This document is a Statement of Work for a federal contract opportunity to provide annual preventative maintenance services for eight indoor growth chamber units used by the USDA Agricultural Research Service's Adaptive Cropping Systems Laboratory in Beltsville, Maryland.

The contractor must provide certified technicians to perform a series of standard preventative maintenance tasks on the growth chambers, which are six CONVIRON PGC-FLEX models and two CONVIRON BDW120 walk-in models. The tasks include inspection, cleaning, and calibration of various components such as lamps, fans, refrigeration systems, and sensors. After completing the maintenance, the contractor must provide a written report detailing the work performed and identifying any potential issues. The period of performance is for a base year with four one-year option periods. The contract is a 100% small business set-aside under NAICS code 334516, with a size standard of 1,000 employees. Interested offerors must submit documentation demonstrating their technical capability, a firm fixed price quotation, and a Unique Entity ID by the May 23, 2024 due date.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

SECTION 1 - GENERAL INFORMATION

1.1 BACKGROUND

The USDA, ARS, Adaptive Cropping Systems Laboratory (ACSL) requires contractor support to provide Annual Preventative Maintenance for Eight (8) Indoor Growth Chamber Units.

ACSL conducts research which involves the use of multiple indoor electric lamp growth chamber units which provide control over lighting, temperature, and other growth conditions needed to support plant growth experiments. These systems incorporate various specialized heating, cooling, and ventilation hardware, electronic sensing and control, software components, and internal components needed for plant cultural purposes. These growth chamber units are also utilized nearly 365 days of the year. Each chamber involves complex, mechanical, electrical, and hardware components which require maintenance to ensure appropriate performance specifications are achieved. Without preventative maintenance (PM) conducted by certified technicians, chambers may fail and create a critical impact on the ability of the laboratory’s research program.

1.2 SCOPE OF WORK

The vendor must provide all personnel, equipment, tools, materials, supervision, and other items and services necessary to perform annual preventative maintenance support services as defined herein.

Preventative maintenance (PM) and repair service is to be conducted on eight (8) individual growth chamber units manufactured by CONVIRON, as noted in this document. Chambers are:

-Six (6) PGC-FLEX models: serial numbers: 210158, 210159, 210160, 210161, 210162, 210163

-Two (2) walk-in BDW120 models: serial numbers 210156, 210157

At the completion of each PM service a report indicating completion of check-lists and potential trouble areas for each individual chamber which may need to be addressed by USDA/ACSL is to be delivered via email to the lead Technical Scientist assigned to the contract.

1.3 CONTRACTOR PERSONNEL

Successful performance of this contract requires that certified technicians for the specified growth chamber equipment, built and designed by CONVIRON, be utilized to conduct this work. The vendor will certify that the individual(s) conducting this annual PM possess the necessary knowledge, skills, and abilities to satisfactory conduct all PM responsibilities. The name of this person(s) must be designated in writing and submitted at the time of service.

1.4 QUALITY ASSURANCE

The Government will inspect and accept all services under this contract. For those tasks listed on the performance requirement summary (PRS) (Technical Exhibit 1), vendor technician will certify on written report a recording of task lists completed. Vendor will also indicate potential trouble areas in writing that the government may need to address as a future need. This report will be provided the lead Technical Scientist at the end of each completed PM.

1.5 HOURS OF SERVICE

The contractor must perform the services required under this contract between the hours of 7:00AM and 4:30PM Monday through Friday, exclusive of federal holidays, except where noted herein. Any services performed outside of these hours, including domestic and/or international travel to attend meetings and/or conferences, must be coordinated with the COR, at least one week in advance and must be approved in writing.

1.5-1 FEDERAL HOLIDAYS

The following federal holidays are observed by ARS. Work is not to be scheduled on these days except if requested by the COR or CO.

• New Year's Day

• Martin Luther King's Birthday

• President's Day

• Memorial Day

• Juneteenth

• Independence Day

• Labor Day

• Columbus Day

• Veteran's Day

• Thanksgiving Day

• Christmas Day

1.6 GOVERNMENT FURNISHED PROPERTY AND SERVICES

All growth chamber units listed above to be serviced as part of this request are located in the climate controlled facility. The Government will furnish required computer access if needed and/or basic office supplies for contractor to use as needed for this task. A temporary office space is available on premises, for contract if needed.

Location:

10300 Baltimore Avenue, BARC-W, Bld 10B Beltsville, Maryland 20705.

SECTION 2 - CONTRACTOR FURNISHED ITEMS AND SERVICES

2.1 GENERAL INFORMATION

Except for those items or services specifically stated in Section 1 as Government furnished, the contractor must furnish everything needed to perform this contract according to all its terms.

SECTION 3 - SPECIFIC TASKS

3.1 GENERAL INFORMATION

Contractor will conduct a series of standard PM tasks and assessments as determined by industry standard. The minimum list is indicated below.

-Basic: inspection/ cleaning / tuning of:

(a) electric lamps

(b) circulating fans, intake and exhaust ports, fresh air inlet filter, and aspirator fans

(c) interior growth chamber surfaces

(d) sight glass

(e) drain pan & strainer, canopy support cables

(f) refrigeration faults, water supply & drain, door gaskets

(g) additive humidity system (where operational)

(h) separate coil dehumidifier

(i) air cooled condenser

(j) CO2 system

(k) humidity sensing unit including dry humidity sensor and calibration -Other:

(a) visually inspect individual lamps and replace where necessary

(b) ensure temperature control is working correctly within original chamber design specifications

(c) ensure lamp control is working properly and provides outputs original chamber design specifications

(d) check sensor calibration and recalibrate including Humidity, Temperature and Light sensors

(e) monitor humidity spray nozzles to ensure 100% performance

(f) check refrigeration unit and report on operating pressures within tolerances

(g) check door hinges and latches and gasket seal

(h) clean water strainer and all drain traps

(i) clean water-cooled condenser

3.2 PERIOD OF PERFORMANCE

Base Year: 12 months Option Year One: 12 months Option Year Two: 12 months Option Year Three: 12 months Option Year Four: 12 months

Travel If required, travel will be coordinated with the Program Office, at least two weeks in advance.

Security Considerations

• All contractor personnel who work at USDA must have approval for facility access. Prior to work starting, the contractor must supply the names of those employees selected to perform the work to the COR. Due to security requirements, pre-notification of all visitors to all USDA facilities is required.

Anyone requiring access must contact the Contract Officer Representative (COR) prior to arrival.

• All contractors must have a valid photo identification, to conduct services at any USDA facilities and locations. Contractors must sign in with security, prior to conducting any services.

EDUCATIONAL AND LEVEL OF EXPERIENCE REQUIRED

Technicians must be certified specialists capable of working on CONVIRON growth chamber systems as outlined in the above tasks.

TECHNICAL EXHIBITS

Technical Exhibit 1 - Performance Requirements Summary

REQUIRED TASK STANDARD ACCEPTABLE

QUALITY LEVEL

METHOD OF

SURVEILLANCE

Basic PM Written check list provided that minimum subtasks indicated above were completed.

Potential problems are indicated in written report and communicated visually with staff member.

Signed report provided to lead Technical staff or Scientist staff

Staff member will be in physical proximity and communication with technician throughout this process.

Other PM Written check list provided that minimum subtasks indicated above were completed.

Potential problems are indicated in written report and communicated visually with staff member.

Signed report provided to lead Technical staff or Scientist staff

Staff member will be in physical proximity and communication with technician throughout this process.

-End-