1-GL-2026-32 50 Nye Road Parking Lot Improvements- Light Poles and FIxtures -Final.pdf

PDF 24 MB Posted

Attached to
50 Nye Road Parking Lot Improvements- Light Poles and Fixtures Installation
Solicitation number
GL-2026-32
Issued by
Hartford County, Connecticut

About this file

File Summary

This is a Town of Glastonbury, Connecticut, Invitation to Bid and Contract Documents (Bid #GL-2026-32) for furnishing and installing exterior parking lot illumination light poles and fixtures at 50 Nye Road. The project involves the installation of decorative steel fluted poles with LED post-top luminaires and one ground-mounted light fixture to support a parking lot reconstruction performed by Town forces. Bidders must submit proposals online through the Town's e-Procurement portal (glastonburyct.bonfirehub.com) by July 7, 2026, at 11:00 A.M. The project advertised on June 23, 2026. Line items include nine Type SA3 light poles and fixtures, eleven Type SA4 units, three Type SA5 units, and one ground-mounted light fixture. The Town will award either the Base Bid or a Bid Alternate based on cost comparison between two different manufacturers (Sternberg Heritage Series or AV Poles and Lighting Utility Series). Contract work must be substantially completed within 30 days of the Notice to Proceed, with work limited to Monday through Friday between 7:00 A.M. and 5:00 P.M. unless approved otherwise. The successful bidder must provide a 100% Performance Bond and 100% Payment Bond prior to purchase order issuance.

Bidders must submit a bid bond equal to 10% of the base bid with electronic submissions, with original bonds mailed within 24 hours of virtual bid opening. The project is subject to Connecticut prevailing wage requirements under General Statutes Section 31-53, and certified weekly payrolls must be submitted. A 25% subcontractor set-aside requirement applies to state-funded portions, with preference for Connecticut Department of Administrative Services-certified Small and Minority-owned businesses and Minority, Women, and Disabled-owned businesses. All work must comply with Form 819 (State of Connecticut Department of Transportation Standard Specifications) and federal safety standards. Municipal sales, use, and service taxes are exempt and should not be included in proposals. The contract includes a liquidated damages clause of $850 per calendar day for delays. Contractors must obtain all necessary permits (excluding local permits), provide general liability insurance with $1,000,000 per occurrence/$2,000,000 aggregate limits, and comply with state-listed species protection requirements for Eastern box turtles, wood turtles, and smooth green snakes identified within project limits. Non-resident contractors must file a surety bond with the Department of Revenue Services if the contract exceeds $250,000. An additional 2% retainage (beyond standard 5%) will be held until the contractor submits an approved affirmative action plan to the Commission on Human Rights and Opportunities.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TOWN OF GLASTONBURY

ENGINEERING DIVISION

PW-2325

CONTRACT DOCUMENTS

FOR

50 NYE ROAD

PARKING LOT IMPROVEMENTS

LIGHT POLES AND FIXTURES

INSTALLATION

DOT PROJECT 53-0202

BID # GL-2026-32

ADVERTISED ON: June 23, 2026

BID DUE DATE: July 7, 2026

INVITATION TO BID

BID # ITEM DATE & TIME REQUIRED

GL-2026-32 50 Nye Road Parking Lot Improvements July 7, 2026 at 11:00 A.M.

Light Poles and Fixtures Installation

The Town of Glastonbury will receive on-line Bids for furnishing and installing exterior parking lot illumination light poles and fixtures of the type and size specified to provide support for the reconstruction of a new parking lot performed by Town of Glastonbury personnel located at 50 Nye Road in Glastonbury.

Bidders wishing to submit a bid proposal for this solicitation are directed to respond online through a secure e-Procurement portal. Responses can be submitted at the following link:

https://glastonburyct.bonfirehub.com/, under the bid title “GL-2026-32- 50 Nye Road Parking Lot Improvements- Light Poles and Fixtures Installation”. All bids will be publicly opened and read aloud via an online Zoom meeting, further instructions to follow via online notice prior to bid opening.

No late bids will be accepted.

This Invitation to Bid, Instructions to Bidders, Drawings, Specifications and other Bidding Documents (as defined in the Instruction to Bidders) are available for viewing and downloading on the Town of Glastonbury website www.glastonburyct.gov or the State’s website at www.das.state.ct.us at no cost.

Each Bid must be accompanied by a bid security in the form of a Bid Bond, certified in an amount not less than 10% of the base bid except as otherwise expressly provided in the Instruction to Bidders. The successful bidder will be required to provide performance and labor and material payment bonds in the full amount of the agreed contract price.

Bidders are further advised that this project is subject to the prevailing wage requirements of Connecticut General Statutes Section 31-53. This project is also subject to State set-aside and contract compliance requirements.

Bidders are also hereby alerted to the schedule requirements as outlined in Special Conditions Section 11.00.

The Town of Glastonbury is An Affirmative Action/Equal Opportunity Employer. Minority/Women’s Business Enterprises are encouraged to bid.

The Town reserves the right to amend or withdraw this Invitation to Bid for any reason, to accept or reject any or all Bids, to waive any informalities or non-material deficiencies in any Bid, and to make such award (or make no award) of a contract in connection with this Invitation to Bid all as determined by the Town, in its discretion, to be in the best interest of the Town. A Bid may be rejected for irregularities of any kind, including without limitation, alteration of form, additions not called for, conditional proposals, and incomplete Bids. A Bid may also be rejected if, in the opinion of the Town, the Bid does not meet the standard of quality established by the Bidding Documents.

