1. POL Pipeline Inspection PWS_SOURCES SOUGHT.docx
DOCX document 113 KB Posted
- Attached to
- POL Pipeline Inspection Services
- Solicitation number
- FA570625R0003
About this file
This Performance Work Statement (PWS) details a pipeline inspection service for the 380th Air Expeditionary Wing at Al Dhafra Air Base in the United Arab Emirates. The contract requires a comprehensive inspection of approximately 4 km of fuel pipeline infrastructure, including four pumps at Tank 1 and four pumps at Tank 2, along with a detailed geometric survey of the entire system. The contractor must perform general inspections of fuel pumps and hydrant pits, run an inspection pig through the lines, conduct a geometric survey using specialized tools, and provide comprehensive reports documenting the findings.
Key requirements include using a geometry tool capable of detecting pipeline anomalies with high precision, measuring wall thickness, and assessing the overall condition and remaining lifespan of the infrastructure. The contractor must have an oil and gas permit from the American Petroleum Institute and a UAE license to work on fuel facilities. The inspection will be conducted across 24-hour periods, with specific technical requirements for the inspection tools, including the ability to traverse pipeline bends, track the inspection pig, and provide electronically stored geometry data. The sources sought notice indicates the government is seeking industry input before potentially releasing a formal solicitation, with responses due by 12:00 noon GMT on 23 May 2025.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Work Statement (PWS) Sewage and Waste Removal
| Introduction | 2 |
| General Requirements | 3-4 |
| Performance Requirements | 5-6 |
| Special Requirements | 7-11 |
| Service Summary | 12 |
Deliverables Schedule………………………………………………………………….13 Hazmat/Hazwaste Regulations…………………………………………………………14 Emergency Response Plan………………………………………………………………18
1 Introduction
The 380TH Air Expeditionary Wing (AEW) has a requirement to inspect the fuel lines leading from the fuel storage facility to Tango Ramp. The existing infrastructure is comprised of a continuous loop of hydrants that supply aircraft at various points on the ramp. They hydrant system involves two pipelines that include dual-supply and return lines and a single line that loops through the aircraft supply points. Overall, the system is 4 km long with pipes that measure 300mm in diameter. The pipes are of stainless-steel construction.
1.1 Scope
The Contractor shall provide all personnel, equipment, tools, materials, vehicles, supervision, and any other items and services necessary to perform the pipeline inspections as outlined in this PWS. Specifically, the contractor will be required to perform general inspections of four (4) pumps at Tank 1 and an additional four (4) pumps at Tank 2. Due to limited information available on the transfer line system, the contractor will also be required to run an inspection pig the line to ensure that the geometric pig can pass through the line. After the contractor runs the inspection pig through the system, the contractor shall perform a geometric survey as outlined in this performance work statement (PWS). Finally, the contractor shall provide reports/surveys to document their findings as a result of the inspection of the pumps at Tank 1 and Tank 2 and the geometric survey.
1.2 Mission Essential
The scope of this PWS is considered essential to mission success. Access to base may be limited depending on alarm status and force protection conditions.
2 General Requirements
2.1 Non-Personal Services
The Government shall neither supervise Contractor employees nor control the method by which the Contractor performs the required tasks. It shall be the responsibility of the Contractor to manage their employees and to guard against any actions that are of the nature of personal services or give the perception of personal services. If the Contractor believes that any actions constitute, or are perceived to constitute, personal services, it shall be the Contractor's responsibility to notify the Government’s Contracting Officer (CO) or Contracting Officer’s Representative (COR) immediately.
2.2 Business Relations
The Contractor shall successfully integrate and coordinate all necessary activities to execute the requirement. The Contractor shall manage the timeliness, completeness, and quality of problem identification. The Contractor shall provide corrective action plans within four (4) hours of issue identification and effectively manage any subcontractors. The Contractor shall prioritize customer satisfaction and professional/ethical behavior of all Contractor personnel.
2.3 Contract Management
The Contractor shall establish clear organizational lines of authority and responsibility to ensure effective management of the resources assigned to the requirement. The Contractor must maintain continuity between the support operations on base and the Contractor's corporate offices. The Contractor’s site lead/program manager shall maintain base-access credentials to respond to site emergencies and/or meetings with the CO/COR.
