This solicitation is for a stewardship integrated resource service contract to implement large-scale forest restoration treatments across multiple areas within the Stanislaus National Forest in California. The contractor will be required to complete surveys, layout and cruising, timber harvesting, road reconstruction and maintenance work. Treatment is expected to occur across approximately 11,412 acres spanning from 2024 through 2029.
The solicitation identifies mandatory and optional work activities with estimated quantities and unit pricing required for each. Mandatory work includes surveys, landline marking, road and harvest unit layout, thinning and piling. Optional work includes additional road reconstruction and maintenance. The contractor must also remove timber/products and may receive payment in stewardship credits. Pricing terms include firm-fixed unit prices and maximum tonnages for hauling non-saw timber. The solicitation requires adherence to detailed specifications and establishes a performance period from award through November 2029.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND
SERVICES - OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
1. REQUISITION NUMBER PAGE 1 OF
1103218 106
2. CONTRACT NO. 3. AWARD/EFFECTIVE
DATE
4. ORDER NUMBER 5. SOLICITATION NUMBER 6. SOLICIATION ISSUE
DATE
12363N23Q4169 July 25, 2023
7. FOR SOLICITATION
INFORMATION CALL:
Email Contact Preferred
a. NAME b. TELEPHONE NUMBER(No collect calls) 8. OFFER DUE DATE / LOCAL TIME
Mark T. Phillipp Mark.Phillipp@usda.gov (541) 487-1187 September 1st, 2023 4:00 p.m. PT
9. ISSUED BY CODE 363N 10. THIS ACQUISITON IS UNRESTRICTED OR SET ASIDE % FOR:
USDA-FS – Procurement & Property Services
National Procurement Operations
Stewardship Contracting Branch
Mark.Phillipp@usda.gov
Kasandra.Meyer@usda.gov
SMALL BUSINESS
WOMEN-OWNED SMALL BUSINESS
(WOSB) ELIGIBLE UNDER THE WOMAN-
OWNED SMALL BUSINESS PROGRAM
EDWOSB
NAICS:
HUBZONE SMALL BUSINESS 115310
SERVICE-DISABLED VETERAN-
OWNED SMALL BUSINESS 8(A)
SIZE STANDARD:
34 M
11. DELIVERY FOR FOB DESTINATION
UNLESS BLOCK IS MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
13a. THIS CONTRACT IS A RATED
ORDER UNDER DPAS (15 CFR 700)
13b. Rating
14. METHOD OF SOLICITATION
RFQ IFB RFP
15. DELIVER TO CODE 363N 16. ADMINISTERED BY CODE 363N
Stanislaus National Forest
Summit Ranger District
1 Pinecrest Lake Rd
Pinecrest, CA 95364
USDA-FS – Procurement & Property Services
National Procurement Operations
Stewardship Contracting Branch
1400 Independence Ave. SW, MS-1138
Washington DC 20250-1138
17A. CONTRACTOR/OFFEROR CODE
FACILITY
CODE
18a. PAYMENT WILL BE MADE BY CODE 363N
Name:
Address:
Email:
Telephone No:
*Invoice Processing Platform (IPP):
All invoices must be submitted electronically through the Invoice Processing Platform via www.IPP.gov.
*All Invoices for Non-Monetary Credits must be submitted to the Forest COR via email.* SAM UEI (12 characters):
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK
BELOW IS CHECKED
SEE ADDENDUM
19. 20. 21. 22. 23. 24.
ITEM N0. SCHEDULE OF SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
SERAL G-Z STEWARDSHIP IRSC
STANISLAUS NATIONAL FOREST
SUMMIT RANGER DISTRICT
REGION 5 - CALIFORNIA
See attached Schedule of items
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA
26. TOTAL AWARD AMOUNT (For Govt. Use Only)
27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED.
ADDENDA
ARE ARE NOT ATTACHED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN 1 COPY TO
Mark.Phillipp@usda.gov and Kasandra.Meyer@usda.gov
29. AWARD OF CONTRACT: REF__________________
ONE (1) COPY TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DELIVER
OFFER DATED________________, YOUR OFFER ON SOLICITATION
____________________________ (BLOCK 5), INCLUDING ANY ADDITIONS OR
ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY CHANGES WHICH ARE SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED __________________________________________________________________
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)
30b. NAME AND TITLE OF SIGNER (Type or print) 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (Type or print) 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION STANDARD FORM 1449 (REV.2/2012)
PREVIOUS EDITION IS NOT USABLE Prescribed by GSA - FAR (48 CFR) 53.212 mailto:Mark.Phillipp@usda.gov mailto:Kasandra.Meyer@usda.gov http://www.ipp.gov/ mailto:Kasandra.Meyer@usda.gov
Seral G-Z Stewardship IRSC Stanislaus National Forest
Page 2 of 106 Summit Ranger District
Revised 10.13.2022
GENERAL INFORMATION:
Proposals shall be valid for 60 days after the date of receipt for the solicitation. If additional time is needed, an extension will be requested. Refer to Section 50 for instructions on preparing your proposal and pricing. Submit technical proposals and price proposals separately, via email, to the individual(s) shown in box 28 of page 1.
All Contractors must be actively registered in the System for Award Management (SAM) https://SAM.gov to be eligible for award under this solicitation. Registration in SAM is a free service – you do not need to pay to register in this system. If your registration is not active, you will not be considered for award.
SCHEDULE OF ITEMS
MANDATORY WORK ACTIVITIES:
ITEM
NO.
