convenience may occur when the Olathe Housing Authority determines that termination is in its best interest.
In the event of termination, the Contractor shall be compensated only for eligible and acceptable work completed through the effective date of termination, subject to the terms of the agreement.
11. Remedies for Breach of Contract The Olathe Housing Authority reserves the right to pursue applicable administrative, contractual, or legal remedies when the Contractor violates or breaches the terms of this agreement.
Available remedies may include withholding payment, requiring corrective action, assessing damages where authorized, or terminating the contract.
12. Domestic Preference and Recovered Materials To the extent applicable and consistent with federal law, the Contractor shall comply with domestic preference requirements under 2 CFR 200.322.
The Contractor shall also comply with applicable recovered materials requirements under 2 CFR 200.323 and Section 6002 of the Resource Conservation and Recovery Act when applicable to the products and materials purchased for this project.
13. Prohibition on Certain Telecommunications and Video Surveillance Equipment The Contractor shall comply with applicable federal restrictions under 2 CFR 200.216 regarding the procurement or use of prohibited telecommunications and video surveillance equipment or services in connection with this federally funded project.
14. Subcontractor Compliance The Contractor shall be responsible for ensuring that all subcontractors performing work under this agreement comply with applicable federal funding requirements and contract provisions.
The Contractor shall provide applicable federal requirements to its subcontractors and shall remain responsible for the performance and compliance of all subcontractors.
15. Additional Federal Requirements The Contractor shall comply with any additional federal requirements applicable to this project, including requirements identified in the CDBG grant agreement, approved environmental review, funding conditions, or written instructions issued by the Olathe Housing Authority.
Where additional requirements apply, the Olathe Housing Authority may provide supplemental instructions or contract provisions.
CONTRACTOR ACKNOWLEDGMENT
By signing below, the Contractor acknowledges receipt and understanding of these Federal Funding and CDBG Contract Provisions and agrees to comply with all applicable requirements throughout the performance of the contract.
Contractor Legal Name: __________________________________ Authorized Representative: _______________________________ Title: _________________________________________________ Signature: _____________________________________________ Date: _________________________________________________
SECTION 3 COMPLIANCE AND PARTICIPATION FORM
Attachment C
Instructions to Proposer: Please complete this form in its entirety and submit it as part of your Proposal.
A. APPLICABILITY OF SECTION 3
This RFP and any resulting contract are subject to the requirements of Section 3 of the Housing and Urban Development Act of 1968, as amended (12 U.S.C. 1701u), and the implementing regulations at 24 CFR Part 75.
The purpose of Section 3 is to ensure that, to the greatest extent feasible, employment and other economic opportunities generated by HUD financial assistance for housing and community development programs are directed to low- and very low-income persons, particularly those who are recipients of government assistance for housing, and to Section 3 business concerns.
B. SECTION 3 COMPLIANCE REQUIREMENTS
Section 3 – Qualitative Efforts.
If a proposer cannot meet the numerical Section 3 benchmarks, they must document “qualitative efforts” as described by HUD.
• See HUD Section 3 FAQs – Qualitative Efforts (Feb 2025):
https://www.hud.gov/sites/documents/11secfaqs.pdf
• PIH Notice 2022-10: Implementation of the Final Rule on Section 3 (examples of qualitative efforts):
https://www.hud.gov/sites/dfiles/PIH/documents/PIH2022-10.pdf
• 24 CFR Part 75 (especially §§ 75.15 & 75.25): https://www.ecfr.gov/current/title-24/subtitle-A/part-75
The Olathe Housing Authority OHA), as a recipient of HUD financial assistance, is committed to full compliance with Section 3 requirements. The selected Contractor will be required to comply with all applicable Section 3 provisions set forth in 24 CFR Part 75, including but not limited to:
1. Quantitative Benchmarks (24 CFR § 75.19): The Contractor must make "greatest extent feasible" efforts to meet the following benchmarks for all Section 3 covered contracts awarded by the OHA for the project:
o 30 percent of the total number of labor hours worked by all workers on the project are performed by Section 3 workers.
o 5 percent of the total number of labor hours worked by all workers on the project are performed by Targeted Section 3 workers (as defined in 24 CFR § 75.5 and § 75.11(a)).