2.4 Contract Administration
The Contractor shall establish processes and assign appropriate resources to effectively administer the requirement. The Contractor shall respond to Government requests for contractual actions within four (4) hours. The Contractor shall have a single point of contact between the Government and Contractor personnel assigned to support this contract. The Contractor shall assign work effort and maintain records of personnel assigned to work on the requirement.
2.5 Contractor Personnel, Disciplines, and Specialties
The Contractor shall accomplish the assigned work by employing and utilizing qualified personnel with an appropriate combination of education, training, and experience. The Contractor shall match personnel skills to the work or task, with minimal over-employment of resources. The Contractor shall provide all the necessary resources to manage, perform, and administer the contract.
2.6 Hours of Work
The contract will be performed Sunday through Saturday and operate twenty-four (24) hours per day. Each Sewage run shall be between 10-12 hours apart. The Contractor shall anticipate security delays to reach the job sites and plan their work schedule accordingly.
2.7 Inclement Weather
The Contractor shall accomplish collection and servicing during periods of inclement weather. In cases of severe weather, the CO may authorize exceptions. When exceptions are granted, the Contractor shall make up all missed collections within 8 hours of severe weather termination. The
CO may authorize additional time under exceptional circumstances.
2.8 Clean Up
The Contractor shall at all times keep the work area, including storage areas, free of accumulated waste materials. Before completing the work, the Contractor shall remove from the work area/premises any rubbish, tools, equipment, hoses and materials that are not the property of the Government. Upon completing the work, the Contractor shall leave the work area in a clean, neat, and orderly condition satisfactory to the CO and/or COR.
3 Performance Requirements
The contractor shall perform general inspections of pumps P-1, P-2, P-3, and P-5 at Tank 1 and the pumps P-5, P-6, P-7, and P-8 at Tank 2 as outlined in para 3.1. The Contractor shall then perform a Geometric Survey of the fuel overall fuel system outlined in para 3.2. In both cases, shall provide surveys/reports of its findings to evaluate the general health and functionality of the system.
3.1. General Inspection of Fuel Pumps
The Contractor shall perform a general inspection of four (4) fuel pumps at Tank 1 and a general inspection of four (4) additional pumps at Tank 2. This general inspection shall consist of, but is not limited to, an evaluation of integrity of existing infrastructure. The contractor shall pig the lines for signs of cracks or leaks in addition to scanning the lines to measure overall thickness. In the process, the Contractor shall clean and remove any debris or objects from the lines that may preclude an effective review of the existing infrastructure.
Finally, the Contractor shall provide a report/survey to the Government at the conclusion of its inspection. This report shall sufficiently detailed enough to provide the Government with an estimate of the viability of existing infrastructure as well provide insight into their remaining lifespan. At a minimum, this report shall include detail about any cracks or leaks identified as well overall pipe thickness.
3.2 General inspection of Hydrant Pits
The Contractor shall perform a general inspection of flightline hydrant pits where indicated. This inspection shall include, but will not be limited to, ensuring that the pits are clean and free or debris that may preclude an effective evaluation. The Contractor shall also pay special attention to hydrant functionality, throughput, and the accuracy of gage readout.
Upon completion of the hydrant pit inspection, that Contractor shall provide to the Government a report/survey of its findings. The report shall be in sufficient enough detail to help the Government evaluate the viability of these assets in terms of the overall functionality, safety, and overall lifespan of these assets.
3.3 Geometry Survey
After a satisfactory inspection gauging pig run, the pipeline geometric defects shall be determined by a geometry tool. The geometry tool shall provide accuracy geometric anomaly detection, and bend radius measuring capability. The data obtained shall be presented in a PC software format to allow user friendly analysis and presentation. The geometry tool assembly shall be capable of:
3.3.1 Operating in hydrocarbon liquid environment, specifically jet fuel, at a pressure of up to ANSI 300 rating operating pressure is typically no greater than 150).
3.3.2 Traversing the pipeline with nominal wall thickness and possible bore restrictions down to 90 percent of nominal pipe inside diameter.