Any or all Bids may be rejected if there is any reason to believe that collusion exists among two or more Bidders. The foregoing provisions are for illustrative purposes and shall in no way limit the right of the Town to reject any and all Bids, in whole or in part.

Gina Consiglio

Purchasing Agent

50 NYE ROAD PARKING LOT IMPROVEMENTS BID #GL-2026-32

LIGHT POLES AND FIXTURES INSTALLATION

INFORMATION FOR BIDDERS

IB - 1

TABLE OF CONTENTS SECTION

INFORMATION FOR BIDDERS IB

GENERAL CONSTRUCTION SPECIFICATIONS GCS

SPECIAL CONDITIONS SC

BID PROPOSAL BP

SPECIAL PROVISIONS SP

ATTACHMENT A: REQUIRED STATE CONTRACT PROVISIONS

ATTACHMENT B: PREVALING WAGE RATES

ATTACHMENT C: CHRO CONTRACT COMPLIANCE REGULATIONS

ATTACHMENT D: TOWN LAND-USE PERMITS

ATTACHMENT E: STATE LISTED SPECIES PROTECTION DATA FROM CTDEEP

ATTACHMENT F: CONSTRUCTION PLANS (UNDER SEPARATE COVER)

ATTACHMENT G: SAMPLE 819 CONTRACT

IB - 2

1. Bidders submitting a response for this solicitation are directed to respond online through a secure e-

Procurement portal. Bids can be submitted at the following link: https://glastonburyct.bonfirehub.com/ under the bid title “GL-2026-23- 50 Nye Road Parking Lot Improvements- Light Poles and Fixtures Installation”. Bidders will be required to create a profile before submitting their bid. Step-by-step instructions on how to register as a vendor are available at this website:

https://customer.eunasolutions.com/public/s/article/vendor-registration

Bidders will be required to upload their bid response in one consolidated pdf document in the following file located in the bid portal:

• Bid Response & Related Documents

2. Whenever it is deemed to be in the best interest of the Town, the Town Manager, Purchasing Agent or designated representative shall waive informalities in any and all bids. The right is reserved to reject any bid when such action is deemed to be in the best interest of the Town of Glastonbury.

3. The award will be on the basis of bid total cost of the lowest responsible and qualified bidder unless otherwise specified. As used in this section, “lowest responsible and qualified bidder” means the bidder whose bid is the lowest of those bidders possessing the skill, ability and integrity necessary to faithfully perform the work. The bid total cost shall be arrived at by the mathematical calculation of the unit price multiplied times the number of units specified for each line item, and the total sum of all line items in the bid. In the event that the Town finds computational errors in a respondent’s bid proposal, the bid total cost shall be recalculated by the Town based on the unit prices contained in the bid proposal.

4. Bids will be carefully evaluated as to conformance with stated specifications.

5. Specifications must be submitted complete in every detail and, when requested, samples shall be provided. If a bid involves any exception from stated specifications, they must be clearly noted as exceptions, underlined, and attached to the bid.

6. The Bid Documents contain the provisions required for the requested item. Information obtained from an officer, agent, or employee of the Town or any other person shall not affect the risks or obligations assumed by the Bidder or relieve him/her from fulfilling any of the conditions of the bid.

7. Each Bidder is held responsible for the examination and/or to have acquainted themselves with any conditions at the job site which would affect their work before submitting a bid. Failure to meet this criteria shall not relieve the Bidder of the responsibility of completing the bid without extra cost to the Town of Glastonbury.

8. Any bid may be withdrawn prior to the above-scheduled time for the opening of bids or authorized postponement thereof. Any bid received after the time and date specified shall not be considered.

No Bidder may withdraw a bid within sixty (60) days after the actual date of the opening thereof.

Should there be reasons why a bid cannot be awarded within the specified period, the time may be extended by mutual agreement between the Town and the Bidder.

9. Each electronic bid submission must be accompanied by a COPY of the bid bond payable to the

Town for ten percent (10%) of the total amount of the bid. Original bid bonds from all respondents must be mailed to the attention of the Purchasing Agent immediately (within 24 hours) following the virtual bid opening at the following address: Town of Glastonbury, PO Box 6523, Glastonbury, CT 06033-6523, Attn: Gina Consiglio, Purchasing Agent. The bid bond of the successful Bidder will

IB - 3

be retained until the payment bond and performance bond have been executed and approved, after which it will be returned.

10. A 100% Performance and a 100% Payment bond are required of the successful bidder. This bond shall cover all aspects of the specification and shall be delivered to the Purchasing Agent prior to the issuance of a purchase order. The Performance and Payment Bond will be returned upon the delivery and acceptance of the bid items.

11. The Bidder agrees and warrants that in the submission of this sealed Bid, they will not discriminate or permit discrimination against any person or group of persons on the grounds of race, color, religion, national origin, sex, or physical disability including, but not limited to blindness, unless it is shown by such Bidder that such disability prevents performance of that which must be done to successfully fulfill the terms of this sealed Bid or in any manner which is prohibited by the laws of the United States or the State of Connecticut: and further agrees to provide the Connecticut Human Relations Commission with such information requested by the Commission concerning the employment practices and procedures of the Bidder. An Affirmative Action Statement will be required by the successful Bidder.

12. Bidder agrees to comply with all of the latest Federal and State Safety Standards and Regulations and certifies that all work required in this bid will conform to and comply with said standards and regulations. Bidder further agrees to indemnify and hold harmless the Town for all damages assessed against the Town as a result of Bidder’s failure to comply with said standards and/or regulations.

13. All correspondence regarding any purchase made by the Town of Glastonbury shall reference the

Town’s purchase order number. Each shipping container shall clearly indicate both Town purchase order number and item number.

