1. Statement of Work.pdf
PDF 864 KB Posted
- Attached to
- 127EAW26Q0003 - Plumas NF Bear Boxes
- Solicitation number
- 127EAW26Q0003
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Statement of Work (SOW) from the US Department of Agriculture for the Plumas National Forest Bearproof Locker Install project. The contractor must procure and install 80 bear-proof lockers at two campgrounds on the Plumas National Forest in California: 70 lockers at Grasshopper Campground (Davis Lake) and 10 lockers at Lone Rock Campground (Antelope Lake). The bear lockers must meet specific ABA-compliant specifications including approximately 350 lbs weight, 48-inch width by 47-inch height by 37-inch length, UV-resistant forest brown powder coat finish, constructed of galvannealed steel with pocket-style touch latch mechanisms, and leveling feet for corrosion resistance. The contractor is responsible for all transportation, materials, excavation, grading, and installation of precast concrete footings (2500-4500 PSI) with anchors, as well as ensuring 95% maximum density compaction and providing testing documentation.
The estimated start date is August 15, 2026, with Lone Rock Campground available for installation beginning September 28, 2026, and Grasshopper Campground available beginning October 12, 2026. The contract performance period ends no later than May 14, 2027. Work is restricted to non-holiday weekdays Monday through Friday from 0700 to 1900 hours, with campgrounds to be cleared by noon the Friday before a Monday holiday if still open. The contractor must provide their own restroom facilities, utilities, and sediment control devices, and is responsible for all construction debris disposal off National Forest land. Key deliverables include a Proposed Project Plan due within ten business days of contract award and weekly status reports due every Friday by 5:00 PM PST. Personnel requirements include a Project Manager, Site Superintendent, and Quality Control Manager, with an onsite contract representative required within five business days of award.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A00001 - RFI Resposnes.pdf | ||
| 127EAW26Q0003 - RFI Official Responses.pdf | ||
| 4. Fire Plan.pdf | ||
| 5. Wage Determination CA20260007 01.23.2026.pdf | ||
| 3. Project Location Maps.pdf | ||
| 7. RFI Form.docx | DOCX document | |
| 2. Schedule of Items.docx | DOCX document | |
| 127EAW26Q0003 - Plumas NF Bear Boxes.pdf | ||
| 6. Contract Administration Information.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Statement of Work
Contents Project
General Information
1.0 Scope of Work
2.0 Background
3.0 Location
4.0 Estimated Start Date / Period of Performance
5.0 Drawings and Specifications
6.0 Restrictions on Work
6.0 Camping and Housing
7.0 Required Submittals
Contractor Requirements
8.0 Technical Requirements / Tasks
9.0 Government Furnished
10.0 Deliverables / Schedule
11.0 Travel
12.0 Contractor’s Key Personnel
13.0 Security Requirements
14.0 Data Rights
15.0 Site Visit
Project Plumas National Forest Bearproof Locker Install
General Information
1.0 Scope of Work
This purpose of this project is for the purchase and installation of 80 bear-proof lockers (bear lockers) at two campgrounds on the Plumas National Forest. The contractor shall provide all management, supervision, labor, personnel, transportation, materials, and supplies, except as otherwise specified, that is necessary to haul, deliver and install the bear lockers in locations throughout the Grasshopper and Lone Rock Campgrounds in accordance with all specifications provided in this document. The contract includes procuring bear lockers and precast concrete footings with anchors required to install the lockers, as well as any excavation and grading needed to ensure the bear lockers are level.
The Contractor shall refer to the Schedule of Items and referenced specifications under Section 5 when making estimates of quantities or work.
2.0 Background
Under this contract 80 bear lockers will be procured and installed by the Contractor at two campgrounds on the Plumas National Forest. The areas where the bear lockers will be installed are in mountainous locations which are typically under snow from December through April. Antelope Lake usually melts out in spring before Lake Davis and both campgrounds can be under snow by December. Access to both sites is via state highways and paved county and Forest Service roads. The campgrounds are busy with visitors in summer months, so construction periods must work around these busy summer months.
3.0 Location
Grasshopper Campground is located approximately 5 miles from the town of Portola, CA at 45° 27' 3.6720" N 113° 7' 25.7880" W. From downtown Portola take West Street for 5 miles, turn right on Lake Davis Road and go 1 mile, then take a left turn on Grizzly Road. Go approximately ½ mile and Grasshopper Campground is the second campground on the left.
Lone Rock Campground is located approximately 30 miles from the small town of Taylorsville, CA at 40° 11' 43.0001" N 120° 37' 1.9999" W. From Quincy take Highway 70/89 north towards Greenville to Arlington Road, take a right turn and go approximately 5 miles to Taylorsville and from there take Antelope Lake Road approximately 20 miles to the lake. At the dam, turn left and go 2 miles, and then turn right on Fruit Growers Road. The campground is 1 mile from the Fruit Growers Road intersection on the right.