3.3.3 Traversing pipeline length at a speed of between 3 and 5 ft/sec when propelled by pumped jet fuel. Pressure differential across pig shall not exceed 50 psi.
3.3.4 Traversing through smooth pipe bends as small as 1 D (1 pipe diameters) radius and single miter bends of up to 10 degrees change of direction.
3.3.5 Include a tracker and tracking equipment. Track the pig assembly above ground during the operation. The battery life of the tracker shall not be less than 72 hours.
3.3.6 Manual loading into the pig trap.
3.3.7 Additional Geometry tool assembly instrumentation capabilities:
3.3.7.1 Battery life to be minimum of 18 hours at operational conditions.
3.3.7.2 Principle of operation to be electronically stored geometry system.
3.3.7.3 Principle of operation to be electronically stored geometry system.
3.3.7.4 Geometry sensing to span full circumference and length of pipe, with associated distance measuring method.
3.3.7.5 Geometry system shall be capable of:
3.3.7.5.1 Positive location and identification of each geometric anomaly.
3.3.7.5.2 Positive location and identification of each bend.
3.3.7.5.3 Positive location and identification of distance marker reference points of either magnetic or electronic type placed on or above the pipe if they exist.
3.3.7.6 Classification of geometric anomalies to be as minimum:
3.3.7.6.1 Discrimination between orality and intrusion anomalies.
3.3.7.6.2 Mechanical damage such as mill defects, dents, internal gouges and buckles.
3.3.7.6.3 Pipeline weld defects (such as excess weld penetration).
3.3.7.7 Geometric thickness anomalies. As a minimum, these shall be reported in the following categories within the listed accuracy:
(aa) magnitude of anomaly (+/- 1 inch)
(bb) span of anomaly (+/- 1 inch)
(cc) ovality (+/- 1 inch) (dd) span of ovality (+/- 1 inch) (ee) anomaly station (+/-1:3,000)
3.3.8 Pipe Wall Thickness Survey:
After satisfactory cleaning, gauging, and geometry pig run, the pipeline wall thickness shall be determined using an ultrasonic testing tool. The tool shall provide accuracy measurement of pipe wall thickness (+/-0.01 inch). The data obtained shall be presented in a PC software format to allow user friendly analysis and presentation
4 Special Contract Requirements
4.1.1 Safety and Security
4.1.2 Contractor Equipment Storage.
Vehicle(s) used for sewage and gray water services may park on the parking lot adjacent to the Materiel Control warehouse on base\ after completion of the route.
4.1.3 Liability
The Government shall not be held responsible for damages to property or for injuries or death to persons, which might occur without fault on the part of the Government as a result of, or incident to, performance of work.
4.1.4 Contractor Employee Conduct on Base
Contractor employees assigned to this contract are required to understand and speak English. Contractors operating on base will be responsible for briefing and ensuring their employees adhere to the traffic rules, regulations and all security measures to include: not asking any security related questions, soliciting any personal information from any government employee, and transporting any items for government personnel. The site supervisor shall ensure the workers comply with these rules and regulations. The speed limit on base is 20 KPH unless otherwise posted. Individuals are to obey all entry procedures. If instructions are given by Security Forces personnel, they will be complied with immediately. If an employee is requested by a member of the Host Nation Security to present his/her Emirati Red Badge, he/she will produce the badge immediately and will not argue with the Host Nation.
4.1.5 Escorts
Upon entry through on base, the contractor personnel are required to be escorted to the government facilities by designated escorts. At which time contractors are required to stay at the facilities at all times. Contractor personnel must be escorted by designated personnel when not located in the government provided drop-off facilities. The Government shall provide escorts. The Contractor shall comply with escort directions. The Contractor shall notify the designated COR 48 hours in advance of any revised personnel/escort requirements. The Contractor shall notify the designated COR 24 hours in advance of any change in time that the escorts shall meet the Contractor and/or when the number of contract workers increases or decreases. The Contractor will not be able to start work until escort arrangements are made. The Government shall not be liable for delays caused by the Contractors’ failure to follow the above notification requirements.
4.1.6 Pass Requirements
The contractor shall follow existing security procedures and instructions applicable to the base and Emirate Gate Procedures. The Government shall not be liable for delays caused by inaccessibility through the Emirate Gate.