14. Bidder is required to review the Town of Glastonbury Code of Ethics adopted July 8, 2003 and effective August 1, 2003 and revised October 29, 2013 and effective November 28, 2013. Bidder shall acknowledge that they have reviewed the document in the area provided on the bid/proposal response page (BP-1). The selected Bidder will also be required to complete and sign an Acknowledgement Form prior to award. The Code of Ethics and the Acknowledgement Form can be accessed at the Town of Glastonbury website at www.glastonburyct.gov. Upon entering the website scroll down to click on Bids & Proposals Icon which will bring you to the links for the Code of Ethics and the Acknowledgement Form.

15. Non-Resident Contractors: (if applicable)

Upon award the Town is required to report names of nonresident (out of state) Contractors to the State of Connecticut, Department of Revenue Services (DRS) to ensure that Employment Taxes and other applicable taxes are being paid by Contractors. A single surety bond for 5% of the entire contract price is required to be filed with DRS by any unverified nonresident prime or general contractor (if awarded) where the contract price for the project is $250,000 or more. The contractor will be required to promptly furnish to the Town a copy of the Form AU-968

- Certificate of Compliance issued by the State of Connecticut, DRS. See State of Connecticut Notice SN 2012 (2).

16. Bidder shall include on a sheet(s) attached to its proposal a complete disclosure of all past and pending mediation, arbitration and litigation cases that the bidder or its principals (regardless of their place of employment) have been involved in for the most recent five years. Please include a statement of the issues in dispute and their resolution. Acceptability of Bidder based upon this disclosure shall lie solely with the Town.

IB - 4

17. Bidder or its principals, regardless of their place of employment, shall not have been convicted of, nor entered any plea of guilty, or nolo contendere, or otherwise have been found civilly liable or criminally responsible for any criminal offense or civil action. Bidder shall not be in violation of any State or local ethics standards or other offenses arising out of the submission of bids or proposals, or performance of work on public works projects or contracts.

18. State Prevailing Wage Rates:

The wages paid on an hourly basis to any person performing the work of any mechanic, laborer or worker on the work herein contracted to be done and the amount of payment or contribution paid or payable on behalf of each such person to any employee welfare fund, as defined in subsection

(i) of section 31-53, shall be at a rate equal to the rate customary or prevailing for the same work in the same trade or occupation in the town in which such construction, remodeling, refinishing, refurbishing, rehabilitation, alteration or repair project is being undertaken. Any contractor who is not obligated by agreement to make payment or contribution on behalf of such persons to any such employee welfare fund shall pay to each mechanic, laborer, or worker as part of such person's wages the amount of payment or contribution for such person's classification on each pay day.

Respondents shall comply with State Statutes concerning Employment and Labor Practices, if applicable, and Section 31-53 of the Connecticut General Statutes, as amended (Prevailing Wages). Wage Rate Determination for this project from the State of Connecticut is included in the Bid Documents. Certified payrolls for site labor shall be submitted weekly to the Town’s Representative or his designee on the correct State of Connecticut form (see RFP). The Town reserves the right to, without prior notice, audit payroll checks given to workers on site in order to ascertain that wages and fringe benefits are being paid as required by the State of Connecticut.

Please make special note of the State requirement to adjust wage and fringe benefit rates on each July 1st following the original published rates.

NOTE that respondent is to include in its proposal all costs required by such annual increases in the PREVAILING RATES. NO escalation clauses are to be included in the respondent’s proposal and NO escalation clauses will be in the Contract Agreement. Respondent is to anticipate any future increases and include these costs in the proposal response.

Contractor’s invoices will not be paid if certified payrolls are incomplete, incorrect or not received in a timely manner.

All Apprentices must be registered with the State of Connecticut and their number shall not exceed the number allowed by law. Otherwise, all workers must be paid at least the Journeyman rate listed including benefits.

OSHA SAFETY AND HEALTH CERTIFICATION

Effective July 1, 2009: Any Mechanic, Laborer, or Worker, who performs work in a classification listed on the prevailing wage rate schedule on any public works project covered under C.G.S.

Section 31-53, both on site and on or in the public building, must have completed a federal OSHA Safety and Health course within the last 5 years.

19. Each bid shall also include a description of three similar (3) projects completed by the bidder with references to demonstrate successful experience with similar projects. Please provide project name, contact information and contract value.

IB - 5

20. Commission on Human Rights and Opportunities (CHRO) Requirements:

The contractor who is selected to perform this State project must comply with CONN. GEN. STAT.

§§ 4a-60, 4a-60g, and 46a-68b through 46a-68f, inclusive, as amended by June 2015 Special Session Public Act 15-5.

State law requires a minimum of twenty-five (25%) percent of the state-funded portion of the contract for award to subcontractors holding current certification from the Connecticut Department of Administrative Services (“DAS”) under the provisions of CONN. GEN. STAT. § 4a-60g. (25% of the work with DAS certified Small and Minority owned businesses and 25% of that work with DAS certified Minority, Women and/or Disabled owned businesses.) The contractor must demonstrate good faith effort to meet the 25% set-aside goals.

Municipal contracts for the construction or renovation of a public works project, where the estimated value is $500,000 or greater, will need to comply with C.G.S. Sec. 4b-91. In such cases the contractors must be pre-qualified by the State of Connecticut Department of Administrative Services (DAS).

For municipal public works contracts and quasi-public agency projects, the contractor must file a written or electronic non-discrimination certification with the Commission on Human Rights and Opportunities. Forms can be found at:

http://www.ct.gov/opm/cwp/view.asp?a=2982&q=390928&opmNav_GID=1806

As stated above, the work for this project falls under the provisions of CONN. GEN. STAT.

