This solicitation package includes a statement of work and specifications for a construction project to upgrade the parking lot and access road at the Chimney Beach Trailhead in Incline Village, Nevada. Key details include that the project scope involves earthwork for a 130-space parking lot and access road, with optional items for aggregate base, curb and gutter, and sidewalk construction. The estimated start date for construction activities is August 15, 2023, with work to begin within 10 days of notice to proceed. The solicitation is set aside for total small business and has an estimated value between $1,000,000 and $5,000,000. The soliciting agency is the Department of Agriculture Forest Service Lake Tahoe Basin Management Unit. All requests for information must be submitted by May 30, 2023 to the listed contracting officer.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 6. RFI Form.docx | DOCX document | |
| 2. Schedule.docx | DOCX document | |
| 5. Davis-Bacon Act WD # NV20230013.pdf | ||
| 4. Fire Plan.pdf | ||
| 127EAW23R0024 - Chimney Beach Parking Lot.pdf | ||
| 3. Chimney Beach Parking Lot Drawings and Plans.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section C – Construction
12-05-01
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
Scope of Contract
The Chimney Beach Trailhead Parking Upgrades Project includes the earthwork construction of a 130-space parking lot and corresponding access road within the Chimney Beach recreation area near
Incline Village, NV. Option items include the construction of aggregate base, concrete curb and gutter, and sidewalk. The work includes, but is not limited to tree removal, roadway excavation, aggregate base placement, and a stormdrain system. Pedestrian access to National Forest Lands will be maintained throughout the project, however public parking will not be permitted in the existing parking area.
Project Location
From the Lake Tahoe Basin Management Unit’s Supervisor’s Office: travel northeast on College Ave.
toward Al Tahoe Blvd. for 305 feet. Continue northeast on Johnson Blvd. for 1.0 miles, turn right onto
US Highway 50 for 14.1 miles, turn left onto Highway 28 for 5.3 miles. Turn right onto Chimney
Beach Trailhead Road. (39.16774° N, 119.92699° W)
NOTE: Any prospective bidder desiring an explanation or interpretation of the solicitation, drawings, specifications, etc., must request it in writing soon enough to allow a reply to reach all prospective bidders before submission of their bids. Oral explanations or instructions given before the award of a contract will not be binding. In no event shall failure to inspect the site constitute grounds for a claim after contract award. (See Section L, 52.236-27, SITE VISIT.)
Estimated Start Date
Construction activities to begin on August 15, 2023
Contractor must begin work within 10 days of the effective date of the Notice to Proceed. See Section
F for additional information.
Restrictions on Work
1. Chimney Beach Trailhead will remain open to the public during construction. The contractor will be required to allow public to access to National Forest Lands at the trailhead.
2. In accordance with the fire plan, if included in Section J.
3. When the Contracting Officer (or designated representative) determines that adverse weather has made access too dangerous or that continued vehicular travel would cause unacceptable damage.
4. See Section H for information on ground disturbance restrictions and the winterization plan.
5. Construction activities will be restricted on all federal holidays. The job site must be in a condition to allow for heavy public use during these periods. See section H for holiday periods.
6. Work will be allowed during daylight hours Monday-Friday.
7. Weekend activities and alternate work hours may be approved by the CO on a case by case basis. A request to work on weekends or alternate hours must be submitted 7 days prior to scheduling to provide adequate time for review.
Worker's Compensation Insurance
The Contractor shall provide evidence of Worker's Compensation Insurance or a written explanation as to why the Contractor is exempt from the requirement. NOTE: The Contractor working alone is not required to carry the insurance.
Camping and Housing (see also Section H, Camping Permit Compliance)
Camping is not permitted in US Forest Service campgrounds. Contractor [ ] will [X] will not be permitted to camp elsewhere on US Forest Service land. Camping on Forest Service land is not a right; permission may be revoked for failure to comply with the terms of the permit.
Maps
INCLUDED WITH DRAWINGS
Drawings and Specifications
Project Drawings: The following drawings are part of this solicitation:
Chimney Beach Trailhead Parking Lot Upgrades Project (21 Sheets)
Specifications:
[ ] Construction Standard Institute (CSI) specifications
These specifications are physically incorporated in the solicitation.
[ X ] Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects
FP-14 (US Customary Units)
This document is incorporated by reference and is available on the web in in PDF format.
https://flh.fhwa.dot.gov/resources/specs/fp-14/fp14.pdf
[ ]1996 road and bridge specifications--
Standard Specifications applicable to this project can be found in Forest Service Specifications for
Construction of Roads & Bridges, August 1996 (EM-7720-100), which is incorporated by https://flh.fhwa.dot.gov/resources/specs/fp-14/fp14.pdf reference. The publication is available for purchase from the Superintendent of Documents, US
Government Printing Office (GPO), Washington, DC 20402 (202-512-1800). The GPO stock number is 001-001-00660-2. It may also be accessed electronically at the following website address: http://www.fs.fed.us/.ftproot/pub/acad
[ ] 1985 road and bridge specifications--
Standard Specifications applicable to this project can be found in Forest Service Specifications for
Construction of Roads & Bridges, April 1985, which is incorporated by reference. The publication is out of print. Contact the issuing office for copies of relevant specifications.
[ ] Trail specifications--
Standard Specifications applicable to this project can be found in Standard Specifications for
Construction and Maintenance of Trails, September 1996 (EM-7720-103), which is incorporated by reference. The publication is available for purchase from the Superintendent of Documents, US
Government Printing Office (GPO), Washington, DC 20402 (202-512-1800). The GPO stock number is 001-001-00661-1. It may also be accessed electronically at the following website address: http://www.fs.fed.us/.ftproot/pub/acad
Special Project Specifications are physically incorporated within this solicitation.
The following Standard and Special Project Specifications are applicable to this contract:
Supplemental Standard Specifications for Construction of Roads and
Bridges on Federal Highway Projects, FP-14 (US Customary Units)
Revision Date
101 Terms, Format, and Definitions 01-22-2020
102 Bid, Award, and Execution of Contract 11-09-2016
103 Scope of Work 11-09-2016
104 Control of Work 11-09-2016
105 Control of Material 06-29-2020
106 Acceptance of Work 07-18-2017
107 Legal Relations and Responsibility to the Public 07-18-2017
108 Prosecution and Progress 11-09-2016
109 Measurement and Payment 02-22-2019
155 Schedules for Construction Contracts 11-09-2016
157 Soil Erosion and Sediment Control 11-01-2016
201 Clearing and Grubbing 02-22-2018
203 Removal of Structures and Obstructions 09-10-2018
204 Excavation and Embankment 11-04-2016
301 Untreated Aggregate Courses 07-17-2017
633 Permanent Traffic Control 11-08-2016
The requirements contained in these specifications are hereby made a part of this solicitation and any resultant contract.
http://www.fs.fed.us/.ftproot/pub/acad http://www.fs.fed.us/.ftproot/pub/acad