The contractor shall submit pass request applications to the Contracting Officer with their proposal. The Contractor is responsible for obtaining registration and badges to access the base before the contract start date. The Contractor will be given four (4) weeks from contract award date to obtain all required registration and badges and begin work. The pass request application require coordination with the Host Nation Liaison. The Government is not liable for delays resulting from Emirate pass coordination/approval. Contractor shall be liable for completing all requirements within the specified time frames. No extensions on work will be granted due to delays from Emirate pass coordination or approval. Should the Contractor make any changes to contractor-personnel, the Contractor shall provide the necessary badging/base access documentation to the CO/COR at least 7 business days prior to when the individual is expected to perform the required services.
The work site is located in a restricted or controlled area. The contractor may therefore experience delays due to compliance with entrance/exit requirements of restricted/controlled areas. The maximum amount of delay should not exceed four (4) hours per occurrence. Contractor is required to contact the Contracting Office for security procedures/ instructions upon award of contract.
If the Contractor already has Al Dhafra Air Base passes, they shall provide a list of approved employees that will perform under this proposed contract. If the Contractor does not have approved access, they shall provide a listing of potential employees they will seek to badge.
4.1.7 Search
Upon entry through the gate, contractor personnel and vehicles shall process through the Vehicle Search Area (VSA).
Tanker truck/trailer cargo compartments shall allow for a complete visual inspection. All tanks and all baffled sections shall have a minimum 3ft /.91 meter diameter visual inspection port. Equipment not meeting the above requirements shall not be allowed entry on base. The Government shall not be liable for delays caused by equipment not meeting the above requirements.
4.1.8 Prohibited Items
Military Uniforms: The wear of any type of military uniform clothing or items is strictly forbidden.
Certain Communications Equipment: Contractor personnel working on base are prohibited from using telephone instruments to include but not limited to, cellular telephones, mobile radios, beepers, pagers or any other type of communication device without expressed pre-approval of responsible security personnel. Contract laborers may carry a cellular telephone (without video/picture capabilities) if they possess a signed letter of authorization approved by Host Nation Security, Det 246 AFOSI, and the Defense Force Commander. This letter must contain the name of the authorized individual, the name of the company represented, the telephone number(s) and an expiration date. This letter is required to be carried on the person at all times when in possession of a cellular telephone. Additionally, the cell phone should be marked with the cell phone number on the exterior for identification purposes. Contact the Contracting Officer in advance for further details. Furthermore, contractor personnel are prohibited from bringing all computer and peripherals onto the installation to include, but not limited to still cameras or video cameras, computers, CD-RW discs, jump drive/thumb drives, external hard drives or any other type of data recording device.
Alcohol and/or Pornography: Contractor personnel working on base are prohibited from bringing alcohol or pornography onto the base.
Drugs: The unlawful manufacture, distribution, dispensing, possession, or use of a controlled substance is prohibited on base. Controlled substances include, but are not limited to: narcotics, qat leaf, betel leaf or nuts, paan chuna, naswar, and gutkha. Any and all types of drug paraphernalia are also prohibited. If contractor personnel require any banned substances for medical or emergency reasons and must carry such medicine with them to work on base, such personnel must carry a valid medical prescription for that particular medication from a host-nation, licensed doctor. You are not permitted to bring more than 24 hour supply of prescription medication onto the base Weapons and Firearms: Contractor personnel are prohibited from bringing firearms or weapons on base In addition to firearms, personnel may not bring any objects/weapons designed to inflict bodily injury or property damage. In addition to firearms, examples of prohibited weapons include, but are not limited to, the following: switchblade knives, gravity knives, any knife with a blade longer than six inches, swords, blackjacks, pellet guns, air or CO2 rifles and pistols, bows, blow guns, arrows, metal knuckles, and/or martial arts weapons.
4.2 Government Furnished Property and Services
The government shall furnish the following in support of this contract:
· Staging area for contractor vehicle storage, maintenance actions and pressure washer in the Material Control Yard (adjacent to Bldg. 1066).
· Water will be provided by the station adjacent from the Vehicle Maintenance Squadron (bldg. 3204).
