About this file
This is a General Notes document prepared by Graff Surveying LLC for the Borough of Saxonburg's John Roebling's Historic Wire Rope Workshop Restoration project in Pennsylvania. The document outlines critical requirements for contractors undertaking foundation renovation and site drainage improvements to the historic structure. The topographic survey was conducted in August 2022 using Pennsylvania state plane coordinates (South Zone) with a 0.5-foot contour interval and US survey feet measurements. Key contractor responsibilities include verifying exact locations of all existing underground utilities before commencing work, notifying PA 1 Call prior to excavation, staking out all construction baselines and verifying setbacks and clearances, maintaining positive drainage throughout the project, and arranging a pre-construction meeting with the Contracting Officer and Designer. All disturbed areas must be stabilized with four inches of topsoil, seed, and mulch, and the tops of all existing utility frames and covers within the contract limits must be adjusted to match new grades.
The document emphasizes that contractors bear full responsibility for the cost of repairs resulting from failure to locate and preserve existing utilities, and that numerical dimensions and elevations in the drawings supersede any scaling discrepancies. Underground utility descriptions shown on the plans are based on field observations and have not been verified against record utility drawings or field test pits, requiring contractors to conduct their own verification. Contractors must also submit a work plan addressing traffic control for vehicles and pedestrians, as well as lay-down and staging areas for equipment and materials, to the Saxonburg Borough municipal office for approval. The survey certifications represent professional opinion only and do not constitute a guarantee or warranty.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
General Notes:
1. Topographic information shown is based on a field survey performed by Graff Surveying LLC in August, 2022.
2. Horizontal datum: PA state plain coordinates. (South Zone.) NAD83(2011) Vertical. Datum: NAVD88 (GEOID 18) Grid North, Bearings and elevations Were derived from Keynet GPS VRS Network.
3. Survey measurements were made in US survey feet. (US ft)
4. Contour shown were produced from an actual ground survey. Contour interval is .5 foot.
5. Additional spot elevations reside in the Electronic. Version of this drawing but are not plotted hereon.
6. The description of the underground utilities as shown hereon were based upon field observations by survey or plan recorded and have not been compared to. Were verified with record utility drawings or field test pits. The size, type and location of the utility lines should be verified by the user of this drawing.
7. The Contractor shall be responsible for verification of the exact location of all existing underground utilities before commencing any work. Contractors shall be fully responsible for the cost or repair of any and all damages which occur as a result of the failure To exactly locate and preserve any and all existing utilities to remain.
8. The Contractor shall be responsible for notifying PA 1 call prior to the start of any excavation work.
9. It is the contractor’s responsibility to field verify actual site conditions prior to the start of any work. There is no warranty or guarantee on the completeness or correctness of the existing condition information. Any discrepancy found shall be brought to the immediate attention of the contracting Officer prior to the start of any work.
10. The Contractor shall stake out all baselines of construction and the location of all new construction and verify all setbacks, offsets, and clearances prior to the start of any work.
11. The Contractor shall verify all existing utility inverts and clearances from new work prior to the start of any work.
12. All disturbed areas not stabilized with structures, paving stone or plantings shall be stabilized with four inches of topsoil seed, mulch and water to establish an adequate growth of grass.
13. All work shall be accomplished in accordance with the requirements of the project specifications.
14. The tops of all frames, grates, and covers of all existing utilities to remain within the limits of the contract and or disturbance shall be adjusted with the new grades.
15. Contractor shall maintain positive drainage at all times and shall provide all needed labor, equipment and materials to protect the project site from ponding water and flooding.
16. Numerical dimensions and elevations shown shall supersede any discrepancy in the scaling of the drawings.
17. Contractor shall arrange a pre construction meeting with the Contracting Officer and Designer prior to commencement of any work.
18. Contractor shall submit for review and approval a work plan addressing traffic control for vehicles and pedestrian and lay down in staging areas for equipment and materials to the Saxonburg Borough municipal office.
19. The word “certify” or “certification” as used herein are understood to be an expression of professional opinion by the undersigned surveyor based upon his best knowledge, information and belief. As such, it does not constitute a guarantee. Nor a warranty, expressed or implied.