This Statement of Work (SOW) is for road maintenance in the San Bernardino National Forest, covering five (16) roads across three Ranger Districts: Front Country, Mountaintop, and San Jacinto. The project involves 94.16 miles of road blading and drainage maintenance, with specific requirements for rocky terrain that mandate using a bulldozer for certain roads (2N47, 3N22, 2N25, 3N34, and 3N34X) instead of a motor grader. The work includes re-establishing drainage features, installing drop inlets, and addressing poor road conditions characterized by ruts and rocky surfaces.
The contract has a 90-day performance period starting in October 2025, with a mandatory completion date of December 31, 2025 for CMXN-funded road maintenance. Work is restricted to non-holiday weekdays from dawn to dusk, and the contractor must be licensed in California, provide their own accommodations, and follow specific environmental and safety guidelines. The contractor will be responsible for sediment control, debris disposal, and road damage mitigation, with access to Forest Service Roads but requiring permission for additional roads and staging areas.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment A00002 - 127EAW25R0059 - BDF Road Maintenance 2025.pdf | ||
| Amendment A00001 - 127EAW25R0059 - BDF Road Maintenance 2025.pdf | ||
| 6. Fire Plan.pdf | ||
| 3. Maps - Road Maintenance CMRD Funded 1 - 4.pdf | ||
| 4. Maps - Road Maintenance CMXN Funded 1 - 3.pdf | ||
| 9. RFI Form - BDF Road Maintenance 2025.docx | DOCX document | |
| 2. Schedule Of Items - BDF Road Maintenance 2025.docx | DOCX document | |
| 7. Service Contract Act WD 2015-5629 - Riverside and San Bernardino.pdf | ||
| 5. Vicinity Map - BDF Road Maintenance.pdf | ||
| 8. R5 Road Maintenance Specifications.pdf | ||
| Solicitation 127EAW25R0059 - BDF Road Maintenance 2025.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Statement of Work
Contents Project General Information
1.0 Scope of Work
2.0 Background
3.0 Location
4.0 Estimated Start Date / Period of Performance
5.0 Drawings and Specifications
6.0 Restrictions on Work
6.0 Camping and Housing
7.0 Required Submittals
Contractor Requirements
8.0 Technical Requirements / Tasks
9.0 Deliverables / Schedule
10.0 Travel
11.0 Contractor’s Key Personnel
Project
Road Maintenance, Mountaintop, Front Country and San Jacinto Ranger Districts, San Bernardino National Forest
General Information
1.0 Scope of Work
The purpose of this contract is to provide road and drainage maintenance for five (16) roads and on three Ranger Districts of the San Bernardino National Forest. The final product will provide needed road maintenance and drainage maintenance to roads shown on the project maps.
This contract provides for the equipment, labor, and services necessary to perform work ordered by the Government for
94.16 miles of road blading and restoring existing drainage features in compliance with the terms, specifications, drawings and provisions of this contract.
Existing drainage features are in poor condition (rolling dips, lead off ditches) and will need to be re-established or re-shaped to get the road to drain in the best possible way. The existing road is in poor condition and is rutted and rocky.
A typical motor grader will not be acceptable due to the extremely rocky areas. Proposed work for 2N47, 3N22, 2N25, 3N34, and 3N34X must be estimated using a bulldozer. All other roads can be bladed with a motor grader.
This contract provides for the equipment, labor, material, and services necessary to perform work ordered by the Government for the installation of drop inlets, in compliance with the terms, specifications, drawings and provisions of this contract.
2.0 Background
The terrain can be relatively flat in a few areas and moderately hilly and steep in others. Soil conditions vary as well, from soft and sandy to compact and extremely rocky. All roads are native surfaced.
3.0 Location
The project is located on several different locations in the Front Country, Mountaintop, and San Jacinto Ranger Districts of the San Bernardino National Forest. A general Vicinity Map is included with this solicitation. San Bernardino National Forest maps are also available to assist in locating the individual roads and can be purchased at the Supervisors Office.
The office is open between the hours of 8:00 am and 4:30 pm, Monday through Friday. The office is located at 602 S.
Tippecanoe Ave. San Bernardino, CA. 92879
The Government will not provide a pre-bid site meeting. All roads are open for review and highly suggested to be driven for existing condition. For additional information regarding the road conditions/project contact Chris SooHoo at
(909) 893-0648.
Work site locations can be viewed on the attached Georeferenced Maps.
4.0 Estimated Start Date / Period of Performance
Period of performance: 90 days Start Date: October 2025 CMXN funded road maintenance must be completed by the end of the calendar year, December 31, 2025.
5.0 Drawings and Specifications
Attachments:
• R5 Road Maintenance Specifications
• FP-14 can be downloaded online
• Road Maintenance CMRD Funded Maps 1 through 4
• Road Maintenance CMXN Funded Maps 1 through 3
• Road Maintenance Vicinity Map
6.0 Restrictions on Work
• Work hours are limited to non-holiday weekdays, Monday – Friday, dawn to dusk
• In accordance with the fire plan.
• When the Contracting Officer (or designated representative) determines that adverse weather has made access too dangerous or that continued vehicular travel would cause unacceptable road damage.
• Contractor is responsible for the security of their tools and equipment at all times.
• All trash and loose materials shall be secured by the contractor daily.
• The Contractor is responsible for installing sediment control devices, such as straw wattles, to prevent sediment runoff to nearby areas in accordance with Erosion Control Plan. Excavation work shall not commence until sediment control devices have been installed and approved by the COR.
• The Contractor shall not use Government trash facilities without the COR’S approval.
• All construction debris remains the property of the Contractor and shall be properly disposed of off National
Forest Land.
• The contractor will be able to utilize the Forest Service Roads; however, the Contractor will be responsible for any damage to the roads due to construction activities. The contractor shall be responsible for obtaining permission to use all other roads and staging areas.
6.0 Camping and Housing
Contractor is responsible for securing their own accommodation. Applewhite Campground is available at public rates.
7.0 Required Submittals
Section 15501 – Schedule
Contractor Requirements
8.0 Technical Requirements / Tasks
The contractor shall be licensed to work on construction and/or service projects in the state of California and is responsible for obtaining and maintaining this license at no additional cost to the Government. For required tasks, refer to contract Specifications.
9.0 Deliverables / Schedule
Refer to FP-14 Section 155 Schedule for Construction Contracts
10.0 Travel
Refer to FP-14 Section 151 Mobilization
11.0 Contractor’s Key Personnel
In addition to Clause 52.236-6, the following applies: The name and the specific authorities of the foreman or superintendent must be designated in writing to the Contracting Officer. The Contractor may use his/her own prepared letterhead stationery or a "Designation of Contractor's Representative" form available from the
Contracting Officer. If the Contractor or the designee is not present when work is being performed on the contract, a Suspend Work Order may be issued with contract time continuing to run. The Contractor shall have a person on-site that is fully conversant in the English language.
| Project |
| General Information |
| 1.0 Scope of Work |
| 2.0 Background |
| 3.0 Location |
| 4.0 Estimated Start Date / Period of Performance |
| 5.0 Drawings and Specifications |
| 6.0 Restrictions on Work |
| 6.0 Camping and Housing |
| 7.0 Required Submittals |
| Contractor Requirements |
| 8.0 Technical Requirements / Tasks |
| 9.0 Deliverables / Schedule |
| 10.0 Travel |
| 11.0 Contractor’s Key Personnel |
File details come from the government source that posted it. Updated .