Sections 46a-68c and 46a-68d which require that prior to the award of this contract, you must have your company affirmative action plan approved by CHRO. A copy of your plan must be submitted to the CHRO within 30 days of your receipt of award. Should you have any questions regarding the preparation of your plan, please contact the Contract Compliance Unit at the Commission on Human Rights and Opportunities at (860) 541-4709.

Affirmative action plans can be sent to:

Commission on Human Rights and Opportunities 25 Sigourney Street Hartford, CT 06106 Attn: Contract Compliance Unit’

The Town will retain an additional 2% of the contract payments made (above and beyond the normal retainage of 5%) until the contractor has submitted an approved affirmative action plan to CHRO and CHRO has granted approval.

Completion of the Bidder Contract Compliance Monitoring Report is REQUIRED as part of this bid response. This form can be found in ATTACHMENT A.

21. Completion of a Certificate of compliance per CGS Section 31-57B is REQUIRED as part of this bid response. This form can be found at the beginning of ATTACHMENT A.

22. Compliance with Town Ordinance Prohibiting Natural Gas Waste & Oil Waste From Natural

Gas Extraction Activities or Oil Extraction Activities: If this bid is for the construction, repair or maintenance of Town owned and/or maintained roads or real property within the Town related to either (a) the purchase or acquisition of materials by the Town to be used to construct, repair or maintain any Town owned and/or maintained road or real property within the Town or (b) the performance of services for the Town to construct, repair or maintain any Town owned and/or maintained road or real property within the Town, the Bidder shall provide the following signed statement to the Town in its bid response, which shall be a certification under penalty of perjury by the Bidder:

IB - 6

“The undersigned Bidder, ____________________________, hereby submits a bid for materials, equipment and/or services for the Town of Glastonbury. The bid is for bid documents titled “GL- 2026-32- 50 Nye Road Parking Lot Improvements- Light Poles and Fixtures Installation”.

The undersigned Bidder hereby certifies under penalty of perjury that in connection with the bid and, if it is awarded the purchase order or contract by the Town, in connection with any purchase order or contract: (1) no materials containing natural gas waste or oil waste from natural gas extraction activities or oil extraction activities shall be provided to the Town or shall be used in providing any services to the Town by the undersigned Bidder or any contractor, sub-contractor or agent of the undersigned Bidder; (b) nor will the undersigned Bidder or any contractor, subcontractor or agent of the undersigned Bidder apply any natural gas waste or oil waste from natural gas extraction activities or oil extraction activities to any publicly owned and/or maintained road or real property within the Town of Glastonbury in performing its obligations under the purchase order or contract.

The undersigned Bidder hereby agrees and acknowledges that this requirement shall be a term of the purchase order or contract, if it awarded the purchase order or contract by the Town, and any breach of this provision shall be a breach of the purchase order or contract.”

23. Any technical questions regarding this bid shall be made in writing (email acceptable) and directed to Patrick Boggs, P.E. Assistant Town Engineer, 2155 Main Street, PO Box 6523, Glastonbury, CT 06033; patrick.boggs@glastonbury-ct.gov. Telephone (860) 652-7743 between the hours of 8:00 a.m. – 4:30 p.m. For administrative questions concerning this bid/proposal, please contact Gina Consiglio, Purchasing Agent, by email to the Purchasing Department at purchasing@glastonbury-ct.gov. All questions, answers, and/or addenda, as applicable, will be posted on the Town’s website at www.glastonbury-ct.gov (Upon entering the website scroll down to click on Bids & Proposals Icon, then scroll down page to see the active bid table. You must click the Bid Title to view all bid details and document links). The request must be received at least five (5) business days prior to the advertised response deadline. It is the respondent’s responsibility to check the website for addenda prior to submission of any bid/proposal.

IMPORTANT:

Failure to comply with general rules may result in disqualification of the Bidder.

Municipal projects are exempt from Federal Excise Taxes, as well as, State of Connecticut Sales, Use and Service Taxes and should not be include in the Bidder’s proposal.

GENERAL CONSTRUCTION SPECIFICATIONS

GCS - 1

01.00 WORKMANSHIP, MATERIALS AND EMPLOYEES

01.01 Wherever in this contract the word “Engineer” is used, it shall be understood as referring to the Director of Engineering and Highways of the Town of Glastonbury acting personally or through any assistants duly authorized.

01.02 The entire work described herein shall be completed in accordance with the plans and specifications to the full intent and meaning of the same. Unless otherwise specified, all materials incorporated in the permanent work shall be new, and both workmanship and material shall be of good quality. The Contractor shall, if required, furnish satisfactory evidence as to the kind and quality of materials.

01.03 The wording “furnish”, “install”, “construct”, “furnish and install”, or any similar terms, unless specifically noted to the contrary, shall include all labor, materials, water, tools, equipment, light, power, transportation, and any other services required for the completion of the work.

01.04 The Contractor shall at all times enforce strict discipline and good order among his employees, and shall seek to avoid employing on the work any unfit person or anyone not skilled in the work assigned to him.

02.00 SUPERINTENDENT

02.01 The Contractor shall keep on the work during its progress, in the absence of the Contractor, a competent Superintendent. The Superintendent shall be acceptable to the Engineer and shall fully represent the Contractor. All directions given to the Superintendent shall be binding as if given to the Contractor.

03.00 PRECONSTRUCTION MEETING

03.01 A Preconstruction Meeting will be held with the Engineer, Contractor, and any private utility company prior to commencing any work. The Engineer shall arrange the meeting based on a mutually convenient time.