DESCRIPTION OF
MANDATORY WORK ACTIVITIES
UNIT
ESTIMATED
QUANTITY
UNIT
PRICE
TOTAL
1 Common Stand Exam (CSE) Surveys Plot 1,750 $ $
2 Landline Re-Posting/Marking Mile 18.73 $ $
3 Landline Survey & Posting/Marking Mile 5.89 $ $
4 Botany Survey and Flagging
(a) Field Survey Analysis/Plan, and
Survey Acre 11,412 $ $
(b) Flag & GPS Feet 1,084,140* $ $
5 Flag Known Cultural Sites Acre 1,050 $ $
6 Road Reconstruction Survey & Plan
(a) Treatment Area 1
(Sourgrass/Dry Meadow) Mile 43.6 $ $
(b) Treatment Area 2
(Bull Creek/Beardsley/Pedro Flat) Mile 32.9 $ $
(c) Treatment Area 3
(Campoodle/Smoothwire) Mile 29.1 $ $
7 Harvest Unit Layout, Boundary Marking, and Cruising
Acre 2,092 $ $
Acre 3,260 $ $
Acre 2,818 $ $
8 Hand Thin/Hand Pile
Acre 196 $ $
Acre 322 $ $ https://sam.gov/
Page 3 of 106 Summit Ranger District
Acre 105 $ $
(d) Treatment within Cultural Sites
(All Areas) Acre 112 $ $
9 Fuelbreak Mastication/Machine Pile
Acre 636 $ $
Acre 622 $ $
Acre 577 $ $
10 Mastication
Acre 958 $ $
Acre 592 $ $
Acre 289 $ $
Total All Mandatory Service Items $
OPTIONAL WORK ACTIVITIES:
ITEM
NO.
DESCRIPTION OF
OPTIONAL WORK ACTIVITIES
UNIT
ESTIMATED
QUANTITY
UNIT
PRICE
TOTAL
Treatment Area 1 (Sourgrass/Dry Meadow)
11 Road Reconstruction
(a) Mobilization Lump Sum
2* $
(b) Construction survey and staking, method I, tolerance B
Lump
(c) Clearing and grubbing, disposal method: limbs g, logs l, stumps f Mile 30.0* $
(d) Removal of culverts, disposal method a, compaction method 5 Each 1* $
(e) Roadway excavation and embankment, compaction placement method 2, tolerance class B
Cubic Yard
375* $
(f) Embankment construction, compaction placement method 2, tolerance class A
Cubic
Page 4 of 106 Summit Ranger District
(g) Drainage excavation, type Armored Dip, compaction placement method 2, tolerance class A
Each 2* $
(h) Drainage excavation, type Roadside Ditch, compaction placement method 2, tolerance class A
Foot 1,385* $
(i) Drainage excavation, type Rocked Swale, compaction placement
(j) Drainage excavation, type Swale, tolerance class A
Each 4*
(k) Drainage excavation, type Rolling
Each 27*
(l) Drainage excavation, type Water Bar, Driveable, compaction placement method 2, tolerance class A
Each 15* $
(m) Drainage excavation, type Lead Off
Each 4* $
(n) Drainage excavation, type Armored Low Water Crossing, compaction placement method 2, tolerance
Each 1*
(o) Linear Grading Mile 2.2*
(p) Aggregate Base, Grading C, Compaction Method C Ton 619*
(q) Subbase, grading, compaction method C Ton 24*
(r) Aggregate surface course, grading
H, compaction method C Ton 129*
(s) Ditch Reconditioning Linear Foot
8,778* $
(t) Roadbed reconditioning, compaction method 2 Mile 6.4* $
(u) Roadway reconditioning, Mile 4.0* $
(v) Full depth reclamation, 2 inch depth, 1 inch minus, compaction
Mile 0.3* $
Page 5 of 106 Summit Ranger District
(w) Aphalt Concrete, California State
DOT, 1/2 in. Type A HMA, PG 64-16 Ton 44* $
(x) Asphalt Concrete Pavement
Patching, Type 1
Square
38* $
(y) Asphalt Concrete Pavement
Patching, Type 2
Square
22* $
(z) 18 inch pipe culvert, round steel, 0.064" thick with 2 2/3" x 1/2" corrugations, compaction placement method 6
Foot 20* $
(aa) 24 inch pipe culvert, round steel, corrugations, compaction
Foot 20*
(bb) 36 inch pipe culvert, round steel, 0.064" thick with 2 2/3" x 1/2" corrugations, compaction
Foot 20*
(cc) 48 inch pipe culvert, round steel, 0.079" thick with 2 2/3" x 1/2" corrugations, compaction
(dd) 60 inch pipe culvert, round steel, 0.079" thick with 3" x 1" corrugations, compaction
(ee) 72 inch pipe culvert, round steel, 0.109" thick with 3" x 1" corrugations, compaction
(ff) 18" Flared End Section Each 1* $
(gg) 24" Flared End Section Each 1* $
(hh) 36" Flared End Section Each 1* $
(ii) 48" Flared End Section Each 1* $
Page 6 of 106 Summit Ranger District
(jj) 60" Flared End Section Each 1* $
(kk) 72" Flared End Section Each 1* $
(ll) Inlet top, type 36" DI Lid Each 1* $
(mm) Metal Spillway, galv. sheet steel, 0.064" thick
(nn) Cleaning culverts in place Each 9* $
(oo) Enlarge catch basin Each 1* $
(pp) Gate steel tube, 16 ft Each 1* $
(qq) Gate, Powder River or equivalent
(rr) Cattle guard relocation Each 1* $
(ss) Earth and log berm Each 4* $
(tt) Erosion control blanket, open weave textile, type 3B
Square
44* $
(uu) Separation and stabilization geotextile, Class 2 Nonwoven
Square
200*
(vv) Roadside Hazardous Fuels
Mitigation – Felling of dead standing fuels (Assume 90 trees per mile and a QMD of 25”)
Mile 25.4* $
12 Timber/Product Removal
(a) Cut and Remove Included
Timber
Acre 2,092 N/A N/A
(b) Cut, Skid and Deck Non-Saw Timber
(i) 3.00-5.99* ccf/acre
Acre 2,092*
Page 7 of 106 Summit Ranger District
(ii) 6.00-8.99* ccf/acre
Acre 2,092*
(iii) 9.00-11.99* ccf/acre Acre 2,092* $ $
13 Hauling of Non-Saw Timber Ton 48,900** $ $
Item 13 will be awarded as a capped tonnage for payment. Pricing data is required to verify product is deficit. Unit Price per Ton above should reflect Removal Cost minus Delivered Value.
