1. Statement of Work.pdf

PDF 277 KB Posted

Attached to
127EAW25R0054 - Lumsden Road Repair
Solicitation number
127EAW25R0054
Issued by

About this file

This Statement of Work (SOW) details a road repair project for the US Department of Agriculture (USDA) in the Stanislaus National Forest, Tuolumne County, California. The project involves repairing two road failures on Lumsden Road (1N10) near Buck Meadows, with work including construction of reinforced soil slope structures, road prism re-establishment, resurfacing, vegetation clearing, drainage system construction, and erosion control. The damage sites are located at Mile Post 9.17 and 10.21, which sustained significant damage during the winter and spring of 2023 and are eligible for Emergency Relief for Federally Owned Roads (ERFO) funding from the Federal Highway Administration.

The project has an estimated start date of October 15, 2025, with a 180-calendar-day performance period. The contractor will be responsible for mobilization, road repairs, obtaining necessary permits, and ensuring safety and quality control. Key requirements include submitting a work schedule within 10 days of contract award, establishing key personnel (Field Superintendent, Safety Manager, Quality Control Manager), and completing all project work prior to the end of the performance period. Lumsden Road will be closed to public motorized vehicle traffic during construction but remain open to foot traffic. The contractor must comply with specified specifications, drawings, and best management practices, and is responsible for all travel, waste disposal, and road use.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

Statement of Work

Contents Project

General Information

1.0 Scope of Work

2.0 Background

3.0 Location

4.0 Estimated Start Date / Period of Performance

5.0 Drawings and Specifications

6.0 Restrictions on Work

6.0 Camping and Housing

7.0 Required Submittals

Contractor Requirements

8.0 Technical Requirements / Tasks

9.0 Government Furnished

10.0 Deliverables / Schedule

11.0 Travel

12.0 Contractor’s Key Personnel

13.0 Security Requirements

14.0 Data Rights

15.0 Section 508 – Electronic and Information Technology Standards

Project Lumsden Road Repair

General Information

1.0 Scope of Work

This project will repair two road failures on Lumsden Road (1N10) near Buck Meadows, CA. Work consists of construction of reinforced soil slope structures, re-establishment of the road prism, and resurfacing of the road to match existing surface type, and repairs to adjacent. It also includes ancillary work such as vegetation clearing, construction of drainage systems and erosion control within the repair areas.

2.0 Background

During the Winter and Spring of 2023, the Groveland Ranger District on the Stanislaus National Forest sustained significant damage to multiple roads. Road failures occurred at two sites on 1N10 (Lumsden Road) and were determined to be eligible for Emergency Relief for Federally Owned Roads (ERFO) funding from the Federal Highway Administration

(FHWA).

3.0 Location

This project is located within the Groveland Ranger District of the Stanislaus National Forest, within Tuolumne County, California. From Buck Meadows, CA, travel on Ferretti Road to the junction of Lumsden Road. The damage sites are located at MP 9.17 (37.834570, -120.081418) and MP 10.21 (37.831927, -120.096630) on 1N10 (Lumsden Road). Access is available to the MP 10.21 site via vehicle from the Ferretti Road junction. Access is available to the MP 9.17 site by foot from the MP 10.21 site or by vehicle from Forest Route 1S01, which meets State Highway 120 near Lost Claim Campground. Both routes are currently closed to public vehicles and will require a key for access that can be obtained from the Groveland District Ranger Station in Groveland, CA or the Stanislaus National Forest Supervisor’s Office in Sonora, CA. The 1S01 route is not currently maintained for vehicle travel and may have rockfall and/or downed trees in the roadway.

4.0 Estimated Start Date / Period of Performance

Estimated Start Date: Notice to Proceed shall be issued no later than 15 calendar days after contract award – Estimated Date of October 15, 2025 Period of Performance: 180 calendar days

5.0 Drawings and Specifications

- Project Plans:

o FR 1N10 Lumsden Road Repair MP 10.21 o FR 1N10 Lumsden Road Repair MP 9.17

- Specifications:

o Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-14

(https://highways.dot.gov/federal-lands/specs/fp-14.pdf) o Forest Service Supplemental Specifications

- Fire Plan

- National Best Management Practices for Water Quality Management on National Forest System Lands, dated

April 2012 (https://www.fs.usda.gov/naturalresources/watershed/pubs/FS_National_Core_BMPs_April2012.pdf)

6.0 Restrictions on Work

• Contractor is responsible for the security of their tools and equipment at all times.