04.00 PERMITS

04.01 Other than local permits, all permits, licenses, and fees required for the performance of the

Contract work shall be secured and paid for by the Contractor.

05.00 PROPERTY ACCESS

05.01 The Contractor shall take all proper precautions to protect from injury or unnecessary interference, and provide proper means of access to abutting property where the existing access is cut off by the Contractor.

05.02 The Contractor shall take all proper precautions to protect persons from injury or unnecessary inconvenience and leave an unobstructed way along the public and private places for travelers, vehicles, and access to hydrants.

05.03 The Contractor shall make arrangements with the adjacent property owners for such trespass as he may reasonably anticipate in the performance of the work. All such arrangements shall be reported, in writing, to the Engineer.

06.00 PROTECTION OF THE PUBLIC AND OF WORK AND PROPERTY

GCS - 2

06.01 The Contractor shall continuously maintain adequate protection of all work from damage, and shall take all reasonable precautions to protect the Town from injury or loss arising in connection with the Contract. Such barriers including temporary construction fence as directed by the Engineer, shall not be measured for payment, but rather included in the general cost of the work. Temporary signage shall be measured for payment under the Construction Signs pay item.

06.02 The Contractor shall adequately protect adjacent private and public property as provided by law and the Contract Documents.

06.03 The Contractor shall make good any damage, injury, or loss of his work and to the property of the Town resulting from lack of reasonable protective precautions.

07.00 EXISTING IMPROVEMENTS

07.01 The Contractor shall conduct his work so as to minimize damage to existing improvements.

Except where specifically stated otherwise in the specifications, drawings, or as directed by the Engineer, it will be the responsibility of the Contractor to restore to their original condition, as near as practical, all improvements on public or private property. This shall include:

a. Property within and adjacent to the side of installation such as shrubs, walks, driveways, fences, etc.

b. Utility mains, ducts, poles, and services. The Contractor is hereby notified that utilities, if/where shown on the plans, are at approximate locations. These locations are subject to possible errors in the source of information and errors in transcription. The Contractor shall make certain of the exact location of all mains, ducts, poles, and services prior to excavation.

08.00 SEPARATE CONTRACTS

08.01 The Engineer reserves the right to let other contracts in connection with this work. The

Contractor shall afford other contractors reasonable opportunity for the introduction and storage of their materials and the execution of their work, and shall properly connect and coordinate his work with theirs. Wherever work being done by the Town of Glastonbury forces or by other contractors is contiguous to work covered by this Contract, the respective rights of the various interests involved shall be established by the Engineer to secure the completion of the various portions of the work.

09.00 INSPECTION OF WORK

09.01 The Town shall provide sufficient personnel for the inspection of the work.

09.02 The Engineer shall at all times have access to the work whenever it is in preparation or progress, and the Contractor shall provide proper facilities for such access and for inspection.

09.03 If the specifications or the Engineer’s instructions require any work to be specially tested or approved, the Contractor shall give the Engineer timely notice of its readiness for inspection and, if the inspection is by another authority other than the Engineer, of the date fixed for such inspection. Inspections by the Engineer shall be made promptly. If any work should be covered up without approval or consent of the Engineer, it must, if required by the Engineer, be uncovered for examination and properly restored at the Contractor’s expense.

GCS - 3

09.04 Re-inspection of any work may be ordered by the Engineer. If such work is found to be in accordance with the Contract Documents, the Town shall pay the cost of re-inspection and replacement. If such work is not in accordance with the Contract Documents, the Contractor shall pay such cost.

10.00 RIGHT TO INCREASE OR DECREASE WORK

10.01 The Town shall have the right to increase or decrease the amount of work herein specified as may be required.

10.02 The Town shall have the right to award either the Base Bid or the Bid Alternate, based on bid results and project funding.

11.00 RIGHT OF ENGINEER TO STOP WORK FOR WEATHER CONDITIONS

11.01 Should the work, in the opinion of the Engineer, be in danger by reason of inclemency of weather, or could not be finished in time to prevent such danger, the Contractor shall cease operations upon order of the Engineer, and shall not resume them until ordered to do so by the Engineer when the weather conditions are favorable. The Contractor shall, upon such orders, discontinue work, remove all materials or appliances for or in use upon the work, and place the streets in proper condition for use by the public during the time the work is suspended as herein provided, without cost to the Town.

12.00 CONTRACTOR TO BE RESPONSIBLE FOR IMPERFECT WORK OR MATERIALS

12.01 Any faithful work or imperfect material that may be discovered before the acceptance and the payment of the work shall be corrected upon the order of the Engineer. The acceptance and payment of the work does not in any manner relieve the Contractor of his obligation to construct work in the proper manner and the use of materials herein specified.

13.00 TOWN MAY NOTIFY CONTRACTOR IF WORK IS NOT CARRIED ON

SATISFACTORILY

13.01 If, in the opinion of the Engineer, the Contractor is not proceeding with the work at a sufficient rate of progress so as to finish in the time specified, or has abandoned said work, or is not complying with the terms and stipulations or the Contract and specifications, the Engineer may serve notice on the Contractor to adopt such methods as will ensure the completion of the work in the time specified.

13.02 If, within five days after the Engineer has notified the Contractor that his work is not being carried on satisfactorily as before mentioned, the Engineer shall have the right to annul the Contract and manage the work under the direction of the Engineer, or re-let, for the very best interest of the Town as a new contract, the work under said new Contract shall be considered the responsibility of the defaulting Contractor.

13.03 Additional costs incurred over and above the original Contract shall be borne by the

Contractor.