Removal Cost (loading/chipping and trucking): $______/ton
Delivered Value: $_______/ton
14 Transport of Surplus/Excess Products Ton N/A N/A N/A
Treatment Area 2 (Bull Creek/Beardsley/Pedro Flat)
15 Road Reconstruction
a) Mobilization
Lump Sum
3* $ $
b) Construction survey and staking, method I, tolerance B
Lump Sum
3* $ $
c) Clearing and grubbing, disposal method: limbs g, logs l, stumps f
Mile 22.4* $ $
d) Removal of culverts, disposal method a, compaction method (5)
Each 1* $ $
e) Roadway excavation and embankment, compaction placement method 2, tolerance class B
Cubic
280* $ $
f) Embankment construction, tolerance class A
Cubic Yard
2* $ $
g) Drainage excavation, type Armored Dip, compaction placement method 2, tolerance class A
Each 2* $ $
h) Drainage excavation, type Roadside Ditch, compaction placement method 2, tolerance class A
Foot 1,035* $ $
i) Drainage excavation, type Rocked Swale, compaction placement method 2, tolerance class A
Each 1* $ $
j) Drainage excavation, type Swale, compaction placement method 2, Each 3* $ $
Page 8 of 106 Summit Ranger District
k) Drainage excavation, type Rolling Dip, compaction placement method 2, tolerance class A
Each 20* $ $
l) Drainage excavation, type Water Bar, Driveable, compaction placement method 2, tolerance
Each 11* $ $
m) Drainage excavation, type Lead Off method 2, tolerance class A
Each 3* $ $
n) Drainage excavation, type Armored Low Water Crossing, compaction placement method 2, tolerance class A
Each 1* $ $
o) Linear Grading Mile 1.6* $ $
p) Aggregate Base, Grading C, Compaction Method (c)
Ton 463* $ $
q) Subbase, grading (), compaction method (c)
Ton 18* $ $
r) Aggregate surface course, grading
Ton 96* $ $
s) Ditch Reconditioning
Linear Foot
6,557* $ $
t) Roadbed reconditioning, compaction method 2
Mile 4.8* $ $
u) Roadway reconditioning, compaction method 2
Mile 3.0* $ $
v) Full depth reclamation, 2 inch depth, 1 inch minus, compaction method C
Mile 0.2* $ $
w) Aphalt Concrete, California State
Ton 33* $ $
x) Asphalt Concrete Pavement
Square
Yard 28* $ $
y) Asphalt Concrete Pavement Patching, Type 2
Square Yard
17* $ $
z) 18 inch pipe culvert, round steel, 0.064" thick with 2 2/3" x 1/2" corrugations, compaction placement method 6
Foot 20* $ $
aa) 24 inch pipe culvert, round steel, Foot 20* $ $
Page 9 of 106 Summit Ranger District corrugations, compaction placement method (6)
bb) 36 inch pipe culvert, (round steel), 0.064" thick with 2 2/3" x 1/2" corrugations, compaction placement method (6)
Foot 20* $ $
cc) 48 inch pipe culvert, round steel, 0.079" thick with 2 2/3" x 1/2" corrugations, compaction placement method (6)
Foot 20* $ $
dd) 60 inch pipe culvert, round steel, 0.079" thick with 3" x 1" corrugations, compaction placement method (6)
Foot 20* $ $
ee) 72 inch pipe culvert, round steel, 0.109" thick with 3" x 1" corrugations, compaction placement method (6)
ff) 18" Flared End Section Each 1* $ $
gg) 24" Flared End Section Each 1* $ $
hh) 36" Flared End Section Each 1* $ $
ii) 48" Flared End Section Each 1* $ $
jj) 60" Flared End Section Each 1* $ $
kk) 72" Flared End Section Each 1* $ $
ll) Inlet top, type 36" DI Lid Each 1* $ $
mm) Metal Spillway, galv. sheet
Each 1* $ $
nn) Cleaning culverts in place Each 7* $ $
oo) Enlarge catch basin Each 1* $ $
pp) Gate steel tube, 16 ft Each 1* $ $
qq) Gate, Powder River or equivalent Each 1* $ $
rr) Cattle guard relocation Each 1* $ $
Page 10 of 106 Summit Ranger District
ss) Earth and log berm Each 3* $ $
tt) Erosion control blanket, open weave textile, type 3B
Square Yard
33* $ $
uu) Separation and stabilization geotextile, Class 2 Nonwoven
Square Yard
149* $ $
vv) Roadside Hazardous Fuels
Mitigation – Felling of dead standing fuels (Assume 90 trees per mile and a QMD of 25”)
Mile 34.3* $ $
16 Timber/Product Removal
(a) Cut and Remove Included
Timber
Acre 3,262 N/A N/A
Acre 3,262*
Acre 3,262*
(iii) 9.00-11.99* ccf/acre Acre 3,262* $ $
17 Hauling of Non-Saw Timber Ton 76,200** $ $
Item 17 will be awarded as a capped tonnage for payment. Pricing data is required to verify product is deficit. Unit Price per Ton above should reflect Removal Cost minus Delivered Value.