4.0 Estimated Start Date / Period of Performance
The estimated start date is August 15th, 2026. Lone Rock Campground will not be available to install bear lockers until September 28th, 2026. Grasshopper Campground will not be available to install bear lockers until October 12, 2026. If earlier installation dates are desired and require a campground closure, the Contractor must inform the COR two weeks in advance of the installation date, and it must be reflected in the contractor's schedule. The end of the performance period will be no later than May 14th, 2027, when the campgrounds open for the 2027 season.
5.0 Drawings and Specifications
a. Bear lockers will have the following specifications shown below and in the drawings in Attachment B3:
• Weight of approximately 350 lbs.
• ABA Compliant and Universally Accessible for height, reach and required pounds of operating force
• Threaded zinc coated leveling feet that are corrosion resistant and can sit directly on the ground
• Assembled Width 48 in, Height 47 in, Length 37 in
• Paint finish will be UV resistant powder coat forest brown color
• Constructed of 12 and 14-gauge galvannealed steel
• Pocket style touch latch with double spring bolt actuation
• Self-closing touch latch composed of zinc plated steel components and hardware
b. Concrete footings must be 2500-4500 PSI precast or cast-in-place.
c. For installation, bear lockers will be installed level to allow doors to work properly. All areas around the bear lockers shall be graded to Architectural Barriers Act (ABA) standards. There shall be no stockpiles of material around the bear lockers after installation is complete to allow for universal access.
d. Contractor is responsible for all testing of materials around the concrete footings to ensure 95% max density of compaction. Contractor to provide testing documentation to COR or CO that demonstrates that minimum compaction results have been met.
The following drawings and specifications are physically incorporated in the solicitation as Attachments B1 – B3
[X] Construction Standard Institute (CSI) specifications [X] B1. Table of quantity of bear lockers and install location [X] B2. Campground Site Maps [X] B3. Bear Locker Install Details & Specifications
6.0 Restrictions on Work
• Work hours are limited to non-holiday weekdays, Monday – Friday, 0700 – 1900. Work site much be clear by noon the Friday before a Monday holiday if the campground is still open.
• Work must be done in accordance with the Fire plan, Attachment C.
• When the Contracting Officer (or designated representative) determines that adverse weather has made access too dangerous or that continued vehicular travel would cause unacceptable road damage.
• For sites requiring archaeology monitoring, contractor must notify COR at least 24 hours prior to any ground disturbing activities and no ground disturbing activities may occur without a Forest Service archaeologist on site.
• When the Contracting Officer or designated representative determines that work must stop due to the presence of archaeological artifacts.
• Contractor is responsible for the security of their tools and equipment at all times.
• Contractor is responsible for removal and disposal of all excavated dirt and shall not leave excavated dirt scattered over the site, unless approved by the COR.
• All trash and loose materials shall be secured by the contractor daily.
• The Contractor is responsible for installing sediment control devices, such as straw wattles, to prevent sediment runoff to nearby areas. Excavation work shall not commence until sediment control devices have been installed and approved by the COR.
• The Contractor shall not use Government trash facilities without the COR’S approval.
• All construction debris remains the property of the Contractor and shall be properly disposed of off National Forest Land.
• The contractor will be able to utilize the Forest Service Roads; however, the Contractor will be responsible for any damage to the roads due to construction activities. The contractor shall be responsible for obtaining permission to use all other roads and staging areas.
6.0 Camping and Housing
Camping is permitted in US Forest Service campgrounds. Contractor [X] will [ ] will not be permitted to camp elsewhere on US Forest Service land. If camping is outside of camping season, Contractor will be required to request permission in the technical proposal prior to construction to allow Forest Service to plan accordingly. Camping on Forest Service land is not a right; permission may be revoked for failure to comply with the terms of the permit.
7.0 Required Submittals
Section 011900 – Mobilization Section 013300 – Submittal Procedures Section 024100 – Waste Material Disposal Section 033000 – Cast In Place Concrete Section 033020 – Concrete from Packaged Dry Mix for Minor Structures Section 312225 – Excavation & Embankment
Contractor Requirements
8.0 Technical Requirements / Tasks
• All equipment and supplies needed to transport the lockers to be installed in their respective campground locations are the responsibility of the contractor.
• Schedule and coordination of accessing facilities where bear lockers are to be installed will be established with the COR. The Forest Service facilities can be accessed by M-F from 0600- 1900.
• For work and other installation location access, the campgrounds will have a Forest Service issued Yale Key lock on the access gate. The contractor will be issued (1) Yale Key for the project and must return immediately after completion of the contract installation requirements.
• The contractor shall provide all supervision, labor and materials required to install bear lockers at the campgrounds and sites designated.
• The Forest Service will mark the specific locations identified on the maps in Attachments B2 where a bear locker is to be installed at each campsite prior to the scheduled installation of locker provided by the Contractor.
Marking will be made with a pin flag or similar.
• Details for bear locker installation are included in Section 5.0 and under Attachments B1-B3. The Contractor shall provide all equipment labor, and materials, unless otherwise noted, to complete the install per the provided details. All lockers should be installed to meet all current ADA/ABA specifications.
• Installation shall occur outside of the campground season unless coordinated with COR. If closure is required prior to these dates, Contractor is responsible for informing the COR two weeks in advance of requested start date. The season runs from mid-May to the end of September at Lone Rock Campground, and mid-May to mid- October at Grasshopper Campground.