14.00 DEDUCTIONS FOR UNCORRECTED WORK

14.01 If the Engineer deems it inexpedient to correct work that has been damaged or that was not done in accordance with the Contract, an equitable deduction from the Contract price shall be made therefor.

GCS - 4

14.02 The Contractor shall promptly remove from the premises all materials condemned by the Engineer as failing to meet Contract requirements, whether incorporated in the work or not, and the Contractor shall promptly replace and re-execute his own work in accordance with the Contract and without expense to the Town, and shall bear the expense of making good all work by other contractors destroyed or damaged by such removal or replacement.

14.03 If the Contractor does not remove such condemned work and materials as promptly as possible after written notice, the Engineer may remove them and store the materials at the expense of the Contractor.

15.00 CLEANING UP

15.01 The Contractor must remove all debris of every description as the work progresses and leave the surroundings in a neat and orderly condition to the satisfaction of the Engineer.

15.02 Upon completion, and before acceptance and final payment, the Contractor shall remove from the site all equipment, forms, surplus material, rubbish and miscellaneous debris and leave the site in a neat and presentable condition.

16.00 ROYALTIES AND PATENTS

16.01 The Contractor shall pay all royalties and license fees. He shall defend all suits or claims for infringement of any patent rights and shall save the Town of Glastonbury harmless from loss on account thereof, except that the Town of Glastonbury shall be responsible for all such loss when a particular manufacturer, product, or process is specified by the Town of Glastonbury.

SPECIAL CONDITIONS

SC - 1

01.00 NOTICE TO CONTRACTOR

01.01 Intent of Contract: The intent of the Contract is to prescribe a complete work or improvement that the Contractor undertakes to do, in full compliance with the specifications, plans, special provisions, proposal, and Contract. The Contractor shall perform all work in close conformity with the lines, grades, typical cross-sections, dimensions, and other data shown on the plans or as modified by written orders, including the furnishing of all materials, implements, machinery, equipment, tools, supplies, transportation, labor, and all other things necessary to the satisfactory prosecution and completion of the project.

Much time and effort has gone into this project in an effort to minimize impact on trees and adjacent properties. Extreme care shall be taken by the Contractor to honor commitments made by the Town. Prior to doing any work, the Contractor should meet with the Engineer to become familiar with the conditions encountered and commitments made.

01.02 The Contractor is hereby alerted to the fact that the State of Connecticut Department of

Transportation Standard Specifications for Roads, Bridges, Facilities and Incidental Construction, Form 819 (Form 819) 2024 latest edition including supplements thereto dated July 2025, are the governing specifications and are to be considered part of the Contract Documents. The Form 819 shall not be provided by the Town and any cost associated therewith shall be the responsibility of the Contractor. In case of any discrepancy between the Contract Drawings or Specifications and the Form 819, the matter shall immediately be submitted to the Engineer. The Engineer shall have sole authority in resolving any discrepancies.

01.03 Protection of State Listed Species of Special Concern Eastern Box Turtle, Green

Snake: The Contractor is hereby made aware state listed species of concern have been identified within the project limits as per correspondence from CTDEEP included in Attachment E. As such, all construction work performed under this contract shall be conducted in such a manner as to protect these species from harm during construction activities. As described in Attachment E and the Environmental Compliance Section 1.10 of the Special Provisions, the Contractor will be required to strictly adhere to these guidelines, including: searching work areas each morning before starting equipment to ensure that no turtles or snakes are within the travel paths or work areas; relocating turtles and snakes away from the construction area; notifying Town staff of the location that turtles or snakes have been found; closing off construction staging areas with silt fence at night to prevent turtles or snakes from accessing these areas, and other related items as described in the Special Provisions. This work will not be measured and paid for separately, but rather will be included in the general cost of the project.

01.04 SEE ADDITIONAL NOTICES TO CONTRACTOR IN SPECIAL PROVISIONS SECTION

02.00 COMMUNICATIONS

02.01 All notices, demands, requests, instructions, approvals, proposals, and claims must be in writing.

02.02 Any notice to, or demand upon, the Contractor shall be sufficiently given if delivered at the office of the Contractor stated on the signature page of the Agreement (or at such other office as the Contractor may, from time to time, designate) in a sealed, postage-prepaid envelope or delivered with charges prepaid to any telegraph company for transmission, in each case addressed to such office.

SC - 2

02.03 All papers required to be delivered to the Town shall, unless otherwise specified in writing to the Contractor, be delivered to the Director of Engineering and Highways, 2155 Main Street, Glastonbury, CT 06033, and any notice to, or demand upon, the Town shall be delivered at the above address in a sealed, postage-prepaid envelope or delivered with charges prepaid to any telegraph company for transmission, in each case addressed to such office or to such other representatives of the Town, or to such other address as the Town may subsequently specify in writing to the Contractor for such purpose.

02.04 Any such notice shall be deemed to have been given as of the time of actual delivery or, in case of mailing, when the same should have been received in due course of post or, in the case of telegrams, at the time of actual receipt, as the case may be.

03.00 PARTIAL USE OF IMPROVEMENTS

03.01 The Town may, at its election, give notice to the Contractor and place in use those sections of the work that have been completed, inspected and can be accepted as complying with the Contractor Documents and if, in its opinion, each such section is reasonably safe and fit for the use and accommodation for which it was intended, provided:

a. The use of such sections of the work shall not materially impede the completion of the remainder of the work by the Contractor.

b. The Contractor shall not be responsible for any damages or maintenance costs due directly to the use of such sections.

c. The use of such sections shall in no way relieve the Contractor of his liability due to having used defective materials or to poor workmanship.

d. The period of guarantee shall not begin until the date of the final acceptance of all work required under this Contract.