18 Transport of Surplus/Excess Products Ton N/A N/A N/A
Treatment Area 3 (Campoodle/Smoothwire)
19 Road Reconstruction
a) Mobilization Lump
2* $ $
b) Construction survey and staking, method I, tolerance B
Lump
2* $ $
c) Clearing and grubbing, disposal method: limbs g, logs l, stumps f Mile 19.8* $ $
d) Removal of culverts, disposal method a, compaction method (5)
e) Roadway excavation and embankment, compaction placement method 2, tolerance class B
Cubic
248* $ $
Page 11 of 106 Summit Ranger District
f) Embankment construction, tolerance class A
Cubic
1* $ $
g) Drainage excavation, type Armored
h) Drainage excavation, type Roadside
Foot 915* $ $
i) Drainage excavation, type Rocked Swale, compaction placement
j) Drainage excavation, type Swale, Each 2* $ $
k) Drainage excavation, type Rolling
Each 18* $ $
l) Drainage excavation, type Water Bar, Driveable, compaction placement method 2, tolerance
Each 10* $ $
m) Drainage excavation, type Lead Off
Each 3* $ $
n) Drainage excavation, type Armored Low Water Crossing, compaction placement method 2, tolerance class A
o) Linear Grading Mile 1.5* $ $
p) Aggregate Base, Grading C, Compaction Method (c) Ton 409* $ $
q) Subbase, grading (), compaction method (c) Ton 16* $ $
r) Aggregate surface course, grading
Ton 85* $ $
s) Ditch Reconditioning Linear Foot
5,800* $ $
t) Roadbed reconditioning, Mile 4.3* $ $
u) Roadway reconditioning, Mile 2.6* $ $
v) Full depth reclamation, 2 inch depth, 1 inch minus, compaction
Mile 0.2* $ $
w) Aphalt Concrete, California State
Ton 29* $ $
Page 12 of 106 Summit Ranger District
x) Asphalt Concrete Pavement
Square
25* $ $
y) Asphalt Concrete Pavement
Patching, Type 2
Square
15* $ $
z) 18 inch pipe culvert, round steel, corrugations, compaction
aa) 24 inch pipe culvert, round steel, corrugations, compaction
bb) 36 inch pipe culvert, (round steel), corrugations, compaction
cc) 48 inch pipe culvert, round steel, 0.079" thick with 2 2/3" x 1/2" corrugations, compaction
dd) 60 inch pipe culvert, round steel, 0.079" thick with 3" x 1" corrugations, compaction
ee) 72 inch pipe culvert, round steel, 0.109" thick with 3" x 1" corrugations, compaction placement method (6)
Foot 20* $ $
ff) 18" Flared End Section Each 1* $ $
gg) 24" Flared End Section Each 1* $ $
hh) 36" Flared End Section Each 1* $ $
ii) 48" Flared End Section Each 1* $ $
jj) 60" Flared End Section Each 1* $ $
kk) 72" Flared End Section Each 1* $ $
ll) Inlet top, type 36" DI Lid Each 1* $ $
mm) Metal Spillway, galv. sheet
Each 1* $ $
nn) Cleaning culverts in place Each 6* $ $
oo) Enlarge catch basin Each 1* $ $
pp) Gate steel tube, 16 ft Each 1* $ $
qq) Gate, Powder River or equivalent Each 1* $ $
Page 13 of 106 Summit Ranger District
rr) Cattle guard relocation Each 1* $ $
ss) Earth and log berm Each 2* $ $
tt) Erosion control blanket, open weave textile, type 3B
Square
29* $ $
uu) Separation and stabilization geotextile, Class 2 Nonwoven
Square
132* $ $
vv) Roadside Hazardous Fuels
Mitigation – Felling of dead standing fuels (Assume 90 trees per mile and a QMD of 25”)
Mile 25.2* $ $
20 Timber/Product Removal
(a) Cut and Remove Included
Timber
Acre 2,818 N/A N/A
Acre 2,818*
Acre 2,818*
(iii) 9.00-11.99* ccf/acre
Acre 2,818*
21 Hauling of Non-Saw Timber Ton 65,900** $ $
Item 21 will be awarded as a capped tonnage for payment. Pricing data is required to verify product is deficit. Unit Price per Ton above should reflect Removal Cost minus Delivered Value.
22 Transport of Surplus/Excess Products Ton N/A N/A N/A
Total All Optional Service Items $
Page 14 of 106 Summit Ranger District
TIMBER/PRODUCT REMOVAL PRICE SCHEDULE:
SPECIES PRODUCT QUANTITY
UNIT OF
MEASURE
MINIMUM
ACCEPTABLE
OFFER
Timber Treatment Area 1 - Sourgrass/Dry Meadow
CS Saw Actual Quantity determined
After Cruise
43,400*** Tons
TBD from Appraisal
$0.25 – 10.00***
CS Non-saw 48,900** Tons $0.01
Total Value Bid Premium – All Products Treatment Area 1**** $
Total Value – All Products Treatment Area 1 (TBD after cruise and appraisal)
N/A – TBD
Will be calculated by FS for evaluation purposes.