2. Qualitative Efforts (24 CFR § 75.31(b)): Even if the quantitative benchmarks are not met, the Contractor must demonstrate comprehensive "greatest extent feasible" efforts to comply with Section 3, including but not limited to:
o Engaging in targeted outreach to Section 3 workers and Section 3 business concerns.
https://www.hud.gov/sites/documents/11secfaqs.pdf https://www.hud.gov/sites/dfiles/PIH/documents/PIH2022-10.pdf https://www.ecfr.gov/current/title-24/subtitle-A/part-75 o Providing technical assistance to help Section 3 business concerns understand how to do business with the Contractor.
o Breaking out contract work into smaller components to facilitate Section 3 business concern participation.
o Forming partnerships and joint ventures with Section 3 business concerns.
o Providing training or apprenticeship opportunities.
o Providing retention and support services to Section 3 workers.
3. Contract Clauses: The executed contract will include all mandatory Section 3 contract clauses as required by 24 CFR Part 75.
4. Flow-Down Requirements: The Contractor shall ensure that all applicable Section 3 requirements are included in any subcontracts for work arising in connection with this project.
5. Reporting: The Contractor will be required to submit HUD Form 60002, Section 3 Summary Report, as directed by the OHA, on at least an annual basis or at contract completion, detailing efforts and outcomes related to Section 3 employment, training, and contracting.
C. PROPOSER'S SECTION 3 PARTICIPATION ELECTION AND COMMITMENT
Please select ONE of the following options and complete the relevant sections.
OPTION 1: We are NOT Certifying as a Section 3 Business Concern for this Solicitation.
Check this box if your firm does not qualify as a Section 3 Business Concern, or you are not seeking a Section 3 preference at this time.
[ ] By selecting this option, our firm acknowledges the applicability of Section 3 to this contract and commits to making good faith efforts, to the greatest extent feasible, to comply with all Section 3 requirements for employment, training, and contracting opportunities as outlined in 24 CFR Part 75. We understand that if awarded a contract, we will be required to demonstrate these efforts and report on Section 3 outcomes as required by the OHA and HUD (e.g., via HUD Form 60002). We will also require our subcontractors to comply with Section 3.
OPTION 2: We ARE Certifying as a Section 3 Business Concern.
Check this box if your firm qualifies as a Section 3 Business Concern under one of the categories below, as defined in 24 CFR § 75.5. Note: Selecting this option does not guarantee preference unless explicitly stated elsewhere in this RFP's evaluation criteria.
[ ] By selecting this option, our firm certifies that it meets the definition of a Section 3 Business Concern. We are claiming Section 3 status under the following category (select ONE that applies to your primary qualification):
• [ ] (i) At least 51 percent or more owned and controlled by low- or very low-income persons.
o Required Documentation: Provide documentation of ownership (e.g., articles of incorporation, partnership agreement) and income certifications for all qualifying owners (e.g., self-certifications, third-party verifications) demonstrating their status as low- or very low-income persons for the Kansas City, MO-KS HUD Metro FMR Area.
• [ ] (ii) At least 30 percent or more of the permanent, full-time employees are currently Section 3 residents or were Section 3 residents within three years of the date of their first employment with the business concern.
o Required Documentation: Provide documentation such as payroll records, Section 3 worker certifications (e.g., HUD-4736, if applicable), and a list of qualifying employees with their hire dates and dates of Section 3 residency.
• [ ] (iii) Provides evidence of a commitment to subcontract in excess of 25 percent of the dollar award of the prime contract (including any modifications) to Section 3 business concerns.
o Required Documentation: Provide a detailed plan listing identified Section 3 business concerns, proposed subcontract scopes and amounts, their Section 3 certifications, and letters of intent or firm commitments from these Section 3 subcontractors.