04.00 INSURANCE

04.01 The Bidder shall, at its own expense and cost, obtain and keep in force during the entire duration of the Project or Work the following insurance coverage covering the Bidder and all of its agents, employees and sub-contractors and other providers of services and shall name the Town of Glastonbury and the State of Connecticut and their employees and agents as an Additional Insured on a primary and non-contributory basis to the Bidders Commercial General Liability and Automobile Liability policies. These requirements shall be clearly stated in the remarks section on the Bidders Certificate of Insurance. Insurance shall be written with insurance carriers approved in the State of Connecticut and with a minimum Best’s Rating of A-VIII. In addition, all carriers are subject to approval by the Town. Minimum Limits and requirements are stated below:

a. Worker’s Compensation Insurance:

Statutory Coverage Employer’s Liability $1,000,000 each accident/$1,000,000 disease-policy limit/$1,000,000 each employee A Waiver of Subrogation shall be provided

b. Commercial General Liability:

Including Premises and Operations, Products and Completed Operations, Personal and Advertising Injury, Contractual Liability and Independent Contractors

SC - 3

Limits of Liability for Bodily Injury and Property Damage Each Occurrence: $1,000,000 Aggregate: $2,000,000 (The Aggregate Limit shall apply separately to each job.)

c. Automobile Insurance:

Including all owned, hired, borrowed, and non-owned vehicle Limit of Liability for Bodily Injury and Property Damage

Per Accident: $1,000,000

d. Umbrella of Excess Liability:

State in the Remarks Section that coverage is follow form.

Limit of Liability Each Occurrence $1,000,000

Aggregate $1,000,000

e. Owner’s and Contractor’s Protective Liability Insurance:

With respect to the Contractor’s Project operations and also those of its subcontractors, the Contractor shall carry, for and on behalf of the State and the Town of Glastonbury, insurance which shall provide coverage of at least $1,000,000 for each accident or occurrence resulting in damages from (1) bodily injury to or death of persons and/or (2) injury to or destruction of property. Subject to that limit per accident or occurrence, the policy shall provide an aggregate coverage of at least $2,000,000 for all pertinent damages arising during the policy period.

04.02 The Bidder shall direct its Insurer to provide a Certificate of Insurance to the Town before any work is performed. The Contractor shall be responsible to notify the Town 60 days in advance with written notice of cancellation or non-renewal. The Certificate shall evidence all required coverage. The Bidder shall provide the Town copies of any such insurance policies upon request.

04.03 INDEMNIFICATION: To the fullest extent permitted by law, the Contractor shall indemnify and hold harmless the Town and the State of Connecticut and its consultants, agents, and employees from and against all claims, damages, losses and expenses, direct, indirect or consequential (including but not limited to fees and charges of engineers, attorneys and other professionals and court and arbitration costs) to the extent arising out of or resulting from the performance of the Contractor’s work, provided that such claim, damage, loss or expense is caused in whole or in part by any negligent act or omission by the Contractor, or breach of its obligations herein or by any person or organization directly or indirectly employed or engaged by the Contractor to perform or furnish either of the services, or anyone for whose acts the Contractor may be liable.

05.00 WORK BY OTHERS

05.01 Private utilities, contractors, developers or other parties may be expected to be working within the Contract area during this Contract. It shall be the responsibility of the Contractor to coordinate his work with the work being done by others in order that the construction shall proceed in an efficient and logical manner. The Contractor shall have no claim or claims whatever against the Town, the Engineer, or other parties due to delays or other reasons caused by the work by others or his failure to coordinate such work.

SC - 4

06.00 CONTRACTOR’S WORK AND STORAGE AREA

06.01 The Contractor shall contact the Town to determine if any specific locations will be designated, or gain its approval prior to using any area for storage of equipment, materials and trailers during the period of this Contract. The Contractor shall confine his work/storage area to the limits as designated or approved and shall be responsible for the security of the work/storage area. Upon completion of the Contract, the Contractor shall remove all equipment and materials, except as otherwise specified, and restore the site to its original condition as approved by the Engineer and at no cost to the Town.

07.00 DISPOSAL AREA

07.01 Disposal of surplus material is the responsibility of the Contractor. The Tryon Street Bulky

Waste Facility will be available to the Contractor for disposal of materials that are accepted at that facility, however all disposal fees will apply. Prior to any disposal, the Contractor is required to register all vehicles being utilized for disposal and obtain a permit for each vehicle from the Sanitation Department. Waste disposal guidelines for the Bulky Waste facility are published on the Town web site at the addresses shown below. Each bidder shall have reviewed and understand these guidelines and the costs associated therewith prior to submitting a bid for the project.

Bulky Waste Facility | Glastonbury, CT (glastonburyct.gov)

WASTE DISPOSAL GUIDELINES (glastonburyct.gov)

Refuse Disposal Permits | Glastonbury, CT (glastonburyct.gov)

Holiday Schedule:

https://www.glastonburyct.gov/home/showpublisheddocument/13112/6388110137260700

Acceptable materials generally include such materials as brush, stumps, demolition materials, and excess excavated earth materials. Unacceptable materials generally include such items as carpet, appliances, upholstered furniture; hazardous wastes such as pesticides, oil based paints and thinners; or other wastes as designated by the State Department of Energy and Environmental Protection. Demolition material cannot contain asbestos or other hazardous materials.

The Contractor shall obtain a disposal area for all other unsuitable or surplus materials at no cost to the Town.

08.00 DUST CONTROL

08.01 During the progress of the work, the Contractor shall conduct his operations and maintain the area of his activities so as to minimize the creation and dispersion of dust. If the Engineer decides that it is necessary to use water or calcium chloride for more effective dust control, the Contractor shall furnish and spread the material, as directed, without additional compensation.