Timber Treatment Area 2 - Bull Creek/Beardsley/Pedro Flat
CS Saw Actual Quantity determined
After Cruise
82,200*** Tons
TBD from Appraisal
$0.25 – 10.00***
CS Non-saw 76,200** Tons $0.01
Total Value Bid Premium – All Products Treatment Area 2**** $
Total Value – All Products Treatment Area 2 (TBD after cruise and appraisal)
N/A – TBD
Will be calculated by FS for evaluation purposes.
Timber Treatment Area 3 - Campoodle/Smoothwire
CS Saw Actual Quantity determined
After Cruise
71,000*** Tons
TBD from Appraisal
$0.25 – $10.00***
CS Non-saw 65,900** Tons $0.01
Total Value Bid Premium – All Products Treatment Area 3**** $
Total Value – All Products Treatment Area 3 (TBD after cruise and appraisal)
N/A – TBD
Will be calculated by FS for evaluation purposes.
Page 15 of 106 Summit Ranger District
Enter delivered saw log value (paid by mill) to be used in determining appraised timber rates:
Product:_______________ Delivered Value: $_________/ton Location:___________
Product:_______________ Delivered Value: $_________/ton Location:___________
Product:_______________ Delivered Value: $_________/ton Location:___________
Product:_______________ Delivered Value: $_________/ton Location:___________
Product:_______________ Delivered Value: $_________/ton Location:___________
Product:_______________ Delivered Value: $_________/ton Location:___________
Firms are required to provide delivered market value prices for products planned to be delivered and to which facilities. This information provided will be used (kept internally to protect proprietary information), coupled with the variable logging cost entries obtained from logging plans produced by the contractor will be used to determine the final timber rates per Timber Treatment Area. This will not be used for evaluation purposes.
Notes: These schedules are for pricing/payment purposes. See Instructions to Offerors for business proposal requirements. Unit prices prevail. Price Proposals MUST be provided on ALL Items in
Schedules: Mandatory Work, Optional Work and Total Value Bid Premium for all Timber Products for each Treatment Area, except for Optional Item 14, 18 and 22. These Items may be negotiated and populated via modification if product is found to be in surplus. Option Item 14, 18 and 22 allows contractors to market surplus wood products outside the local area.
Contractors are required to submit a primary proposal for all work as shown in the SOI on 4
Treatment Areas. Contractors proposing to complete work in less than 4 Treatment Areas or that have an alternative plan must submit a second Alternative price proposal and Alternative technical proposal.
*Total quantities are unknown and shown as estimated gross quantity. Completion and acceptance of
Item 4a will determine true needed quantities for Item 4b, and completion of Items 6a-c, and 7a-c will determine true needed quantities for all other Items. The use of “Stepladder Pricing” enables the
Government to establish Firm-Fixed Pricing at time of award for all Items based on differing complexity. Contractor shall provide a fixed price per Item based on the estimated quantity shown and the complexity level as described in Appendix A. Awarded Firm-Fixed unit prices prevail and
WILL NOT be renegotiated or changed in future modifications to adjust quantities once known.
**Total tons of non-saw products awarded to be removed shall be negotiated and populated via modification after cruise is completed for each Timber Treatment Area. Awards made for non-saw product removal will be set as a capped tonnage for payment per Treatment Area.
***The gross acres of commercial sawtimber for each Treatment area were determined using GIS.
Gross sawtimber volume was calculated assuming 4.0 MBF/acre. Gross sawtimber volume for each
Treatment Area is for evaluation purposes. Final commercial timber acres may be more or less than the estimated amount per Treatment Area based on contractor proposals for number of Timber
Treatment areas (1 area up to the 3 areas as shown in the Schedule of Items).
Page 16 of 106 Summit Ranger District
Advertised timber rates, specific to economically viable (non-deficit) sawtimber, from the past three years for sawtimber on the Stanislaus National Forest have a range of $0.25 – $10.00/ton. When Final
Cruise for each Timber Treatment Area has been completed and accepted, the FS will complete an independent Timber Sale Appraisal to determine the Advertised Timber Rate and Bid Premiums to be collected. Harvest Layout Cards once accepted from Item 7 WILL be used for appraisal data entries to calculate logging costs. Commercial material will not be removed from Service Only areas, unless proposed by the Contractor as Timber Subject to Agreement. Low volume/value/quality treatment units should not be analyzed as commercial timber removal units, these should be proposed as service only units.
****Contractors shall provide a Total Value Bid Premium for all products per treatment area
≥$0.00. The Total Value Bid Premium for each Treatment Area will be distributed evenly over all final awarded products (non-saw and saw timber) per treatment area to have one combined rate for all products per Treatment Area. This will allow maximum flexibility to contractors in marketing all products. To reduce risk to both parties due to over/under-run of products, cruising standards have been increased to “Tree Measurement” maximum allowed error. Timber products will be scaled due to the use of Designation by Prescription.
If the final appraised Timber Rate for Saw timber are between $0.25/ton and $10.00/ton, Total Value
Bid Premiums shall be binding and applied in full. If appraised timber rate is greater than
$10.00/ton, Bid Premiums shall be lowered incrementally until not applicable. Appraised Timber
Rates below $0.25/ton, potentially indicating deficit conditions, will either prompt reassessment of treatment units (move uneconomical unit acres from Timber Removal Item to Service only treatment) for that Treatment Area to bring appraised Rates above $0.25 or Bid Premiums will be waived.