4.3 Quality Control
The Contractor shall develop a Quality Control Plan (QCP) and maintain an effective quality control program to ensure services are performed in accordance with the contract and this PWS. The Contractor shall develop and implement procedures to identify, prevent, and ensure non- recurrence of defective services. The Contractor’s QCP is the means of assurance that the work complies with the requirements of the contract.
The finalized QCP will be accepted by the Government at the post-award conference. The Contracting Officer may notify the Contractor of required modifications to the plan during the period of performance. The Contractor then shall coordinate suggested modifications and obtain acceptance of the plan by the Contracting Officer. Any modifications to the program during the period of performance shall be provided to the Contracting Officer for review no later than 10 working days prior to effective date of the change. The QCP shall be subject to the Government’s review and approval. The Government may find the QCP "unacceptable" whenever the Contractor’s procedures do not accomplish quality control objective(s). The Contractor shall revise the QCP within 10 working days from receipt of notice that QCP is found "unacceptable."
A draft QCP is required with the Contractor’s solicitation response.
4.4 Quality Assurance Surveillance Plan (QASP)
The Government shall monitor the Contractor’s performance under this contract in accordance with the QASP.
4.5 Phase-In and Phase-Out Plan
The Contractor shall develop, maintain and implement comprehensive phase-in/phase-out plan. The phase-in plan shall ensure the transition in the change of work effort will cause no gap or delay in required services. The phase-in plan must emphasize the steps and procedures that will be taken to effectively mobilize personnel on base and be fully operational. The phase-in plan must demonstrate an understanding of the requirement and the ability to ensure a seamless transition, uninterrupted sewage removal service, and compliance with the PWS. The contractor shall provide a phase-out plan for the transition of services to another contractor or Government agency in the event the service is not renewed for an option period, the last option period is due to end, or termination.
4.6 General Requirements
4.6.1 The Contractor shall hold a valid license issued by the authority having jurisdiction for the work that is to be accomplished.
4.6.2 The Contractor shall read and review the Statement of Work (SOW), General Specifications and Drawings; therein the Contractor shall be familiar with all applicable specifications, standards and any pertinent documentation in order to meet the US Government expectations
4.6.3 Contractor personnel shall comply with Al Dhafra AB Contractor escort policy. Violations of this policy may result in contract termination or removal from the site.
4.6.4 Contractor personnel found outside of the prescribed work area will be detained and then removed from the site.
4.6.5 The Contractor shall provide all employee food and water, transportation for materials and personnel, and material handling equipment as necessary to complete the work.
4.6.6 The Contractor shall clean-up the work site daily to include removing all debris and refuse, to the satisfaction of the Contracting Officer. Government rubbish bins shall not be used by Contractor.
4.6.7 The Contractor shall clean-up the work site daily to include removing all debris and refuse, to the satisfaction of the Contracting Officer. Government rubbish bins shall not be used by Contractor.
4.6.8 Contractor personnel found outside of the prescribed work area or otherwise in violation of any security requirements will be subject to removal from the work site for the entire work period.
4.7 Contractor Qualifications
4.7.1 The contractor shall have an oil and gas permit for inspection and/or or a maintenance license from American Protroleum Institute, (API) to perform services for this project. A license from the UAE to work on fuel oils facilities is also required.
4.7.2 If there is a confined space, the contractor shall submit a confined space hazards plan and mitigation measures. This hazards plan shall include, but not limited to, the risks from reduced oxygen levels, a risk of fire, flooding/drowning. etc.
4.9. Coordination
4.91. The contractor shall coordinate with Airfield Management, (AFM) to gain appropriate access.
4.10. Existing Utilities
4.10.1 All trenching within 2 m of existing utilities shall be accomplished by hand. Dig permit required on all excavation
4.10.2 The US Government shall provide the location of known underground utilities; however, the Contractor shall maintain awareness that there may be some unknown buried utilities.
4.10.3 Contractor assumes liability due to any mishaps.
4.10.4 Preliminary inspection and stake-out shall be performed by all involved parties and a dig permit shall be requested.