• The contractor shall provide their own restroom facilities during the entirety of the project since campgrounds will be closed. The Contractor shall be physically and financially responsible for properly disposing of any garbage/waste created during the install process.
• Technical specifications for bear lockers can be found in the links included in Section 5.0. Drawings and Specifications.
• The Contractor will be responsible for procuring bear lockers and precast concrete footings with anchors required to install the lockers. Cast-in-place concrete with anchors will be allowed with approval by the CO or designated COR on this project.
• The Government will not provide any power or water at installation locations. The contractor shall be responsible for providing their own utilities required to complete the installation at each site. The Contractor shall be responsible for mitigating fire danger on any tasks they are to perform and must adhere to the fire plan under Attachment C.
• The Government will identify a Government Inspector for each campground location. The inspector will verify that the installation occurs according to installation details and is in the correct location as part of their quality assurance. The contractor is required to provide their own inspection to ensure the installation occurs according to the installation details provided in this contract and per manufacturer requirements.
• The government inspector or GTM will inspect all bear lockers and footings for damage and correct installation.
If damage has occurred to bear lockers or footings, the Contractor will remove damaged materials and replace them with new materials. All costs associated with replacing damaged lockers and/or footings will be the Contractor's responsibility.
9.0 Government Furnished
It is the responsibility of the Contractor to procure bear lockers and all associated materials required for installation. All lockers to be installed shall be approved for installation by the COR or GTM prior to installation.
The intent of the Contract is to provide for the complete construction of the project described in the contract. The Contractor shall furnish all labor, materials, equipment, tools, transportation, to perform all work required to complete the project in accordance with specifications, and provisions of the contract. Payment for contract work will be made only for and under those pay items included in the Schedule of Items.
10.0 Deliverables / Schedule
Key Deliverables
Item No. Deliverable Objective Due
1 Proposed Project Plan Submit a plan defining the responsibilities, timeline, risks and milestones of contract objectives
No later than ten (10) business days after contract award
2 Weekly Status Report Once construction work begins on site, Contractor will submit a report documenting tasks completed under Section 8.0
Weekly, every Friday, by 5:00 PM PST until the contract expires
11.0 Travel
There is no anticipated travel requirement other than travel to and from the work site.
12.0 Contractor’s Key Personnel
Personnel shall include at minimum a Project Manager, Site Superintendent, and Quality Control Manager. The Contractor shall provide an onsite contract representative who will oversee the performance of the work specified in this contract no later than five (5) business days after contract award. Designate in writing to COR, the name of the contract representative and an alternate who shall have the authority to act for the Contractor on all contract matters relating to daily operation of this contract. The CO/COR shall be notified at least 10 working days in advance of any subsequent personnel changes. Replacement personnel shall have the same level or better experience as the person being replaced.
13.0 Security Requirements
A Forest Service key (yale key) will be required for access to the campgrounds when they are closed. The COR can provide a yale key that will be returned at the end of the performance period. No other security requirements are needed.
14.0 Data Rights
Not applicable.
15.0 Site Visit
A pre-proposal site visit will not be offered. It is recommended that contractors visit the campgrounds prior to bidding.
The sites will be accessible for Contractors on their own by parking at the entrance gates and walking in. The sites will be open to the public by May 15th. If further information is desired on accessing the campgrounds, FS personnel can be contacted for details.
Attachment B1. Table of quantity of bear lockers and install location
Recreation Site
Recreation Area
# lockers to be installed
Specific site numbers for installation
Site Map included in Attachment A / x = yes
Specifications
Grasshopper CG
Davis Lake
Sites 1-70 x
• Weight of approximately 350 lbs.
• ABA Compliant and Universally Accessible for height, reach and required pounds of operating force
• Threaded zinc coated leveling feet that are corrosion resistant and can sit directly on the ground
• Assembled Width 48 in, Height 47 in, Length 37 in
• Paint finish will be UV resistant powder coat forest brown color
• Constructed of 12 and 14-gauge galvannealed steel
• Pocket style touch latch with double spring bolt actuation
• Self-closing touch latch composed of zinc plated steel components and hardware
Lone Rock CG
Antelope Lake
Sites 60-69 x
• Weight of approximately 350 lbs.
• ABA Compliant and Universally Accessible for height, reach and required pounds of operating force
• Threaded zinc coated leveling feet that are corrosion resistant and can sit directly on the ground
• Assembled Width 48 in, Height 47 in, Length 37 in
• Paint finish will be UV resistant powder coat forest brown color
• Constructed of 12 and 14-gauge galvannealed steel
• Pocket style touch latch with double spring bolt actuation
• Self-closing touch latch composed of zinc plated steel components and hardware
Total 80
Attachment B2. Campground Site Maps Lone Rock Campground
Attachment B2. Campground Site Maps Grasshopper Campground
Attachment B3. Bear Locker Install Details & Specifications
Attachment B3. Bear Locker Install Details & Specifications
Attachment B3. Bear Locker Install Details & Specification