For evaluation of price proposals, FS will calculate the Total Value of all products per Treatment
Area based on the assumptions shown in the Timber Removal Price Schedule and the Total Value
Bid Premium offer. The following calculation will be used for both evaluation of proposals as well as when determining final single timber rate per Treatment Area:
[(Saw Volume * Saw Minimum Rate) + (Non-saw volume * $0.01) + Total Value Bid Premium] = Total Value of all products
(Saw Volume + Non-saw Volume)
Payment and Performance Bonds are required for Re-construction greater than $150,000.00. See
FAR 52.228-15 Performance and Payment Bonds -- Construction (JUN 2020) (DEVIATION APR
2020) and FAR 52.228-1 Bid Guarantee (SEP 1996) (DEVIATION MAY 2020). The estimated average culvert length is 20’ and contractor shall provide culverts as part of their bid if replacement is required and awarded.
A Site Visit has been scheduled for Wednesday, August 2nd, 2023, with a meeting time of 9:00 AM
PT, at the Summit Ranger Station in Pinecrest, CA.
PERIOD OF PERFORMANCE IS FROM DATE OF AWARD THROUGH NOVEMBER 30, 2029
Page 17 of 106 Summit Ranger District
LAND MANAGEMENT ACTIVITIES.
Performance of land management activities shall be in accordance with Project Description and Work
Specifications. Payment for Land Management Work Activities in Schedule of Items will be made in
Stewardship Credits and Appropriated Funds.
All Base Work Activities (Mandatory) shall be performed. Optional activities are listed in order of planned priority. Award may be made for optional items in any order that the Contracting Officer determines is in the best interest of the Government.
1. FAR 52.212-4 CONTRACT TERMS AND CONDITIONS - COMMERCIAL PRODUCTS AND
COMMERCIAL SERVICES (NOV 2021)
(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post-acceptance rights-
(1) Within a reasonable time after the defect was discovered or should have been discovered; and
(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.
(b) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act (31 U.S.C. 3727). However, when a third party makes payment (e.g., use of the Government wide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.
(c) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.
(d) Disputes. This contract is subject to 41 U.S.C. chapter 71, Contract Disputes. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at Federal Acquisition
Regulation (FAR) 52.233-1, Disputes, which is incorporated herein by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.
(e) Definitions. The clause at FAR 52.202-1, Definitions, is incorporated herein by reference.
(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of
God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The
Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.
(g) Invoice. (Using IPP now) See #42.
http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/52.233-1#FAR_52_233_1 https://www.acquisition.gov/far/52.202-1#FAR_52_202_1
Page 18 of 106 Summit Ranger District
(1) The Contractor shall submit an original invoice and three copies (or electronic invoice, if authorized) to the address designated in the contract to receive invoices. An invoice must include-
(i) Name and address of the Contractor;
(ii) Invoice date and number;
(iii) Contract number, line item number and, if applicable, the order number;
(iv) Description, quantity, unit of measure, unit price and extended price of the items delivered;
(v) Shipping number and date of shipment, including the bill of lading number and weight of shipment if shipped on Government bill of lading;
(vi) Terms of any discount for prompt payment offered;
(vii) Name and address of official to whom payment is to be sent;
(viii) Name, title, and phone number of person to notify in event of defective invoice; and
(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.
(x) Electronic funds transfer (EFT) banking information.
(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.
(B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct EFT banking information in accordance with the applicable solicitation provision, contract clause (e.g., 52.232-33, Payment by Electronic Funds Transfer-
System for Award Management, or 52.232-34, Payment by Electronic Funds Transfer-Other Than System for
Award Management), or applicable agency procedures.
(C) EFT banking information is not required if the Government waived the requirement to pay by EFT.
(2) Invoices will be handled in accordance with the Prompt Payment Act (31 U.S.C.3903) and Office of Management and Budget (OMB) prompt payment regulations at 5 CFR Part 1315.
(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees and agents against liability, including costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any United States or foreign patent, trademark or copyright, arising out of the performance of this contract, provided the Contractor is reasonably notified of such claims and proceedings.
(i) Payment.-
(1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.
(2) Prompt payment. The Government will make payment in accordance with the Prompt Payment Act
(31 U.S.C.3903) and prompt payment regulations at 5 CFR Part 1315.
(3) Electronic Funds Transfer (EFT). If the Government makes payment by EFT, see 52.212-5(b) for the appropriate EFT clause.
(4) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date which appears on the payment check or the specified payment date if an electronic funds transfer payment is made.
(5) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the
Contractor shall-
(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the-
(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);
(B) Affected contract number and delivery order number, if applicable;
https://www.acquisition.gov/far/52.232-33#FAR_52_232_33 https://www.acquisition.gov/far/52.232-34#FAR_52_232_34 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/52.212-5#FAR_52_212_5
Page 19 of 106 Summit Ranger District
(C) Affected line item or subline item, if applicable; and
(D) Contractor point of contact.
(ii) Provide a copy of the remittance and supporting documentation to the Contracting Officer.
(6) Interest.
(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the Treasury as provided in 41 U.S.C. 7109, which is applicable to the period in which the amount becomes due, as provided in (i)(6)(v) of this clause, and then at the rate applicable for each six-month period as fixed by the Secretary until the amount is paid.
(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.
(iii) Final decisions. The Contracting Officer will issue a final decision as required by 33.211 if–
(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt within 30 days;
(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the
Contractor has requested an installment payment agreement; or
(C) The Contractor requests a deferment of collection on a debt previously demanded by the
Contracting Officer (see 32.607-2).
(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.
(v) Amounts shall be due at the earliest of the following dates:
(A) The date fixed under this contract.
(B) The date of the first written demand for payment, including any demand for payment resulting from a default termination.