4.10.5 Host Nation shall be involved in the request for a dig permit as required.
4.10.6 All trenching shall be inspected by US Government Representative prior to covering.
4.10.7 If the Contractor encounters unexpected obstacles, they shall notify the Contracting Officer immediately.
SERVICES SUMMARY ITEMS (SSI)
| Performance Objective |
| PWS |
| Performance Threshold |
| Perform general inspection of fuel pumps at Tank 1 and 2 |
| 3.1 |
| Contractor performs work in timely fashion and in a manner that meets specifications identified in PWS. Direct observation. |
| Perform general inspection of hydrant pits |
| 3.2 |
| Contractor performs work in timely fashion and in a manner that meets specifications identified in PWS. Direct observation. |
| Conduct Geometry Survey |
| 3.3 |
| Contractor performs Geometry Survey in the manner outlined in the PWS in a timely manner. Direct observation |
DELIVERABLES SCHEDULE
| DELIVERABLE |
| PWS |
| Timeframe |
| Short Term base access |
| 4.1.6 |
| Contract award + 10 business days |
| DIG PERMIT AF 103 |
| 4.10 |
| Contract award + 10 business days |
| Fuel Pump General Inspection Report/Survey Results |
| 3.1 |
| Within +10 days of conclusion of performance period |
| Hydrant Pit General Inspection Report/Survey results |
| 3.2 |
| Within +10 days of conclusion of performance period |
| Geometry Survey Report/Survey results |
| 3.3 |
| Within +10 days of conclusion of performance period |
HAZMAT/HAZWASTE Regulations
| 380TH AEWI 32-7042- Hazardous Waste Management Section 8.1 Removal by Contractors |
| Hazardous waste, regulated waste, and regulated recyclable commodities transported off installation boundaries will be accompanied by a manifest, bill of lading, or other document listing the items and quantities being removed. The form of documentation will be determined and prepared by the 380 ECES/CENV Hazardous Waste Manager. |
Locally developed forms appropriate for tracking the items being transported will be used. At a minimum, these forms will include:
Generator’s name, address, and telephone number Transporter’s name, address, and telephone number Destination Facility Description of the waste Quantity of the waste Date of the shipment
Waste containers will be labeled, marked, meet packaging specifications, and be segregated in accordance with United States Department of Transportation (USDOT) requirements, as contained in Title 49, Code of Federal Regulations (CFR) Parts 172 through 178.
The cargo must be secured to the vehicle in a manner that will not allow shifting, tipping, or spilling of cargo during transport.
Transpiration will be accomplished only by companies and vehicle authorized by the Emirate of Abu Dhabi to transport hazardous or regulated waste.
| 380TH AEWI 32-7002 Hazardous Material Management Section 4.13 Contractors |
| 4.13.1. Contractors who provide services, and/or support construction work on base through non-380 ECONS managed contracts will: |
4.13.2. Submit EESOH-MIS-based authorization requests before purchase of any hazardous material, hazardous chemical, or any system or equipment using hazardous chemicals or producing regulated or hazardous waste.
4.13.3. Comply with all hazardous material acquisition, storage, management, and disposal processes described in this IHMP.
4.13.4. See Chapter 7 for additional Contactor requirements
| 380TH AEWI 32-7002 Hazardous Material Management Section 7.2 Locally Contracts and Contractors |
| Contractors working under contracts issued by 380 Expeditionary Contracting Squadron (380 ECONS), Host Nation-based contractors, and other local contractors are expected to comply with fundamental “spirt and intent” of this IHMP, including: |
7.2.1. Submitting a listing of hazardous chemicals used during performance of the specified work to the Contracting officer.
7.2.2. Submitting copies of Safety Data Sheets (or reasonable facsimile thereof) to the Contracting Officer; and maintaining copies of Safety Data Sheets at the primary workplace.
7.2.3. Preparing and maintaining an inventory of hazardous chemicals stored at the work site or storage location.
Maintaining hazardous chemicals and hazardous materials in a neat and orderly manner, not exposed to the elements or direct sunlight, and stored in a manner sufficient to prevent discharge to the ground surface, surface waters, or ground water.