• All trash and loose materials shall be secured by the contractor daily.

• The Contractor is responsible for installing sediment control devices in accordance with the Best Management Practices and erosion control plan. Excavation work shall not commence until sediment control devices have been installed and approved by the COR.

• The Contractor shall not use Government trash facilities without the COR’S approval.

• All construction debris remains the property of the Contractor and shall be properly disposed of off National Forest Land.

• The contractor will be able to utilize the Forest Service Roads; however, the Contractor will be responsible for any damage to the roads due to construction activities. The contractor shall be responsible for obtaining permission to use all other roads and staging areas.

6.0 Camping and Housing

Camping and/or housing are not provided.

7.0 Required Submittals

Specify what type and section of submittals are required example:

Section 011900 – Mobilization Section 013300 – Submittal Procedures Section 024100 – Waste Material Disposal Section 033000 – Cast In Place Concrete Section 033020 – Concrete from Packaged Dry Mix for Minor Structures Section 312225 – Excavation & Embankment Section 323113 – Chain Link Fences and Gates Section 331113 – Potable Water Supply Wells Section331415 – Site Water Distribution Piping

Contractor Requirements

8.0 Technical Requirements / Tasks

The following work shall be performed as mandatory work items under this contract. All work shall be completed in accordance with attached project specifications, drawings, and best management practices. The work includes all labor, material, and equipment necessary to perform all the operations required to complete the work specified.

Lumsden Road will be closed to public motorized vehicle traffic during construction but is open to foot traffic.

Mobilization:

Mobilization as necessary shall include preparatory work and operations necessary for the movement of personnel, equipment, supplies, and incidentals to the project site. Staging areas can be evaluated by the Forest Service upon request by the contractor. All staging and storage areas will be completely removed, and the areas restored to pre-construction conditions upon completion of use. Disposal of waste materials will be off National Forest land and in compliance with local, state, and federal laws regarding disposal of construction waste.

Road Repairs:

All work included in the plans, specifications, and schedule of items shall be performed to provide a well-functioning road. The work shall meet the requirements of the specifications incorporated by reference and supplied as well as the specifications established in the drawings.

NOTE: At both sites, the HDPE geomembrane (identified on the typical RSS section and RSS details sheets) shall extend across the entire road section to the toe of cut slope. The top two tiers of the RSS reinforcement shall also extend across the entire road section unless bedrock is encountered.

The contractor is responsible for safeguarding employees, public, existing facilities, and forest resources from project operations. Signs and barricades as necessary shall be erected to make unguarded operations safe.

Permits:

The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses, permits, and letters of certification. The Contractor shall comply with any applicable Federal, State, County, and Municipal laws, codes, and regulations in connection with the performance of the work specified under this contract.

9.0 Government Furnished

Borrow sites will be designated by request prior to construction. No other government-furnished support, data, property, or facilities shall be provided.

10.0 Deliverables / Schedule

Within 10 days of contract award, the contractor shall submit a proposed work schedule for the project to the Contracting Officer. The Contracting Officer shall be notified at least 48 hours in advance of any activity which requires inspection, acceptance, or approval. The contract shall update the approved schedule as necessary when significant changes occur during the progress of work, or when requested by the Contracting Officer.

All project work and restoration/cleanup of the project area shall be completed prior to the end of the project period of performance.

11.0 Travel

The Contractor is responsible for all travel necessary to accomplish the project.

12.0 Contractor’s Key Personnel

The Contractor shall establish the following key personnel:

Field Superintendent Safety Manager Quality Control Manager

All personnel identified above shall have substantial experience in these roles comparable to that identified in the Response to Evaluation Factors for the overall Contractor.

During the first 90 days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events. After the initial 90-day period, the Contractor shall submit changes in personnel to the Contracting Officer at least 15 days prior to making any permanent substitutions.

13.0 Security Requirements

No project-specific security requirements.

14.0 Data Rights

No project-specific data rights requirements.

15.0 Section 508 – Electronic and Information Technology Standards No project-specific electronic and information technology standards.

File details come from the government source that posted it. Updated .