Please provide the following additional information if selecting Option 2:
• Brief description of how your firm meets the Section 3 Business Concern definition (referencing the category chosen above):
(Example: "Our firm is 75% owned by Jane Doe, a certified low-income resident..." or "35% of our permanent full-time staff meet the Section 3 resident criteria..." or "We commit to subcontracting 30% of our contract value to certified Section 3 Business Concerns...")
D. PROPOSER'S SECTION 3 COMPLIANCE PLAN / STATEMENT OF INTENT
Regardless of whether your firm certifies as a Section 3 Business Concern, all proposers are REQUIRED to submit a narrative Section 3 Compliance Plan. This plan should be a standalone document (no more than 1 page) attached to your Proposal.
Your Section 3 Compliance Plan should demonstrate your understanding of and commitment to the Section 3 requirements, specifically addressing how your firm will meet the "greatest extent feasible" efforts, including both the quantitative benchmarks and qualitative efforts defined in 24 CFR Part 75. Your plan should address, at a minimum:
1. Hiring and Training: Specific strategies for maximizing the employment and training of Section 3 workers and Targeted Section 3 workers, including outreach, recruitment methods, and any proposed training or apprenticeship programs.
2. Contracting Opportunities: Specific strategies for maximizing contracting opportunities with Section 3 business concerns, including outreach to Section 3 firms, breaking out contract work, and partnering opportunities.
3. Reporting and Tracking: Your proposed methods for tracking labor hours and contracts, and for submitting required Section 3 reports (e.g., HUD Form 60002).
4. Flow-Down to Subcontractors: How you will ensure your subcontractors comply with Section 3 requirements.
5. Monitoring and Accountability: How your firm will monitor its own performance and ensure accountability for Section 3 compliance throughout the contract term.
E. CERTIFICATION
By signing below, the undersigned hereby certifies that the information provided in this Section 3 Compliance and Participation Form is accurate and complete to the best of their knowledge and belief. The undersigned further acknowledges the Section 3 requirements and commits to complying with all applicable provisions of 24 CFR Part 75 if selected.
Firm Name: ____________________________________________________
Authorized Representative Name (Printed): _________________________
Authorized Representative Signature: _____________________________
CONFLICTS OF INTEREST CERTIFICATION
Attachment D
Instructions to Proposer: Please complete this form in its entirety and submit it as part of your Proposal. Failure to disclose potential conflicts of interest may result in the disqualification of your Proposal or termination of any resulting contract.
A. PURPOSE AND APPLICABILITY
The Olathe Housing Authority is committed to maintaining the highest ethical standards in its procurement processes and contractual relationships. This Conflicts of Interest Certification is required to ensure transparency and to identify, prevent, or mitigate any actual, apparent, or potential conflicts of interest that could arise during the selection process or the performance of any resulting contract.
This certification applies to the Proposer and its principals, officers, directors, key personnel, and any immediate family members of such individuals, as they relate to the OHA, its employees, officials, and Board members.
B. DEFINITION OF CONFLICT OF INTEREST
For the purpose of this RFP, a "Conflict of Interest" includes, but is not limited to, any situation where:
1. Financial Interest: The Proposer, its principals, officers, directors, key personnel, or their immediate family members (spouse, children, parents, siblings) have a direct or indirect financial interest in the OHA, its employees, officials, or Board members, or in any other entity or individual that would benefit financially from the award of this contract or the underlying development project.
2. Familial Relationship: A familial relationship (e.g., spouse, child, parent, sibling) exists between any principal, officer, director, or key personnel of the Proposer (or their immediate family members) and any employee, official, or Board member of the OHA involved in the selection process or oversight of this contract.
3. Prior Employment/Association: Any principal, officer, director, or key personnel of the Proposer (or their immediate family members) has been employed by or served on the board of the OHA within the past 5 years or has a current or recent business association with any OHA employee, official, or Board member that could create an unfair advantage or perception of undue influence.
4. Shared Ownership/Control: The Proposer, its principals, officers, or directors have any direct or indirect ownership interest, management control, or significant influence over any other firm or entity that is also submitting a Proposal for this RFP, or that could be a subcontractor, consultant, or otherwise financially benefit from the same project.