7.2.5. Ensuring hazardous chemical containers are clearly labelled, in English, with the contents.
7.2.4. Hazardous chemicals and hazardous materials shall not be stored in direct contact with the ground, and will at all times be placed upon impermeable surfaces such as drop clothes
| 380TH AEWI 32-7002 Hazardous Material Management Section 7.3 General Requirements Applicable to All Contractors |
| 7.3.1. The requiring agency will seek the necessary guidance from Bioenvironmental Engineering and/or the CE Environmental Office to ensure military and government personnel are not adversely affected by contractor hazardous material use. |
7.3.2. Any hazardous material on base must be safely stored and will be subject on base inspections to ensure safety to personnel and protection to the environment.
7.3.3. Any unused serviceable or unserviceable material used by a contractor for on base project or service shall be removed from baseby the contractor upon completion of the project.
Table 1 Spill Response and Cleanup/Disposal Guidance for Various Spill Volumes
Table 1 - Spill Response Guidance and Cleanup / Disposal Guidance for Various Spill Volumes
| Spill Category |
| Response |
| Cleanup / Disposal |
Small Spills less than 10 gallons Use internal resources and available spill supplies to collect spilled fluids.
Containerize contaminated soil and absorbent material in drums/ Deliver containerized soil and cleanup wastes to the hazardous waste operations yard, Bldg. 2180. .
| Immediately notify the Fire Department. Completion of a Spill Report Form is required for spills in excess of 10 gallons. |
| Deliver containerized soil and |
Spill in excess of 10 gallons but less than 110 gallons cleanup wastes to the hazardous waste operations yard. Notify Fire Protection Services to ensure area is “Fire Safe,” and contact Base Environmental regarding cleanup requirements.
Spills in excess of 110 gallons Immediately notify the Fire Department. Completion of a Spill Report Form is required.
Notification of AFCENT is required for spills in excess of 110 gallons.
Same as above except that notification to AFCENT A7 is required. ECES CC is responsible for accomplishing the notification, with technical guidance from CE Environmental
Bulk Fuel Tank failure or related release up to 6,000 gallons
| Considered a major event and requires mobilization of the Spill Response Team members as requested by ECES CC. |
| Use hand tools or heavy equipment |
as required to contain the spill. Use mobile tanks, bowsers, or other portable tanks for storage of recovered product. Use absorbent pads and socks to contain spill and prevent impacts to surface water, sewer manholes, and storm water inlets.
Emergency Action Response Plan
GENERAL SPILL RESPONSE PROCEDURES:
Stop the flow of fuel or hazardous material by sealing the breach in the line or tank, shutting off the pump, stopping the fuel transfer pump, closing the valve, plugging the hole or breach, or enacting other physical methods. For quick reference, see Exhibit 1 on the following page.
Dike, Divert, or Dam or otherwise contain the spill. Stop the fuel spill from spreading by using available tools to create earth berms, or deploy absorbent materials, socks, gradual absorbent materials. Use covers or physical barriers to block storm drain inlets. For large spills, request heavy equipment to create earthen dams to prevent fuel from reaching waterways.
Cordon off the area and eliminate ignition sources. This includes prohibiting smoking or open flames, limiting vehicular access and consider using non-sparking tools and equipment. Eliminate static electricity sources by grounding and bonding all equipment, tools, and personnel.
Conduct notification: Notify Chain of Command, Fire Protection Services, and Base Environmental for major “reportable” spills.
Assess the situation and develop a cleanup plan. Carefully plan, assemble equipment and materials, and implement cleanup of the spilled material. Coordinate with Occupational (Wing) Safety regarding safety procedures and ensure oversight from Bioenvironmental Engineering is provided regarding selection and use of personal protective equipment (PPE) and exposure monitoring.
Free Product Recovery and Storage Procedures
· Free product can be recovered using pumps, buckets, pumper vehicles, or other expedient methods and stored in mobile bulk storage containers or 55-gallon closed top drums. CE Environmental maintains one
(1) 1,000 - gallon trailer-mounted tank that can be used for such purposes.
· Additional 500-gallon fuel storage tanks are located adjacent to Hazardous Waste Operations, Bldg. 2180, near the Power Pro generator ready line. These tanks are double walled and can be lifted with a forklift for movement to a spill location.
· ELRS/LGRV may designate R-11 refuelers C-301 tanks, at their discretion, to be used as product recovery vehicles / mobile recovered product storage tanks.
image1.png image2.png