09.00 MAINTENANCE / GUARANTEE PERIOD

09.01 The Contractor shall be held responsible to the Town for maintenance with respect to defects, settlements, etc. for a minimum period of one-year following the date of final acceptance of the project by the Town.

SC - 5

10.00 PROTECTION OF EXISTING UTILITIES

10.01 Prior to opening an excavation, effort shall be made to determine whether underground installations, (i.e., sewer, water, fuel, electric lines, etc.) will be encountered and, if so, where such underground installations are located. Before starting any excavation, the Contractor shall submit to the Engineer plans or details showing the proposed method the Contractor will use to support and protect all existing utilities during construction. The furnishing of such plans and details shall not serve to relieve the Contractor of any responsibility for the proper conduct of the work.

10.02 When the excavation approaches the estimated location of such an installation, the exact location shall be determined by careful probing or hand digging, and when it is uncovered, proper supports shall be provided for the existing installation. Utility companies shall be contacted and advised of proposed work prior to the start of actual excavation.

10.03 There will be no extra payment for submitting plans or details or for any work related to supporting and protecting all existing utilities during construction.

11.00 TIME FOR COMPLETION/NOTICE TO PROCEED

11.01 The work under this Contract shall commence on a date that is mutually agreed upon by the Contractor and the Engineer. After the work has begun, it shall continue in an orderly fashion such that all contract work is substantially completed within 30 days.

Within five (5) business days after the date of the Notice of Award, the Contractor must provide the appropriate bond and insurance certificates to the Town Purchasing Agent and must be issued a Notice to Proceed and Purchase Order for the Project prior to initiating any work.

11.02 When the Contract time is stated on a calendar-day basis, that time shall be the number of consecutive calendar days contained in the Contract period, excluding the time period from each December 1 through the following March 31 (the “winter shutdown period”). The time will be computed as herein provided on a consecutive-day basis, including all Saturdays, Sundays, holidays, and non-work days from April 1 through November 30 of each included year. Time will not be charged for days in the winter shutdown period. If the Engineer so approves, the Contractor may work on certain tasks of the Project during the winter shutdown period with no charge being made against the Contract time. If work during winter shut down is approved by the Town, approval may be granted with the condition that work under the items Trafficperson (Municipal Police Officer) or Trafficperson (Uniformed Flagger) will not be measured for payment, at the discretion of the Town.

12.00 LIQUIDATED DAMAGES

12.01 As actual damages for any delay in completion of the work that the Contractor is required to perform under this Contract are impossible to determine, the Contractor and the Sureties shall be liable for and shall pay to the Town the sum of $850.00 as fixed, agreed and liquidated damages for each calendar day of delay from the above-stipulated completion, or completion as modified in writing by both parties, until such work is satisfactorily completed and accepted.

SC - 6

13.00 SCHEDULE OF DRAWINGS

13.01 The Contractor is hereby alerted that the plans and detail sheets related to the work to be performed under this contract located in Attachment F are to be considered part of these specifications and include the following: Plans entitled “Site Electrical Plans and Details” prepared by Bemis Associates and red-lined by The Town of Glastonbury, Sheets 18 thru 20 of 26 containing three (3) sheets.

14.00 CHANGES IN THE WORK

14.01 The Town reserves the right to perform portions of the work in connection with these plans and specifications. The reduction in the work to be performed by the Contractor shall be made without invalidating the Contract. Whenever work is done by the Town contiguous to other work covered by this Contract, the Contractor shall provide reasonable opportunity for the execution of the work and shall properly coordinate his work with that of the Town.

15.00 LAYOUT OF WORK

15.01 The Town shall provide stake-out of the work in accordance with the plans or as directed by the Engineer. The Contractor shall protect all stakes from damage or destruction and shall be responsible to assure that the grade stakes have not been altered prior to actual construction. The Town shall replace grade stakes that have been removed, at no cost to the Contractor, if their removal was caused by reasons beyond reasonable care and protection by the Contractor. If it is determined by the Engineer that the Contractor did not provide reasonable protection, the cost of re-staking will be deducted from any amounts due the Contractor in the performance of the work.

16.00 REMOVAL AND STORAGE OF MATERIALS AND STRUCTURES FOUND ON THE

WORK

16.01 All salvable materials, including traffic signal equipment, topsoil, gravel, fill materials, etc.

and structures, including drainage pipes, catch basins and manhole frames and covers, guide railing, etc. that are not to remain in place or that are not designated for use in the work, shall be carefully removed by the Contractor and delivered to the Town Highway Garage located at 2380 New London Turnpike. All salvable materials removed and stored shall remain the property of the Town. The Engineer shall determine the materials or structures to be salvaged.

17.00 PROSECUTION AND PROGRESS

17.01 ADVANCE NOTICE: The Contractor shall give the Engineer a seven-day advance written notice of construction activities that will alter traffic patterns that result in lane shifts, detours, temporary closures of lane(s), permanent closure of lane(s), or lane reductions.

This advance notification will allow the Town to publish news releases and/or provide public radio announcements to inform the public of revised traffic patterns or possible traffic delays. Failure of the Contractor to provide such timely notice shall be considered a breach of Contract and will subject the Contractor to stop work orders until such time as the seven-day notice has been satisfied.

17.02 Limitations on work hours are described in the Prosecution and Progress Special Provision.

The Contractor shall understand and strictly comply with these limitations. Work on weekends or during time periods other than those described above will not be permitted.

No work will be allowed on designated Town Holidays…