5. Confidential Information: The Proposer has obtained or used confidential information from the OHA not generally available to other proposers, which provides an unfair competitive advantage.
6. Any Other Relationship/Circumstance: Any other relationship, circumstance, or interest that could be perceived as impairing the objectivity, independence, or fair judgment of the Proposer, or that could provide an unfair advantage in the selection process or during contract performance.
C. DISCLOSURE OF CONFLICTS OF INTEREST
1. No Conflicts to Disclose:
[ ] Check this box if, after diligent inquiry, the Proposer certifies that there are NO actual, apparent, or potential conflicts of interest as defined above, or any other relationships that could reasonably be perceived as a conflict, concerning this RFP, its principals, key personnel, or their immediate family members, with the OHA, its employees, officials, or Board members.
2. Conflicts to Disclose:
[ ] Check this box if the Proposer HAS actual, apparent, or potential conflicts of interest to disclose as defined above.
If this box is checked, the Proposer MUST provide a detailed explanation for each conflict on a separate sheet, including:
• The nature of the relationship or interest.
• The individuals or entities involved.
• How the conflict arose.
• The steps the Proposer has taken or proposes to take to avoid, mitigate, or manage the conflict to ensure fair dealing and protect the OHA's interests.
D. ONGOING OBLIGATION AND CONSEQUENCES
The obligation to disclose conflicts of interest is ongoing. If any actual, apparent, or potential conflict of interest arises or is discovered after the submission of this Proposal and prior to or during the term of any resulting contract, the Proposer/Contractor must immediately notify the OHA in writing.
The OHA reserves the right to:
• Disqualify any Proposal based on an undisclosed or unresolved conflict of interest.
• Terminate any resulting contract if a conflict of interest is discovered or arises and cannot be satisfactorily resolved or mitigated.
• Pursue any other remedies available by law.
E. CERTIFICATION
By signing below, the undersigned hereby certifies that they have read, understood, and complied with the requirements of this Conflicts of Interest Certification. All information provided herein is accurate and complete to the best of their knowledge and belief. The undersigned further acknowledges the ongoing obligation to disclose any conflicts that may arise.
Firm Name: ____________________________________________________
Authorized Representative Name (Printed): _________________________
Authorized Representative Signature: _____________________________
NON-COLLUSIVE / NON-IDENTITY OF INTEREST AFFIDAVIT
Attachment E
Instructions to Proposer: This Affidavit must be completed, signed, and submitted with your Proposal. Providing false information may result in disqualification and other legal consequences.
A. AFFIDAVIT OF NON-COLLUSION
The undersigned, being duly sworn, deposes and says that:
1. The Proposer has prepared the response to this RFP.
2. The Proposal is made without any understanding, agreement, or connection with any other person, firm, partnership, or corporation making a submission for the same purpose, and is in all respects fair and without collusion or fraud.
3. No action has been taken or will be taken by the Proposer in restraint of free competitive bidding or proposing in connection with this Proposal.
4. No officer, employee, or agent of the Proposer has been in any way involved in the development of the specifications or scope of services for this Proposal.
5. No attempt has been made or will be made by the Proposer to induce any other person, firm, or corporation to submit or not to submit a Proposal for the purpose of restricting competition.
6. The Proposal is genuine and not made in the interest of, or on behalf of, any undisclosed person, firm, or corporation.
B. AFFIDAVIT OF NON-IDENTITY OF INTEREST
The undersigned further deposes and says that:
1. No federal, state, or local public official or employee who exercises responsibility or decision-making authority in connection with any project assisted under a HUD program has any financial interest, direct or indirect, in this Proposer firm or in any contract or subcontract for work or services to be performed in connection with the project for which this Proposal is submitted.
2. No officer, employee, architect, attorney, engineer, or other consultant or firm of consultants of the OHA, or any of their immediate family members (spouse, child, parent, sibling), who is in a position to influence a decision on the award of this contract, has any direct or indirect financial interest in the Proposer firm.
3. The Proposer, its principals, officers, or directors, do not have any identity of interest with any OHA official,…