1. Statement of Work.pdf
PDF 143 KB Posted
- Attached to
- 127EAW22R0014 - Noble Canyon Trail Work
- Solicitation number
- 127EAW22R0014
- Issued by
-
Department of Agriculture Forest Service
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFI Official Responses - 1.pdf | ||
| A00001.pdf | ||
| 127EAW22R0014 - Noble Canyon Trail Work.pdf | ||
| 6. Davis Bacon Decision Number CA20220001 01142022.pdf | ||
| 7. RFI Form.docx | DOCX document | |
| 2. Specifications - Section 37.pdf | ||
| 5. Site Locations & Map.pdf | ||
| 4. Fire Plan.pdf | ||
| 3. Specifications - Section 805.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GAOA-Noble Canyon National Recreation Trail and Trailhead Work
DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
SCOPE OF CONTRACT
The purpose of this contract is to restore three (3) parking lots by crack cleaning/sealing, large crack cleaning/patching, slurry coating, and replace in kind the handicap parking striping. The 3 locations are the Noble Canyon Trailhead Parking area and the Penny Pines Trailhead Parking (both sides of Sunrise Hwy).
This contract provides for the equipment, labor, and services necessary to perform work ordered by the Government for road maintenance on unsurfaced roads, in compliance with the terms, specifications, drawings and provisions of this contract. Locations of work will be directed by the Forest Service.
PROJECT LOCATION
The project consists of two different locations. Noble Canyon Trailhead is located approximately 3 miles from the town of Pine Valley. Penny Pines Trailhead is approximately 14 miles from the town of Pine Valley on Sunrise Highway. Pine Valley is 45 miles East of downtown San Diego off interstate 8. A general vicinity map is included with this solicitation. Cleveland National Forest maps are also available to assist in locating the individual roads and can be purchased at the respective Ranger District Office. The office is open between the hours of 8:00 am and 4:30 pm, Monday through Friday. The offices are located at:
• Descanso Ranger District 3348 Alpine Blvd. Alpine, CA 91901
PERIOD OF PERFORMANCE
Projected start date: July 5, 2021.
Time for completion: 30 calendar days from the issuance of the “Notice to Proceed”.
REQUIREMENTS
The Contractor shall furnish the necessary personnel, material, equipment, services and facilities to perform the Statement of Work/Specifications referenced below.
The Contractor shall minimize mechanical activity during rainy periods and the CO may shut down the operation if excessive soil disturbance and/or erosion problems occur.
The Contractor shall repair all associated damage on established roads, adjacent vegetation or other improvements caused by their operations or equipment prior to partial or final payment.
The Contractor shall provide technical submittals for all materials that may be furnished on this project for Forest Service review and approval prior to installation.
The Contractor shall dispose of all project related trash and debris off Forest lands prior to final payment.
GAOA-Noble Canyon National Recreation Trail and Trailhead Work
The Contractor is responsible for contacting the Forest dispatch center to obtain the fire predicted Project Activity Level (PAL) each day and restrict work accordingly.
The Contractor shall adhere to the pertinent requirements addressed in the Fire Plan. Fire Plan restrictions may require work to cease at 1:00 pm or not be initiated at all on a high fire activity day.
The Contractor is responsible for traffic control and equipment staging requirements in work areas when working on National Forest System Lands.
There are some heritage resource areas that need to be monitored while working in the designated sensitive areas.
If additional heritage resources are discovered during implementation, all project related work shall cease immediately and notification to the COR initiated.
The Contractor shall provide clean equipment for the project prior to driving on Forest and between project areas to prevent the introduction of invasive weeds to the Forest.
SPECIFICATIONS
The following standard Forest Service specifications are included as a part of this contract
ATTACHMENTS
805 Mobilization 818 Asphalt Crack Cleaning and Sealing 814 Asphalt Pavement Patching/Preparation Fire Plan
MAPS
1 Noble Canyon, Penny Pines Vicinity Map 2 Noble Canyon Site Map 3 Penny Pines Site Map
File details come from the government source that posted it. Updated .