(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on-
(A) The date on which the designated office receives payment from the Contractor;
(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or
(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.
(vii) The interest charge made under this clause may be reduced under the procedures prescribed in
FAR 32.608-2 in effect on the date of this contract.
(j) Risk of loss. Unless the contract specifically provides otherwise, risk of loss or damage to the supplies provided under this contract shall remain with the Contractor until, and shall pass to the Government upon:
(1) Delivery of the supplies to a carrier, if transportation is f.o.b. origin; or
(2) Delivery of the supplies to the Government at the destination specified in the contract, if transportation is f.o.b. destination.
(k) Taxes. The contract price includes all applicable Federal, State, and local taxes and duties.
(l) Termination for the Government’s convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/33.211#FAR_33_211 https://www.acquisition.gov/far/32.607-2#FAR_32_607_2 https://www.acquisition.gov/far/32.608-2#FAR_32_608_2
Page 20 of 106 Summit Ranger District audit the Contractor’s records. The Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.
(m) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance.
In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.
(n) Title. Unless specified elsewhere in this contract, title to items furnished under this contract shall pass to the Government upon acceptance, regardless of when or where the Government takes physical possession.
(o) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.
(p) Limitation of liability. Except as otherwise provided by an express warranty, the Contractor will not be liable to the Government for consequential damages resulting from any defect or deficiencies in accepted items.
(q) Other compliances. The Contractor shall comply with all applicable Federal, State and local laws, executive orders, rules and regulations applicable to its performance under this contract.
(r) Compliance with laws unique to Government contracts. The Contractor agrees to comply with 31
U.S.C. 1352 relating to limitations on the use of appropriated funds to influence certain Federal contracts; 18
U.S.C. 431 relating to officials not to benefit; 40 U.S.C. chapter 37, Contract Work Hours and Safety
Standards; 41 U.S.C. chapter 87, Kickbacks; 41 U.S.C. 4712 and 10 U.S.C. 2409 relating to whistleblower protections; 49 U.S.C. 40118, Fly American; and 41 U.S.C. chapter 21 relating to procurement integrity.
(s) Order of precedence. Any inconsistencies in this solicitation or contract shall be resolved by giving precedence in the following order:
(1) The schedule of supplies/services.
(2) The Assignments, Disputes, Payments, Invoice, Other Compliances, Compliance with Laws
Unique to Government Contracts, and Unauthorized Obligations paragraphs of this clause;
(3) The clause at 52.212-5.
(4) Addenda to this solicitation or contract, including any license agreements for computer software.
(5) Solicitation provisions if this is a solicitation.
(6) Other paragraphs of this clause.
(7) The Standard Form 1449.
(8) Other documents, exhibits, and attachments.
(9) The specification.
(t) [Reserved]
(u) Unauthorized Obligations.
(1) Except as stated in paragraph (u)(2) of this clause, when any supply or service acquired under this contract is subject to any End User License Agreement (EULA), Terms of Service (TOS), or similar legal instrument or agreement, that includes any clause requiring the Government to indemnify the Contractor or any person or entity for damages, costs, fees, or any other loss or liability that would create an Anti-Deficiency Act violation (31 U.S.C. 1341), the following shall govern:
(i) Any such clause is unenforceable against the Government.
(ii) Neither the Government nor any Government authorized end user shall be deemed to have agreed to such clause by virtue of it appearing in the EULA, TOS, or similar legal instrument or agreement. If the EULA, TOS, or similar legal instrument or agreement is invoked through an "I agree" click box or other comparable mechanism (e.g., "click-wrap" or "browse-wrap" agreements), execution does not bind the
Government or any Government authorized end user to such clause.
http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/52.212-5#FAR_52_212_5 https://www.gsa.gov/forms-library/solicitationcontractorder-commercial-items
Page 21 of 106 Summit Ranger District
(iii) Any such clause is deemed to be stricken from the EULA, TOS, or similar legal instrument or agreement.
(2) Paragraph (u)(1) of this clause does not apply to indemnification by the Government that is expressly authorized by statute and specifically authorized under applicable agency regulations and procedures.
(v) Incorporation by reference. The Contractor’s representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.
ADDENDUM TO FAR 52.212-4 The following clauses are hereby incorporated by reference or full text as appropriate:
NUMBER TITLE DATE
52.219-9 SMALL BUSINESS SUBCONTRACTING PLAN OCT 2022
52.236-2 DIFFERING SITE CONDITIONS APR 1984
52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK APR 1984
52.236-5 MATERIAL AND WORKMANSHIP APR 1984
52.236-6 SUPERINTENDENCE BY THE CONTRACTOR APR 1984
52.236-7 PERMITS AND RESPONSIBILITIES NOV 1991
52.236-8 OTHER CONTRACTS APR 1984
52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENT S APR 1984
52.236-10 OPERATIONS AND STORAGE AREAS APR 1984
52.236-11 USE AND POSSESSION PRIOR TO COMPLETION APR 1984
52.236-12 CLEANING UP APR 1984
52.236-13 ACCIDENT PREVENTION (ALTERNATE I) NOV 1991
52.236-17 LAYOUT OF WORK APR 1984
52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION FEB 1997
52.236-26 PRECONSTRUCTION CONFERENCE FEB 1995
52.242-14 SUSPENSION OF WORK APR 1984
52.245-1 GOVERNMENT PROPERTY SEP 2021
52.246-12 INSPECTION OF CONSTRUCTION AUG 1996
452.236-71 PROHIBITION AGAINST THE USE OF LEAD-PAINT NOV 1996
452.236-73 ARCHEOLOGICAL OR HISTORIC SITES FEB 1988
452.236-76 SAMPLES AND CERTIFICATES FEB 1988
2. FAR 52.217-7 – Option for Increased Quantity – Separately Priced Line Item
The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within the period of performance prior to contract expiration. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.
