1. Draft Requirements Description.docx
DOCX document 16 KB Posted
- Solicitation number
- W50S8925RRD01
- Issued by
-
Department of the Army National Guard
About this file
The document is a Draft Requirements Description for a Sources Sought Synopsis issued by the Nebraska Air National Guard to conduct market research for constructing a fabric storage facility. The project requires designing, engineering, fabricating, delivering, and erecting a 64'x30' facility to accommodate two Negatively Pressurized Conex (NPC) units, with specific technical requirements including 28-ounce fabric, a 10-year warranty, comprehensive power infrastructure, and electrical systems capable of supporting equipment and lighting needs.
Key technical specifications include provisions for HVAC systems maintaining temperatures between 50-80 degrees with 80% relative humidity, security features like a 22'x14' garage door and two personnel doors with keyed locks, exterior and interior lighting solutions, and high-line docks with roller decks. The solicitation targets small businesses, specifically 8(a), HUBZone, Small Disadvantaged Business, and Service-Disabled Veteran-Owned Small Business categories. Interested vendors must submit a capability statement via email to reid.dalton@us.af.mil, including company name, UEI, and referencing the solicitation number W50S8925RRD01, with the goal of developing an acquisition plan for the temporary storage facility.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2. NPC Specifications.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
***A general site plan can be provided upon request to reid.dalton@us.af.mil
Construct Fabric Storage Facility:
1. Design, engineer, fabricate, deliver, and erect a 64’x30’ fabric storage facility to accommodate (2) NPC’s.
2. 28-Ounce Fabric minimum, with 10-year Parts and Labor Warranty.
Power Requirements:
1. Contractor to assess available power at B2600 Fuel Cell Hangar and design suitable connection to support the fabric storage facility. Requirement includes 50A circuit breaker at the exterior mounted subpanel on the east side of the Fuel Cell Hangar, with suitable cable bored underground to the site (approximately 750 LF). Increase capacity of electrical system as needed to accommodate the HVAC system outlined in Option 1. The new storage facility shall be independently metered. Coordinate and comply with all Lincoln Electric System (LES) metering and city building permit requirements.
2. Provide interior main electrical panel and service capable of supporting all NPC power requirements depicted in attachment 2 in addition to all mechanical equipment and lighting solutions supporting the fabric storage facility.
Lighting Requirements:
1. Interior Lighting: The fabric storage facility shall have general purpose fluorescent light fixtures throughout.
2. Exterior Lighting: The fabric storage facility shall have a weather rated flood light above all building entrances, to include the garage door, to provide nighttime and safety illumination.
3. Emergency Lighting: Emergency exit lighting and signs with integral battery backup shall be installed at appropriate places within the facility.
Security and Access Requirements:
1. The fabric storage facility shall have (1) 22’Wx14’H garage door oriented towards the flightline. Ensure the clear height of the garage door can accommodate the total height of the NPC on top of the proposed high-line dock solution in Option 2. The garage door shall be secured/locked from the inside.
2. Provide two (2) personnel doors, one (1) on each end, with keyed locks using the base standard BEST system.
Anchoring Requirements: Provide suitable anchoring system to the concrete pad rated for anticipated wind loads in Lincoln, NE.
Option #1: Heating, Ventilation, and Air Conditioning (HVAC), and Insulation:
1. Fabric storage facility shall have a heating and cooling system capable of minimally maintaining temperatures between 50 and 80 degrees, and 80% relative humidity, at all times throughout the year respective to climate averages in Lincoln, NE.
Option #2: High-Line Docks:
2. Provide and install high-line docks with integral roller deck capable of supporting NPC specifications depicted in attachment 2.