Page 22 of 106 Summit Ranger District
3. PROJECT DESCRIPTION
(a) Description of Work- The intent of the project is to dramatically increase the pace and scale of forest restoration treatment to mitigate risk of catastrophic wildfire. The project will obtain forestry and logging related services to implement a large-scale landscape treatment. The objective of this project is for the contractor to complete the end-results from planned treatment handoff through final completion of the project including removal of forest products and other on-the-ground service work. Contractor shall complete required resource survey work in each treatment area prior to completing on-the-ground timber/product removal and service work. After the initial resource survey marking and flagging has been accepted and approved, contractors will then layout and mark boundaries for timber/product removal, including marking of designated openings, and complete timber cruises for each treatment area. Upon acceptance and approval of layout and timber cruising Forest Service will appraise included sawtimber to determine contractors bid premium for included timber/product prior to exercising the optional item for on-the-ground timber/product removal.
(b) Resulting Contract – Any resultant contract will be a commercial services contract with requirements for timber removal.
(c) Project Location- T4N, R16E, Sec 23-13. T4N, R17E, Sec 1-18 & 19-20. T4N, R18E, Sec 4-9 &
17-19. T5N, R17E, Sec 1-3, 10-15, 22-27, & 32-35. T5N, R18E, Sec 18-21 & 28-33. MDBM.
4. SPECIFICATIONS
General specifications for each Contract Activity individually described by an item number in the Schedule of
Service Items can be found in Appendix A. Specifications for timber removal can be found in Appendix B and associated road plans and specifications in Appendix C for Stewardship related projects. Incidental construction or reconstruction specified road work plans, drawings, exhibits, and specifications can be found in Appendix D.
5. CONTRACTOR QUALITY CONTROL INSPECTION SYSTEM
The Contractor shall identify the quality control inspection system it will use to ensure that contract specifications will be achieved. At no time shall the contractor rely upon Government inspections to provide notification of unsatisfactory performance. The Contractor shall produce written inspection records in a format and at times and places satisfactory to the Contracting Officer. Inspection records shall be made available upon request of the Contracting Officer and be maintained until the date of contract closure. The Contracting Officer may observe the Contractor's inspection at any time and shall otherwise have unlimited access to the inspection data.
6. ACCEPTANCE
The Forest Service shall perform an inspection upon Contractor’s written request and assurance that work has been completed. Request shall be for a reasonable portion of work. Acceptance may be made for all or portions of work.
7. GOVERNMENT QUALITY ASSURANCE SURVEILLANCE PLAN
Quality assurance plans specific to individual items will be found in Appendix A.
Page 23 of 106 Summit Ranger District
8. FAR 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR
1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after receipt of Notice to Proceed or Order for specific work items, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than November 30, 2029. The time stated for completion shall include final cleanup of the premises.
Performance shall be made only as authorized by orders issued in accordance with the Ordering clauses. Except as this contract otherwise provides, the Government shall order all services within the scope that are required by
Government activities specified in the Schedule only with the vendor holding this contract for the specified services. Timber Removal activities shall be scheduled and carried out in accordance with the Timber Removal
Specifications in Appendix B and/or C and as approved by the Contracting Officer.
9. AGAR 452.211-74 PERIOD OF PERFORMANCE (FEB 1988)
The period of performance of this contract is from date of award through November 30, 2029.
The following is the Forest Services desired schedule and will be used to determine/track if contractor will successfully complete all work on time. Failure to meet the following timelines may result in Optional work Items not being awarded. Continued failure to meet the desired schedule below may result in
Termination for Cause for failure to perform.
Items 1, 2, 3, 4, and 5 Completed by October 31, 2024
Treatment Area 1 (Dry Meadow/Sourgrass):
Items 6 and 7 Completed by October 31, 2025
Items 11 Completed by October 31, 2026
Item 8, 9, 10, 12, and 13 Completed by October 31, 2027
Treatment Area 2(Bull Creek/Beardsley/Pedro Flat):
Item 6 and 7 Completed by October 31, 2026
Item 14 Completed by October 31, 2027
Item 8, 9, 10, 15, and 16 Completed by October 31, 2028
Treatment Area 3 (Campoodle/Smoothwire):
Item 6 and 7 Completed by October 31, 2027
Item 17 Completed by October 31, 2028
Item 8, 9, 10, 18, and 19 Completed by October 31, 2029
Page 24 of 106 Summit Ranger District
10. SCHEDULES AND REPORTS
Pursuant to contract requirements, the following submittals are required within 10 days after issuance of a
Notice to Proceed for review and/or approval, unless stated elsewhere in the specifications or otherwise mutually agreed:
ITEM DESCRIPTION
Proposed progress schedule showing starting and completion dates of planned treatment areas and various phases of the work.
List of proposed sub-contractors and their intended work. Sub-contractors must have Contracting
Officers Written approval prior to starting work on the project. Large businesses must submit a Small
Business Sub-Contracting Plan as required per FAR 52.209-9. Plan shall be submitted after award.
Fire Plan
Equipment Load Limitations List
Designation of Contractor personnel describing responsibilities and authorities
Operator Identification Number from the County Agricultural Commissioner or Pest Control Business
License
All schedules and reports shall be submitted to the COR.
11. PAYMENT
It is anticipated that funds will be exchanged in the performance of this contract because the value of the timber will not completely offset the value…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .